PROJECT PHASES
ARE 459 CONTRACTS & SPECIFICATION CLASS -2
By
Zulfikar Aliyu Adamu ARE DEPT
1
Presentation Outline
Objectives of Class :
To acquire a working knowledge of the principal project phases. To identify activities associated with each phase of a construction project. To provide an understanding of the design and construction process and the roles of the different participants, and the types of documents produced during each phase
Schematic Design
The A/E reviews and evaluates the owners program and budget requirements and discusses with the owner alternative approaches to the design and construction During schematic design, the A/E prepares conceptual design documents. These may include: Preliminary sketches ,Small scale schematic plans, elevations, sections, diagrams, renderings, and other graphic and written documents, General written description of project. The completion of the schematic design phase represents approximately 30 percent design completion for the project
Design Development
The design development phase takes the project from about 30 percent to approximately 60 percent design. It is the time when the design team will be evaluating and selecting all the major systems and components of the project. During this phase of the project the design team is involved in the evaluation and finalization of all the architectural components and project systems. The project's budget and schedule continue to be monitored and adjusted.
9
10
11
12
Specifications
Architectural Drawings
Structural Drawings
Phase 4: Construction
Mobilization
Subcontracting Purchasing Permits Site preparation
14
15
Secure Financing
Construction
Architect
Architect
Contractors
Developers Owners
16
17
18
Cost-Influence Curve
19
CONCLUSION
The major phases in the project cycle are : Project Planning Design Schematic Design Design Development Contract Documents Construction Procurement (Bidding Phase) Construction Post Construction( Occupancy)