Beruflich Dokumente
Kultur Dokumente
REV 0 1
BY AL AL
C792_DEIA_AppendixE1_OMPlan.doc
Page 2 of 34
TABLE OF CONTENTS
1 TECHNICAL DATA........................................................................................................... 5 1.1 BACKGROUND......................................................................................................... 5 1.2 SUMMARISED TECHNICAL DESCRIPTION ........................................................... 5 1.3 RAW AND FINAL WATER QUALITY AND FLOW .................................................... 6 TREATMENT PLANT ....................................................................................................... 7 2.1 TREATMENT PLANT OVERVIEW............................................................................ 7 2.2 EQUIPMENT DETAILS ............................................................................................. 7 2.2.1 Diversion sump .................................................................................................. 7 2.2.2 Control valve sump ............................................................................................ 8 2.2.3 Float valve sump with flow control...................................................................... 8 2.2.4 Collection sump.................................................................................................. 8 2.2.5 Screening facility - Inlet box with manual rake screen........................................ 8 2.2.6 Flow equalisation and anaerobic digestion Septic tank modules .................... 9 2.2.7 Anoxic Zone Recycle sump ............................................................................. 9 2.2.8 Trickling filter towers with collection basins ...................................................... 10 2.2.9 Secondary Clarifier ........................................................................................... 12 2.2.10 Disinfection Chlorine contact channel ........................................................... 12 2.2.11 Final Water Discharge ...................................................................................... 13 2.2.12 Valves .............................................................................................................. 13 2.2.13 Instruments ...................................................................................................... 13 2.3 SOLID WASTE REMOVAL ..................................................................................... 13 2.4 OPERATING PARAMETERS & PROCEDURES .................................................... 14 2.4.1 Influent flow ...................................................................................................... 14 2.4.2 Chlorine Dosing (Treated effluent) ................................................................... 14 2.4.3 Plant Start-Up................................................................................................... 14 2.4.4 Normal Operation ............................................................................................. 14 2.4.5 Plant Shutdown ................................................................................................ 15 2.4.6 Maintenance..................................................................................................... 15 2.4.7 Septic Tank Inspection ..................................................................................... 16 CONTROL PHILOSOPHY.............................................................................................. 18 3.1 PLANT INLET FEED PUMPS ................................................................................. 18 3.2 TRICKLING FILTER FEED PUMPS........................................................................ 18 3.3 SECONDARY SETTLER DESLUDGE .................................................................... 18 3.4 DOSING CONTROL................................................................................................ 18 3.5 FINAL WATER DISCHARGE PUMPS .................................................................... 19 3.6 CONTROL PANEL MCC1000 ................................................................................. 19 3.7 ALARM CONDITIONS ............................................................................................ 20 3.8 HMI PARAMETER SETTING .................................................................................. 20 3.9 HMI PASSWORD .................................................................................................... 20 3.10 CONTROL PANEL MCC2000 ................................................................................. 21 ELECTRICAL CONTROL ............................................................................................... 22 RECOMMENDED SPARES ........................................................................................... 23 DRAWINGS, DIAGRAMS, TABLES, SCHEDULES & PROCEDURES.......................... 24 6.1 Pump Schedule ....................................................................................................... 24 6.2 Valve Schedule ....................................................................................................... 24 6.3 Instrument Schedule ............................................................................................... 24
4 5 6
C792_DEIA_AppendixE1_OMPlan.doc
Page 3 of 34
6.4 Plant General Layout Drawings ............................................................................... 24 6.5 Process & Instrument Diagrams .............................................................................. 24 6.6 Electrical Diagrams & Panel Drawings .................................................................... 24 6.7 Civil Drawings.......................................................................................................... 24 7 SUPPLIER DOCUMENTS.............................................................................................. 25 7.1 Chemicals Data Sheets & MSDS ......................................................................... 25 7.2 Collection Sump Grundfos pumping station ......................................................... 25 7.3 Instruments ............................................................................................................. 25 7.3.1 Flow measuring system Endress + Hauser Promag ......................................... 25 7.3.2 Flow transmitter Endress + Hauser Prosonic.................................................... 25 7.3.3 Level switches Grundfos ................................................................................... 25 7.3.4 Level switches ITT Flygt ................................................................................... 25 7.3.5 Pressure indicators WIKA ................................................................................. 25 7.4 Lifting Equipment..................................................................................................... 25 7.5 Manhole covers Coalition Trading polymer covers ............................................... 25 7.6 Media Trickling filter packing ................................................................................ 25 7.7 Nozzles Trickling filter .......................................................................................... 25 7.8 Pumps ..................................................................................................................... 25 7.8.1 Collection sump Grundfos ................................................................................ 25 7.8.2 Dosing pumps Grundfos Alldos ........................................................................ 25 7.8.3 Effluent sump Sakuragawa ............................................................................... 25 7.8.4 Recycle sump Grundfos ................................................................................... 25 7.9 Tanks Chemical dosing ........................................................................................ 25 7.10 Valves ..................................................................................................................... 25 7.10.1 Valve actuators Noah ....................................................................................... 25 7.10.2 Float valve Vosa ............................................................................................... 25 7.10.3 Gate valves Pleix-Quip ..................................................................................... 25 7.10.4 PVC valves .......................................................................................................... 25 8 COMMISSIONING & HANDOVER ................................................................................. 26 8.1 Installation & Commissioning Checklist ................................................................... 26 8.2 Installation Parameters............................................................................................ 26 8.3 Commissioning Parameters .................................................................................... 26 8.4 Normal Operating Parameters ................................................................................ 26 8.5 Operator Training Register ...................................................................................... 26 8.6 Commissioning Certificate ....................................................................................... 26 8.7 Handover Certificate................................................................................................ 26
C792_DEIA_AppendixE1_OMPlan.doc
Page 4 of 34
1 TECHNICAL DATA
1.1 BACKGROUND
VWS Envig is a total solutions water and wastewater treatment company, offering a full range of activities from turnkey contracting for small and large projects, to specialised services and speciality chemicals for the industrial and municipal markets. These activities are all undertaken from the company's offices in South Africa, Botswana and Namibia. VWS Envig specialises in the design, construction, commissioning and operation of water and wastewater treatment plants and offers a full range of operational contracts including technical assistance, complete outsourcing, and financing of projects. VWS Envig is recognised worldwide for its water treatment expertise. VWS Envig was contracted to design a sewage treatment plant for XXX in XXX to alleviate the pressure on the overloaded oxidation ponds currently in use. VWS designed the plant in conjunction with Aqua Services and Engineering our Namibian sister company. VWS constructed all steel work and provided all process and mechanical equipment including the design guidelines of the civil structures for the sewage treatment plant. VWS also constructed the steel work for the treated effluent sump including supply of pumps and piping within the contract battery limits. Guidelines were given to the civil engineer for design of the diversion sump, float valve sump and effluent sump.
C792_DEIA_AppendixE1_OMPlan.doc
Page 5 of 34
The parameters can not be guaranteed due to these being dependant on the effluent supply content. Further treatment processes might have to be added dependant on the supply effluent analysis.
C792_DEIA_AppendixE1_OMPlan.doc
Page 6 of 34
2 TREATMENT PLANT
2.1 TREATMENT PLANT OVERVIEW
A complete treatment based on new generation trickling filter technology, was provided. The plant includes all unit processes and treatment components required to accomplish rough screening before entering the septic tank, primary treatment, carbon removal and nitrification, solids removal (secondary settling) and disinfection (chlorination). Raw sewage from the inlet pipe to the oxidation ponds is diverted from a sump above the trickling filter plant. From the diversion sump it flows through a float valve sump which is equipped with a flow control valve and float valve which will shut the flow to the trickling filter plant to prevent overflow during power outages. From the float valve sump raw sewage flows into the final collection sump TK-1000 fitted with duty/standby pumps pumping the raw sewage to the trickling filter sewage treatment plant where it discharges into an inlet box CT-1100 before flow is diverted equally into the septic tank modules CT1200 & CT-1201. The following section describes the process and equipment that is provided. Please also refer to the included process and instrumentation diagram. An effluent treatment plant to serve a mining community with shift workers must cater for extreme fluctuations in flow (and load) throughout the year. This requires great flexibility if a biological treatment plant is employed. New generation trickling filter technology in conjunction with a septic tank to serve as buffer tank was considered to be the most appropriate technology for this application. Trickling filters employ fixed film technology, which can accommodate considerable fluctuations in flow and load (biological), incorporate simple technology and require no process control. The trickling filter design incorporates continuous recirculation through and wetting of the media, even during times of low or no inflow. This ensures that the bioculture is kept alive during times of low or no inflow. The sludge settled in the secondary clarifier CT-1600 of the trickling filter system is recycled back to the primary treatment tank (septic tank) CT-1200 & CT-1201 and the recycle stream is variable. Latter is achieved by an adjustable timer, which is set to switch the sludge recycle flow on/off on a time basis. Also, part of the mixed liquor (outflow from the trickling filter) is recycled. For biological treatment the following unit processes are as follows: Flow equalisation / smoothening and anaerobic digestion in septic tank (CT-1200 & CT1201); Anoxic treatment with nitrate rich recycle in a recycle sump (CT-1300); Aerobic/attached growth treatment for carbonaceous material removal and nitrification in trickling filters (TF-1400 & TF-1401). Solids removal in a secondary clarifier (CT-1600)
C792_DEIA_AppendixE1_OMPlan.doc
Page 7 of 34
Ancillaries
Ancillaries
C792_DEIA_AppendixE1_OMPlan.doc
Page 8 of 34
Occasionally, the sludge accumulated in the septic tank must be removed. The amount of sludge accumulated in especially the first compartment of each train of the septic tank has to be assessed at least every six months. This is further described in Section 2.4.7 of this manual. When approx. 400 to 500 mm of sludge has accumulated on the bottom of the first compartment of the septic tank, desludging is required. Only the sludge and scum in the first compartment needs to be removed by pumping it out. To remove this sludge, the operator can use his own desludge pump or he may use one of the trickling filter feed pumps which is on standby for this purpose. The effluent from the septic tank is discharged into the recycle sump (CT-1300).
During times of no inflow to the plant, there will be no discharge from the septic tank into this sump. The pumps will then continue recirculating water from the trickling filter basin through the recycle sump back to the filter media, ensuring that the biomass on the media is kept wet (and alive). The pumps are fitted with a run dry protection level switch (LS1300 LL). If the period of non-inflow to the plant is very long, it can be expected that water will be lost through evaporation and the level in this sump will drop. To then prevent the pump(s) from running dry, they will be switched off (trip) at low low-level. Should the plant receive inflow again, the level in the sump will rise and the level switch (LS1300 L) will switch the pump(s) on automatically. The recycle flow is reduced as the level in the pump sump rises due to closing of the electrically actuated return valves (XV1501, XV1502, XV1503 & XV1504) by high level switch (LS1300 H) and more effluent is discharged to the clarifier. This also ensures that no operator will be required to switch the plant on or off.
C792_DEIA_AppendixE1_OMPlan.doc
Page 9 of 34
An access platform is provided for manual valve operation and for maintenance purposes on the pumps, valves and level switches within the recycle sump. Pumps in sump See detailed pump section / pump schedule
C792_DEIA_AppendixE1_OMPlan.doc
Page 10 of 34
Water (effluent) from the trickling filter feed sump (recycle sump CT-1300) is distributed (not necessarily evenly) and sprayed over the top surface of the media using a simple system of open, non-clogging nozzles positioned on a 100mm OD uPVC header. The water then percolates through the media. The orifice sizes of the nozzles have been set to 18mm. The uPVC header is equipped with flushing valves on the ends of each leg. After checking / cleaning the nozzles once a week, these valves need to be opened to clear any sludge that accumulated in the pipes. The reason for an aerobic and anaerobic layer being established is an increase in the thickness of the microbial layer, causing the diffused oxygen to be consumed before it can penetrate the full depth of the microbial layer. Therefore, oxygen only reaches the outer layer of micro organisms resulting in aerobic conditions, whereas deeper into the biological film no oxygen is available resulting in anaerobic conditions. Figure 3 demonstrates this principle.
Water that has passed through the trickling filter is collected in the trickling filter basins (CT 1500 & CT-1501) and then flows to a static settler. Biological solids that have become detached from the packing media must be removed before the effluent is disinfected and can be finally discharged. Removal of the biomass is achieved in a conventional, secondary settling tank. The design parameters of the trickling filter are as follows: Tag Number Type Design Flow (ADWF) Design Load : TF-1400 & TF-1401 : Modern, plastic media packing (UV stabilised PVC) : 240 m/d : 192 kg/d COD + 11.7 kg/d NH4-N
A simple system of non-clogging, open nozzles will be used to distribute the water from the recycle sump over the top of the media. The wastewater is sprayed over and percolates through the media. Organic material in the wastewater is absorbed by the micro-organisms growing as a biological film on the media and ammonia nitrogen is converted to nitrites and nitrates. The water, after percolating through the media, is collected in the trickling filter basin (CT-1500 & CT-1501), where part of the nitrate-rich water is recycled back into the recycle sump and part overflows into the secondary clarifier (CT-1600). The trickling filter basins are each fitted with 45 V-Notch weirs to control the level in the system.
C792_DEIA_AppendixE1_OMPlan.doc
Page 11 of 34
Biological solids that have become detached from the packing media have to be removed before the effluent is disinfected and can be finally discharged. The hydraulics of the plant will ensure that water from the trickling filter basin will only overflow into the secondary settling tank if there is inflow into the plant. The clarifier design parameters are as follows: Tag Number Type Surface Area Draw off system Stilling well Design Flows (Hydraulic): ADWF PWWF : CT-1600 : Square tapering sides casted concrete structure : 3.5 m x 3.5 m = 12.25 m2 : 90mm OD uPVC pipe system with inverted draw off holes : Stainless steel structure & internals
The clarifier is be fitted with a centre mixing/stilling well, clarified water draw off piping, and sludge removal pipe.
C792_DEIA_AppendixE1_OMPlan.doc
Page 12 of 34
:1 : PD1800 : Grundfos Alldos : DMI 208-1.0-10 : 0.22 lph @ 10 bar : 0.011 kW @ 220-240 VAC, 50 Hz, 1~
2.2.12 Valves
Refer to valve schedule
2.2.13 Instruments
Refer to instrument schedule
C792_DEIA_AppendixE1_OMPlan.doc
Page 13 of 34
Caution: Inhaling chlorine fumes may cause serious lung damage. Avoid direct skin contact with liquid chlorine solution. Use of correct PPE is recommended.
C792_DEIA_AppendixE1_OMPlan.doc
Page 14 of 34
2.4.6 Maintenance
This plant requires very little maintenance. However, the following routine maintenance is necessary:
Daily
Remove all objects accumulated on the bar screen of the inlet box. Use a rake to remove these and discard into waste bin; Check that the chlorine dosing tank still contains sufficient chemical replace when almost empty; Check free chlorine concentration of the final effluent at the outlet of the chlorine contact tank. It should be at least in the range of 0,5 to 1,0 mg/l. Adjust if not within this range; Check all indicating lights on the electrical panel. If any pump/motor has tripped, a red light as well as the general alarm (strobe) light will come on; Check pump operation.
Weekly
When operating in low-flow mode, check nozzles of trickling filter weekly and clean if necessary. If a nozzle does not spray water, it is clogged. Manually clean nozzle with a piece of wire. Use extreme care and put on safety gloves when working with effluent; Remove collected grit and sand in inlet box and behind the inlet screen. Open screen to gain access to grit and sand collected behind it.
Monthly
Dispose of contents in waste bin to a suitable landfill site. Cover with at least 800 mm soil. Or incinerate if possible; Check nozzles of trickling filter. If a nozzle does not spray water, it is clogged. Manually clean nozzle with a piece of wire. Use extreme care and put on safety gloves when working with effluent; Check functionality of all manual valves by opening and closing each valve replace if necessary.
C792_DEIA_AppendixE1_OMPlan.doc
Page 15 of 34
Bi-Annually
Check sludge and scum accumulation in septic tank (see method below Section 2.4.7). Empty sludge into sludge drying bed and allow to thoroughly dry.
Annually
Clean settling tank pipework; Inspect and maintain feed pumps as per manufacturers manual; Check sludge and scum accumulation in septic tank (see method below Section 2.4.7). Empty sludge into sludge drying bed and allow to thoroughly dry; Check all pipework and valves for leaks. Paint, repair or replace if necessary.
C792_DEIA_AppendixE1_OMPlan.doc
Page 16 of 34
When handling sludge, operators should wear overalls and boots at all times and direct contact with the sludge should be avoided to prevent infection with worms or diseases.
For safety reasons, any person that is required to open or inspect the septic tank, that person is required to wear a life jacket prior to and during opening of any hatch. It is recommended to install a rope ladder on the inside of each chamber to assist in case of accidental falling into the tank.
C792_DEIA_AppendixE1_OMPlan.doc
Page 17 of 34
3 CONTROL PHILOSOPHY
3.1 PLANT INLET FEED PUMPS
Two pumps PC1000/1001 (duty/standby) are situated in the collection sump. These pumps are controlled automatically by level switches. Effluent level falling below switch LS1000LL stops the duty pump, effluent level rising above switch LS1000L starts the duty pump. This is a normal condition and does not alarm. Pump duty is swapped each pump start. If the duty pump trips or fails to start then the standby automatically takes over duty. Effluent level rising above switch LS1000H will issue an alarm.
C792_DEIA_AppendixE1_OMPlan.doc
Page 18 of 34
C792_DEIA_AppendixE1_OMPlan.doc
Page 19 of 34
C792_DEIA_AppendixE1_OMPlan.doc
Page 20 of 34
C792_DEIA_AppendixE1_OMPlan.doc
Page 21 of 34
4 ELECTRICAL CONTROL
Refer to EC&I document C10-1436-06-11 for panel schematics.
C792_DEIA_AppendixE1_OMPlan.doc
Page 22 of 34
5 RECOMMENDED SPARES
The following spare holding is recommended to minimise long period shutdown in the event of failure: All spares can be obtained from VWS Envig. Please refer to Engineering Schedules for detail on items. Item
1 2 3 4 5 6 7 8 9 10 11 12
Qty
1 ea 1 ea 1 ea 2 ea 2 ea 1 ea 1 ea 1 ea 1 ea 1 ea 2 ea 6 ea
Description
Submersible pump Grundfos SLV65.65.30.2.50D Submersible pump Sakuragawa U-2153AW Dosing pump Alldos DMI 208 1,0-10 and service kit + installation set DN4 suitable for Cl 2 Level switch ITT Flygt ENM-10 (13 m) Pressure indicator Wika, 63 mm, 0-1000 kPa, glycerine, back entry BSPT Endress + Hauser Prosonic Flow transmitter Prosonic S FDU90 Endress + Hauser Promag 10W80 with local display PVC non return valve DN65 PVC ball valve DN65 Pleix-Quip butterfly valve 80NB Noah Electrical valve actuator SA-005 Trickling filter distribution nozzles orifice sized down to diameter 18mm Electrical Spares Refer to Electrical Bill of Quantities on drawings Section 6
C792_DEIA_AppendixE1_OMPlan.doc
Page 23 of 34
C792_DEIA_AppendixE1_OMPlan.doc
Page 24 of 34
7 SUPPLIER DOCUMENTS
Chemicals Data Sheets & MSDS Collection Sump Grundfos pumping station Instruments 7.3.1 Flow measuring system Endress + Hauser Promag 7.3.2 Flow transmitter Endress + Hauser Prosonic 7.3.3 Level switches Grundfos 7.3.4 Level switches ITT Flygt 7.3.5 Pressure indicators WIKA 7.4 Lifting Equipment 7.5 Manhole covers Coalition Trading polymer covers 7.6 Media Trickling filter packing 7.7 Nozzles Trickling filter 7.8 Pumps 7.8.1 Collection sump Grundfos 7.8.2 Dosing pumps Grundfos Alldos 7.8.3 Effluent sump Sakuragawa 7.8.4 Recycle sump Grundfos 7.9 Tanks Chemical dosing 7.10 Valves 7.10.1 Valve actuators Noah 7.10.2 Float valve Vosa 7.10.3 Gate valves Pleix-Quip 7.10.4 PVC valves 7.1 7.2 7.3
C792_DEIA_AppendixE1_OMPlan.doc
Page 25 of 34
Installation & Commissioning Checklist Installation Parameters Commissioning Parameters Normal Operating Parameters Operator Training Register Commissioning Certificate Handover Certificate
Reference documents:
General Layout Process & Instrumentation Diagrams Electrical Panel Diagrams Operating & Maintenance Manual C10-1436-00-01 C10-1436-01-01 & C10-1436-01-02 C10-1436-06-11 C10-1436 O&M
C792_DEIA_AppendixE1_OMPlan.doc
Page 26 of 34
Section 8.1 Doc. No. : C101436 INSTALLATION & COMMISSIONING CHECKLIST Sheet: 1 / 1 Date :
No. 1 2 3 4 5 6 7 Description All equipment mounted securely All mechanical & process connections done and checked All electrical and control instrumentation connections done and checked Chemical dosing tank positioned and dosing line connected and tested All installation measurements taken and recorded All panel tests performed All spares and chemical supply handed to client Comments Done Yes Yes Yes Yes Yes Yes Yes
___________________ Signature
C792_DEIA_AppendixE1_OMPlan.doc
Page 27 of 34
___________________ Signature
C792_DEIA_AppendixE1_OMPlan.doc
Page 28 of 34
___________________ Signature
C792_DEIA_AppendixE1_OMPlan.doc
Page 29 of 34
Section 8.4 Doc. No. : C101436 NORMAL OPERATING PARAMETERS Sheet: 1 / 1 Date :
No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Description Collection sump PC1000/1001 Recycle sump PC1300/1301/1302 Dosing pump setting Effluent sump PC1900/1901 Design 4.2 l/s @ 15 mWG 7.8 l/s @ 17 mWG 69 % 30 m3/hr @ 65 mWG Actual flow rate not recorded pressure 6 m WG flow rate not recorded pressure 10 m WG 80 % 56 m3/hr @ 20 mWG Unit
___________________ Signature
C792_DEIA_AppendixE1_OMPlan.doc
Page 30 of 34
Section 8.5 Doc. No. : C101436 OPERATOR TRAINING REGISTER Sheet: 1 / 1 Date :
No. 1 2 3 4 5 6 7 8 9 10 Name Signed copy attached Title Signature
Training has been given to the above persons in respect of: Operation of plant Mixing and safe handling of chemicals Cleaning Procedure & general maintenance of plant
For VWS
___________________ Signature
C792_DEIA_AppendixE1_OMPlan.doc
Page 31 of 34
8.6 COMMISSIONING CERTIFICATE CLIENT DESCRIPTION : : XXX WASTE WATER TREATMENT PLANT XXX m3/DAY TRICKLING FILTER STP XXX XXX
This certificate is the final Commissioning Certificate and precedes the final Contract Handover Notification and Acceptance. The attached sheets cover the mechanical/electrical equipment acceptance and may include certain items awaiting finalisation for reasons noted. All operating parameters have been set and tested; performance and sampling reports are attached where possible with available testing instrumentation. All relevant staff members have been trained, the training register is attached. The following documents are issued with this certificate: C101436 O&M C101436 C101436 C101436 Updated Operating & Maintenance Document (Final copy to be couriered) Installation & Commissioning Checklist Operating Parameters Operators Training Register
Please sign one copy and return to the VWS Commissioning Technician to acknowledge receipt of this certificate and all accompanying documents as listed above. Issued By (for VWS)
__________________ Signature
__________________ Date
Received By Client
__________________ Signature
__________________ Date
C792_DEIA_AppendixE1_OMPlan.doc
Page 32 of 34
HANDOVER
For handover the following requirements must be satisfied:
1 2 Installation & Commissioning Checklist C101436 must be complete. Any outstanding snag-list items must be clearly described on Checklist, including the action plan and time period as agreed by VWS and Client. Commissioning Operating Parameters C101436 must be complete. Operating and maintenance training must be complete and register C101436 signed by all attendees. Two copies of Updated Operating & Maintenance documents issued. Commissioning Certificate is issued.
3 4
5 6
C792_DEIA_AppendixE1_OMPlan.doc
Page 33 of 34
CLIENT DESCRIPTION
: :
XXX WASTE WATER TREATMENT PLANT XXX m3/DAY TRICKLING FILTER STP XXX ES10-1436
Project Manager XXX
Dear Sir/s, We have pleasure in confirming that the above upgraded equipment has been checked and tested by our commissioning engineer. We will look upon the date of _____/_____/ 20_____ as the hand over date. This letter serves to confirm that the contract is complete and we are confident that all items and equipment are functioning properly, and in accordance with our specification. This handover may be signed subject to minor outstanding items to be corrected within a time period as agreed between yourself and Veolia Water Systems. All outstanding items are to be clearly identified in writing as well as the agreed course of correction / resolution and time period. Please sign both copies of this certificate and return one copy to the Veolia Water Systems commissioning engineer. If you are not completely satisfied, please advise Veolia Water Systems, in writing within 7 days. If, within 30 days, no correspondence or signed copy is received, Veolia Water Systems will assume acceptance and the guarantee period will start from the handover date. Assuring you of our best attention at all times. For Veolia Water Systems
__________________ Signature
__________________ Date
For Client
__________________ Signature
__________________ Date
C792_DEIA_AppendixE1_OMPlan.doc
Page 34 of 34