Investment budget

Grinding plant for mineral rock with Gegenstromvermahlung

In the region of Bacau / Romania is the construction of a grinding plant for Mineralgestein planned to high-quality, finest materials. The heart of the system are two countercurrent mills which a grinding of raw materials up to a Fineness of less than 20 m to ensure The entire system configuration is based on an existing plant in Austria

Technical parameters and system performance: Based on results of the test operation to the plant in Austria with the facility to be constructed following benefits are achieved. Task Mineralgestein 0/3 with an annual capacity of at least 10,000 tons

First Conditioning equipment for material handling and loading / storage Silo 200m including substructure Silo 80m including substructure Silo 50m including substructure Conveyor approx 25m. Total length Elevator Siloverladegerte Trough Screw about 60lfm. Total length Centrifugal fans Conveyor belt with pockets about 12lfm. Rotary Drive with motor: 1.1 kW-1.500U/min-400V-50Hz Speed monitor Xsav built 11,373 oCoating: 1x Base, 1x top coat per 40 my oSichteranlage oCyclone oMaterial input and output mills oFailure cyclone oFilter failure Convection fan Sichteranlage Exhaust fan mill

Total Pos 1:00 Second Filters and separation Ultrafine Incl. 45kW drive unit Technical parameters and system performance: oSichteraufgabe: about 30 tons / h oParticle size distribution of the feed material: 0-2mm oFines: 0-63my oBulk density of the feed material: about 1 ton / m oMohs hardness of feed material: 3 oSichterluftmenge: about 22.000m / h oEntstaubungsluftmenge of Sicters: 2,000 - 5000m / h

1,795,000.00

oTemperature: 90 C Cyclone for Sichteranlage Execution: oEntry spiral into hard steel HB-400 oDip tube and fittings s = 4mm oIncl. Substructure oCoating: 1x Base, 1x top coat per 40 my Pulse filter system for classifier, General Mills and exhaustion Split design Specifications: oAir flow: 20.000 m / h oFilter area: 210 m oWing loading: 95.2 m / m / h oWall thickness: 3-5mm oCompressed air requirements: 5.5 bar oCompressed air consumption: 16 Nm / h Consisting of: Filter housing FGH-12-05-3375-02 Filter head CRC-12-05-3375-02 Filter sump FST 05/12/02 Filteraustragschnecke Power: 0.75 kW, 400V-50Hz Maintenance platform with galvanized ladder Filter control unit Filter differential pressure monitoring Pressure reducer with oil separator FE DM " Air monitoring unit FE D " Level indicator Filter bag PE 520-lo l = 4500mm, d = 160mm Designed as a double snap ring Support cage with venturi Filter support Galvanised - Complete H 4000mm approx Dry erase line with 2 pieces extinguishing nozzles per unit Riser 2 "for construction. Fire water connection Coating: Powder coating 90my

Total pos. 2:00 Third 2 countercurrent mills:

1,475,500.00

Technical parameters and system performance: Task: about 25to / h Feed material limestone or slag as described above. Specifications: Drive motors 1x90kW-400V-50Hz, 1-110kW 400V-50Hz Technical design of the machine, the machine of the same design as the plant in Austria Modifications to the existing machine because of the adjustment to the dasRohmaterial Wheel assembly area and Feingutausbringung made. The machine is equipped with drives for drive operation. Coating: 1x Base, 1x body color depending 40my Total Item 3.00 6,415,000.00 .

4th Pipe and fittings, valves and control devices including: Pipe and fittings for the suction of Sichteranlage, mill 1 and Mill 2, and for the filter system: Incl. Required control devices and valves, inspection openings and supports Complete with mounting hardware req bolts and gaskets Coating: 1x Base, 1x body color depending 40my Total Pos 4:00

679,000.00

5th Electrical switchgear, control and supervising drying System design: Energy cabinets with oRated current 1250A oSupply via emergency generator 800KVA oEmergency - off relay with 3pcs. Emergency - off switches Control Siemens CPU 315/2DP 2 pcs operating units in the operating room (surgery panels) Communication switching / control panels for operating room professional bus FU in cabinets to control the speed on operating units 2 mills (4 drives) Hopper Exhaust classifier Controls for starting and stopping the system in automatic and manual mode, in dashboard built-in Item 5.00 Total 976,500.00

6th Engineering, project management, construction Plant engineering for the installation on the intended area with Support in the preparation of applications and authorities participating in negotiations Planning (detailed planning of construction company) Mechanical system detailed design with assembly planning Electrical system design, electrical control measuring and control technology technical project management Settlement of the prefabrication plants in Austria / Romania Schedule coordination and technical supervision of manufacturing Coordinate the construction work Coordination of on-site assembly and system installation Construction, installation supervision on site Site equipment with material and tool storage, site office Monitoring the construction, machinery installation with installation supervisor for Ventilation Installation Mechanical engineering installation Electroinstallation Item 6.00 Total 618,500.00

7th Transport and logistics for the delivery of the system components Packaging of machinery and equipment Transport and Insurance Material identification and inventory system Loading and unloading Movements on site Item 7.00 Total 652,500.00

8th Commissioning, Trial operation Provision of qualified personnel for commissioning in Mechanical and electrical tests Functional testing of components Ventilation function tests Determination of setting values for safe start Plant startup Optimization of operating parameters Provision of qualified personnel for the test run Education and training of personnel Further optimization of the operation of the plant Reconciliation of trial operation to normal operation Total Pos 8:00 385,500.00

Subtotal total investment (excluding construction)

12,997,500.00

9th Premises Building operations, sanitation and social rooms 10th Production hall Building for housing the plant 11th Raw material and product storage including equipment Warehouses with storage for raw materials and products Loading and unloading Weighing System (weighbridge in the driveway, scales for individual products) 12th Laboratory equipment, equipment for quality assurance Complete equipment for material analysis Quality equipment, Equipment for the certification of products 13th Tools, equipment and vehicles for operation management Tools for maintenance and service Device for the operation Loading and transport vehicles 14th The regulatory approval process (commercial law, building laws) Creation derEinreichunterlagen Payment of Fees Expenditure for any expert opinion and support

Total Pos 9:00 to 14:00

2,002,500.00

Total

15,000,000.00