These elements must work in conjunction with compliance to building codes, ordinances, and zoning regulations. Allowable access road grades also dictate much of what happens in site geometry and layout. Site Soils Subsurface exploration is required for an understanding of the soil conditions affecting the building and other structures placed on the site. These are required in areas with expansive or low strength soils. Other conditions would include when the site foundation will be supported by fill, projects with steep slope locations and higher ground water and sites with poor subsurface material and bedrock. The geotechnical report will make recommendations for duff removal (excess vegetative material) and foundation material depths for supporting the structures. Determining these quantities and minimizing the construction within zones of bad soils will be beneficial in lowering the projects cost.
www.paceengrs.com
100 or more feet depending on the project size and the accuracy desired. For each grid square, final elevations are established for each corner of every grid square. These are subtracted from the existing elevations at the same location to determine the depth of cut or height of fill at each corner. For each grid square an average of the depths/heights of the four corners is multiplied by the area of the square to determine the volume of earthwork associated with the grid area. The total earthwork volume for the project is calculated by adding the volumes of each grid square in the excavation area. Volumes are calculated as follows: Foundation Materials V= (D1 + D2 + D3 + D4) /4) * A * (1/27) Balancing the site requires looking at the base materials used in constructing the facilities. The soils engineer will analyze the existing surface and sub-soils to determine what criteria and materials are needed to support the buildings, walls, vaults and flexible surfaces such as roads and parking. These foundation materials usually consist of base material to support the structures. The foundation material in cut areas will result in an additional amount of material to be moved. Fill areas therefore require smaller quantities of general fill material. Where, V= volume (cubic yards) A= area of the grid square (square feet) D= depth of cut/fill at each grid corner (ft.) A shrinkage or swell factor is then implemented to account for the condition upon which the calculated volume is to be used. For example, some soils may swell in volume up to 25% - 30% from a bank (in place) condition to a truck (transported) condition. Due to the complexity of the various strata and time consuming method of the calculation many designers utilize Autodesks land development software to perform the calculation. The softwares capabilities allow for survey data of an existing site to be compared with design data for the future site. The grids can now be measured to squares of two-feet or less which increases the accuracy of the estimated materials. Bad soils, duff, borrow areas and volumes for asphalt, concrete, base and other materials can also be calculated. The calculations are performed quickly and the design can be fine tuned (designed site raised or lowered) to better match the reality of the site conditions. A comprehensive look at all the conditions for balanced cut/fill and lesser amount of earthwork, results in a much more cost-effective project.
The Calculation The theoretical calculation that is often performed to determine cut and fill quantities is known as the Grid Method. This method (also known as the Borrow Pit Method) calculates an excavation volume by applying a grid to an area of excavation with varying depths. The grids can be measured to squares of 10, 20, 50,
www.paceengrs.com