Project Schedule and Budget Data Provided: Task A B C D E F G Duration (days) 2 5 3 4 6 4 3 Predecessor(s) ----A B B C,D E Project Totals: Budget $1,600 $4,000 $14,050 $5,800 $12,000 $5,200 $3,900 $46,550
Status of the project at the end of day 6: Task A B C D E F G % Complete 100% 100% 90% 10% 0% 0% 0% Actual Cost of Work Performed $1,800 $4,500 $13,500 $500 $0 $0 $0
Document1
Page 2
Tasks
Duration (Days)
10
11
12
13
14
15
16
Document1
Page 3
2. Calculate the cost variance for each task and the total project. Task A (1600 1800) = -200 Task B (4000 4500) = -500 Task C (12,645 13500) = -855 Task D (580 500) = 80 Task E (0 0) = 0 Task F- = 0 Task G = 0 Total C = -1475
3. What is your assessment of the project at this time? The project is behind schedule and over budget at the end of day 6. Therefore it is not likely that the project will be completed unless additional funding is approved and an assessment of resources (more or less) is needed to complete the project. There will be NO celebration for the project team!!!!