Sie sind auf Seite 1von 114

Hindustan Construction Co Ltd

Erecting Long Span Briges to suit Indian Conditions and Requirements


Presentation by

Suhas P Khedkar (AVP- Engineering,) Hindustan Construction Company To 3rd Annual Bridges India Summit 2012 On 17th May 2012
2 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Table of Contents
Different Methods of erection of Superstructure Cast in Situ Construction Comparison of Conventional and Cantilever Construction Method Innovative Construction of III rd Godavari Railway Bridge at Rajamahendri Bandra Worli Sea Link Superstructure Construction entirely by Precast segmental Construction. Segment Casting and Erection of Appraoch Spans Specaial Challenge during Construction- Relocation of LG Construction of Cable stayed bridge Conclusions

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Different Methods of Erection of Superstructure

Different methods of Superstructure Erection


Cast in situ construction

1. Conventional method for normal spans by use of staging 2. Using specialized technology for longer span bridges:
e.g.. Use of centering girders, and bridge builders for cantilevering superstructures

Construction using Precast elements

Construction using precast girders of entire length, Construction using precast segments to be assembled during erection to form girders of complete length

Special techniques like Incremental launching method


28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Different methods of Superstructure Erection


Method of Erection of Superstructure is site specific. And also design specific. In fact design should suit the method of erection dictated by site conditions and other constraints Final Choice is to be made from cost considerations. Evaluation of a couple of alternatives is many times necessary for major projects to decide cost effectiveness.

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Construction

Cast in Situ Construction for Superstructure


Conventional casting on staging


Method suitable for normal spans

1. More suitable for normal span viaducts as staging can be supported on


ground

2. Has been used for both I girders and Box Girders. 3. If number of spans are small , use of precast girders and launching
system is not cost effective

4. For box girders conventional casting can not be avoided as launching


system may not be feasible due to excessive weight of span.

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Construction for Superstructure

Conventional casting on staging of long span superstructure is generally not feasible beyond about 50 m span due to

excessive weight, Large quantity of staging and increased cycle time and concrete pour size. Especially difficult for River Bridges as staging needs to be supported
on temporary piles.

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Construction for Superstructure

Cast in Situ Cantilever Segmental Technique

10

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Construction for Superstructure

Cast in Situ Cantilever Segmental Technique

Method suitable for long span box girders. Advantages as follows:

1. Each stage of construction is self supporting after completion. The


erection system or the bridge builder can be erected on the tip of units cast earlier.

2. Construction is done in segments of convenient length, so that formwork


and bridge builder frames supporting the formwork can be optimally designed.

3. Construction progresses from pier in both directions towards centre of


span. This allows maintaining feed lines for concrete and access for men and material from the pier location up to the working point.
11 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Conventional Casting Vs Cantilever Construction


Comparison of two methods: Yamuna bridge at Naini Allahabad 60 m spans Cast in Situ on Conventional staging Elaborate staging arrangement needed for the span at 20 m from water level

Bridge over River Brahmaputra at Tezpur Compare the small Bridge Builder on the tip of the cantilever with the staging of Naini Bridge

12

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Conventional Casting Vs Cantilever Construction

Yamuna Bridge Staging Elevation and Side View


13 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Conventional Casting Vs Cantilever Construction

Tezpur Bridge Bridge Builder Elevation and Side View


14 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Cantilever Construction for Long Span River Bridges

Tezpur Bridge over River Brahmaputra Different spans in different stages of construction
15 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Cantilever Construction for Long Span River Bridges

Ganga Bridge at Varanasi - Bridge Builder in Elevation and Side


16

ViewMay 2012 28

Presetation to 3rd annual Bridges India Summit 2012

Cast in Situ Cantilever Construction for Long Span River Bridges

Ganga Bridge at Varanasi after Completion

17

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Railway Bridge at Rajamahendri

Innovative Construction for III Godavari Bridge Superstructure

III Godavari Railway Bridge 28 spans of 98 m each 94 m C/C of bearings


19 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure


III Godavari Railway Bridge near Rajamahendri has been constructed using an innovative technique. The design itself was developed for the innovative erection technique, under typical constraints posed in the tender specifications. The foundations and substructure was designed to suit standard railway span of 94.0 m using steel girders. The tender for superstructure invited alternatives with prestressed concrete (PSC) superstructure. Challenge to design a PSC superstructure within the design capacity of the substructure and foundations, which were designed and constructed for the lighter loads of the steel superstructure.
20

A bow string girder design was proposed by HCC.


28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure


Salient Features: 1. Structural System Bow String Girder in Prestressed Concrete 2. Span of Girder: 94.0 m 3. Arches in Reinforced concrete Constructed using Cast in situ segmental technique 4. Suspenders in High tensile Steel BBR Dyna hangars 5. Tie Girder in Prestressed Concrete Box shaped
21 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Innovative Features: 1. Top down Construction Arch was constructed first 2. Tie girder constructed using formwork supported on suspenders 3. Arch was constructed using cast in situ cantilevering segmental technique in 7 stages 4. Arches from the two piers progressed to meet at the midspan, connected by a closure pour

22

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Stages of Construction of Arch: 1. Erect central tower 2. Cast starting stubs 3. Erect formwork for typical segment supported by stay cables 4. Cast first segment 5. Repeat stages 3 and 4 for balance 6 segments 6. Erect formwork for closure pour on the last segment at crown 7. Cast closure pour
23 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Stage 1 Cast starting stubs


24 28 May 2012

Stage 2 Erect Formwork for first segment on starting stubs

Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
25 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
26 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Closure Pour: Formwork supported on the last segment of 1/2 arch


27 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Arches for various spans completed


28 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Construction of Tie Girder


29 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Innovative Construction for III Godavari Bridge Superstructure

Completed Bridge
30 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Bandra Worli Sea Link Project Superstructure Construction entirely by Precast Segmental Technique, for both Cable Stayed and Approach Spans.

Bandra Worli Sea Link Project special Features


First Sea Link in India and with Precast Segmental construction The entire sea link, including the cable stayed bridges has been constructed using precast segments for the superstructure.

32

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Bandra Worli Sea Link Project special Features


Many Firsts in our country First Cable Stayed Bridge across sea: Indias first open sea and longest cable stayed bridge. First Cable Stayed Bridge with a Single Central Pylon.

33

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Bandra Worli Sea Link Project special Features


Many Firsts in our country The entire sea link, including the cable stayed bridges has been constructed using precast segments for the superstructure. Total 2342 segments have been cast and used. The precast segments used for this sea link are one of the widest and heaviest in our country; - 18.1 m & 20 m in width , weight 120 to 140 MT
Needing a very large casting yard with short line casting cells, large capacity gantries, matching capacity multi axle trailer for segment transportation, and specially designed gantries for segment erection.

34

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Special Features of the Project


Engagement of Asian Hercules, one of the largest floating shear leg crane in the world for shifting 1260 MT launching truss from Bandra end to Worli end of the main cable stay bridge Up to 25-m high piers in open sea, giving ample headroom to marine traffic Use of Politron Disc bearings for the first time in India Piling through rocks exceeding 120 Mpa crushing strength Use of Automatic Climbing Formwork for Pylon Construction

35

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Bandra Worli Sea Link Salient Design Features


Precast Segmental superstrucure except KAGK Link Bridge Aesthetically pleasing deck profile, with uniform depth for all
bridges - Bandra approach , Bandra Cable Stayed, Worli Cable Stayed, Worli Approach.

Unique Design of Bandra Cable Stayed - 250 m spans on either


side , supported on a Central Pylon,
NORTH APPROACH BRIDGE 16x50 = 800m PRECAST SEGMENTAL (SPAN-BY-SPAN)
600m 350m BANDRA CABLE STAY WORLI CABLE STAY 500m 4X50=200m PRECAST SEGMENTAL 150m (BALANCED CANTILEVER) (SPAN-BY-SPAN) PRECAST SEGMENTAL P19 (FORWARD CANTILEVER)

BANDRA

SOUTH APPROACH BRIDGE 28X50 = 1400m PRECAST SEGMENTAL (SPAN-BY-SPAN)

WORLI

A1
R AD ND RO BA 6m CH ZA 54 OA LA P PR L L AP T O &

P6

P12

P17

A1

AP PR OA CH

BR IDG E

P19
600m BANDRA CABLE STAY 200m 350m WORLI CABLE STAY 1400m SOUTH APPROACH BRIDGE

36

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

811m LINK BRIDGE


H RT NO 0m 80

A
WORLI

Bandra Worli Sea Link Project Segment Casting and Erection

Casting Yard and Erection Gantry at BWSLP


The project needed a very large casting yard, and two specially designed LGs, which needed to to be supplemented by one more LG from Worli end in the last season.

38

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Advantages of Precast Superstructure Vs Cast in Situ

Construction of Superstructure in parallel with Foundation construction. When Foundations are being constructed at various site locations, superstructure elements can be precast in a separate casting facility. Advantages of factory production, with ease in quality control, and dimensional accuracy, due to easy acces, and dedictaed equipment, and survey stations. Good quality control due to planned facilities like proper curing arrangement, dedicated supervision. The above are relatively much difficult at actual site locations due to difficult access, great heights and different locations.

39

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Principles of Precast Segmental Construction

Span is divided into a number of segments of full deck width The segments are match cast to attain the final geometry as of the erected span. Match casting and geometric control are of great importance as the bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers. Precision Survey in casting yard to attain desired geometry Precast Segmental Construction offers use of industrialized, repetitive construction procedures, which contribute to improved quality control as well as reduction in construction time .

40

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Importance of Precision in Precast Segmental Construction


Span is divided into a number of segments which are match cast to attain the final geometry as of the erected span.

The bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers. The bridge has both vertical gradient, and Horizontal curvature. The bridge deck therefore follows a space curve.

41

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

SEGMENT : MATCH CASTING

Precast Segmental Construction for Bandra Worli Sea Link Project, Mumbai CEMCON 2007

February, 23 - 2007

Page 42

Planning and Management for Casting Yard

(REBAR JIGS)

(CASTING CELL) (STORAGE BAY 1) TYPICAL CROSS SECTION AT CASTING CELL AND STORAGE AREA (TRANSVERSE DIRECTION)

(STORAGE BAY 2)

TYPICAL CROSS SECTION AT SEGMENT STORAGE AREA (LONGITUDINAL DIRECTION)

CASTING YARD & STACKING YARD CROSS-SECTION

43

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Precasting Yard at BWSLP- Capacity to stack 400 segments. And 9 casting cells.

44

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Prefab Reinforcement Cage handling

45

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Match casting at Precasting Yard

46

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Precast Segment Pour Sequence


2.52 CUM 7 2.19 CUM 9 2.69 CUM 8 4.28 CUM 10 2.69 CUM 8a 2.19 CUM 9a 2.52 CUM 7a

6 1.66 CUM 5 1.26 CUM 3 1.26 CUM 2 3.17 CUM 1 5.33 CUM 2a 3.17 CUM 4 1.66 CUM 4a 1.66 CUM

6a 1.66 CUM 5a 3a 1.26 CUM 1.26 CUM

CONCRETE PLACING SEQUENCE


TOTAL CONCRETE QUANTITY = 44.30 CUM

47

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Segment Handling at Precast Yard

48

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Segment Transportation on Special Trailer

49

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Launching Girder at BWSLP


Suspension Frames Front Leg Main Truss Rear Leg

Rear Trolley Front Pylon

Front Trolley Connection Beam Rear Pylon


50 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Center Leg

Segment Transportation in Sea on Barge

51

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Main Challenge During Construction of Approach Span: Relocation of LG from Bandra Approach spans beyond Bandra Cable Stayed bridge: Shifting by 500 m in the sea.

Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).

Need for Relocation

Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).

54

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules

Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).

55

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules

56

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules
Entire LG weighing 1260 MT , of length 105 m was physically lifted and shifted from P17-P18 to P20-P21

57

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Construction of Cable Stayed bridge

Need for detailed Construction Stage Analysis

59

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Results of stage-by-stage Analysis


Stage-by-Stage Analysis
Tower Construction Deck Erection

Precamber Values

Fibre Stresses

Strutting Requirements and Force Levels

Casting Curve, Erection Curve and Control Lines

Stay Cable Forces for Installation, Tensioning and fine tuning Forces

Stage Deformations

Temporary PT
60 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012

Casting Curve

61

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Stage by Stage Deck Camber Curves


Deck Camber Curves for Bandra Bridge Stage by Stage
450 440 430 420 410 400 390 380 370 360 350 340 330 320 310 300 290 280 270 260 250 240 230 220 210 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100

-300

-275

-250

-225

-200

-175

-150

-125

-100

-75

-50

-25

Elevation y [mm]
25

50

75

100

125

150

175

200

225

250

275

Chainage x [m]

62

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

300

Stage Deflections
Lift Non-stay Segment
28 27 26 25 24 23 22 21 20 19 18

42 41 40 39 38 37 36 35 34 33 32 31 30 29

S7

17 16 15 14 13

S8 S9 S11

S10 S13

S12

S14 S15

S16 S17

S18 S19

S20 S21

S22 S23

S24 S25

S26 S27

S28 S29

S30 S31

S32 S33
8 7 6

12 11 10 9
3 2 1 0 1 2 3 6 7 8

S33
9 10 11 12 13

66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9

Segment Node No. 5090


5 4 3 2 1

7 6

Segment Node No. 5113

Def ormation at previous stage

Def ormation af ter completion of this stage : LC1190

420 Def ormation at handover f or traf f ic movement (Design Camber) @ T=0 : LC1298

370

320

270

220

170

120

70

20

-300

-294

-288

-282

-276

-270

-264

-258

-252

-246

-240

-234

-228

-222

-216

-210

-204

-198

-192

-186

-180

-174

-168

-162

-156

-150

-144

-138

-132

-126

-120

-114

-108

-102

-96

-90

-84

-78

-72

-66

-60

-54

-48

-42

-36

-30

-24

-18

-12

-6 -30

12

18

24

30

36

42

63

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

-80

Stage Deflections
Stress Previous Cable to Ft
27 26 25 24 23 22 21 20 19 18

42 41 40 39 38 37 36 35 34 33 32 31 30 29 28

S7

17 16 15 14 13

S8 S9 S11

S10 S13

S12

S14 S15

S16 S17

S18 S19

S20 S21

S22 S23

S24 S25

S26 S27

S28 S29

S30 S31

S32 S33
8 7 6

12 11 10 9
3 2 1 0 1 2 3 6 7 8

S33
9 10 11 12 13

66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9

Segment Node No. 5090


5 4 3 2 1

7 6

Segment Node No. 5113

420

Def ormation at previous stage

Def ormation af ter completion of this stage : LC1191

Def ormation at handover f or traf f ic movement (Design Camber) @ T=0 : LC1298


370 320

270

220

170

120

70

20

-300

-294

-288

-282

-276

-270

-264

-258

-252

-246

-240

-234

-228

-222

-216

-210

-204

-198

-192

-186

-180

-174

-168

-162

-156

-150

-144

-138

-132

-126

-120

-114

-108

-102

-96

-90

-84

-78

-72

-66

-60

-54

-48

-42

-36

-30

-24

-18

-12

-6

-30

12

18

24

30

36

42

64

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

-80

42

Stage Deflections
Lift Stay Segment
27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 28

41 40 39 38 37 36 35 34 33 32 31 30 29

S8 S7 S9 S11

S10 S13

S12

S14 S15

S16 S17

S18 S19

S20 S21

S22 S23

S24 S25

S26 S27

S28 S29

S30 S31

S32 S33
8 7 6

12 11 10 9
3 2 1 0 1 2 3 6 7 8

S33
9 10 11 12 13

67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9

Segment Node No. 5090


5 4 3 2 1

7 6

Segment Node No. 5113

Deformation at previous stage

Deformation after completion of this stage : LC1192

Deformation at handover for traffic movement (Design Camber) @ T=0 : LC1298


370 320

420

270

220

170

120

70

20

-300

-294

-288

-282

-276

-270 -264

-258

-252

-246

-240

-234

-228

-222

-216

-210

-204

-198 -192

-186

-180

-174

-168

-162

-156

-150

-144

-138

-132 -126

-120

-114

-108

-102

-96

-90

-84

-78

-72

-66

-60

-54

-48

-42

-36

-30

-24

-18

-12

-6 -30 0

12

18

24

30

36

42

65

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

-80

Stage Deflections
Install Cable and stress to Fi
27 26 25 24 23 22 21 20 19

42 41 40 39 38 37 36 35 34 33 32 31 30 29 28

S6

18 17 16 15 14 13

S8 S7 S9 S11

S10 S13

S12

S14 S15

S16 S17

S18 S19

S20 S21

S22 S23

S24 S25

S26 S27

S28 S29

S30 S31

S32 S33
8 7 6

12 11 10 9
3 2 1 0 1 2 3 6 7 8

S33
9 10 11 12 13

67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9

Segment Node No. 5090


5 4 3 2 1

7 6

Segment Node No. 5113

Deformation at previous stage

Deformation after completion of this stage : LC1194

420 Deformation at handover for traffic movement (Design Camber) @ T=0 : LC1298 370 320 270 220 170 120 70 20

-300

-294

-288

-282

-276 -270

-264

-258

-252

-246

-240

-234

-228

-222

-216 -210

-204

-198

-192

-186

-180

-174

-168

-162 -156

-150

-144

-138

-132

-126

-120

-114

-108

-102

-96

-90

-84

-78

-72

-66

-60

-54

-48

-42

-36

-30

-24

-18

-12

-6 -30 0 -80

12

18

24

30

36

42

66

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

Erection Monitoring

67

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

P19 tower Pilecap

Tower Leg Construction in Progress

Isometric View of Piertable

Piertable Truss Erection

Pier table Truss Erection

Lifting Frame Operations

Lifting Frame Operations

Segment Transportation on Barge

Piertable Segment Lifting with Lifting Frame

Pier Table Segment Alignment

Segment Supported on Pier Table Truss

Pier Table Segments Alignment in Progress

Diaphragm Concreting

Isometric view of Middle Tower Legs

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

Construction of Middle Tower with ACS

P19 Middle tower leg in Progress

P19 Middle tower leg in Progress

P19 Middle tower leg in Progress

Strutting at Junction Top

Strutting at Junction Top

Assembly of tower head formwork prototype

Alignment of Anchorage Boxes at 100m above MSL

Construction of Tower Head

Erection of Deck

Erection of Deck

Erection of Parallel Wire Stay Cables

Erection of Parallel Wire Stay Cables

Erection of Parallel Wire Stay Cables

Erection of Precast Segmental Deck

Erection of Precast Segmental Deck

Erection of Precast Segmental Deck Deck Closure

Erection of Precast Segmental Deck

Erection of Precast Segmental Deck

Erection of Precast Segmental Deck

Completed View of Bandra CSB

Conclusions
Indian Engineers are Well Experienced in Construction of loang
Span Bridges, and Erection of Bridge Decks, using various methods

Choice of the method is Site Specific and Design Specific Bridge Design should Suit Erection Method

112

28 May 2012

Presetation to 3rd annual Bridges India Summit 2012

I acknowledge with Thanks opportunity given to me for presentation of a very important and interesting topic. I thank the organizers, and the audience.

Disclaimer

This presentation contains certain forward looking statements concerning future business prospects and profitability of HCC, which are subject to a number of risks and uncertainties and actual results could materially differ from those in such forward looking statements, important developments that could affect the company's operations include a downtrend in the infrastructure sector, significant changes in political and economic environment in India, tax laws, labor relations, litigation etc. The company does not undertake to make any announcement in case any of these forward looking statements become materially incorrect in future or update any forward looking statements made from time to time by or on behalf of the company.

Das könnte Ihnen auch gefallen