Beruflich Dokumente
Kultur Dokumente
Suhas P Khedkar (AVP- Engineering,) Hindustan Construction Company To 3rd Annual Bridges India Summit 2012 On 17th May 2012
2 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Table of Contents
Different Methods of erection of Superstructure Cast in Situ Construction Comparison of Conventional and Cantilever Construction Method Innovative Construction of III rd Godavari Railway Bridge at Rajamahendri Bandra Worli Sea Link Superstructure Construction entirely by Precast segmental Construction. Segment Casting and Erection of Appraoch Spans Specaial Challenge during Construction- Relocation of LG Construction of Cable stayed bridge Conclusions
28 May 2012
1. Conventional method for normal spans by use of staging 2. Using specialized technology for longer span bridges:
e.g.. Use of centering girders, and bridge builders for cantilevering superstructures
Construction using precast girders of entire length, Construction using precast segments to be assembled during erection to form girders of complete length
28 May 2012
2. Has been used for both I girders and Box Girders. 3. If number of spans are small , use of precast girders and launching
system is not cost effective
28 May 2012
Conventional casting on staging of long span superstructure is generally not feasible beyond about 50 m span due to
excessive weight, Large quantity of staging and increased cycle time and concrete pour size. Especially difficult for River Bridges as staging needs to be supported
on temporary piles.
28 May 2012
10
28 May 2012
Bridge over River Brahmaputra at Tezpur Compare the small Bridge Builder on the tip of the cantilever with the staging of Naini Bridge
12
28 May 2012
Tezpur Bridge over River Brahmaputra Different spans in different stages of construction
15 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
ViewMay 2012 28
17
28 May 2012
Innovative Features: 1. Top down Construction Arch was constructed first 2. Tie girder constructed using formwork supported on suspenders 3. Arch was constructed using cast in situ cantilevering segmental technique in 7 stages 4. Arches from the two piers progressed to meet at the midspan, connected by a closure pour
22
28 May 2012
Stages of Construction of Arch: 1. Erect central tower 2. Cast starting stubs 3. Erect formwork for typical segment supported by stay cables 4. Cast first segment 5. Repeat stages 3 and 4 for balance 6 segments 6. Erect formwork for closure pour on the last segment at crown 7. Cast closure pour
23 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
25 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
26 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Completed Bridge
30 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Bandra Worli Sea Link Project Superstructure Construction entirely by Precast Segmental Technique, for both Cable Stayed and Approach Spans.
32
28 May 2012
33
28 May 2012
34
28 May 2012
35
28 May 2012
BANDRA
WORLI
A1
R AD ND RO BA 6m CH ZA 54 OA LA P PR L L AP T O &
P6
P12
P17
A1
AP PR OA CH
BR IDG E
P19
600m BANDRA CABLE STAY 200m 350m WORLI CABLE STAY 1400m SOUTH APPROACH BRIDGE
36
28 May 2012
A
WORLI
38
28 May 2012
Construction of Superstructure in parallel with Foundation construction. When Foundations are being constructed at various site locations, superstructure elements can be precast in a separate casting facility. Advantages of factory production, with ease in quality control, and dimensional accuracy, due to easy acces, and dedictaed equipment, and survey stations. Good quality control due to planned facilities like proper curing arrangement, dedicated supervision. The above are relatively much difficult at actual site locations due to difficult access, great heights and different locations.
39
28 May 2012
Span is divided into a number of segments of full deck width The segments are match cast to attain the final geometry as of the erected span. Match casting and geometric control are of great importance as the bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers. Precision Survey in casting yard to attain desired geometry Precast Segmental Construction offers use of industrialized, repetitive construction procedures, which contribute to improved quality control as well as reduction in construction time .
40
28 May 2012
The bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers. The bridge has both vertical gradient, and Horizontal curvature. The bridge deck therefore follows a space curve.
41
28 May 2012
Precast Segmental Construction for Bandra Worli Sea Link Project, Mumbai CEMCON 2007
February, 23 - 2007
Page 42
(REBAR JIGS)
(CASTING CELL) (STORAGE BAY 1) TYPICAL CROSS SECTION AT CASTING CELL AND STORAGE AREA (TRANSVERSE DIRECTION)
(STORAGE BAY 2)
43
28 May 2012
Precasting Yard at BWSLP- Capacity to stack 400 segments. And 9 casting cells.
44
28 May 2012
45
28 May 2012
46
28 May 2012
6 1.66 CUM 5 1.26 CUM 3 1.26 CUM 2 3.17 CUM 1 5.33 CUM 2a 3.17 CUM 4 1.66 CUM 4a 1.66 CUM
47
28 May 2012
48
28 May 2012
49
28 May 2012
Center Leg
51
28 May 2012
Main Challenge During Construction of Approach Span: Relocation of LG from Bandra Approach spans beyond Bandra Cable Stayed bridge: Shifting by 500 m in the sea.
Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).
Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).
54
28 May 2012
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules
Text (Font Arial 16, Color Black, Line Spacing 30 points). Text (Font Arial 16, Color Black, Line Spacing 30 points).
55
28 May 2012
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules
56
28 May 2012
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane Asian Hercules
Entire LG weighing 1260 MT , of length 105 m was physically lifted and shifted from P17-P18 to P20-P21
57
28 May 2012
59
28 May 2012
Precamber Values
Fibre Stresses
Stay Cable Forces for Installation, Tensioning and fine tuning Forces
Stage Deformations
Temporary PT
60 28 May 2012 Presetation to 3rd annual Bridges India Summit 2012
Casting Curve
61
28 May 2012
-300
-275
-250
-225
-200
-175
-150
-125
-100
-75
-50
-25
Elevation y [mm]
25
50
75
100
125
150
175
200
225
250
275
Chainage x [m]
62
28 May 2012
300
Stage Deflections
Lift Non-stay Segment
28 27 26 25 24 23 22 21 20 19 18
42 41 40 39 38 37 36 35 34 33 32 31 30 29
S7
17 16 15 14 13
S8 S9 S11
S10 S13
S12
S14 S15
S16 S17
S18 S19
S20 S21
S22 S23
S24 S25
S26 S27
S28 S29
S30 S31
S32 S33
8 7 6
12 11 10 9
3 2 1 0 1 2 3 6 7 8
S33
9 10 11 12 13
66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9
7 6
420 Def ormation at handover f or traf f ic movement (Design Camber) @ T=0 : LC1298
370
320
270
220
170
120
70
20
-300
-294
-288
-282
-276
-270
-264
-258
-252
-246
-240
-234
-228
-222
-216
-210
-204
-198
-192
-186
-180
-174
-168
-162
-156
-150
-144
-138
-132
-126
-120
-114
-108
-102
-96
-90
-84
-78
-72
-66
-60
-54
-48
-42
-36
-30
-24
-18
-12
-6 -30
12
18
24
30
36
42
63
28 May 2012
-80
Stage Deflections
Stress Previous Cable to Ft
27 26 25 24 23 22 21 20 19 18
42 41 40 39 38 37 36 35 34 33 32 31 30 29 28
S7
17 16 15 14 13
S8 S9 S11
S10 S13
S12
S14 S15
S16 S17
S18 S19
S20 S21
S22 S23
S24 S25
S26 S27
S28 S29
S30 S31
S32 S33
8 7 6
12 11 10 9
3 2 1 0 1 2 3 6 7 8
S33
9 10 11 12 13
66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9
7 6
420
270
220
170
120
70
20
-300
-294
-288
-282
-276
-270
-264
-258
-252
-246
-240
-234
-228
-222
-216
-210
-204
-198
-192
-186
-180
-174
-168
-162
-156
-150
-144
-138
-132
-126
-120
-114
-108
-102
-96
-90
-84
-78
-72
-66
-60
-54
-48
-42
-36
-30
-24
-18
-12
-6
-30
12
18
24
30
36
42
64
28 May 2012
-80
42
Stage Deflections
Lift Stay Segment
27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 28
41 40 39 38 37 36 35 34 33 32 31 30 29
S8 S7 S9 S11
S10 S13
S12
S14 S15
S16 S17
S18 S19
S20 S21
S22 S23
S24 S25
S26 S27
S28 S29
S30 S31
S32 S33
8 7 6
12 11 10 9
3 2 1 0 1 2 3 6 7 8
S33
9 10 11 12 13
67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9
7 6
420
270
220
170
120
70
20
-300
-294
-288
-282
-276
-270 -264
-258
-252
-246
-240
-234
-228
-222
-216
-210
-204
-198 -192
-186
-180
-174
-168
-162
-156
-150
-144
-138
-132 -126
-120
-114
-108
-102
-96
-90
-84
-78
-72
-66
-60
-54
-48
-42
-36
-30
-24
-18
-12
-6 -30 0
12
18
24
30
36
42
65
28 May 2012
-80
Stage Deflections
Install Cable and stress to Fi
27 26 25 24 23 22 21 20 19
42 41 40 39 38 37 36 35 34 33 32 31 30 29 28
S6
18 17 16 15 14 13
S8 S7 S9 S11
S10 S13
S12
S14 S15
S16 S17
S18 S19
S20 S21
S22 S23
S24 S25
S26 S27
S28 S29
S30 S31
S32 S33
8 7 6
12 11 10 9
3 2 1 0 1 2 3 6 7 8
S33
9 10 11 12 13
67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9
7 6
420 Deformation at handover for traffic movement (Design Camber) @ T=0 : LC1298 370 320 270 220 170 120 70 20
-300
-294
-288
-282
-276 -270
-264
-258
-252
-246
-240
-234
-228
-222
-216 -210
-204
-198
-192
-186
-180
-174
-168
-162 -156
-150
-144
-138
-132
-126
-120
-114
-108
-102
-96
-90
-84
-78
-72
-66
-60
-54
-48
-42
-36
-30
-24
-18
-12
-6 -30 0 -80
12
18
24
30
36
42
66
28 May 2012
Erection Monitoring
67
28 May 2012
Diaphragm Concreting
Erection of Deck
Erection of Deck
Conclusions
Indian Engineers are Well Experienced in Construction of loang
Span Bridges, and Erection of Bridge Decks, using various methods
Choice of the method is Site Specific and Design Specific Bridge Design should Suit Erection Method
112
28 May 2012
I acknowledge with Thanks opportunity given to me for presentation of a very important and interesting topic. I thank the organizers, and the audience.
Disclaimer
This presentation contains certain forward looking statements concerning future business prospects and profitability of HCC, which are subject to a number of risks and uncertainties and actual results could materially differ from those in such forward looking statements, important developments that could affect the company's operations include a downtrend in the infrastructure sector, significant changes in political and economic environment in India, tax laws, labor relations, litigation etc. The company does not undertake to make any announcement in case any of these forward looking statements become materially incorrect in future or update any forward looking statements made from time to time by or on behalf of the company.