Beruflich Dokumente
Kultur Dokumente
Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
through the tunnel as they dig. They do not have built-in systems for reinforcing the tunnels they dig, relying on the structural integrity of the rock to support itself. 2. Shielded Hard Rock TBMs Shielded TBMs are designed for operation in hard rocks that are not stable or have a high degree of fracturing, making cave-ins likely. These single shield TBMs have a system of automated machines which place concrete segments on the tunnel wall as a reinforcing sheath as they dig. These machines cannot propel themselves like open TBMs; they can only push off from the concrete segments they lay as they go along. A special type of shielded TBM called a double shielded TBM is designed to work in either type of condition. These machines are used where engineers expect to encounter both stable and fractured rock during a tunnel project.
3. Soft Ground TBMs Soft ground TBMs are designed for tunneling through softer types of earth like clays, soft rocks like sandstone, and loose or very wet ground. Earth pressure balance TBMs use sophisticated controls to maintain a balance between forward motion and excavated material to keep the tunnel stable. Soil stabilizers are often injected into the surrounding soil or soft rock to help keep it stable. Slurry shield TBMs operate in soils or rocks that are exceedingly wet, or even saturated. Some of these machines are completely airtight, and use a slurry and pump system to remove excavated material. Both types of soft ground TBMs are shielded; they lay a sheath of concrete segments as they go.
4. Raise and Shaft Boring Raise and shaft boring TBMs are used for tunneling vertically; these machines dig ventilation shafts, access shafts, and maintenance shafts as well as traditional mine shafts and drainage tunnels. These machines are designed in much the same way as other TBMs, but are made to tunnel vertically instead of horizontally or nearly so.
And form Herrenknecht AG (the world market leader in mechanized tunneling), there are a lot of type of tunnel boring machine, divided from their purpose Soft Ground EPB TBM Soft Ground Mixshield TBM Hard Rock Gripper TBM
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Hard Rock Single Shield TBM Hard Rock Double Shield TBM Hybrid Convertible TBM Pipe Jacking / Microtunnelling TBM Horizontal Directional Drilling (HDD) rigs Vertical Shaft Sinking Machines
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
2. Cutter motor sensor There are various types of geological conditions such as weathered rock, sand, clay and residual soils. The cutter-motor sensor determines proper operation in order to excavate, as well as a guide whether cutter pressure or excavation speed should be increased or reduced. It all depends on this cutter-motor sensor.
3. Screw conveyor sensor The excavated soil is conveyed from the chamber to the screw conveyer. To maintain the ideal face pressure the revolution speed of the screw-conveyor and hydraulic oil pressure is adjusted during excavation. In addition, the screw-conveyor discharge gate opening hydraulic pressure and ratio are also monitored.
4. Shield jack sensor The TBM uses jacks to push against installed segments to move the TBM forward. The condition of the earth being excavated can be judged from the total thrust of these shield jacks. Also, it is the most important part in controlling the direction of the TBM machine. Based on the alignment design, suitable jacks shall be used. The stroke of the
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
jack influences the excavation length. Thus the excavation speed is controlled by the speed of the jack stroke. These sensors are very important to manage the TBM excavation, but all depends on various ground conditions and water levels. Therefore information gathered from these sensors will be studied and decided for the following excavation parameters.
Water level sensor. The measurement unit is connected to the control unit with a hose. The control unit is connected with hose drums and this hose drum and standard units are connected to these drums. The hoses extend automatically as the excavation distance increases. The measurement unit is set up inside the TBM, and the control unit and hose drums are set up in the backup car. It is then fitted to a standard unit on the segment behind the backup car. Water is filled in these hoses and the water level difference between the measurement unit and a standard unit is measured and thus vertical control of TBM machine is observed. This is done for every 1m excavation. Concurrently, 1m of the hose will be extended. It is possible to excavate along an incline if the excavation control is adjusted according to an increase in water level in the valve of 1mm, which means that once excavation has been carried out over 1m the TBM will have traveled up 0.1%. This information will be observed by the TBM operator and he will guide the TBM to its correct position and alignment.
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
(Step 3 of 4) Set up a survey control network, the new stations were rigidly tied to the known stations. All field measurements were to meet the following acceptance criterias before computation was performed.
(Step 4 of 4) Carried out field measurements of angle and distance among the stations followed by computation of global coordinates of control stations. All field measurements were to meet the following acceptance criterias before computation was performed.
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Construction Stage
(Step 1 of 5) Prior to the initial drive of TBM, secondary control station was established at the TBM Launching Shaft at surface by transferring co-ordinates from the primary control stations.
(Step 2 of 5) Transferred the secondary control station from surface at the TBM Launching Shaft to the tunnel control station at underground level
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
(Step 3 of 5) Moved up the tunnel control station by Double Zigzag Traverse behind the TBM as the machine travelled ahead, and transferred a temporary station to the shoulder position of the erected ring at the back-up gantry of the TBM
(Step 4 of 5) Traversed the temporary control stations at the erected rings above the TBM back up gantry to reach the Laser Station located about 30m behind the TBM.
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
(Step 5 of 5) The Laser Station carried the coordinates from the control station shot the prism target affixed to the bulkhead of TBM to determine the absolute spatial coordinates (x,y,z) of the TBM at that point. The tunnel guidance system and the dual axial inclinometers simultaneousely measured the amount of rotation along the three perpendicular axis of the TBM to determine the orientation of the heading of the machine.
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung
Vibrating rollers, used to compact the road fill, approx 15% of the tunnel is backfilled to give a flat road surface, the roller works approx 200m behind the TBM cutter head.
Siti H. Fauziah D4 Teknik Perawatan dan Perbaikan Gedung Teknik Sipil Politeknik Negeri Bandung