Beruflich Dokumente
Kultur Dokumente
Roussos Dimitrakopoulos
Canada Research Chair in Sustainable Mineral Resource Development and Optimization under Uncertainty
Overview
The economic side of uncertainty Models of geological uncertainly Limits of traditional mine design optimization Shifting the paradigm: Stochastic mine planning Using uncertainty to improve project performance Conclusions - Uncertainty is great!
Reserve
-100
NPV, $MM
600
Alternative development plans may have different risk profiles and expected values. Example:
Design - cant capture high reserves Design can capture
-100
NPV, $MM
600
-100
NPV, $MM
600
60% of mines had an average rate of production LESS THAN 70% of planned rate In the first year after start up, 70% of mills or concentrators had an average rate of production LESS THAN 70% of design capacity Key contributor to mining risk felt in all downstream phases: Geology and reserves
Real Options View: Current Value of Option to Produce Contingent Decision Payoff Function (future price known)
$0
No production NPV = 0 Production NPV > 0
$-
Probability
Reserves
Reserves
The goal of technical evaluation should be to strive for an accurate assessment of uncertainty, not a single precise answer
Traditional view
Reserves
Probability
Probability
Reserves
Model characteristics: o Large number of blocks o Multiple domains o Resource classes with specific sample selection criteria
A gold load
Multiple simulations
Pit Limit
Pit Shells
7 5 3 1 0 -1 -3 -5 0 2
10
12
14
100% probability of falling within the pit for a given metal price Pit limit determined conventionally
DCF
Upside
Min acceptable return
Downside Value
1 2
Pit design
Upside or D ow nside =
CB-2 2.41
CB-3 1.8
1.3
4
2.1
1.6
-0.78
-0.15
-0.51
2.4
6
2.43
1.9
0.0
-0.022
-0.28
2.9
12
2.40
1.2
0.0
-0.16
-0.96
Re-writing optimizers
c1
c2 c4
c3
Period 1
c1x1p+c2x2p+. bp
Period p
s11x1p+s21x2p+.
b1
Ore Production
Mt Mt Mt Mt
13.9% 13.5% 8.7% 18.2% 12.7% 12.4% 12.5%
Avrg. Deviation Target Ore Production Maximum Ore Expected Ore Minimum Ore
10.8% 11.4% 12.4% 10.4% 12.3% 9.0% 14.5% 11.9%
Mt Mt 1 2
10% 0%
10
11
12
13
14
15
16
17
Period
3.5%
0%
Period
Ore Production
Year
Max [ E{(NPV) } b
t =1
U
i =1
t i
t i
Part 1
- E{(NPV) + MC } s
i =1 M t i
t t i * i
Part 2
Stockpile input
Part 3
+ (SV) (P) q
s =1 t s
t s
Stockpile output
Part 4
ty ty - (c d su + clty d sl )] s =1 ty u
Risk management
2 4
Orebody Model 2
Deviation R
Ore Grade R Metal
Orebody Model R
- TARGET [ ]
Periods 1 2 3 4 5 6
2.5
22
1.5
11
0.5
00
0 1 1 2 2 3 3 4
Periods Ct=Ct-1 * RDFt-1 RDF risk discounting factor RDFt=1/(1+r)t r orebody risk discount rate
Orebody risk discounting rate Cost of shortage in ore production Cost of excess ore production Cost of shortage in metal production Cost of excess metal production Number of simulated orebody models
- 16 - 12 -8 -4 0 1 2 3 4 5 6
Periods
Stockpiles Profile
6 Tonnes (million) 4 2 0 1 5 Tonnes (million) 4 3 2 1 0 1 2 3 4 5 6 Periods 2 3 4 5 6
Difference = 17%
Some conclusions
. uncertainty is (not) a problem and should be avoided ? you can take advantage of uncertainty. .uncertainty will create opportunities and value.
once your way of thinking explicitly includes uncertainty, the whole decision-making framework changes. We need: Stochastic mine planning and NEW mathematical models
And
It is all about good people: Education and training in a long term sense