Beruflich Dokumente
Kultur Dokumente
PERT analysis
PERT analysis
Expected time calculated from 3 estimates for the duration of each activity
PERT analysis
Based on distribution, the expected time te
is calculated as: te = [o + 4m + p] / 6
Expected time te is 5, longer than the most likely time This could change the critical path in the network diagram
5
PERT analysis
try out the tasks past exam questions
Gantt charts
Devised by Henry Gantt (early 1900s) Block representation of tasks Length of task bar proportional to duration Each start/end time represented by task bar Graphical representation of project Can translate network diagram into Gantt chart Easy to read
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Can set questions while requesting and reviewing papers Might not need two full weeks
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Might not have to start this task straight away Might want to delay while doing other things
10
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
Gantt charts
week 6 week 7 week 8
Time line: Activities: Request Jones paper Request Smith paper week 10 week 1 week 2 week 3 week 4 week 5 week 9
review Smith paper Interview subjects set q's for questionnaire issue questionnaire Analyse data from q'naire have report proof read Write report Submit report
16
Gantt charts
In their basic form Gantt charts:
Do not explicitly show logical dependencies Do not optimise resources and costs Do not display current progress
W T
12 Mar '00 S S M T W T
19 Mar '00 S S M T W T
AB AB[50% ],CD[50% ] EF
Gantt charts
In more advanced forms Gantt charts:
Soon become cluttered
Gantt charts
try out the tasks including past exam papers
20
Resource histogram
Identifies resource requirements over time
Helps to identify peak resource requirements Helps to identify unnecessary peaks and troughs (resource smoothing: keep within limits) Commonly used to analyse staff resource levels
21
Resource histogram
20 18 16 14 12 10 8 6 4 2 0 1 2 3 4 5 6 7 8 9 10 Week number
Staff required
22
Resource histogram
upper limit of staff resources
23
Resource histogram
upper limit of staff resources
24
Staff resources
try out the tasks including past exam papers
25
As risks could prevent the achievement of objectives, plans for achieving objectives must be in place before risks can be considered
26
Risk revisited
Identify:
What are the potential risks?
Assess:
What is the impact of each risk? What is the likelihood of the risk occurring? How can the risk be prevented or identified early? What needs to be done if the risk does occur?
Allocate:
To whom can I assign the risk?
27
Containment
A new MS Access/Visual Basic system for a retail company Duration:
requirements capture: 2 weeks development: 8 weeks acceptance testing: 2 weeks
28
Sequence of Activities
Requirements
Development
Acceptance
Capture
2 Weeks
8 Weeks
2 Weeks
90% Acceptance
Containment Calculation
Expected value of additional duration = 0.9 * 2 = 1.8 weeks This evaluates the 90% chance of a 2 week delay Expected value of additional effort = 0.9 * 7 = 6.3 person-weeks This evaluates the 90% chance of a further 7 person-weeks This calculation is without a containment action
32
Containment
A 3-week training course in parallel (i.e. 1 extra week) with the requirements capture would reduce the risk to 25% with an additional 2 person-weeks effort Draw a diagram to show the containment action and recalculate the revised impact on effort and duration
33
Course
Containment Calculation
Expected value of additional duration = 1 + (0.25 * 2) = 1.5 weeks This evaluates the extra week on the course, plus the reduced risk of 25% of a 2 week delay Expected value of additional effort = 2 + (0.25 * 7) = 3.75 person-weeks This evaluates extra 2 person-weeks on the course, plus the reduced risk of 25% of a further 7 person-weeks This calculation includes a containment action
35 35
36 36
Risk analysis
try out the tasks - including past exam papers
37 37
38
Further reading
Bentley C (1997) PRINCE 2: A Practical Handbook Oxford: Butterworth-Heinemann Brooks F. (1995) The Mythical Man-Month (Anniversary Edition), Harlow: Addison-Wesley Burke R (1999). Project Management: Planning and Control Techniques, Chichester: Wiley Central Computer & Telecommunications Agency (1997) PRINCE 2: An Outline, London: The Stationery Office Field M & Keller L (1998) Project Management, Oxford: International Thomson Business Press
39