Beruflich Dokumente
Kultur Dokumente
Outline
Background
- Why the interest in Mars? - Mars missions under Faster, Better, Cheaper (FBC) approach. - Account of the Mars Climate Orbiter (MCO) failure.
Conclusions Questions
Why Mars?
MISSION STATISTICS
Lockheed Martin Astronautic was the main contractor and the Jet Propulsion Laboratory was the administrator of all these missions. Total cost of the Mars missions under FBC of $921.6 Millions. Under FBC 3 out off 6 Mars missions failed.
MCO Launch
At Cape Canaveral, FL on December 11th, 1998 Delta II Lite Launch Vehicle Launch sequence lasted 42 minutes Hoffman transfer to Mars Earth-Mars launch window considered every 2 years
MCO Cruise
416 million miles over 9 months 4 Trajectory Correction Maneuvers Anomalies in trajectory caught but dismissed
Planned trajectory
Installed both in ground & spacecraft Wrong unit in log file Trajectory modeling from file Corrections issued based on this modeling Thrusters fired 4.45 times shorter
Critical Altitude
Training
The Incident, Surprise, Anomaly (ISA) procedure. The ground software development process. The Mission Operations Software Interface Specification (SIS). The MCO attitude control system and related subsystem parameters. The Trajectory Correction Maneuver (TCM) -5.
Staffing
The Mars Surveyor Operations Project (MSOP) was running 3 missions simultaneously (MGS, MCO, MPL).
The absence of a mission assurance manager. Absence of mission science personnel in the management process.
Lessons Learned
The team should be provided with proper training and detailed information regarding systems which may have a high impact on the well behavioral of the project. The project manager should identify or provide backup personnel that could be available to serve in some of the critical roles when needed. The human resource department should provide a staff with well defined roles and responsibilities.
Communication Management
Report Performance
Distribute Information
Plan Communications
Identify Stakeholders
Communications Management
THE PROBLEM START IN FBC
Communications Management
Interfaces and Relationships
Communications Management
NASA- JPL RELATIONSHIP
Communications Management
NASA- JPL RELATIONSHIP
Absence of a single interface resulted in multiple inputs to the JPL Mars Program
Input 1 Input 3 Input 2 Input 1 Input 2 Input 3
Communications Management
JPL-LMA RELATIONSHIP
RISK
Communications Management
COMMUNICATION BARRIERS
Communications Management
LESSONS LEARNED
Senior management must be receptive to communications of problems and risks. A dedicated single interface at NASA Headquarters for the Mars Program is essential.
Contractor responsibilities must include formal notification to the customer of project risk and deviations.
Increase the amount of formal and informal face-to-face communications with all team elements and especially for those elements that have critical interfaces.
Quality Management
Plan Quality
Identification
Review
Solve
Lessons Learned
Risk Management
Identify Risk
Its comprised of six sequential processes: Plan Risk Management, Identify Risks, Perform Qualitative Risks Analysis, Perform Quantitative Risks Analysis, Plan Risk Responses and Monitor and Control Risks.
Starts at initiation and finish with project closure. Its iterative, ones planned, should be reassessed and control. Could impact costs, schedule, scope, quality, customers satisfaction and stakeholders interests. When its integrated in a project prevents unnecessary threats and promote wanted opportunities.
Unmitigated risks has an owner with a clear contingency plan, launch depending on risk triggers.
Project managers put more emphasis on lower cost and schedule, and more ambitious scope, while risks increase was not considered.
No proper procedure to implement TCM-5 as an emergency plan.
Lessons Learned
Risks caused by deviation from project management principle shouldnt be allow. All team members should know what is acceptable risks.
All mission should perform the six processes of risk management. In all project meetings and reviews risks mitigation plan should be reported and reassessed.
Scope
Success
Time
Risk
CONCLUSIONS
"Faster, better, cheaper" missions place too much emphasis on cost and schedule reduction and too little on management, oversight, leadership and evaluating risk. Key positions in the staff and well trained personnel are critical points that any PM must not sacrifice because of reducing cost strategies. A routine forum should be established for informal communication between all team members at the same time so everyone can hear what is happening. The absence of a sound Risk Management Plan prevented that the mission could overcome any important threat, reducing significantly its chances for success. A comprehensive contingency plan to execute TCM-5 could have increased the probability of success of the mission.
QUESTIONS
THANK YOU !!