Date: 15th Oct.

2012 Marafiq STG-5 & 6 Project Electrical Department Turn-over Notes (Narrative) A) Erection of 380kV GIS

Pending work is the approval by T & D of the Method Statement for 380 KV GIS Bus Stability and Sensitivity Tests. The latest update was that, I sent an e-mail addressed to Mr. Dawoud of Marafiq on 30th Oct. 2012 with the attached revised M/S (Revision-1) for second pass review and /or approval. Up to this writing, no response yet received from them (T & D). Please note that without the completion of this task, other works for the 380kV will not proceed to include the establishment of control communication and status signals between the GIS and LDC and associated works during the N- and S outages. Consequently, the ultimate tie-in of the new GIS to the existing with the installation of Bus Adapters will not push through as scheduled.

Lighting installation inside the Box Culvert is not yet done. Request Hanwha to submit approved layout drawing for review; and subsequently proceed to installation should there be no comment. Access Door located at the north side of Building 21 is now obstructed by the installation of IPBs members and structural supports of the new 380kV GIS erection. The Access Door steps shall be re-furbished to a new direction to avoid the obstruction of the same. (Note: This is a civil work refer it to Civil Discipline) Erection of 115KV GIS Earlier, with the switching of the GIS breakers and associated On-line Disconnect Switches and Earth Switch only proved that work for the same was completed prior to the powering up of Start-up Transformer No. 5. However, with my latest intimation with Hanwhas Mr. Ju-young Lee, he was informed by LDC that they are not getting status signals of the Line Disconnect Switches and Earth Switches; hence, inhibiting the switching of the breaker to energize Start-up Transformer No. 6.

B)

C)

Start-up Transformer A Comment Tracker for FAT and SAT Reports for transformers was forwarded by myself (P. Zandueta) to Marafiq Mr. Aresteo Olaybar via email on 11th Oct, 2012, awaiting for approval.
Page 1 of 2

As of 14th Oct. 2012, an e-mail received from Ju-young Lee disclosed that Mr. Aristeo had already responded on the Comment Tracker which subsequently forwarded to Mr. Dawoud. Follow-up shall be made for this issue for immediate closure.

Note: Approval of the Comment Tracker for FAT and SAT reports for Transformers wherein Start-up Transformer No.6 is included; and completion of the verification and restoration of the open and closed status of Line Disconnect Switches and Earth Switches of 115kV GIS at LDC will conclude when the Start-up Transformers will be energized. D) STG 5 & 6

Some bits and pieces of work still to be done for STG-5 & 6 as follows: Cathodic protection for STG 5 & 6 Lighting Fixture installation inside AVR Room, STG-6, Mezzanine Floor Installation of additional lighting fixture in STG-5 & 6. CT and PT testing for LV MCCs Laying of cable and testing for FGD Lighting Fixture inspection for Aeration Fan Area Inspection for Lightning System for STG-5 & 6 Inspection for Lightning System for CPP Motor Run Test

1) 2) 3) 4) 5) 6) 7) 8)
E)

One motor run test will be conducted at DM Plant 9) 9 motor run test will be conducted at CPP. Note: Each of the above listed tasks will be done with an RFI provided by Hanwha QA/QC Dept.

Prepared by: P. Zandueta