Live Well Completions

Hydraulic Workover Units (HWO)

TOPICS for DISCUSSION

Live Well Completions Applications Mechanics of Hydraulic Workover M h i f H d li W k Stripping Procedures Engineering and Well Planning HWO Live Well Completions Case Histories p

Live Well Completion Applications with HWO p pp


Live Completion/Re-completion in Sensitive F i S iti Formations ti Especially gas wells where conventional methods result in loss of production l f d ti Running / Pulling Tubing, Drill Pipe, or Casing Under Pressure Conventional Live Well Completions Horizontal Live Well Completions

Mechanics of Hydraulic Workover


The Rotary and Traveling Slips can work simultaneously. y Cudds Hydraulic Rig Assist Unit has a passive rotary - requires PDM or power swivel for rotational requirements i t

Mechanics of Hydraulic Workover


Stationary and Traveling Slips are both engaged at beginning of snubbing stroke.

Mechanics of Hydraulic Workover


Stationary Slips are disengaged With Traveling Slips engaged, the hydraulic cylinders are extended retracted - lowering the tubing - and completing the stroke.

Mechanics of Hydraulic Workover


At completion of downward stroke, the stationary slips are engaged engaged. The Traveling Slips are disengaged, then the hydraulic cylinders are extended to make the next stroke.

Mechanics of Hydraulic Workover


Process is repeated as the tubing is snubbed through the BOP Stripper rams or annular

Ram to Ram HWO Procedures


STEP1: With tree valve open, BHA is lowered through snubbing stack All BOP rams are open. PV#1, PV#4, PV#7, PV#8 are closed

BOP #2 Stripper rams are closed around tubing above BHA

Tubing is snubbed until tool joint/connection is between BOP #1 rams and BOP#2 rams

Ram to Ram HWO Procedures


STEP 2: Close BOP#1 stripper rams STEP 3: Open Hydraulic PV#1 STEP 4: Allow pressure under BOP #2 stripper rams to equalize below BOP#1 stripper rams

10

Ram to Ram HWO Procedures


STEP 5:Open BOP#2 stripper rams pp STEP 6: Snub tubing into the well bore until tool joint/ connection is below BOP #2 stripper rams STEP 7: Close PV#1

11

Ram to Ram HWO Procedures


STEP 8:Close BOP#2 stripper rams pp STEP 9: Open PV#4 and allow pressure between Bop#1 ans BOP#2 stripper rams to bleed off STEP 10: Allow pressure to bleed to -0- between stripper rams

12

Ram to Ram HWO Procedures


STEP 11:Open BOP#1 stripper rams STEP 12: Close PV#4 STEP 13: Again, tubing is snubbed until joint/ connection is between BOP#1 and BOP#2 stripper rams REPEAT THE PROCESS

13

ENGINEERING

14

Engineering Calculations For HWO/Snubbing Applications


Collapse / Burst calculations for tubing - based on anticipated compression, tension, and torsional loads Critical Buckling Load Limitations - calculations based on comprehensive list of factors Required Snubbing Force q g Required Hydraulic Snub / Lift Pressure - Jack Forces Well Control considerations Unit stability (wind loading analysis) Applied loads to wellhead Torque & Drag

15

Engineering Calculations For Snubbing Applications

Critical Buckling

16

Engineering Calculations For Snubbing Applications

Combined Stresses

17

HWO Live Well Completions Case Histories

18

Case History #1 - Onshore ESP Workover Campaign


Completed 8 wells ESP Change-Out p g Average Well Depth: 3415m (11,205 ft) Tubing Sizes: 3 1/2 & 4 1/2 Average Rig Up time: 10.5 hrs g g p Average POOH time: 25.1 hrs (446 ft/hr) Average RIH time: 21.2 hrs (529 ft /hr) Average RD time: 7.8 hrs

19

Case History #2 Live Well Completion y p


Type Job: Date: Location: Unit Type: Pressure: Tubing: Well Depth: Duration: Trip Speed: Live well completion 13 Jan., 2003 South Texas 150K Quick Jack 20.7 MPa (3000 psi ) (well flowing) 2-3/8 4.7# P-110 8RD-MOD 4,977 (16,330 ) 4 977 m (16 330) 2 days (daylight) 579 m/hour (1,900 foot/hour)

Description: MU 3-3/4 Mill, Hyd-disconnect, 1jt. Tbg. & 1.875 X-Nipple. TIH live, to top of CIBP @ 15,190, mill up plug and wash down to PBTD @ 16,330. Drop 1-1/4 ball, pressure up tbg. w/ N2 & disconnect mill. POOH to 12,570. Space out and MU extended neck hanger so that when hanger lands, BOT is @ approx. 12,570. ND snubbing unit and BOPs. BOP
20

Case History #3 High Pressure S ubb g sto y g essu e Snubbing


Type Job: Date: Location: Unit Type: Pressure: Workstring: Well Depth: Duration: Trip Speed: Washout 3-1/2 Production Tubing, H2S April - May, 2002 GOM 150K Jack 90 MPa (13,100 PSI ) 1-1/4 CS. Hydril tubing 7,003 m (22,978 ) 17 days (8 days snubbing) 122 to 304m/hr (400 to 1,000 ft/hr)

Description: Repair Xmas Tree, R/U BOPs & Unit, Test, MU Mill, BPVs, Nipple on 1-1/4 workstring. TIH to bridge at 2,472, wash & mill to 4,800, circ out. TIH to 10,100, tag bridge, wash & mill to 10,200 circ out . Bullhead into well POOH Run W/L gauge. Cmt perfs. Perforate new zone. 10 200 well. POOH. gauge perfs zone R/D snubbing unit and BOPs, turn well over to production.
21

Case History #3 High Pressure Snubbing


150K Snubbing Jack

p17

Stand Pipe

e1 e2

e-2 e-1
Equalizing Pump Bleed Off Pump Line ( routed to GBor safe area)
e3 e4

p9 p10
Pump Bleed Off (routed to GBor safe area)

1)p-1,p-3,p-9,p-7 1) 1 3 9 7 CUDD 2)p-4,p-2,p-8,p-10 3)p-16 Circulation Drawing for 4)p-15 High Pressure H2S Wash Out 5)p-6,p-5,p-11 6)p-12,p-13,p-14 Operation # 3 Well Mobile 903 7)Remove check k-3,#5 Blind ram,c-2,c-3, Rental crown valve, 26 April; 2002 8) #5 Blind ram,c-1,c-5,c-4,Rental Master ) 9) P/U 1-1/4''tbg.,#9 1-1/4'' safety,p-17 circdrawing.dsf 10) #8 1-1/4'' safety No scale 11) #4 1-1/4''safety,c-6,k-1 12) #2 1-1/4 stripper,e-4,e-5,c-7,c-22,c-21 15) #2 1-1/4''stripper,e-2,c-18,c-10 c-24,k-2 16) #1 1-1/4''stripper,b-1,c-11,c-12,c-17,c-16 13) M/U check k-3,#2 1-1/4'' stripper,e-3,e-6, 17) #1 1-1/4''stripper,b-2,c-13,c-15,c-14 c-20,c-8,c-23,c-25 18) hydril,d-1,note 10m, L/D 1-1/4''tbg. 14) #2 1-1/4'' stripper,e-1,c-18,c-9 19) P/U 1-1/2''tbg.,#7 1-1/2'' safety ram Diverter line to rig manifold or flare stack 20) kill line,stabbing valve(t.i.w.),b.p.v. line stabbing valve(t i w ) b p v d-1 d1 21) 1-13/16''20m csg. valve 22) 2'' 1502 stabbing valve b-1 b-2 23) 2'' 1502 stabbing valve #1 1 1/4 stripper ram 24) 1-1/4'' b.p.v. 25) 1-1/4'' b.p.v. e5 e6 #2 1 1/4 stripper ram Bleed Off Line to rig manifold or flare stack #3 1 1/4 slip ram choke manifold 15m
Choke #4 1 1/4 safety ram Line c-6

c-9 c-8

c-10

c-11

p7p8

Choke Line

Mud Pump #2 , 6'x14', 24k Mud M Pump #1 6'x14', 24k

p6 p-15 Fastorq Check Valve test unit p-16 p12 p11


Check Valve p5

c-1

c-2

c-3

c-5

#5 blind ram

3-1/16''20mx2-1/16''15m c-7 c7 spool to manifold


c-4
Glycol Injection

Choke Manifold c-22 c-23

c-12 c-13 c-14 14 c-15 c-16

Mud/Gas Separator

#6

sh ea r ram

p1

p-2

p13 p14

k-1k-2

#7 1 1/2 safety ram

c-21 c-20 c-19

k-3

Transducer c-24 c-25

#8 1 1/4 safety ram


Kill Line

p3 p4 15M Pump p Manifold Pump Bleed Off ( routed to GB or safe area)

#91 1/4 safety ram

c-18

c-17

125 bbl Mud Tank

22

Case History #3 High Pressure Snubbing


CUDD R/U Drawing for High Pressure H2S Wash Out Operation # 3 Well Mobile 903
26,April : 2002 RU drawing H2S. No scale
150K Snubbing Jack
240"

4-1/16"15m X 3-1/16''20mBOP Stack 2-9/16''I.D.X4''O.D.Guide to Bottom of Jack and Top of Hydrill 4-1/16''15mX4-1/16''10m Adapter Spool 4-1/16''10mX4-1/16''10m Swivel Spool 4-1/16''10m Hydril 4-1/16''10x4-1/16''15m D.S.A. 4-1/16''15m Diverted Line 4-1/16''15m Helical Adapter W/2-9/16'' Guide to Top of # 1- Stripper # 1-1-1/4''Stripper Ram 4-1/16''15m 4-1/16''15mSpool w/ 2-9/16''I.D. # 2 1 1/4''Stripper Ram 4 1/16''15m 2-1-1/4 Stripper 4-1/16 15m
2'';1502

Elevation = 1188" (Approx. 99')

12'' 53'' 25.25'' 6.0'' 17.75'' 6.25'' 29.25'' 24'' 29.25 29 25'' 29.25'' 11'' 32'' 32'' 16''
2'';1502 2'';1502 10m

Elevation= 751'' (Approx:62.58 (Approx:62 58' above rig floor)

2'';1502 10m

# 3-1-1/4''Slip Ram 4-1/16''15m 4-1/16''15mX3-1/16''20m D.S.A


Choke Line
2'';2202

Choke Line
2'';2202

# 4-1-1/4''Safety Ram 3-1/16''20m # 5-Blind Ram 3-1/16''20m Flow Cross


3-1/16''20mX2-1/16''15m

32'' 32'' 32'' 32'' 12'' 432'' 26.5'' 26.5''

2'';1502

# 6-Shear Ram 3-1/16''20m # 7-1-1/2''Safety Ram 3-1/16''20m

Kill Line
2'';1502

# 8-1-1/4'' Safety 3-1/16''20m # 9 1 1/4''S f t 3-1/16''20m 9-1-1/4''Safety 3 1/16''20 3-1/16''20mX2-9/16''20m D.S.A

Rig floor

Rig floor

Spool 2-9/16''20m 33' 2-9/16'' 20m Crown Valve 2-9/16'' 20m Master Valve

23

Case History #4 Gas Storage Well: 4-1/2 Tubing Changeout


Type Job: Pull 4-1/2 Injection Casing and Set Plug (rig ( i an replacement string) l t ti ) Date: April, 1994 Location: Wyoming, USA Unit Type: yp 170K Hydraulic Rig Assist Jack Unit y g Well Press: 12 to 15 MPa (1,800 to 2,200 psi ) Workstring: 4-1/2 Casing Well Depth: 2,743 m (9,000 ) (approximately) Duration: 1-1/2 1 1/2 Days per well (snub phase only) only). (3 Well Campaign) Description: Preset plug in 4-1/2 and rigup workover rig, Remove down p p g g p g Xmas Tree, install rig BOPs, R/U Snub Unit, Test, Snub out 4-1/2 Casing and lay down, Rig Down Snub Unit, Run W/L plug and set in tail pipe, Run new 41/2 Injection Casing w/seal assy on Rig.

24

Case History #5 JI #1 Gas Storage Well: Pull 5-1/2 Tubing P ll 5 1/2 T bi


Type Job: Date: D Location: Unit Type: Well Press: Workstring: Well Depth: Duration: Pull 5-1/2 Injection Casing April, A il 2002 Mississippi, USA 340K Hydraulic Standalone Jack Unit 9 MPa (1,300 psi ) 5-1/2 Casing 2,743 m (6,000 ) (approximately) 4 Days (10 wells total)

Description: Preset plug in 5-1/2, Remove Xmas Tree, R/U Snub Unit & BOPs, T t S b t 5 1/2 Casing d lay down, Ri D BOP Test, Snub out 5-1/2 C i and l d Rig Down S b U it Snub Unit

25

Case History #5 Gas Storage Well

26

Case History #5 Gas Storage Well

27

Gas Storage Wells Typical Uses of S bbi T i lU f Snubbing Snub out injection/wash strings (up to 7) p g g Remove and replace Tubing/Casing/Packer Reposition tubing/casing within cavern ( g g) Washout Obstructions (through tubing)

28

Case History #6 Live Well Completion


Type Job: Date: Location: Unit Type: Well Press: Tubing: Well Depth: Duration: Trip Speed: Live well completion 27 March., 2005 Qui 101 Burlington Resources China 225K 35.8 MPa (5200psi) shut in; 10.3 MPa (1500psi) well flowing) 2 3/8 4.7# P 110 2-3/8 4 7# P-110 8RD 3250 m (10,662) 4 days (daylight) 377 m/hour (1240 foot/hour) 225K Rack Jack

Description:

MU 4-1/2 Mill, Pump through-Pump off Bit Sub, 1jt. Tbg. & 1.875 XNipple. TIH live, to 3150 m tag sand and clean out with water and well gas to 10 meters below perfs @ 3250 m. Pull up to 3140 m (10 meters above perfs). Make up and land t bi h f ) M k d l d tubing hanger. Ri d Rig down snubbing unit and bbi it d BOPs, Nipple up production tree. Drop 7/8 ball in tubing and pressure up with water to release bit. Turn well over to production.

29

Case History #7 Live Well Completion


Type Job: Date: Location: Unit Type: Pressure: Tubing: Well Depth: Duration: Description:
Make up 4-1/2 Blade bit, bit sub, 1 joint, 2 BPVs, 1 joint and 2.313 X-nipple. Snub in hole with well flowing at 3 to 4 MPa. Tag top of sand @ 3116 m, clean out using well gas and water to top of bridge plug @ 3244 m. Mill out Bridge plug at 3244 m and clean to PBTD, depth of 3310 m. Snub and Strip out of hole racking back tubing. p g g Snub and strip in with composite bridge plug and set manually @ 3196 m. Bleed well to 0 psi and test Casing and plug to 62 MPa, 9000 psi. Strip out of hole laying down tubing. Rig down snubbing unit and BOPs. Well is ready to perforate and frac frac. 30

Live well clean out and drill out bridge plug 10 March, 2005 Jiao 61-1B Burlington Resources China 225K 41.7 MPa (6000 psi) shut in; 3.4 MPa (500 psi) well flowing 2-7/8 6.5# P-110 8RD 3310 m (10859) 6 days (daylight)