Sie sind auf Seite 1von 123

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL &

HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DEWATERING DURING CONSTRUCTION

VOLUME: IV PART: 3 SECTION: B1 SHEET 1 OF 3

Doc. No TCE.5270A-H-112-601

1.0 1.1

SCOPE OF WORK Contractor shall provide all labour, material and equipment necessary to design, build, operate, maintain and remove the temporary dewatering facilities for protecting Works under construction against river flood and creeks. He shall design, build, install, operate, maintain and dismantle the temporary dewatering facilities and remove the service or ground water seepage and natural surface flow from surface working areas as well as from underground. He shall be responsible for maintaining work sites free of water always and shall make good any damage caused by flooding of worksites due to failure of equipment, improper maintenance of protective works and acts of negligence in his Work performance. All the work shall be executed in accordance with design, approved specifications and sequence. He shall also indemnify Owner against claims arising out of any failure due to other contractors, land holders or other persons. SUBMITTALS In 15 days of Order to Commence, Contractor shall submit detailed planning of all diversion, protection measures, dewatering plans and the necessary flow measurements. This design shall be consistent with the outline description submitted by the Contractor with his Tender, and shall include the following: a) b) c) Design assumptions and calculations, Layouts of diversion and drainage facilities, Layout and capacity of pumps and pipes, sumps, drains, both open and covered, well points, etc., including efficiency and heads, piping arrangement and discharge points, Details of standby dewatering arrangements, Proposal for treating polluted water either by settling basins, filters, traps for separating silt or any other suitable method, Any other arrangements or installations Contractor may propose for temporary protection of the Works and dewatering of the working areas both in the open air and underground.

1.2

2.0 2.1 2.2

d) e) f)

2.3

At least 15 days prior to scheduled construction of the particular work, Contractor shall submit full details of equipment to be installed and all necessary construction details required for the dewatering purposes and its induction schedule. Latter reserves the right to require any additional information deemed necessary to be included in submitted documents. EXEAVATION General Contractor shall supply, install, maintain, and operate all dewatering pumps, pipes, supports, channels, troughs, electrical installations, and necessary accessories, and other consumables required to maintain the different work sites free of water during construction, both for the over ground and under ground works. All electrical equipment shall be provided with Earth Leakage Circuit Breakers (ELCB). All equipment within the tunnel shall be provided with power supply at an voltage of 24 V.

3.0 3.1 3.1.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DEWATERING DURING CONSTRUCTION

VOLUME: IV PART: 3 SECTION: B1 SHEET 2 OF 3

Doc. No TCE.5270A-H-112-601

3.1.2

He shall provide standby power supply unit commensurate with the capacity of the pumps in order to cope with the water inflow into construction sites during power shut downs and in order to maintain his main power supply units. De-watering of surface and underground sites shall be undertaken by gravity whenever possible. Only where dewatering by gravity is not practical, pumping shall be resorted to after this mode is got approved from PROJECT MANAGER. . Contractor shall plan location of permanent sumps. .The energy meters for measuring energy consumed in dewatering shall be installed at those locations. Where, in the opinion of PROJECT MANAGER, existing or potential water inflows into excavations can be reduced or controlled by grouting, Contractor shall perform grouting in accordance with Section "Drilling and Grouting". Pumped water carried in pipes or flumes is discharged at point sufficiently away from edge of excavation. No seepage or backflow to working areas will be allowed. Dewatering of Surface Construction Sites Contractor shall perform all works necessary to drain his construction sites of rain, groundwater and service water. All components of the dewatering systems shall be installed and operated in accordance with the agreed method and the construction time schedule or approved modification thereof. Dewatering near the river or stream shall be done down to natural water level by gravity. Suitable drainage shall be made joining the course downstream of the construction site to provide required gradient to facilitate proper and efficient dewatering. Below the natural water table, dewatering shall be done by pumping water collected in the sumps and discharging the same into the river course downstream of the construction site. Adequate pumping equipment including standby units shall be installed, maintained, and operated to drain all water from any surface construction sites. In addition, sumps, pumps and / or well points in the immediate vicinity of structure foundations shall be provided using water conductors to guide the water away from excavation and concrete placement locations. The system shall be so designed that modifications and extensions to system are possible even while they are in full operation. Drainage ditches shall be excavated along top of excavated slopes and on the berms. These ditches shall be kept well back from the excavation edges in order to prevent saturating the upper part of the slopes. The ditches shall have sufficient longitudinal gradient and shall be regularly got cleaned of accumulated silt and other matter to allow free flow of water. Where excavation is to be required below groundwater table in loose material, the water table should be lowered sufficiently below the working surface in advance, by means of properly screened wells and pumps. Where excavation extends below the water table in rock, 6 m deep holes shall be drilled below the final grade, each 100 m apart and piezometric head measured in these holes for 2 days prior to blasting. Excess hydrostatic pressure in the rock shall be relieved to prevent upheaval or any other damage to foundation. Where concrete is to be placed, the water table shall be maintained below the lowest finished excavation level for minimum one day following the raising of structure above the natural groundwater table and for such additional time as may be necessary to preclude damages to structure foundation.

3.1.3

3.1.4 3.1.5

3.1.6 3.2 3.2.1

3.2.2

3.2.3

3.2.4

3.2.5

3.2.6

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DEWATERING DURING CONSTRUCTION

VOLUME: IV PART: 3 SECTION: B1 SHEET 3 OF 3

Doc. No TCE.5270A-H-112-601

3.2.7 3.3 3.3.1

On completion of dewatering, temporary pipes and pump sumps beneath permanent structures shall be closed off and completely filled with grout, mortar or concrete as required. Dewatering of Underground Construction Sites Contractor shall perform all work necessary to collect and drain service and infiltrating groundwater, convey it to main conduits, and lead it out from underground Works such as tunnels, caverns, adits or shafts. Work shall include, in addition to normal functions stated above, jobs as Design, construct and operate pits, trenches, settlement ponds with oil separators at portals. Plot holes shall be drilled, if needed, to provide information on the inflow of water into the tunnel or shaft as excavation proceeds. Where the indications are that flows are likely to be large, grouting may be carried out to seal off water flows or drainage holes may be drilled. Contractor shall work out dewatering system for both descending and ascending headings, latter being by gravity alone. He shall design and construct corresponding drainage trenches in the tunnel inverts with or without lining as appropriate. After break-through in tunnel or shaft, drainage water from descending heading shall be taken over by the upgrade drainage system of ascending heading (dewatering by gravity). After the excavated profile has been checked, water that drips into excavated space shall be diverted into the drainage trench through water collectors, plastic foils, pipes or steel lagging. Damp surfaces or seepage areas with low volume in flows can be sealed off with a quicksetting sealing compound. Special care needed where excavation passes through softer and swelling material when it comes into contact with water. In such locations, water entering the excavated space shall be collected immediately and carried away in a pipe or impervious channel, without allowing it to come into contact with such material. If tunnel invert portion deteriorates from lapse in this regard, PROJECT MANAGER may order removal and replacement of the affected material with concrete and / or may order installation of additional rock supports, at no extra cost to the Owner. If water from tunnel portion flows into a lower section where concreting is on going, of which, the quality is likely to get effected, such water shall be diverted past this area in an appropriate manner without allowing it to damage the concreting activity. . Any openings such as pipes, boreholes, ducts, pump sumps etc., used for temporary drainage purposes in any part of Works shall be completely sealed by filling with grout, mortar or concrete when no longer required, unless specifically directed. Contractor shall notify PROJECT MANAGER before any such openings are permanently closed.

3.3.2 3.3.3

3.3.4

3.3.5 3.3.6

3.3.7

3.3.8

3.3.9

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 1 OF 7

Doc. No TCE.5270A-H-112-601

1.0 1.1

SCOPE OF WORK This Section covers removing all existing material of all types to the lines and grades shown on the Construction Drawings or as directed by PROJECT MANAGER. This also includes drilling, blasting, loading, hauling and disposal of materials in designated spoil, stockpile areas or consumption directly as construction materials. Contractor shall also be responsible for excavation which is not specifically required for construction of Permanent Works, but incidental to installation of temporary facilities as site roads, office buildings, campsite, construction plants, etc. Approval given by PROJECT MANAGER to methods and equipment shall not relieve Contractor of his full responsibility for proper and safe execution of surface excavations or of liability for injuries to, or death of persons or any obligations under this Contract. SUBMITTALS With his tender, Contractor will submit Work plan, drawings and programme for excavation at barrage site, surface and cut & cover penstocks This shall detail the plant and equipment planned to be used for excavation and haulage, blasting methods, site drainage, procedures for the installation of rock supporting and stabilisation etc. 15 days prior to start of any surface excavation, Contractor shall submit an updated method statement and programme for activities set out in (1) above. Any variations from corresponding data submitted with his tender will be justified to satisfaction of PROJECT MANAGER. Data to be submitted now shall include the following: a) b) c) d) e) Location and area of blasts. Diameter, spacing, depth, pattern and orientation of blasting holes Type, strength, amount, column load and distribution of explosives to be used per hole, per delay and per blast. Type of detonators, powder factor, sequence and pattern of delays to be used per blast. Description and purpose of any special methods or equipment to be adopted by the Contractor.

1.2

1.3

2.0 2.1

2.2

2.3

Within a week, PROJECT MANAGER will convey his approval or comment on the submitted plans, giving reasons for any disagreement. Drilling and blasting shall only be carried out in areas for which the plan has been accepted by PROJECT MANAGER. . Thereafter, before minimum of 24 hours of each blast, Contractor shall submit a detailed report showing the final details of the proposed blast. He shall not proceed with the blast until permission to load holes with explosives has been given by Project Manager . At least 15 days prior to dumping or stockpiling any material, Contractor shall submit the layout of spoil or stockpile areas, which will be within the areas designated on the Tender Drawings or as approved by Project Manager. This shall also include stability, permanent drainage of the areas, details of volumes, material types, heights and grades to be provided etc. In this subject, please see para 12.0 Section I / Part 1 of this Volume under Rock Disposal . Prior to starting excavation in any site, Contractor shall confirm his agreement with the existing surveys and topographical data showing the original ground surface for the area in question. If he has any doubts on this, he shall carry out an independent survey and report to

2.4

2.5

2.6

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 2 OF 7

Doc. No TCE.5270A-H-112-601

Project Manager for approval. In case of differences of opinion, both shall jointly review the data and reconcile before job commencement. Contractor's failure to follow this procedure will forfeit his right to claim any other locations of original ground surface than that established. 2.7 To enable Project Manager to verify all necessary elevations and cross-sections of original ground surface prepared, Project Manager shall be notified 7 days before actual work commencement. Contractor shall submit and agree with Project Manager monitoring plan for excavation to observe potential or actual movement of the slopes excavated in the rock. This plan shall also give the procedure and equipment to be employed to stabilise or protect such vulnerable areas where it is apprehended that that untoward movement or deformation is likely. LINES AND GRADES Contractor is responsible for setting-out all structures and slopes as shown in Construction Drawings, in accordance with the Section "Surveying and Setting-out Work". Extra work and over excavation caused by improper setting-out shall be corrected immediately. Final excavation grades shall in general be rock of required quality. However, where the final excavation grades are defined by line and grade, Contractor shall take every precaution, and use the most appropriate method of excavation to avoid the loosening of material or the breaking of rock beyond the lines and grades shown on the Construction Drawings. Bottoms of all excavations shall be trimmed to line and grade. Upon request of PROJECT MANAGER, excavation in the final 200 mm of any loose geological formation where concrete is to be placed, shall be done by hand to avoid internal disturbances. If, for any reason, excavation is carried out beyond the lines and grades shown on the Construction Drawings, the Contractor shall remove the excess material and take necessary measures to restore the required lines and grades with approved backfill or concrete. SLOPES, SLIDES, GEOLOGICAL OVERBREAK AND UNSUITABLE FOUNDATIONS If geological conditions during performance of work do not permit excavation of slopes as shown in Construction Drawings or where the material is unsuited to form a firm foundation for structures, PROJECT MANAGER will modify drawings or issue direct order to change slopes and grades. If over break, slides or rock falls occur, which are held by PROJECT MANAGER as due to improper work method or negligence and effective excavated surfaces are beyond excavation lines shown in Construction Drawings, Contractor shall remove all excessive material and, place approved backfill in the excavated voids. Excavation beyond lines and grades shown in Construction Drawings is defined as over break. Geologically accepted meaning for over break in surface excavation is that which occurs while both of the following conditions are simultaneously fulfilled: a) b) PROJECT MANAGER is informed and given an opportunity for inspection while both the cause and the extent of the over break are clearly visible, Over break occurred while, in opinion of Project Manager, Contractor was using proper working methods or was otherwise careful and it could not have been prevented by prompt and appropriate installation of supports.

2.8

3.0 3.1

3.2

3.3

3.4

4.0 4.1

4.2

4.3

5.0

EXCAVATION

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 3 OF 7

Doc. No TCE.5270A-H-112-601

5.1 5.1.1 5.1.2

General All excavated areas shall be drained properly. Any surface or subsurface water shall be satisfactorily controlled by technically acceptable methods. At all times during construction, specially in excavation, Contractor shall adopt such procedures that ensure total stability of any slope. The acceptance by Project Manager of the excavation procedure or equipment shall in no way relieve Contractor of his sole responsibility for safeguarding stability of all rock faces and slopes excavated. Barrage construction has to be undertaken when the surface is dry. Final surfaces shall be protected against damage by erosion or movement of construction equipment. Any damage caused shall be repaired promptly. . Rock faces and surfaces at sensitive sites such as tunnel portals shall be carefully handled and preserved by resorting to appropriate smooth blasting techniques or line-drilling as deemed fit. Rock supports may be installed to suit the actual geologic conditions. In all such cases, acceleration due to blasting shall be monitored as specified hereunder. . Water shall be sprinkled on work sites to ensure dust free atmosphere Classification of Excavation Surface excavation is classified according to the method used to carry out the work, as follows: a) b) c) d) Common Excavation. Rock Excavation by Blasting. Dental Excavation. Minor Excavation Work.

5.1.3

5.1.4

5.1.5 5.2

5.3

Common Excavation

5.3.1 Common excavation comprises clearing shrubs, stumps, debries, structures, stripping of rubbish, organic top soil, clay, silt, sand, gravel and boulders of size up to 2 m3, soft and disintegrated rock and all kinds of excavation except solid mass of rock, which can be removed by common earth moving equipment without ripping and blasting. . 5.3.2 Loose excavation means general excavation of material such as organic topsoil, clay, silt, sand, gravel, and boulders of up to 2 m3 in volume and soft or disintegrated rock, which can be removed by common earth moving equipment without ripping or blasting. 5.3.3 When bottom of excavation indicated in Drawings is not rock and natural foundation material is disturbed or loosened, for any reason, Contractor shall improve it by compaction or replace it with approved fill and compact. 5.4 5.4.1 Rock Excavation General

5.4.1.1 Rock excavation by blasting includes all solid rock in place which cannot be removed until loosened by blasting, barring or wedging, removal of all boulders or detached pieces of solid rock larger than 2 m3 in volume, as well as any existing structural foundation made of concrete or masonry placed in mortar which cannot be removed during common excavation or by ripping.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 4 OF 7

Doc. No TCE.5270A-H-112-601

5.4.1.2 Lines shown in Tender or Construction Drawings such as "sound rock", "top of rock" etc. are approximate and for information only. . 5.4.1.3 In excavation where plain surfaces of rock are required as in sides and bed of channels etc, faces of such excavation shall be formed in such manner as to least shatter the rock mass. Only light blasting or rim holes or similar methods shall be adapted in such areas. 5.4.1.3 All excavation shall be performed using methods and techniques that will produce smooth and sound rock surfaces with minimum over break and fracturing beyond lines and grades or limits of excavation shown in Construction Drawings and will preserve the structural integrity of the excavated openings. All precautions shall be taken to achieve this result. Particular care shall be exercised where vertical or near vertical faces are required. 5.4.1.4 Drilling and blasting shall be planned in such way as to ensure rock break only along the desired lines and grades. Rock shattered by blasting operations outside established limits of excavation shall be removed and replaced by concrete if necessary. Rock faces and slopes shall be scaled or cleaned of loose or overhanging rock immediately after excavation. Rock surfaces, both temporary and permanent, shall be regularly inspected and rectified. 5.4.1.5 Rock excavation close to the final excavated surface shall be performed using controlled blasting methods, namely, pre-splitting", "cushion blasting", "smooth blasting" defined hereinafter. Line-drilling and broaching shall be used to limit over break and damage of surrounding rock. 5.4.1.6 As excavation at any site approaches its final lines, depth of holes and the strength / amount of explosives should be progressively and suitably reduced up to within 300 to 600 mm of designed foundation level. Further excavation up to the designed foundation level shall be carried out by barring, wedging and chiselling only. 5.4.1.7 Diameter, spacing of blast holes and blasting technique appropriate to the days activity shall be constantly modified to suit surface in question and this got endorsed by PROJECT MANAGER. 5.4.1.8 Shattering or splitting or opening up of seams and joints in rock beyond limits of excavation shall be avoided. If in opinion of PROJECT MANAGER, such damage occurs due to Contractor's negligence, additional rock support shall be installed and any resultant shattered material beyond such lines shall be removed and replaced with rock fill or concrete. 5.4.1.9 Immediately after blasting, all loose material that appears to be unsafe or risky to man movement, work or property shall be scaled and removed. The fact that such scaling and removal may enlarge the excavation beyond the required excavation lines shall not relieve Contractor from necessity of performing such scaling and removal. 5.4.1.10 After scaling and prior to excavation of next bench or round, Contractor shall install rock stabilisation and reinforcement and provide any surface treatment. All blasted rock shall be removed from the bench toe before the next bench is shot. The maximum bench height shall be as shown in Drawings and may be changed only with approval of PROJECT MANAGER. 5.4.1.11 Final excavated surfaces shall have no abrupt slope changes and sharp projections beyond 500 mm. If more, this shall be treated by supplementary excavation to produce desired surface of contact between concrete and rock. 5.4.1.12 Whenever, it is considered that further blasting may injure the rock upon or against which concrete is to be placed or is otherwise undesirable, the use of explosives shall be limited to light charges or discontinued, and the excavation shall be completed by wedging, barring, line-drilling or other suitable methods.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 5 OF 7

Doc. No TCE.5270A-H-112-601

5.4.1.13 Should the presence of rock appear to make excavation for the foundations of any structures unnecessary to the extent shown in Construction Drawings, Contractor shall consult Project Manager,, who shall advice on the next step. 5.4.1.14 When excavation has been completed to specified grade, surface shall be cleaned off by barring, wedging, picking or other approved methods and with an air and/ by high pressure water jet for purpose of inspection. If foundation is found to be not satisfactory, supplementary excavation will be carried out and this surface re cleaned. This procedure is repeated again if needed. Just prior to placing concrete, all loose, shattered, or disintegrated material shall be removed and final surface cleaned with jets of air and/or water under high pressure. 5.1.4.15 Contractor shall regularly inspect all excavation sites and shall promptly remove any loose, unsound, disintegrated rock or that in any way considered unsafe. 5.4.2 Control Perimeter Blasting 5.4.2.1 Bench or open-cut excavation of permanent rock slopes shall be carried out using the cushion blasting or pre splitting techniques. However, depending upon the detailed geometry of rock slopes, other techniques such as line-drilling may be used as approved. Production holes within 3 m of the perimeter row of holes shall be drilled at a reduced spacing and charged with a reduced load. Perimeter holes shall be drilled in such a manner to meet the following tolerances with respect to length, collar, locations and alignment: a) Collar of perimeter holes shall be located within 75 mm of perimeter line, b) Perimeter holes shall not be longer than 6.0 m unless agreed by PROJECT MANAGER. c) All perimeter holes shall be aligned so that each hole terminates within 200 mm of line to which the holes are being drilled, d) Within one m of corners, hole spacing shall be reduced by drilling intermediate holes so that satisfactory and high-quality excavation lines are maintained. Intermediate guide holes may or may not be loaded, depending on results obtained. 5.4.2.2 Holes for perimeter blasting technique shall be at spacing of 450 mm, 600 mm or 750 mm. The selection of centre-to-centre spacing of holes for perimeter blasting shall be developed by trial. In initial stages of excavation, perimeter holes shall be assumed, drilled at 450 mm spacing and based on results this spacing may be varied. 5.4.2.3 Contractor's controlled perimeter drilling and blasting techniques will be agreed to be in conformity with Specifications for controlling the completed rock surfaces if: a) At least 50% of the drill hole traces of each round are visible in the final rock surface, distributed uniformly, after the scaling down of all loose and shattered rock that is liable to fall before or during rock reinforcement installation and if all drill hole traces are close to the lines shown in Construction Drawings, b) PROJECT MANAGER may modify the above criteria if, in its opinion, the achievement of such results is not reasonably possible because of adverse rock conditions. 5.4.2.4. Drill holes for controlled perimeter blasting shall be loaded in a manner and detonated in a sequence so as to ensure a minimum of damage to the rock beyond the excavation lines.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 6 OF 7

Doc. No TCE.5270A-H-112-601

5.4.3 Line-drilling 5.4.3.1 Line-drilling shall be used where control perimeter blasting may cause excessive damage to the surrounding rock or where there are structures adjacent to the excavation. Line-drilling is anticipated near and around the intake structure and spillway. 5.4.3.2 Line-drilling is defined as a single row of unloaded holes along neat excavation line, spaced no more than two to four times the hole diameter on centres. These will form a surface of weakness to which the primary blast can break. Light blasting with well-distributed charges fired after main excavation material is removed as may be permitted in the holes. If, however blasting may injure the rock, use of explosives shall be discontinued and excavation completed by broaching, wedging, or barring. 5.4.4 Dental Excavation 5.4.4.1 Dental excavation shall include the removal of unsuitable material from shear zones, clay seams, pockets, joints, caverns, or from spaces between boulders beyond the lines of excavation shown on the Construction Drawings or established in the field, which are too small to be excavated by common earth moving equipment. 5.4.4.2 Dental excavation will require the use of a back-hoe, hand tools, or other small excavating equipment, as well as the use of a high velocity air-water jet. Method selected shall be that ensures avoiding fracturing of the rock adjacent to the material being removed to maximum extent. . 5.4.4.3 Extent to which such material shall be removed, including the depth, direction and dimensions of work, will be pre decided. In general, however, excavation into cracks or seams shall be to depth that is a minimum of three times the seam width and such excavation 6.0 6.1 EXCAVATED MATERIALS All suitable materials from excavations shall be utilised to maximum extent possible as construction material in Permanent Works. For this, blasting and excavating techniques adapted shall be such that construction materials of desired grade and quality will be produced. In fact, such materials shall be excavated separately from that needing to be disposed off to spoil tip. These could later be transported to the designated final locations for its use. If immediate placement in the final location is not possible, the materials shall be stockpiled. If the moisture content of excavated materials is too high, such material shall be drained and dried in the stockpile until it gets sufficiently reduced to allow for placement. Contractor shall remove any cobbles, boulders or rock fragments found in otherwise approved materials which are greater or smaller than permitted for specific embankment zones and place them in other zones or dispose of them appropriately. DISPOSAL OF EXCAVATED MATERIALS Excavated materials which are not suitable for or are in excess of the construction requirements shall be disposed of in the spoil area shown in Tender Drawings. Contractor shall be responsible for the stability of all fills, embankments and stockpiles created by these. Spoil tips shall be located where they will not interfere with the natural flow of streams or rivers, with construction operations in the borrow area and quarry areas, with reservoir operation, with flow of water to or from spillway or outlet works, or with accessibility to the Site. Surfaces of all disposed excavated materials which are to remain permanently exposed shall be finished to prescribed lines and to stable slopes. Contractor is liable for any damage to

6.2

6.3

7.0 7.1

7.2

7.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SURFACE EXCAVATION

VOLUME: IV PART: 3 SECTION: B2 SHEET 7 OF 7

Doc. No TCE.5270A-H-112-601

Temporary or Permanent Works or to third parties and their property caused by inadequate drainage of the spoil or stockpile areas. In this context, please also see paragraph 3.9.2 under same title Excavation. 8.0 8.1 PREPARATION AND PROTECTION OF EXCAVATION SURFACES If, during excavation work, material beyond the limits of excavation shown in Construction Drawings is loosened or disturbed, Contractor shall re compact the loosened material or replace it with other compacted fill as directed. If, during excavation in rock for concrete structures or linings, the rock beyond the limits of excavation shown in Construction Drawings becomes broken or shattered, Contractor shall replace it with concrete or shotcrete as directed. Foundation excavation shall be kept well drained and free of standing water. When foundations are affected by water, affected material shall be replaced with approved backfill. Shotcrete shall be applied to finished excavation surfaces where, in the opinion of PROJECT MANAGER, it is deemed necessary to prevent air slaking, erosion or other deterioration of the surface. The protective coating shall be applied to excavated surfaces either with or without steel wire mesh reinforcement in accordance with the provisions of the Section "Shotcrete". MONITORING AND PROTECTION FROM BLASTING Contractor shall adequately protect existing structures from effects of blasting both from impact with rock or debris and from excessive shock. Structures at risk shall be inspected before and after blasting and shall be monitored during the blasting operations by appropriate means. PROJECT MANAGER may monitor part or all of the blasting operations utilising velocity transducers, vibrographs or other equipment. Contractor shall cooperate with PROJECT MANAGER in placing, operating and recording of monitoring equipment. In case of concrete structures and cement grout maximum particle velocities that result from blasting operations shall not exceed the following limits: a) For concrete and grout in place for more than 60 hours, the maximum particle velocities shall not exceed 5 cm/s, b) For concrete or grout in place for less than 60 hours, the maximum particle velocity shall not exceed 1 cm/s, c) For complete or partially complete portions of platforms in fill, peak particle velocity shall not exceed 5 cm / sec. Maximum particle acceleration shall not exceed1.0 g, 9.4 Blasting within 25 m of concrete or grout will be permitted only after concrete or grout is 7 days old under specific approval of PROJECT MANAGER of a plan showing the relative positions of structures or grouted area and the area to be blasted, Contractors drilling and blasting plan, together with outline of precautions to be taken. All concrete and other completed work within 25 m of blasting shall be protected by limiting the size of blasts. Blasting will not be permitted within 10 m of structures or installations vulnerable to damage by blasting. Replacement or repair of work damaged by blasting shall be carried out at no expense to Owner. Blasting restrictions stated above are given as a guide only and may be revised by PROJECT MANAGER on basis of seismic measurements and site observations. If results indicate that blasting methods endanger excavation, grout or concrete work, he shall be required in Under Ground

8.2

8.3 8.4

9.0 9.1

9.2

9.3

9.5.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 1 OF 21

Doc. No TCE.5270A-H-112-601

1.0 1.1

General Description of works involved. Water Conductor System in Bhira Project is of length 2035 meters, of which about 1155 m shall be Underground pressure tunnel and rest of 880 m shall be open and cut & cover of 2900 to 2300 mm diameter. Alignment of 771 meters long penstocks is located in first part of the system, follows the hill ridge parallel to existing penstocks of the operating power houses. At tail end, about 109 meters of cut & cover and open penstocks shall be constructed. At its other side, a portal will open to the 710 meters long horizontal and then the 315 m long inclined tunnel. Scope of required Works: Distinct elements of this system are following: (Please see para 3.0 / Section III Part 1 of this Volume) a) 130 m point: This is the junction between Pressure tunnel starting from Surge shaft and Cut and Cover pen stock. Appropriately designed portal structure will provide smooth passage for water. From 130 to 901 m, it is entire surface penstock. b) At chainage, 296 m to 324 m, alignment takes a right turn, then system crosses the existing penstocks over an elevated bridge structure and thereafter follows all along the right hand side of present pipes. c) In reach 634 to 744 m, there is a drop over a length of 180 m. The free land available for construction is maximum 15 m wide. Contractor shall devise his technology and method of tackling this area to suit to the Site conditions. d) For preparation of pedestal for penstocks or pedestals, excavation has to be carried out carefully. Blasting shall be avoided as the existing penstock pipes of operating project can not be disturbed. If any rock surfaces are needed to be re shaped for providing proper seating, Excavators, Back hoe operated rippers, rock breaker or manual means shall be adapted. Blasting, if inevitable at certain spots, muffler accompanied with contour or smooth blasting shall be resorted to with all precautions. e) Pressure tunnel of 1180 m long requires steel liners of various thicknesses and grades. The cavity around this shall be concrete lined to thickness of above 200 mm after erection and then grouted. Fabrication, transportation and erection of these liners shall be responsibility of this Contractor. Lastly, from 1926 to 2035 m up to Power house it is Cut & Cover penstock.

2.0 2.1

f)

2.2 Updated design Drawings are provided with Bid documents, which, Contractor shall examine and provide his methodology for handling assignment in a technically competent manner for which purpose, details of all studies and investigations carried out are provided. Contractor shall examine the entire Water conductor System from surge shaft to power house and suggest any alternative alignment which is advantageous from angles as power generation, construction cost, simplicity of job, project schedule and submit with his offer. 3.0 CODES AND STANDARDS 3.1 Fabrication, erection and testing of surface penstock and penstock in tunnel shall comply with all current statutes, regulations and safety codes. Penstocks shall confirm in all respect to latest applicable Indian/British/American standards. Few latest Standards are listed below. a) b) c) IS: 2062 ANSI B31.1/ ASME Section VIII Div-1/TS 2825 IS: 5878

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 2 OF 21

Doc. No TCE.5270A-H-112-601

d) e) f) g) h)

ASME Section 11 ASA Standards/AWWA Standard (bolts, nuts and gaskets will have dimensions, material, grade and description covered in AWWA-C207, ASA 16:24 and IS: 1367). ASCE Manual No.79 steel penstocks IS:5330 IS:11625

3.2 Materials: Plates for penstock and accessories will be high strength alloy steel, quenched and tempered of designation i) ASTM A 517 Grade F ii) ASTM A537 Class 1 Or iii) Structural Steel conforming to IS: 2062, Grade E 250, Quality B or C, Normalised & Quenched 3.1 Welding consumable as electrodes, fillers rods and wires shall conform to IS: 814 Part II, IS: 3613, IS: 6419 & IS: 7280 for indigenous steel and (as per relevant ASME / ASSM standard for ASTM A 517 F grade plates). Welding rods shall be from reputed manufactures such as (a) Advani overlikon (h) D & H secheron, Indian Oxygen and others got approved by PROJECT MANAGER. 4.0 Fabrication

4.1 Contractor shall get fabrication and accessories work done in his licensed factory or that of an approved Sub Contractor, equipped with following equipment. . i) Plate bending machines for rolling of pipe drums. ii) Automatic wielding machines (suitable for circumferential as well as longitudinal welding iii) Hydraulic testing Equipment iv) Travelling gentry or Crane of adequate capacity. v) Lathe for machining of the flanges, ranges plates etc, vi) Mobile Cranes for loading/unloading of plates, pipes etc. vii) Equipment for sand blasting and painting. viii) Equipment for cold pressing of plates to the required curvature (domes, plug, plates, M. H. covers etc) ix) Bending machine of adequate capacity for fabricating ring girders & other necessary items. x) Stress relieving equipment. xi) Factory shall have sufficient yard for stacking plates, structural, fabricated pipes and scrap xii) Tack welding shall be avoided to the possible extent; if unavoidable, tacks shall be of the same material along with approved procedure of welding This factory shall also be used later for testing, machining and painting. Bidder shall indicate location of factory and its distance from Site. The stipulations and practices in the following BIS codes shall be adhered to: I S 4880(part VII)-Code of practice for design of tunnels conveying water-Structural design of steel lining. I.S.11639 (part 1):- Criteria for structural design of penstocks Surface penstocks. I.S.11639 (Part 2):- Buried/ embedded penstocks. I.S.11639 (Part 3):-Structural design of penstock-Specials for penstock. I.S.2825:- code of practice for unfired pressure vessels.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 3 OF 21

Doc. No TCE.5270A-H-112-601

Also, facility for radiography, Ultrasonic and other tests shall be established at site. 5.0 Grout Holes For grouting behind the penstocks inside tunnel, 38 mm diameter holes are drilled in pipe shells at intervals shown in Drawings. Holes shall be suitably threaded and provided with matching screw plugs of length at least equal to plate thickness. Thread on pipe holes and plugs shall be matching, so that a weld of sufficient thickness could be applied around the plug head to prevent water leakage during hydraulic test. Screwed head and weld shall be ground flush with pipe inner surface after completion of final grouting. Grout holes shall be drilled only after shop hydraulic testing of pipe. 6.0 6.1 Cutting Plates to Size Plates shall be procured in such lengths as to ensure minimum wastage and to make the penstock as far as possible with one longitudinal joint. Before cutting, all plate edges shall be cleaned by brushing/grinding on both sides. In case of gas cutting, 1.6 mm of heat affected zone shall be removed by grinding and then subjected to non-destructive testing (NDT) to ensure defect free edges. Plates shall be cut individually and stack cutting shall not be allowed. If plasma cutting is done, nitrogen shall be avoided as shielding gas. Next, plate edges shall be made smooth, even, free from inequities and perfect straight by polishing with electrical or pneumatic grinder. Jigs to be used for this purpose shall depend upon type of cutting machine used. Plates cut to required shape shall be rechecked for correctness before rolling into pipe drums. If needed, re cutting shall be resorted top for achieving corrections. Any plate which is warped or having corrugations shall be put under a roller press. During cutting, any plates found laminated or badly corroded shall be rejected. . Rolling of plates Plates cut to exact size shall then be rolled of required diameter into pipes in rolling machine. This machine shall be so adjusted to provide a uniform curvature to pipe over its circumference. If curvature is defective at spots or corners, repeat the rolling. Heating of plates is not permitted for this objective. 8.0 8.1 Tacking the Drums Rolled drums are then kept on an assembly platform for tracking, with their end faces at right angles to pipe axis.. While tacking, a gap of about 2 to 4 mm. has to be maintained, which is not necessary if welding is by automatic machine. In tacking, clamp spiders, tightening rings and / or any other approved gadgets shall be used. Each such drum is numbered on the inside with oil paint, mentioning the plate thickness as well before being taken to assembly platform. Assembly of drums into Pipes Tacked drums are then taken to assembly platform and tack-welded together to desired lengths. Plate shall be bent in the maximum width to reduce circumference joints. Longitudinal joints shall be staggered, preferably at 2O clock and 10O clock positions. When tacked together, drums shall have no circumferential welding gap if automatic welding is used. But in hand welding, gap of 2 to 4 mm is provided to get a good butt welded joint. Longitudinal seam welding, where required, is done using on-off plates, job on each ferrule

6.2

7.0

9.0 9.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 4 OF 21

Doc. No TCE.5270A-H-112-601

longitudinal seam completed first (welding & testing) before circumferential seam welding is taken up on next ferrule. 9.2 The assembly shall be truly cylindrical, without any kinks. Faces shall be at right angles to cylinder axis. For testing the trueness of the faces at the assembly platform, a suitable gadget shall be devised. Welding It is advisable to have automatic arc welding machine by metallic shielded arc process with A C or D.C. Reverse polarity (electrode positive) to weld all components of a standard shell, whether straight of bent. Electrode size depends on plate thickness and type of joint. By experimenting, one decides on the standard current and arc voltage required, which shall be maintained firm during the entire process. Members to be joined shall be rolled or pressed to proper curvature as per Drawings. Their edges shall be sheared, flame or machine cut to enable the required type of welding and allow 100% weld penetration. Plate surfaces shall be free from rust, grease and other foreign matter for a distance of at least 15mm from weld edges. Plates shall be pressed or rolled to true circular shape with circumference continuous from plate edge. Curvature corrections shall be by pressure and not by blows. All longitudinal and circumferential joints are double welded butt joints. For this, underneath portion of first side shall be back chipped/gouged to sound metal, liquid penetrant tested satisfactorily before welding second side. Due to non accessibility of both sides for welding, field girth joints are achieved by using back-up plates. Circumferential welds involving plates of unequal thickness shall be so handled that plate inside surfaces match and provide streamlined joints without alteration in internal diameter. The welding should be free from flaws, burns, etc. Equipment ovens should be used to keep electrodes at desired temperatures and dry. Welding procedure, welders and entire operation shall conform to IS: 7307, IS: 7310 and ASME (latest). Defects noted in pipes already welded shall be set right. All check tests and defect rectifications shall be at cost of contractor. Record is maintained of welders who welded each joint, its location, type, date, time of completion, voltage, speed etc Hand welding shall preferably be carried out by two welders jointly so that, by observing proper sequence, distortion can be avoided. A joint entrusted to a particular individual or a pair shall be as far as possible, completed by them in all respects, including sealing run. . Welded joint should not become brittle or sensitive to blows. There should be no loss of toughness after welding or heat treatment. It has to be tougher than the base metal and retain its original quality. No allowance will be made for thinning of weld, which should at no point be less than the nominal plate thickness. Plate lengths are so chosen that there will be only one longitudinal weld in each pipe. Still, there can be one more longitudinal weld if pipe is short. . Welding Procedure Prior to start fabrication, Contractor shall submit and get approved his planned Welding procedure for the job, opting always to have machine welding. It shall include thermal stress relieving where required.

10 10.1

10.2

10.3

10.4

10.5

10.6

11.0 11.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 5 OF 21

Doc. No TCE.5270A-H-112-601

11.2

Pre heating of plates Minimum preheating and inter pass temperature shall be maintained as given below to achieve sound welding: ASTM A 517M Gr F plates 0.25 mm thick 25-50 mm thick Above 50 mm thick Preheating temperature No preheating required except initial heat to remove moisture 65 C 950 C
0

12.0 12.1

Testing of welded joints After completion of welding, all welded joints of pipes are radiographed or tested ultrasonically to detect welding defects. All longitudinal joints are 100 % tested radiographically. Each circumferential joint shall be subjected to minimum 10%, but up to 100% radiographic test. Weld ripples or surface irregularities inside and outside shall be removed to such extent that resulting radiographic contrast due to remaining irregularities shall not mask or be confused with that of objectionable defect. The radiograph test shall be made strictly as per latest requirements, with the known efficient techniques as x-ray or gamma ray equipment. Ultrasonic test shall be carried out after properly qualifying a written procedure using defect standards. Any additional tests also may be demanded of by Owner. Radiographs are to be marked in such a way that corresponding portion of welded seam can be readily identified. All radiographs will be reviewed to identify defects and determine which must be removed. Defects not acceptable shall be removed by chipping, machining or flame gouging to sound metal. Resulting cavities shall then be welded. After rectification, joint shall be radiographed again to observe quality of repair. If still unacceptable, reject piece. Acceptance / Rejection of weld are also subject to the provisions in ASME 2007 SECTION VIII DIVISION 1. Films shall be developed within 24 hours of exposure and these shall be readily accessible at all times for further inspection in suitable x-ray viewing equipment. X-ray films shall be properly preserved and later handed over to Owner on completion of Contract. All films shall be identified by the number and chart prepared indicating location of joint each x-ray photo represents. Similar records shall also be maintained for ultrasonic testing. A chemical analysis if required, including determination of oxygen and nitrogen content may be taken of weld metal deposited in a sample joint, in which, the parent plate material is to be the same as that used for pipe fabrication. Test may also be carried to ensure that heat affected zone near welding has minimum specified tensile and impact strength. Additional production test coupons to ensure weld quality on penstock and evaluation of tensile and impact strength shall be as bellows: 12 mm to 25 mm thick plates----------one per 90 metres 26 mm to 50 mm thick plates----------one per 60 metres 51 mm thick plates and above --------one per 30 metres

12.2

12.3

12.4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 6 OF 21

Doc. No TCE.5270A-H-112-601

12.5

Where site welding is possible only from inside penstock, using backing strip on outside surface as in case of embedded penstock in tunnel and embedded penstock in Anchor block portions, the following non-destructive tests shall be done. a) Magnetic particle test (MT) of liquid penetrant test (PT) after root pass; b) MT or PT, as directed by ENGINEER, for every 6 mm layer of weld deposit. For MT by prod method, care to be taken to locate the pods within the weld groove (not on the plate surface); c) MT or PT, as directed by ENGINEER after final pass, MT to be done using yoke and not prods as prods may cause local hardening and micro cracks; d) Ultrasonic test (UT) after properly qualifying a written procedure using defects standards.

13 13.1

Welding Inspection General Inspector shall assure himself of the welding procedure, welders employed ( whether qualified or not ) and consumables used. He shall inspect the records of Contractor and witness tests of welding operator. Such welding inspection shall be carried out only after 48 hours of completion of welding and post weld treatment to check delayed cracking due to hydrogen embitterment.

13.2

All welded joints shall be examined in accordance with latest codes. i) ii) iii) iv) v) vi) IS : 2529 IS: 4853 IS: 1182 IS: 2598 ASME Section V ASME Section VIII Div 1- This is for Acceptance criteria of welding.

Reinforcement on each side of all butt welded joints shall not exceed 0.2 times Thickness of plates or 2.4 mm whichever is minimum. 13.3 In testing techniques & methods, publication SNT-TC-1A, supplement 7 its part Recommended Practice for Non-destructive Testing personnel Qualification and certification by American Society for Non-destructive Testing shall be relied upon.. Final acceptance of radiographs shall be based on ability to see prescribed penetrameter image and the specified hole. Weld sections that show in radiography any cracks, zone of incomplete fusion or penetration, elongated slag inclusion of length beyond 6 mm, any slag inclusion of length beyond 12 times the thickness, rounded indications in excess of acceptable standards given earlier - all are un acceptable, so repaired.. Thermal stress relieving All heavy and rigid parts like shell piece with manholes and parts to be machined such as expansion joints and components of thickness above 38 mm, again when the welded joint connects plates of different thickness all these shall be thermally stress relieved as per IS: 5878 (part VI) in a suitable furnace. This is not required for imported plates specified in UHT 56 of ASME Section VIII Div A 517 M Grade F alloy steel plates.

13.4

14

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 7 OF 21

Doc. No TCE.5270A-H-112-601

15 15.1 15.2

Tolerance Shell of completed work shall be full round. Tolerable difference of inside diameter between max & min values being 1% of nominal diameter of cross section, limited to 10mm. Machined parts shall be within the following limits: a) For mitred finished surface = 20 minutes of arc b) For elbow angles = 20 minutes of arc c) For Length of elbow pieces = 6 mm. d) Perpendicularity of pipes: Max deviation of 2 mm on either side pf plane.

16 16.1

Shop Hydraulic Testing After fabrication, all pipes are shop hydraulic tested. Standard lengths of these are directly tested, but non-standard ones and elbows are tested before being cut to size. Grout holes shall be drilled only after shop hydraulic testing. Plate material is subjected to test pressure such that it is stressed to 80% of minimum yield strength and at least 150% of the allowable working pressure. Each pipe is painted in its inside with its serial number, thickness, diameter, length etc. These details are recorded in Register maintained. Prior to testing, the pipe shall be inspected for any apparent welding defects such as jumps, porosity, etc. which are repaired. Two pressure gauges, tested and calibrated for accuracy, are mounted one on one of the closures which close the pipe ends and the other on the test pump. Pressure is applied gradually and maintained for 10 minutes. All weld joints are inspected and 1 kg hand hammered by sharp blows along its length. Pressure is then gradually reduced, this procedure repeated 3 times. Any leakage, oozing and sweating shall require re conforming and repairs. After hydraulic test, all welds shall be tested by MT by using yoke and not prods or PT

16.2

17 17.1

Field hydraulic testing On penstock erection, this shall hydrostatic tested at field. For this, it shall be provided with bulk heads at both ends, which are filled with water. The filling of penstock shall be done gradually to the required pressure and during filling, closing and tightness of all the valves, inspection openings and other accessories shall be properly vented at high points to prevent formation of air pocket. The water shall be maintained to required head so long as is considered necessary for inspection of all joints. Any joint leakage shall be repaired and retested. Submission of daily progress report Daily progress report shall be submitted in prescribed proforma showing details of steel materials taken for fabrication, finished sections available etc. Contractor shall also keep good account of all steel materials and ensure proper security for same.

18

19 19.1

Procedure for erection and storage of Steel penstock pipes For smooth continuance of erection work, stock of pipes, standard specials, flanges rings, manhole covers, etc, are retained at field stores always, roughly a months requirement. Padding shall be provided between coated pipes at suitable intervals. Gaps shall be left at intervals to permit free movement. Surface treatments and coatings on pipes, fittings and specials shall not be damaged in storing or movement. Slings of canvas or equally non-

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 8 OF 21

Doc. No TCE.5270A-H-112-601

abrasive materials of suitable width of special attachment shaped to fit the pipe ends shall be used to lift and lower pipes to prevent damage the coating. 19.2. Plates used for pipe fabrication shall be stored in such way that when the shells are completed, one set of original identification markings on the material will be plainly visible. In case these markings are damaged or cut out, they shall be re marked visibly. After shop hydraulic tests on the specials and other items, the number of the shell in sequence of erection and the direction of flow shall be stamped prominently.. Transporting of pipes, specials etc. Pipes are handled carefully during transport from fabrication site to the Worksite, both in loading and unloading from trucks by cranes or other means. Props /spiders of approved designs shall be fixed to pipes during transit to avoid undue sagging and distortion, till point of stacking. But pipes which sag more than 3 mm under their own weight shall always have props/spiders till final erection. Expansion joints, composite bends, Wye branches and other complicated materials are stacked in Main stores till required for usage. Fabricated materials, such as manhole covers appurtenances, bolts, nuts, distance pieces, flanges, saddles, collars, by-pass arrangements, etc. shall also be stored till actual need at site. Regarding access to Work sites, roads are available at Surge shaft and Power house end. In remaining places, Contractor shall make his own arrangements. Erection Erection shall be commenced as per Approved Construction plan. For this, a temporary track of gauge, type shall be laid as required at site. The track laid for erection of surface penstock shall not be dismantled and will be retained at site. Erection of Shells Erection shall be true to position, lines and grade as shown in drawings. Necessary saddles, pads, spiders, all necessary instruments and other materials shall be provided for proper erection and for PROJECT MANAGER to check its correctness.. 21.2 Alignment of section at edges to be butt welded shall be such that the maximum offset is not greater than the values given below: Thicknesst offset in longitudinal joints (mm) Up to 12 13to 20 21 to 40 41 to 50 Over 51 0.25 t 3 3 3 Less of 0.0625 t Or 10mm offset in girth joints (mm) 0.25 t 0.25 t 5 1/8 t Less of 0.125 t or 20 mm

20 20.1.

20.2

21 21.1

21.2

----------------------------------------------------------------------------------------------------------

----------------------------------------------------------------------------------------------------------

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 9 OF 21

Doc. No TCE.5270A-H-112-601

22.0 22.1

In-situ welding Single welded butt joint Welding all field girth joints of penstock embedded in tunnel shall be single welded V butt joints with backing strips. Shell edges shall therefore be machined to take this inside welding. Material for backing strips shall be same or compatible with base material. Field circumferential joints in penstocks not embedded shall be double V butt welded. These shall be ground smooth. In welding of continuous shells, they shall be so placed that adjacent longitudinal joints are staggered in position.

22.2

Welding Inspection at site All longitudinal field joints and circumferential joints of surface penstocks and those embedded in tunnel and in pressure shaft shall be inspected 100% by radiography or ultrasonic testing.

23.0 23.1

Support while welding & backpacking with concrete & grouting Shells shall be supported on studs, stools or pads etc, suitably held in place before commencing field welding of circumferential joints. No timberwork is permitted as support.. When supported, shell shall be perfectly in line and level and in shape, subject to specified tolerances. This position gets disturbed during the process of welding, or during backpacking.. The pipes shall be suitably braced from inside with spiders while packing and grouting are carried out. Specials Bends a) Bends shall be fabricated considering the vertical and horizontal angles for each case. They shall have welded joints and the upstream and downstream ends of each shall have a straight piece of variable length as per Drawings. Bends are designed with deflection angle of maximum 6 to 7 deg. between segments. When the points of interaction of a horizontal angle coincides with that of a vertical angle, or when these points can be made to coincide a single combined or compound bend shall be used, designed to accommodate both the angles. The combined bend should have a pipe angle equal to the developed angle, arrived at from appropriate formula. All joints in bends shall be thermally stress relieved as specified.

23.2 24.0 24.1

b)

c) 24.2 Manholes

a) Manholes, fabricated out of steel plates, shall be placed in suitable position in top quadrant of pipeline. . b) Testing and thermal stress relieving after welding of manhole shall be as per ASME Section VIII. 24.3 Closing of Makeup sections Closing or make up sections shall be furnished at appropriate locations on the line to permit field adjustments in pipe line length to compensate for shrinkage in field welded joints, differences between actual and theoretical lengths and discrepancies in measurements.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 10 OF 21

Doc. No TCE.5270A-H-112-601

24.4 Test Heads Test heads may be ellipsoidal, standard dished as per ASME code or hemispherical heads. Test heads provided shall be suitable for testing all sizes of ferrules fabricated in the shop. 24.5 Walkways, stairs, Ladders, Hand Rails etc Walkways, stairs, ladders, handrails etc shall be provided as required. This shall conform to well established design and construction practices. 25.0 Chainage Markers Chainage markers shall be provided along the tunnel at 30 meter centres. These shall be a 12 mm plate of size 100mmX100 mm, with curvature to suit the penstock and shall be welded to it. All 30 meter points such as 30, 60, 90 etc shall be inscribed on the plate by chiselling or any other method decided upon.. 26.0 26.1 Painting of penstock and accessories General a) Fabricated pipes and accessories shall be painted before being dispatched to erection site or at site after erection on installation.. Paint shall be applied only to dry freshly cleaned surfaces, free from dust, rust, seals, grease or other substances which might affect adhesion or durability of coating. It shall not be applied to surfaces during rainy or misty weather in which case the work shall have be maintained until it got dried. b) Skilled workmen only shall be deployed. Average coverage shall be equal to that recommended for first class work with type of paint and on kind of surface being painted. c) Painting may be done by brushing or spraying unless a particular method of application is specially directed. Time gap of not less than seven days should be allowed after final coat before the object is submerged in water. Finished painting shall be smooth and free from runs, sags or blisters. d) Paint shall be in thoroughly mixed condition at time of application. On completion of Work, oil stains or paint spots etc shall be removed, leaving the structures and equipments in a clean and acceptable condition. Colours used on various items of Work shall be as per the approved colour schedules. 26.2 Surface Preparation

26.2.1 Surface Penstock Internal and external surfaces of fabricated material shall be washed with suitable solvent wherever necessary to remove oil and grease, wiped clean and blast cleaned to SA 2.5 as per BS 7079. Blast cleaning can be done by using either chilled cast iron grit or river sand of size G-24 of BS: 2451 at an outlet pressure of 80 p. s .i. (about 0.8 bars). In case steel shots are used for blast cleaning, their size shall conform to S-230 size. 26.2.2 Penstock Embedded in Tunnel Internal surface of fabricated material shall be prepared similar to that of exposed penstock surface described above. External surface shall be wire brushed to remove rust spots, if any, should be washed with suitable solvent wherever necessary to remove oil or grease stains..

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 11 OF 21

Doc. No TCE.5270A-H-112-601

26.2.3 Surface penstock External surface Prepared external prepared surface shall then be given one shop coat of zinc silicate primer of a dry film thickness of 30 microns. Over this, two shop coats of zinc epoxy coat of total dry film thickness of 120 microns shall be applied, making overall paint coat and primer of 150 microns. Curing time of 7 days in dry weather (humidity not exceeding 70 percent) shall be provided. No coating shall be applied closer than 150 mm from the ends of pipe which will be field welded. This exposed steel should be protected during transport by rust preventive compound which shall not interfere with the field welding. Painting of these end parts shall be carried out and completed in the same manner as that in shop, after erection. 26.2.3.1 Embedded Penstock-External Surface External cleaned surface shall then be given one shop coat of cement wash. 26.2.3.2 Surface Penstock and Embedded Penstock Internal Surface Internal surface of fabricated material shall be given one shop coat of zinc rich epoxy primer to a dry film thickness of 30 microns. Over the coat of primer, three shop coats of cold application epoxy coal tar paint or equivalent to aggregate thickness including primer to 250 microns shall be applied. No coating shall be applied closer than 150mm from the ends of pipe which will be field welded. This exposed steel shall be protected during transport by a rust protective compound which shall not interfere with the field welding. Painting of these end parts shall be carried out and completed in the same manner as that in shop, after erection. 26.2.4 Repair of Shop coats Metal work which has been shop painted shall be handled with care so as to preserve the shop paint in the best practicable condition. After erection or installation of the metal work, all rust spots. All damages areas and welds shall be cleaned and painted with the same kind of paint as used for the shop coat. 26.0 Technical Personnel All technical personnel such as welders, fitters, erection crew and others shall be suitably qualified for their respective jobs. 27.0 Best Practices Design, manufacture and erection of penstocks including tolerances and procedures shall conform to the best prevalent international practices such as in the Recommendations for the Design, Manufacture and Erection of steel penstocks of welded steel construction for Hydroelectric Installations of European Committee for Boiler Making and Kindred Steel Structures.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 12 OF 21

Doc. No TCE.5270A-H-112-601

1.0 SCOPE OF WORK 1.1 As planned, this Project has a stretch of about 315 m of inclined and 840 m of horizontal tunnel, alignment of which passes close to existing components of the operating projects or the surface. Hence very close monitoring is required in the blasting operations in much of the reaches. Details of configuration are given at para 3.0 Part 1/ Section III of this Volume. This Section covers all excavation work for underground structures to be constructed under this Contract performed by conventional tunnelling and shaft driving methods using drilling and blasting or, in exceptional cases, by manual means. Work shall include all drilling and blasting, loading, transporting and disposal of materials in spoil or stockpile areas as well as the removal of all loose material and cleaning of excavated surfaces. Contractor may be required to perform exploratory drilling during excavation of tunnels and shafts to ascertain the geological conditions. The configuration of Water Conductor System given in the drawings is based on studies conducted by Owner. Contractor shall examine the entire system and optimise the excavated section and may suggest an alternative system for discharging the same quantity of water 3 (24 m /sec) over a head available of 480 m and thus generate 740 MU during peaking and 62 MU during non peaking hours, with installed capacity of 100 MW. Cost differentials of such system will not be passed on to Owner. His Bid shall contain his proposals in this regard. 1.4 Approval given by Project Manager to Contractor's methods and equipment shall not relieve the Contractor of total responsibility for proper and safe execution of underground excavations, or of liability for injuries to, or death of persons or any obligations under this Contract. In technical details, contents of Chapter on over ground Excavation apply here, unless these are modified by additional script specific to Under Ground Works. SUBMITTALS At least 15 days prior to start of excavation, Contractor shall update the details of his excavating methods and sequences for portal excavation and all underground works over that which he submitted along with this Bid. This shall include Muck and passenger hoisting arrangement, Ventilation, Drilling & blasting, Dewatering, Mucking, Shotcreting, Rock support system, concrete placing, survey system lighting / safety and other important issues and problem areas etc. At least 15 days prior to dumping or stockpiling any material, Contractor shall submit layout of spoil and stockpile areas, which will be those designated on the Tender Drawings or that approved. All pertinent data including the security, stability, and temporary or permanent drainage of the areas shall be included in this. Details of volumes, material types, heights and grades shall be provided. To enable PROJECT MANAGER to verify all necessary setting-out and elevations carried out by the Contractor, the latter shall notify PROJECT MANAGER in writing, giving at least 7 days notice, of his intention to start excavation. During the advance of underground excavations, Contractor shall record and submit weekly to PROJECT MANAGER three copies of following: a) b) c) Advance of each face and chainage of face before blasting of each round, Type and number of drill holes, and length of each round, Pattern of drill holes, their diameters and length,

1.2

1.3

1.5 2.0 2.1

2.2

2.3

2.4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 13 OF 21

Doc. No TCE.5270A-H-112-601

d) e) f) g) j) l) m) n) o) 2.5 3.0

Type, quality and location of explosives in each drill hole, and blasting scheme (direct or retarded), Theoretical volume of solid material excavated according to typical sections, shown in Construction Drawings, Geology, competence of the rock formations, rock falls, zones of instability, and information obtained from any pilot holes, Surface of shotcrete, and wire mesh installed, Water inflows at the face and the rate of discharge of water from the Dewatering systems, and the temperature of the water, Personnel employed during various stages of the operation and their qualification, Time required and detailed for each activity, Unusual occurrences, all delays and the reasons for delays, Volume of fresh air in the heading zone.

PROJECT MANAGER reserves the right to require any additional information deemed necessary to be included in the documents to be submitted. Geology of site Geological information and data provided in this tender document are only for general guidance of Bidder. Owner assumes no responsibility for deducting any conclusions or interpretations that may be made by Bidder. Latter may carry out additional investigation, if he deems fit, to establish the characteristics of rock before taking up tunnelling work, which will entitle him no extra payment.

4.0 4.1

Setting out Work: Contractor shall establish at suitable points permanent reference marks on the centre line of shafts and tunnel as directed. These shall be inscribed in bronze pegs, set in substantial concrete blocks where they shall be free from any disturbances. Such bench marks also shall be established near the portals of terminals and construction shafts. As tunnelling work progresses, centre line marks shall be made on pegs inserted into tunnel roof and other hollow cuts for checking the alignment, grades, levels etc and also the maximum excavation lines. Sufficient accuracy shall be maintained in this job. While actual tunnelling, a minimum stretch of 10 m from the junction with the existing tunnel shall be removed only after the entire work of tunnelling and laying of penstock is completed in that section. Latest technology shall be adopted for setting out works such as Total Intelligent Station and Laser to get proper Hand-Shake in tunnels excavated from different faces. One bench mark and other reference points shall be fixed by PROJECT MANAGER in the works area and the position and location of these shall be intimated to Contractor, who shall fix his permanent points and bench marks with reference to these points. Contractor shall carry out tunnel excavation true to alignment, grade and levels within a tolerance limit of 75 mm and shall continue to check them regularly. He shall provide suitable rigs and make arrangements for moving these along the alignment and grade of tunnel and shafts to check the dimensions of minimum excavation lines.

4.2

4.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 14 OF 21

Doc. No TCE.5270A-H-112-601

5.0 5.1 5.2 5.3

EXCAVATION LINES Typical cross sections, excavation lines, and dimensions of excavations and thickness of lining, where appropriate, are shown on the Tender Drawings. "A"-line (Minimum Excavation Line) shown on the drawings is the line within which no rock and no support, other than permanent support systems will be permitted to remain. Contractor shall perform excavation works in such a way, which guarantees that the theoretical thickness of the concrete lining is never reduced. All out-of-line excavations shall be rectified so that A"-line as defined above is maintained. Immediately behind the face, excavated profile shall be measured by means of a profile template or any other method approved by PROJECT MANAGER. Excavation not shown in Construction Drawings and not included in the Schedule, but which Contractor considers necessary for his own purposes, such as excavation for passing and turning niches / train switches or stations, rail foundations, mucking pits, pump sumps, drain ditches other than those shown in Drawings, adits, spaces for supply facilities, may only be carried out with prior approval of PROJECT MANAGER. All such excavations shall be backfilled with Class M15/A40 concrete up to B"-line prior to commencement of final tunnel or shaft lining. Location of portals shown in Construction Drawings is only approximate. Actual position will depend on the ground conditions and will be determined by Project Manager during progress of work. OVERBREAK Excavation beyond the "A"-line is defined as over break. In case cavity or chimney formation occurs during the excavation works, they shall be deemed to be covered by this definition of "Over break". Geologically accepted Over break in underground excavation is defined as a locally originated Over break which occurs while each of the following three conditions is simultaneously fulfilled: a) b) c) Over break occurs above the tunnel invert level, i.e. Over break at invert will not be recognised, PROJECT MANAGER is immediately informed and given an opportunity for inspection while both the cause and extent of Over break are clearly visible, Over break was, in the opinion of PROJECT MANAGER, not result of Contractor's using improper or improperly applied working methods or his otherwise negligence, and could not have been prevented by prompt and appropriate installation of supports.

5.5 5.6

5.7

6.0 6.1

6.2

6.3

Contractor shall survey and plot cross sections at sufficient intervals (say 2 m) to allow for a reasonably accurate estimate of the volume of over break, which he claims to be due to geological surprises. All voids created by over break shall be filled up with concrete or shotcrete. The class of concrete and time of placing of the concrete shall be as instructed by PROJECT MANAGER. The cross section for purpose of measurement shall be taken by establishing the tunnel centre line and the springing level. The cross section shall be recorded by taking off sets correct to

6.4

6.5

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 15 OF 21

Doc. No TCE.5270A-H-112-601

nearest cm at a regular interval of 30 cm above and below springing line. These readings shall be plotted against the design sections to indicate any under cuts, over cuts etc. For tunnels as well as shafts, the sections shall be plotted at 5 m intervals. 7.0 SUPPORTS FOR UNDERGROUND EXCAVATION 7.1 Provisional or permanent supports for underground excavation shall principally consist of the shotcrete with or without wire mesh as primary element and supplemented as needed by individual or pattern rock bolts. Structural steel supports shall be used only when required by the rock conditions as determined by PROJECT MANAGER. . PROJECT MANAGER, after consulting with Contractor, will determine the rock support system to be used during particular excavation advance and his decision shall be final in this regard. Contractor shall employ competent engineers and supervisors who shall inspect each rock face through out the duration and after each excavation advance and ensure that the rock support system is installed as ordered. Required supports shall be installed without delay during the process of excavation within the heading zone, without which further advance shall not be allowed. In the rear zone, additional supports shall be installed immediately after it is observed that the natural material or the supporting system previously installed is not sufficient to prevent further loosening of the material surrounding the excavation. Shotcrete, with or without steel wire mesh, shall be applied to excavated surfaces in accordance with the provisions of the Section "Shotcrete". Contractor shall take into account in his construction planning that placing of shotcrete support may be required immediately after blasting a round but before mucking-out is started. Rock bolts, rock anchors, wire mesh and structural steel supports shall be installed in accordance with the provisions of the Section "Rock Supports". Timber is not permitted for tunnel supports in any form, even for temporary purpose. Contractor shall bear whole responsibility for the proper and safe execution of works, including the provision of extra supports and special protection for the personnel even though he works under directions of PROJECT MANAGER.

7.2

7.3

7.4

7.5

7.6 7.7 7.8

8.0

CLASSIFICATION OF UNDERGROUND EXCAVATION 8.1 Compactness or fracturation of the rock and the inflow of groundwater during excavation shall not be taken as the criteria for assigning of the excavation classes. Underground excavation is divided into different classes in order to differentiate the difficulties and hindrance during excavation work, which the Contractor has to cope with, due to the properties of material encountered. Difficulties caused by the ingress of excessive water during the excavation are covered in the section Dewatering during construction The class of excavation is defined in relation to the hindrance in the progress of the excavation works caused by the type and amount of rock supports installed, and approved by the PROJECT MANAGER during excavation within the tunnel heading zone. No excavation classes shall be applicable for the excavation of caverns or shafts by any method, or where multi drift or multi segment al excavation is performed. .

8.2

8.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 16 OF 21

Doc. No TCE.5270A-H-112-601

8.4 8.5

Subsequent or supplementary installation of supports behind the heading or bottom range zones shall have no influence on the designation of the excavation classes. The definition of each excavation class is based only on the supporting measures installed and shall be valid irrespective of the excavation method used, i.e. full-face or partial excavation (e.g. top heading and benching). The assignment of an individual excavation class shall always apply to the whole of the theoretical excavation cross section as defined by the "B"-line, even if the partial excavation method is being used. The underground excavation classes are specified as follows: Class I Definition: Installation of rock supports does not cause any hindrance to the excavation work. Measures: The excavated section remains basically unsupported and individual rock bolts or anchors and shotcreting in localised areas, which may be applied, will not be taken into consideration for classification purposes. Class II Definition: The installation of supports causes minor hindrance of the excavation work, but basically it does not influence or delay the progress of excavation. Measures: Support system consists of shotcrete which is applied to the ordered thickness possibly with some rock bolts or anchors, or pattern rock-bolting or anchoring. Class III Definition: Installation of supports causes some hindrance and slowing down of the excavation work. Measures: Support system consists of shotcrete in one or more layers and pattern rock-bolting or anchoring, possibly combined with wire mesh as shotcrete reinforcement. Class IV Definition: Installation of supports causes a heavy hindrance of the excavation work, such that support installation becomes a part of the work cycle. Measures: Support system consists of steel ribs, with or without invert bracing, and steel or pre-cast concrete lagging (backfilled with concrete) may be required; the steel rib supports must be complemented with rock bolts or anchors and shotcrete, and with wire mesh between or encasing the steel ribs. Class V Definition: Excavation is only possible by heading and benching with the simultaneous installation of supports, and under their protection. Measures: Support system consists of steel ribs, wall plates and lagging placed continuously at the face immediately after excavating any part of the cross-section; steel ribs and lagging shall be complemented with systematic rock bolting or anchoring and the steel ribs may have to be completely encased in shotcrete, with wire mesh reinforcement as required, when lagging is not used. The Class of rock excavation shall decided by the Project Manager in consultation with a competent Engineering Geologist and is binding on the Contractor

8.6

8.7

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 17 OF 21

Doc. No TCE.5270A-H-112-601

9.0 9.1

EXCAVATION Excavation Procedures 9.1.1 Before commencement of underground excavations for tunnels, Contractor shall construct a portal of sufficient rigidity. In this excavation, Contractor shall deploy to maximum extent the Back hoes, pavement breakers and even manual labour, in order to reduce impact on nearby structures. This portal shall be of reinforced concrete or steel ribs-shotcrete-wire mesh construction or excavated surface supported with shotcrete wire mesh and rock bolts depending on the rock conditions. 9.1.2 In tunnelling, fore poling and advance probing shall be carried out as directed by PROJECT MANAGER. . 9.1.3Contractor shall use drilling and blasting techniques which will produce a smooth final profile, a minimum of over break and a minimum of fracturing of the rock beyond the required excavation lines. Techniques used shall be at all times subject to Project Managers Consent, who may order several blasting tests to be undertaken by the Contractor to substantiate his proposed methods of blasting.

9.1.4

Blasting pattern proposed to be adopted shall be submitted well in advance to PROJECT MANAGER for approval. However, during the progress of excavation the drilling and blasting pattern, specifically number and depth of holes, quantity, quality, and distribution of explosives, shall be varied as necessary to suit the rock conditions encountered, taking into consideration the information obtained from the pilot holes and actual drilling work (velocity, colour of rinsing water, etc.), as well as of the previous blasting results. Only wet drilling is permitted in order to reduce dust in the underground excavations. Perimeter drill holes shall be placed to control over excavation beyond "A"-line. Utmost caution shall be exercised to obtain a smooth uniform excavation surface. Should the entire length of most of the perimeter drill holes not be visible after each round of blasting, blasting pattern used shall be reviewed and approval obtained. Any damage to, or displacement of the supports, and any damage to any part of the Works caused by blasting or any other of Contractor's operations shall be repaired by him in a satisfactory manner at no cost to Owner.. No new round shall be blasted until the support work required within or behind the heading zone has been installed.

9.1.5 9.1.6 9.1.7 9.1.8

9.1.9

9.1.10 Immediately following blasting and at frequent intervals during the progress of the work, and finally during clean-up prior to placing the final tunnel lining, all rock material projecting inside the A line and loosened material that is likely to fall shall be removed. 9.1.11 Contractor shall constantly check the progress of excavation by means of Laser survey in order to avoid any substantial rectification of the already opened profile and eventual rearranging of the installed rock supports. 9.1.12 Where excessive inflows of water occur at the face, Contractor shall take special care to execute the excavation work safely and properly, including provision of extra supports and any special equipment necessary for working in waterlogged conditions.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 18 OF 21

Doc. No TCE.5270A-H-112-601

9.2

BlastingAll tunnels and shafts excavations shall be performed by controlled blasting techniques as described below. Controlled blasting: consists of drilling a number of closely spaced holes along the final excavation perimeter, placing light charges in the holes and detonating the charges at the end of round. The outer line of drill holes for the main blast is set at an approved distance inside the final perimeter leaving an annulus of rock to be peeled off the damaged final excavation perimeter by the smooth blast. The smooth blast holes are drilled, charged and blasted in the same tunnelling cycle as the main blast. Pre-splitting: Consists of drilling a single row of closely spaced holes along the final excavation perimeter. These holes are lightly charged and detonated before the main blast, to produce a pre split crack which limits the propagation of cracks from the subsequent main blast, and in such a way reduces damage in the rock beyond it. The blasting of the main excavation zone requires a reduced explosive charge in the line of holes nearest to the pre split line, and a limit on the distance between the pre-split line and the nearest line of main blast holes. The pre split holes shall be drilled deeper than the depth of the round. Cushion blasting: A special case of blasting in which considerable air space or stemming surrounds charges in the holes and serves to reduce undesired blast effect on the final excavation perimeter. Contractors controlled blasting techniques shall be considered acceptable and in conformity with Specifications for Controlling the completed rock surfaces if : i) At least 50% of the drill hole traces of each round are visible in the final rock surface, distributed uniformly, after the scaling down of all loose and shattered rock that is liable to fall before or during rock reinforcement installation and if all drilling hole traces are between A & B lines. PROJECT MANAGER may modify the above criteria if, in its opinion, the achievement of such results is not reasonably possible because of adverse rock conditions.

ii)

9. 3

Line drilling in Tunnel and Power House (1) Line drilling is carried out where control perimeter blasting may cause excessive damage to the surrounding rock or where there are structures adjacent to the excavation. (2) Line-drilling is defined as a single row of unloaded holes drilled along the neat excavation line, spaced no more than two to four times the hole diameter on centres. These will form a surface of weakness along which primary blast can break. Light blasting with well-distributed charges fired after main excavation is removed may be permitted in these holes. If blasting is considered to injure rock, use of explosives shall be discontinued and excavation shall be completed by broaching, wedging, or barring.

9.4

Protection of Tunnel Invert In case small grain or broken excavation material is used for invert protection, it shall be removed prior to placing of invert concrete or the final tunnel lining. No vehicular traffic shall be permitted over the tunnel invert after removal of the protective material.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 19 OF 21

Doc. No TCE.5270A-H-112-601

9.5 Excavation of Caverns/Chambers Initially a central heading along longer axis shall be excavated and supported with the primary supports. The either side of the heading shall be excavated by slashing and shall be supported simultaneously as shown on the drawings. Contractor shall get his excavation sequence approved, indicating the line, level and sequence numbers of excavation methodology. He shall be allowed to carry out benching only when the entire primary rock support as envisaged in Drawings is fully placed in entire width of the chambers and accepted by PROJECT MANAGER. 9.6 Excavation of Shafts Shafts shall generally be excavated by full sinking method. In case the Contractor prefers to excavate any of the shafts by first driving a Pilot shaft followed by slashing, Owner is not liable to bear any additional expenses as it is Fixed Price Contract. 10.0 EXCAVATED MATERIALS Use and or Disposal of excavated materials Contents of similar paragraphs under Surface Excavation fully apply hare. 11. 0 EVACUATION OF WATER Contractor shall carry out all work required to drain service area of infiltrated groundwater during construction as stipulated in the Section "Dewatering during Construction". 12.0 12.1 CONCRETE FOR BACK PACKING Concrete for tunnel lining shall conform to the grade given below: Grade Slump in mm Comp. strength (28 days) Max aggregate size Min cement = kg /cum M- 20 80 125 200 kg / cm 20 mm 350

Self Compact concrete using fly ash is the preferred option to ensure proper back filling without gaps. 12.2 A system of agitator cars for transporting concrete, concrete pump for placing concrete in position through suitable windows in the shuttering system and vibrating by internal / external vibrator etc shall be deployed as required.

12.3 Especially in job of Concrete back packing behind the inclined tunnel steel liners, utmost precaution is needed to ensure that concrete shall not segregate before placement. For this purpose, correct type of mix design, slump control, right admixtures, equipment and procedures all have to be put into place, after due deliberations with Project Manager Method used for transporting, placing and consolidation of concrete all shall lead to homogeneous concrete before initial set takes place and uniform surface free from rough patches, air holes etc. For this purpose, quick transportation by agitator cars which are kept constantly rotating the mix before transferring this to concrete pump all shall be arranged. Self compacted concrete and slow setting admixtures will have to be used as situations demand, o avoid segregation of concrete while pouring. 12.4 Concrete shall be placed by pump of sufficient capacity to ensure desired rate of progress. Discharge lines should be straight to minimise friction and clogging of pipe. Flow of fresh, plastic and un separated concrete of proper consistency should be constant to avoid a plugged or clogged pump line and also avoid cold joints. This line should be rigid and strong

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 20 OF 21

Doc. No TCE.5270A-H-112-601

enough to withstand the impact of placing during operation and, if required, may be cooled of excessive temperatures. Immersion type vibrators are more effective in concrete vibration, so these shall invariably be used. 12.5 Suitable admixtures like retarders, plasticizers, air-entrainers may be used with concrete for proper placement of a homogeneous concrete. Concreting shall be planned depending on the external weather conditions. 12.6 Hand placing of concrete may be permitted by Project Manager only if quantity is small and other means are not practicable. Utmost care should be taken here to avoid segregation of concrete. 13.0 Form work: Form work as needed for concrete lining of Surge shaft and any other components consist of approved type of telescopic, collapsible steel shuttering of robust design of suitable lengths. It shall be capable of being removed and re erected without disturbing the concrete lining and other forms placed, also without hindering the concrete placement in other stretches. This should have, on sides, openings of suitable size at close intervals for facilitating of concrete pumping concrete and insertion of vibrators and also for inspection during concreting. These shall be flush with the lining to produce uniform surface finish, but should not cause leakage of concrete. Such forms shall be removed only after 24 hours after completion of concreting. Subject of Shotcreting in tunnel excavation has been outlined in Section B6: Shotcreting and Grouting behind the Steel liners has been dealt with under Section B7: Drilling and Grouting. 14.0 14.1 SAFETY CODES AND STANDARDS In execution of Works, latest revisions of I S codes shall be followed. If the Write up conflicts with I S codes, latter shall prevail. Where no Indian codes exist, relevant British or American Standards shall apply. Following I S codes shall form part of these Specifications. IS 4081 - Safety code for Blasting and related Drilling operations. IS - 4138 - Safety code for working in compressed air IS - 4167 - Glossary of terms relating to air pollution IS - 4756 - Safety code for tunnelling Work IS - 4880 (All parts) Code of practices for design of tunnels conveying water. IS - 5878 (All parts) -- Code of practices for construction of tunnels. Safety measures as per Indian Mines Regulations and Indian Explosive Act 14.2 Safety precautions: Material contained here is in addition to that provided in Part 2, Volume- II on Safety matters. 14.2.1 Wet drilling shall be adapted to ensure dust free conditions within shaft. 14.2.2 Blasting shall be controlled such that the peak particle velocity at any adjacent/ nearby structure is within safe limits as determined by seismologist. Contractor shall devise appropriate blasting pattern by resorting to trial blasts and get the pattern regularly approved by Project Manager before general adoption. Hoisting equipment shall have suitable standby power supply arrangement for mechanical operation as specified in IS 807 Code of

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES UNDERGROUND WORKS AND TUNNELING

VOLUME: IV PART: 3 SECTION: B4 SHEET 21 OF 21

Doc. No TCE.5270A-H-112-601

practices for design, manufacture, erection and testing ( structural portions) of cranes and hoists A limit switch or automatic brake shall be provided on the hoist to control speed. 14.2.3 If Contractor selects, installs and operate rail transport system for underground works it shall comply with all requirements for such systems stipulated in the Section "Safety Precautions". If chain of cars is deployed, one man in front shall carry whistle and flash light for warning men inside. 14.2.4 If adapting rail movement for muck carriage, the track shall be properly laid with points, crossing and junctions. Dead man switches or other installations as required for checking accidents due to runaway muck cars. Trolley speed shall be under control all the time. 15.0 15..1 VENTILATION AND CONTROL OF DUST, SILICA AND NOXIOUS GASES Contractor shall install and operate equipment and carry out all works required for the ventilation and control of dust, silica and noxious gases as stipulated in the Section "Safety Precautions" Concentration of various gases by volume inside the tunnel, shaft and adit shall reasonably conform to the following limits to avoid any harmful effects on personnel working inside. a) Oxygen Not less than 19.5 % b) Carbon Monoxide Not more than 0.005 % c) Carbon dioxide not more than 0.5 % d) Nitrogen fumes not more than 0.0003 % e) Methane - Not more than 0.5 % at any place in the tunnel, even in cavity in the roof. f) Hydrogen sulphide not more than 0.001 % g) Aldehydes Not more than 0.0002 % Besides using only battery operated electric locomotives, in tunnel work, 4.5 cum of air per minute shall be considered as the minimum requirement per man. If diesel equipment is used, 4.50 cum of air are needed per minute per each BHP of prime mover. COMMUNICATION SYSTEM Contractor shall install and operate the communication system between each face and entrance to tunnel or shaft as stipulated in the Section "Site Installations".

15.2

15.3

16.0

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 1 OF 6

Doc. No TCE.5270A-H-112-601

1.0

SCOPE OF WORK 1.1 Works under this Section include all labour, materials, tests, equipment and services required to protect, stabilize or support rock faces, cuts, slopes and masses exposed in the course of surface and underground excavation works, as well as the anchoring of any concrete structures into surrounding or underlying rock. 1.2 1.3 This Section covers Rock bolt (Expansion shell) and rock anchor, Principal works required are as follows: a) b) Stabilizing of surface slopes and cuts: Rock supports in tunnels,

2.0 2.1

GENERAL Rock stabilizing and supporting measures in surface work may be warranted in Barrage and Power house. Contractor shall be equipped to handle works in technically competent and safe manner, considering the presumed behaviour of the rock or ground. PROJECT MANAGER retains the right to order Contractor to change the method or system of rock supports being used, if he considers that Contractor's method of work is unsafe. The principal rock types in and around the area of project Works including Under ground tunnel portion are known to belong to Plateau basalts of Deccan Volcanism of Cretaceous age, such as Massive basalts, Jointed basalts, Amygdaloidal basalts with a few vescular with vesicles filled up by quartz rock type and chalcedony. More details are furnished in Part 5 Appendix-1 Report on Geology and geo-technical Assessment. Hence rock bolting shall not be required as a matter of course. However if site situation warrants rock stabilisation, Contractor shall be duly equipped with suitable equipments to execute the same even though this might have not been included in this Chapter. In underground works, installation of rock supports shall follow closely the excavation and done before next round of excavation. Contractor is responsible for timely and proper installation of the rock supports and for checking and maintaining it until the final lining or structure is placed. Nothing contained in this Section shall be construed to relieve the Contractor from sole responsibility either for safety of Works or for liability for injuries to or death of persons or damage to property, or of any of his obligations under this Contract. Contractor shall also be equipped with grout pumps of appropriate type for grouting of rock bolts and rock anchors when required. SUBMITTALS Within 15 days of Order to Commence, but before procuring or shipping the materials to Site, Contractor shall submit to PROJECT MANAGER the following: a) b) Full details of type and quality of rock reinforcement which is proposed to use together with manufacturer's instructions and certificates, methods of installations and testing. Complete details concerning type, and materials of the post-tensioned rock bolts (tendons), if considered applicable, together with all installation and other technical details.

2.1 2.3

2.4

2.5

2.6

2.7 3.0 3.1

3.2

Not later than 15 days prior to ordering any of the above materials, Contractor shall submit his proposed materials delivery schedule. Any amendments to the delivery, if demanded later, will also have to be got approved.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 2 OF 6

Doc. No TCE.5270A-H-112-601

3.3

Contractor shall record results of all tests performed on the rock bolts prior, during and after their installation, record the readings taken at the load cells installed and submit to PROJECT MANAGER. Rock Bolt (Expansion Shell), Rock Anchor, Rock Bolt (Grouted Anchorage) Rock Bolt (Expansion Shell) This is a stressed (i.e. post-tensioned) reinforcing element consisting of a rod, an expansion shell anchorage, a plate and a nut for stressing by tightening the nut. Expansion shell rock bolts shall be of 25 mm and shall be of lengths as specified in Bill of quantities (for longer lengths, couplers may be required).These shall be manufactured from reinforcing bar of Yield strength above 500 N/mm2 (Reinforcing bar shall comply with IS 1786). When coupler is used, the threading in the bar shall not reduce the effective diameter of bar. Coupler itself should be able to transfer at least 125 % of the yield load of the bar. Rock bolts shall be furnished complete with all accessories and other materials needed for their installation, fixing, stressing and grouting.. 25mm diameter rock bolt 1 no. plate of 150x150x10 mm

4.0 4.1 4.1.1 4.1.2

4.1.3

4.1.4 Bearing plates shall be flat steel plates of following minimum dimensions: Plate shall conform to IS 2062 for Structural Steel and nuts of heavy hexagonal type. 4.1.5 Threads on projecting ends of bolts shall be protected, duly lubricated with rust preventive compound. 4.1.6 Expansion shell rock bolts shall be tensioned to following maximum values: 25 mm dia. rock bolt 15 t. Diameter drilled for installation of these shall be 45 mm. 4.1.7 Length of drill hole shall be such as to receive the specified rock bolt and to provide for its satisfactory anchorage and sufficient protrusion of the threaded portion out of hole to fix plate, nut, and coupling for any kind of extension piece. The holes shall extend 150 to 200 mm beyond the length of the rock bolt or anchor. 4.1.8 After drilling each hole in sound rock, drill hole shall be washed with clean water and cleaned by blowing out all drill cuttings and debris with compressed air. Holes in rock, which tend to swell or interspersed with clay filled fissures, shall be cleaned with compressed air only. Compressed air shall not contain oil or any other material which could prevent the bond between rock and grout. 4.1.9 Prior to installing rock bolt, which will be stressed, rock surface around the hole shall be prepared for the bearing plate. When surface is not perpendicular to hole axis, bevelled washer shall be placed between bearing plate and nut or dished bearing plate and hemispherical washer used, to ensure uniform bearing. 4.1.10 Rock bolts shall be stressed immediately after installation in hole, by torque or jacking by means of a regularly calibrated stressing device to an extent specified by manufacturer on basis of values established during pullout tests. 4.1.11 After initial installation, rock bolts should continue to act as effective supports by periodically testing these and, if necessary, re-tightening to required torque or tension, till grouted.

4.1.12 Grouting of expansion-shell rock bolts shall be performed without de-stressing the bolt. It shall
be performed soon after, but in any case not later than 7 days of rock bolt installation. Bearing plate shall be caulked around its perimeter and grout shall be introduced into hole through a plastic tube fixed to the shaft and extended to outside through a hole provided in the bearing

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 3 OF 6

Doc. No TCE.5270A-H-112-601

plate, at a pressure sufficient to fill completely the space around each bolt for full length without any air-pockets remaining inside hole. A grout return tube through another hole in plate shall be provided to ensure full column grouting. 4.1.13 Grout mix used shall have a water cement ratio of not more than of 0.32. Grout mix shall contain an expanding plasticizer admixture (allowing up to 3.5% expansion in neat cement), from a reputed manufacturer and dosage of admixture to be as recommended by him. For additional workability, a compatible super-plasticizer may also be required. Grout mix shall have strength of 35 N/mm at 28 days. 4.1.14 Cracks and fissures adjacent to the rock bolt which the grout is found to be flowing from, during the grouting operation, shall be plugged or caulked at the excavation surfaces. 4.1.15 Prior to installation of rock bolts, a series of pull-out tests shall be carried out in different rock types and which will be representative of the rock expected to be encountered during the excavation. During this, both the load applied and movement undergone shall be measured. At least 5 tests shall be required for each combination of type of rock bolts/installation condition to be able to assess the suitability of expansion shells. These tests shall be carried out sufficiently in advance of installation of rock bolts. Contractor shall maintain detailed records of the tests and the results of which will be used to establish relation between rock quality and type of expansion shell and tensioning. 4.1.16 Invariably, such tests shall be performed in presence of Project Manager on at least 2 % of Rock bolts installed. In case of failure in tests, additional testing shall be performed on selected rock bolts installed near the failed one. These shall be replaced free of cost. If large scale failure is reported, effectiveness of whole lot of bolts installed shall be decided by P M. 4.2 Rock Anchor 4.2.1 Rock Anchor is an un-tensioned reinforcing element consisting of a rod embedded in a cement grout filled hole. Rock anchor shall have a plate and a nut. It may be stressed nominally or not stressed and shall be fully grouted with cement grout. 4.2.2 Rock anchors to be used in this project shall be of 25 mm and of length as specified in Bill of quantities. (For longer lengths, couplers may be required). 4.2.3 Rock anchors shall be manufactured from reinforcing bar of Yield strength above 500 N/mm2, the bars complying with IS 1786. When coupler is used, threading in bar shall not reduce effective diameter of bar. Coupler itself should be able to transfer at least 125 % of yield load of the bar.

4.2.4 Rock anchors shall be furnished complete with all accessories and other materials necessary for their installation, fixing and grouting. 4.2.5 Bearing plates shall be flat or dished steel plates of following minimum dimensions: 25mm diameter rock anchor 1 no. plate of 150x150x10 mm Plate shall conform to IS 2062 for Structural Steel and nuts be heavy hexagonal type. 4.2.6 Threads on projecting ends of anchors shall be protected, duly lubricated with rust preventive compound. 4.2.7 Diameter of hole drilled for installation of 25 mm rock anchor is 45 mm. Spacers (centralizer) to be used for 25 mm. rock anchors shall be longer by 4 m for equal grout annulus all around the bolt.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 4 OF 6

Doc. No TCE.5270A-H-112-601

4.2.8 Length of drill hole shall be such be such as to seat the rock anchor and to provide for its satisfactory anchorage and with sufficient provision of threaded portion out of hole to fix plate, nut and coupling and any kind of extension piece. Holes shall extend 150 to 200 mm beyond length of the rock anchor. 4.2.9 After drilling each hole in sound rock, drill hole shall be washed with clean water and cuttings and debris shall be blown with compressed air. The compressed air shall not contain oil or any other material which could prevent the bond between rock and grout. 4.2.10 Prior to installing the rock anchor, the rock surface around the hole shall be prepared for the bearing plate. When the surface is not perpendicular to the hole axis, bevelled washer shall be placed between the bearing plate and the nut, or dished bearing plate and hemispherical washer used, to ensure uniform bearing. 4.2.11 Both for overhead application and horizontal (slightly downward) application, the grout shall be introduced into the end of the hole through a pipe. The pipe will be gradually withdrawn as the hole is filled. 4.2.12 Grout shall have a water to cement ratio of 0.25-0.28. An admixture containing an efficient water reducing agent, a shrinkage compensating component and thixotropizing agent shall be used. The grout mix shall have strength development of min 25 MPa at 24 hours. Doses of the admixture shall be as per the manufacturers recommendation to achieve the required properties. 4.2.13 Anchor bar shall be forced into the grout-filled hole before the initial set of the grout and good contact between steel surface and grout ensured. 4.2.14 Anchors bars shall be protected after installations in such a manner as to prevent any movement until the grout has hardened. Any bars found to be loose after the grout has set shall be replaced promptly... 4.2.15 Invariably, such pull out tests shall be carried out in presence of Project Manager in at least 2 per 100 of cases. In case of failure in test, additional testing shall be performed on selected rock anchors installed in near the failed one. Rock anchors shall be replaced free of cost as directed 4.3 Rock Bolt / Rock Anchor Extensions into Concrete Threaded portion of Rock Bolts and Rock Anchor, where required to be extended into structural concrete, shall be protected during excavation and shotcreting and shall protrude sufficiently beyond shotcrete. Extension shall consist of a L-shaped reinforcing bar of similar size (as that of bolt/anchor) and shall be welded to bolt. Welding and overlap of bolt with extension piece shall be as approved by Project Manager. 4.4. 4.4.1 Drilling of Holes Holes shall be drilled as specified herein and in accordance with applicable provisions of Section "Drilling and grouting" at locations, depth and inclination shown in Drawings, deciding method and drill hole diameter appropriate type of ground. Diameter of holes shall be 125 mm minimum. Depth of hole shall exceed total rock bolt length (including the fixed length) by 500 mm or by such additional amount as required in case drill cuttings cannot be removed from the bottom of the hole. Holes shall be either drilled by rotary method with water flush or pneumatic percussion method with air and/or water flush or any other type such that the disturbances to adjoining

4.4.2

4.4.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 5 OF 6

Doc. No TCE.5270A-H-112-601

rock are minimal. Use of bentonite, rod grease or other lubricants on drill rods will not be permitted. 4.4.4 Drilling of holes shall conform to the least of the following tolerances: a) b) 4.4.5 Initial alignment when setting up the drilling rig shall not deviate by more than 2 from the specified axis of the drill hole Deviation of the hole during drilling shall be limited to 1/30 of the overall hole length.

During drilling operations, all changes in rock type should be recorded together with notes on drilling rates, flushing losses or gains, and stoppages and after drilling, the entire length of hole shall be washed out with clean water. Upon completion, the drill hole shall be tightly plugged in suitable manner to prevent contamination by foreign matter. Hole shall be washed clean prior to inserting the rock bolt. In loose material the walls of the drill hole shall be supported by casing until rock bolt has been installed. In earth or rock liable to swell the rock bolt shall be installed and grouted immediately. Any hole that gets clogged or otherwise obstructed before completion of rock bolting shall be cleaned or re-drilled. If not possible, another hole shall be provided.. Installation and Rock Bolt Grouting A reinforced concrete pad shall be constructed on the prepared excavated ground in accordance with provision of Section B8 "Concrete". Concrete shall be of Class M30/A20. No stressing of rock bolt may be performed until the cube compressible strength of base concrete has reached 20N/mm2. Such admixtures shall be added in concrete, which allow required strength to be developed within 72 hours. Tendon shall be slowly inserted into the hole in such a manner as to prevent damage and tangling of the individual wires/strands. At bottom of tendon sleeve or nose cone shall be used to minimize the risk of tendon or borehole damage during homing. Special care shall be taken to ensure that existing corrosion protection (epoxy coating) remains undamaged during insertion into the hole. After being inserted, rock bolt shall be fixed in position so that no displacement occurs during grouting work. Immediately after installing the rock bolt, primary grouting of anchorage zone and outside of sheathing shall be carried out, with grout pressure up to 20 bars. Grout shall have a water to cement ratio of 0.25-0.28. An admixture containing an efficient water reducing agent, a shrinkage compensating component and thixotropizing agent shall be used. Grout mix shall have strength development of min 25 MPa at 24 hours. Doses of the admixture shall be as per the manufacturers recommendation to achieve the required properties. Proper grout pipes shall be used to ensure grouting from bottom to top and achieve complete filling with neat cement grout. This requirement applies to all rock bolt grouting operations including end cap filling. As soon as possible, after stressing or re-stressing have been completed, secondary grouting inside and outside the sheathing shall be performed to encase completely the strands/wires for full length of hole and to fill all voids.

4.4.6

4.4.7 4.5 4.5.1

4.5.2

4.5.3

4.5.4

4.5.5

4.5.6.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES ROCK SUPPORTS

VOLUME: IV PART: 3 SECTION: B5 SHEET 6 OF 6

Doc. No TCE.5270A-H-112-601

4.5.7 5.0 5.1

Recess left in the concrete pad for accommodating the head shall be filled with concrete if not otherwise directed by Project Manager. Wire Mesh Wire mesh shall consist of welded wires in a fabric shape.. Wire mesh shall be installed in surface and underground excavation as reinforcement for shotcrete usually in combination with rock reinforcement. It may also be used with steel ribs, when it shall be laid over the outer flange of the rib and pinned or fixed to the excavated surface between the ribs where necessary. Wire mesh shall conform to IS 4948 (Welded Steel Wire Fabric for general use). The wire mesh shall have a square mesh of 100x100 mm spacing made of mild steel wires having yield strength not less than 275N/mm2. Diameter of wires shall be between 3 and 5 mm. Where possible, the wire mesh shall be placed at same time as the rock reinforcement installation. It shall not be placed between the rock surface and bearing plates, but over the heads of rock reinforcement and fastened to them by separate plates and nuts. It shall be ensured that the fabric is drawn close to excavated surface so that when shotcrete is applied subsequently, the mesh neither sags nor vibrates excessively and impair the effectiveness of the shotcrete. Welded wire mesh shall be fixed to rock with suitable mesh anchor (in addition to rock reinforcement near by, if any) of minimum 5 KN capacity at minimum spacing of 1m x 1 m. Usage of wooden pegs for fastening of the wire mesh to the rock surface will not be permitted. Wire mesh shall be firmly stretched between mesh anchors and drawn close to excavated surface. Overlap of wire mesh shall be at least 3 times the mesh spacing with the clearance between parallel bars but not less than 300 mm.

5.2

5.3

5.4

5.5

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 1 OF 8

Doc. No TCE.5270A-H-112-601

1.0

SCOPE OF WORK 1.1 The work under this Section includes all labour, materials, equipment and services required for the execution of Shotcrete work to be carried out by Contractor under this Contract. Shotcrete shall be applied to surfaces and in underground excavations, where shown on the Construction Drawings or as directed by PROJECT MANAGER. Contractor shall design the mix, furnish materials, place, cure and test shotcrete as necessary to provide temporary or permanent protection and/or support of excavated surfaces either in surface or underground excavations. Contractor shall furnish all materials, labour and equipment for preparing test panels, both for trial mixes and during the course of work and for testing cores from panels or from in-situ shotcrete.

1.2

1.3

1.4 When shotcrete is applied as a temporary rock supporting or protection measure, number and thickness of layers to be applied shall be governed by prevailing rock conditions. 1.5 When shotcrete is intended as a permanent lining or protection of rock surfaces, thickness of such lining shall be as shown in Construction Drawings. 1.6 Shotcrete shall be placed with or without steel wire mesh reinforcement, as directed and may be used in conjunction with rock bolts, steel ribs and other rock supporting measures. Contractor shall maintain adequate stockpiles of materials for shotcrete for immediate use in cases of emergency. Any damage or delay resulting from shortage of such materials shall be the Contractor's entire responsibility. Shotcrete is defined as a mixture of cement, aggregate, water and accelerators in correct proportions, with maximum size of aggregate less than 10 mm projected at high velocity from a spray nozzle on to a surface to form a layer of pneumatically applied concrete on that surface. Shotcrete can be either wet or dry mix. It will be used for protection and supporting rock surfaces after excavation, to fill the cavities caused by overbreak or weathering. Dry-Mix Process: The cement, aggregates and accelerator batched by weight, are thoroughly mixed dry (with enough moisture to prevent dusting) and fed into a purposemade machine wherein the mixture is pressurised, metered into a dry air stream and conveyed through hoses or pipes to a nozzle in which water as a spray is introduced to hydrate the mix which is projected without interruption into place. Wet-Mix Process: All materials including cement, aggregates weigh batched and mixed together with water, but without accelerators, to produce mortar or concrete. The mixture is then conveyed by positive displacement or compressed air to a nozzle where air, and accelerator, is injected to increase velocity, and projected without interruption into place. This is expectedly not required in this project. Layer is a term used for a discrete thickness of shotcrete built up from a number of passes of the nozzle and allowed to set. Rebound is a term used for all material, which, having passed through the nozzle does not adhere to the target surface.

1.7

2.0

DEFINITIONS 2.1

2.2

2.3

2.4 2.5

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 2 OF 8

Doc. No TCE.5270A-H-112-601

3.0

SUBMITTALS 3.1 At least 60 days from date of Order to Commence the following submittals shall be made for approval: a) b) c) Details, including numbers and type of equipment proposed for mixing and applying the shotcrete, Qualifications and experience of the proposed personnel (foremen, nozzlemen and delivery equipment operators), Manufacturers' certificates giving full details of any proposed admixture, and the Contractor's proposal regarding the use of such admixtures, including certification of harmlessness to operators, Contractor's proposed mix proportions prior to commencement of testing and work, Details of methods to be employed for controlling the thickness of the layers of shotcrete applied (e.g. plug gauges or boreholes).

d) e) 3.2

The selection of method, i.e. dry-mix or wet-mix process as defined above is Contractor's option. Should the Contractor intend to apply the dry-mix process, he shall submit to Project Manager all relevant documents and references to prove that such method will in no way impair quality and efficiency of Work and will not cause any increase in cost.

4.0 MATERIALS 4.1 General 4.1.1 Cement used in shotcrete shall be OPC conforming to IS: 8112 4.1.2 Cement, aggregates, water, admixtures, shall conform to the requirements of the Section "Concrete", except as specifically amended hereafter. 4.1.3 The water content of aggregate at the time of incorporating into the mix shall be less than 2% by weight of oven dry aggregate. 4.1.4 Air used to apply shotcrete shall be clean and free of oil and other contamination. 4.2 Aggregates 4.2.1 Aggregate gradation used in shotcrete shall conform to those established by the preconstruction trial mix tests. The gradation shall not be changed without the prior approval of Project Manager . 4.2.2 The following aggregate gradation shall be taken as a guide for mix design purposes, but may be modified, subject to the results of the trial mix tests specified hereinafter: Square Mesh Sieve Opening 9.50 mm 4.75 mm % Passing (by weight) 90-100 73-100

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE
2.36 mm 1.18 mm 0.60 mm 0.30 mm 0.15 mm 0.075 mm 55-90 37-72 22-50 11-26 4-12 2

VOLUME: IV PART: 3 SECTION: B6 SHEET 3 OF 8

Doc. No TCE.5270A-H-112-601

4.2.3 Should the nature of the aggregates used during the course of the work change (e.g. source, rock type, shape) from that used in the trial mix tests, the Contractor shall produce new trial mixes, using the new aggregates. 4.3 Admixtures 4.3.1 Admixtures shall be used to develop fast setting and high early strength of shotcrete, to ensure good workability, low pumping pressure, adequate slump retention and low rebound, conforming to relevant standards. Only proven admixtures which meet the requirements of the specifications on field trials and long-term satisfactory performance on other projects already constructed shall be approved .The consumption of admixtures shall be recorded daily. (1) Super-plasticisers: Shall meet the requirements of ASTM C 494 type F shall be compatible with cement & accelerator. Super-plasticisers shall be added at the batching plant to keep the shotcrete mix workable during transportation and to ensure good pump ability at an acceptable low water cement ratio. The Superplasticisers shall be free of chlorides. Accelerators: Only liquid accelerators shall be used. The accelerator shall be added at the nozzle. -The maximum dosage shall not exceed 6 % (by mass of cement) 4.3.2 Testing of accelerators in accordance with this specification with regard to setting time and early strength gain shall be in accordance with the following a) b) Initial set of cement/admixture paste Final set of cement/admixture paste 3-hour strength of shotcrete 8-hour strength of shotcrete 24-hour strength of shotcrete 3 min 12 min 0.7 N/mm2 4.0 N/mm2 10.0 N/mm2

(2)

5.0

MIX DESIGN AND QUALITY REQUIREMENTS 5.1 Shotcrete mix shall be designed by the Contractor such that they achieve the strengths specified. The mixes shall be approved by Project Manager.

5.2 The cube compressive strength at 28 days for structural or permanent shotcrete shall be 35 N/mm2 and compressive cylinder strength shall be 28 N/mm2. The compressive strength after 7 days shall reach 70% of the specified strength at 28 days. 5.3 To determine that the shotcrete meets the requirements to the compressive strength, the in-situ strength requirements given below shall be met, which are based on a 50

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 4 OF 8

Doc. No TCE.5270A-H-112-601

mm diameter by 100 mm long core and include a 0.85 reduction factor to allow for effects of in-situ coring. Minimum compressive strength (Mpa) Strength class Core C28/35 24

5.4

Mixes shall be such that the aggregate gradation and cement content after placing are as those obtained from samples taken from test panels produced using approved trial mixes. All constituents shall be uniformly dispersed throughout the mix, and the 3 assumed cement content shall be 400 kg/m . Water content of the mixes shall be limited to prevent sloughing. The water-cement ratio of fresh shotcrete in place shall be between 0.32 and 0.40. Project Manager reserves right at any time during the progress of the work to instruct the Contractor to vary the proportions of the constituents of the shotcrete or order further trial applications to ensure that adequate strengths are maintained. For purpose of approving mix design by Project Manager Contractor shall prepare initially not less than a set of three test panels for each mix for testing at least 30 days before any shotcreting work is started. For any subsequent change in additive or equipment, Project Manager may order fresh testing. All tests shall be done as per IS: 516 and IS: 9012. For the purpose of routine quality control, the number of panels to be supplied shall 3 generally consist of 3 for every 50 m of shotcrete to be placed. A set of three test panels for mix design approval and for routine quality control shall consist of one shot downward onto a horizontal surface, one shot onto an inclined or vertical surface and one shot overhead onto a horizontal surface. Test panels for shotcrete quality control and to determine the suitability of additives shall be made as specified herein and in accordance with the requirement of Project Manager. The Contractor shall furnish all plant, materials and assistance necessary and carry out all work to obtain representative tests panels of shotcrete. Test panels shall be obtained by securely attaching an approved 1 m x 1 m by 100 mm deep timber box to an area of rock similar to that to be shotcreted or an approved alternative surface arrangement, wetting the box and applying shotcrete to the area contained by the box in the manner specified herein and using the same mixing and placing equipment to be used for the works. All test panels shall be of a minimum thickness of 100 mm, and shall be made in the presence of Project Manager. The panels shall be left undisturbed at the point of placement until the final set has taken place. Test panels and specimens shall be transported by the Contractor to the site laboratory immediately after final set has taken place, not sooner than two hours and not later than eight hours after manufacture, and in such a manner as to prevent them from being damaged in any way.

5.5 5.6

6.0

TESTING 6.1

6.2 6.3

6.4

6.5 6.6

6.7

6.8

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 5 OF 8

Doc. No TCE.5270A-H-112-601
6.9

Compressive strength tests shall be performed on drilled cores from the sprayed concrete structure or from the sprayed test panels. Their minimum diameter shall be 50 mm and the height/diameter ratio shell be in the range of 1.0 to 2.0. Test results from cores with height/diameter ratio different from 2.0 shall be converted to equivalent cylinder strength using the values given in table below. Conversion factors to equivalent cube and cylinder strengths. Cube factor 1.15 1.12 1.10 1.07 1.03 1.00 0.88 Cylinder factor 1.00 0.97 0.95 0.93 0.89 0.87 0.76

Height/diameter ratio of core 2.00 1.75 1.50 1.25 1.10 1.00 0.75

6.10 Core test results will be statistically analysed in accordance with the recommendations of IS: 456. Test results shall meet all the acceptance criteria specified in IS: 456. 6.11 If tests performed on cored specimens indicate that the shotcrete fails to meet the specified requirements of insitu strengths then Contractor shall carry out such remedial works as Project Manager may require, including placement of additional shotcrete, and if deemed necessary repair and/or removal and replacement of shotcrete. 7.0 7.1 7.2 EQUIPMENT Only modern, properly operating mixing, delivery, and placing equipment approved by Project Manager shall be used for the performance of the work. Compressor shall provide a supply of air adequate to maintain sufficient nozzle velocity for all parts of the work while simultaneously operating a blowpipe for clearing away rebound when required. The delivery equipment shall be a pneumatic feed type or, for the wet-mix process, positive displacement type. The equipment shall be capable of delivering a continuous smooth stream of uniformly mixed material at the proper velocity from the discharge nozzle at all heights of the work. Delivery equipment shall be properly cleaned after each shift. Its parts,especially nozzle liner and water ring shall be regularly inspected and replaced as required. The discharge nozzle, for the dry-mix process, shall be equipped with a manually operated water injection system (water ring) for directing an even distribution of water to the aggregate- cement mixture. The water valve shall be capable of ready adjustment to vary the quantity of water and shall be convenient for the nozzle man. Water pressure shall be maintained at a uniform level which shall be at least 1 bar above operating pressure and sufficient to ensure adequate hydration at all times. The nozzle shall be capable of delivering a conical uniform discharge stream. Distortion of this stream shall be remedied by examination of the nozzle and any malfunction rectified by replacement of defective parts before further work is carried out.

7.3

7.4 7,5

7.6 7.7

8.0

PROFICIENCY OF WORKMEN

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 6 OF 8

Doc. No TCE.5270A-H-112-601
8.1

Nozzlemen shall have had previous experience in the application of coarse aggregate shotcrete or shall work under the immediate supervision of a foreman or instructor with such experience. Each crew shall demonstrate acceptable proficiency in the application of shotcrete to vertical and overhead test panels before beginning production work. Only approved work crews shall perform the work. Acceptable shotcrete shall consist of a dense uniform concrete without major rebound inclusions and discernible weakness of bond between layers. Nozzle men shall shoot shotcrete with uniform consistency and at the wettest consistency short of the sag point. Nozzle shall be held at a predetermined distance and position so that the stream of flowing material shall impinge as nearly as possible at right angles to the surface to be covered. When shotcrete is to be applied to excavated surface immediately after blasting, the surfaces shall be prepared by a minimum of scaling followed by washing with clean water. All surfaces shall be wet & clean and already shotcreted surface on which another shotcrete layer is to be placed, free of rebound, at the time of application of shotcrete. The surface shall be kept moist until shotcrete is applied. Where water flows from rock against which shotcrete is to be placed and that water cannot be sealed off by shotcreting alone, the water shall be excluded from the area by caulking or diverted by pipes, pans or other approved means in such a manner that the shotcrete will be unaffected by action of the water through percolation, by hydrostatic pressure or erosion. A layer of shotcrete, which is to be covered, immediately by a succeeding layer shall first be allowed to take its initial set. A layer of shotcrete, which is to be covered by a succeeding layer after its final set has taken place, shall have all laitance, loose material, dirt or other deleterious material and rebound removed by sweeping with brooms, sluicing or other means acceptable to Project Manager. Shotcrete surfaces shall be kept moist until either the succeeding layer of shotcrete is applied or alternatively the curing requirements set out in this Section have been observed. At any time during surface preparation, Project Manager may order Contractor to apply shotcrete to isolated areas before proceeding with surface preparation due to safety reasons in case of emergency.

8.2

9.0

SURFACE PREPARATION 9.1

9.2

9.3

9.4

9.5

10.0

MIXING AND PLACING 10.1 Shotcrete materials shall be accurately weigh-batched before mixing. Aggregates shall be thoroughly mixed without the addition of water before being deposited in the placing equipment. Mixes, which are not applied within 60 minutes of adding cement, shall be discarded. Rapid hardening additive shall be accurately proportioned. 10.2 The minimum thickness of shotcrete in any one layer shall be 25 mm. The maximum thickness of shotcrete applied in any one layer at any location shall be 50 mm. 10.3 Project Manager will examine rock faces after each blasting and scaling in underground excavation. On examination, he may require, immediate shotcreting of surfaces, in which case shotcrete shall be applied within 4 hour of blasting and before drilling the next round. Shotcrete equipment shall be available before blasting where poor rock conditions are anticipated so that shotcrete can be applied with minimum delay.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 7 OF 8

Doc. No TCE.5270A-H-112-601

10.4 Shotcrete, other than that placed soon after blasting, shall not be placed in any area till completion of all blasting within 20 m of the area, unless ordered otherwise by Project Manager. 10.5 Shotcrete in open area works shall not be carried out when shotcrete cannot be placed effectively because of adverse weather conditions, unless adequate cover is provided over the working area until the shotcrete has been cured sufficiently to prevent damage. 10.6 Contractor shall develop operating procedures and operations to give: a) b) c) d) e) minimum rebound, Smooth finished surface, no hollow areas in the shotcrete, minimum of shrinkage cracks, good adherence of the shotcrete to rock or other surface.

10.7 The flow of the material at the nozzle shall be continuous and uniform and the rate of application over any given area shall also be uniform. Slugs, sand spots, wet areas or other defects shall be cut out and corrected as specified herein. 10.8 An approved method of establishing layer thickness, such as the use of plug gauges or boreholes, shall be employed. 10.9 In shotcreting vertical or steeply inclined surfaces, other than roofs of underground excavations, application shall begin at the lowest point and the shotcrete layer shall be built up in horizontal strips until the entire surface is covered. 10. 10 Where drain holes have been drilled and instruments have been installed into rock on which shotcrete is to be placed, the Contractor shall take all necessary precautions to prevent such holes from being plugged or instruments from being damaged. 10.11 When shotcreting is to be performed near existing structures, Contractor shall ensure that no damage results to the structure and shall protect the surfaces of structures before and during shotcreting. 10.12 Application of shotcrete in any area shall be considered complete when the shotcrete has been built up to the thickness specified. The thickness of shotcrete specified on Drawings shall be the minimum thickness measured anywhere in the treated area, with the exception of protrusion of rock whose dimensions in plan are less than the thickness of the shotcrete specified, in which case the minimum cover shall be not less than the 2/3 of the specified nominal thickness. 10.13 Where shotcrete is placed over wire mesh and supporting bolts, it shall be covered with shotcrete to a depth of at least 25 mm. Where rock bolt extensions are to be added to existing rock bolts, the exposed ends of the rock bolt threads shall be suitably protected before shotcreting. 11.0 REBOUND 11.1 Rebound shall be kept to a minimum and continuously monitored. Special care shall be taken that rebound does not build up at the junction of walls and floors both underground and on the surface. 11.2 Rebound shall be removed and disposed of before any adjacent area is shotcreted. Rebound shall not be reused.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES SHOTCRETE

VOLUME: IV PART: 3 SECTION: B6 SHEET 8 OF 8

Doc. No TCE.5270A-H-112-601

11.3 Contractor shall make every effort to keep rebound to a minimum. If the rebound is excessive, Contractor may revise the mix design or the application procedures or take other measures deemed necessary to reduce the rebound. 12.0 PROTECTION, CURING, AND FINISHING 12.1 Suitable screening of the nozzle and of the application surface shall be provided during periods of windy or draughty conditions. 12.2 Freshly laid shotcrete shall be protected from rain or water until the surface is of sufficient hardness to prevent damage. 12.3 When dry specks first appear at the surface of any shotcrete layer, it shall be wetted with a water jet at least once in every 4 hours or otherwise cured for a minimum period of 7 days. Membrane curing shall not be used when a further layer of shotcrete or other bonded finish is to be applied. 12.4. In underground excavations and surface excavations the shotcrete shall be water cured.

12.5 The surface of the shotcrete shall be left as shot without any finishing. As an exception, the surface of the annulus of reinforced gunite placed at the internal surface of the tunnel concrete lining shall be smoothened. 13. 0 REPAIR 13.1 Before a succeeding layer of shotcrete is placed, the preceding layer shall be checked for drumminess. 13 . 2 Contractor shall repair all drummy, sandy, cracked or spalled areas and any other areas where, in the opinion of PM, the shotcrete is faulty, by removing the shotcrete to a sound area of rock or shotcrete, carrying out surface preparation as specified herein and replacing that area to the satisfaction of Project Manager. 14. 0 TOLERANCES 14.1 For shotcrete on natural surfaces or surfaces with an undefined shape, the thickness at any point shall not be less than 80% of the specified nominal thickness and also the average thickness of shotcrete shall not be less than specified nominal thickness. 14.2 The thickness over the individual protruding rock pieces may not be less than two-thirds (2/3) of the specified nominal thickness.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 1 OF 17

1.0 1.1

SCOPE OF WORK The work under this Section includes all labour, materials, equipment, operations and services required for the execution of drill holes, water-pressure test, performance of grouting in the holes from surface and from the underground construction sites, at locations shown in Drawings or as directed by Project Manager.. The following grouting activities shall be required to be executed in underground works: a) Contact grouting in all concrete lined tunnels. This contact grouting is performed to fill the voids between concrete lining and the surrounding rock b) Contact grouting in steel lined pressure shafts between backfill concrete and rock. c) Contact grouting between concrete and rock surface in tunnel plugs including diversion tunnel plug. d) Consolidation grouting in head race tunnel near adit junctions and other identified locations with poor geology. e) Consolidation grouting in surge shafts, pressure shafts and other shafts. f) Consolidation grouting during excavation process in headrace tunnels / shafts / caverns when geological conditions so require. g) Curtain grouting around tunnel plugs The following grouting activities shall be required to be executed in surface works: a) Consolidation grouting for surface excavations for dam, inlet and outlet portals of various tunnels and adits, when geological conditions so require. b) Consolidation grouting of dam foundations and foundations of the other structures such as tail race tunnel outlet. The following drainage activities shall be required to be executed in underground works: a) Drainage holes required during tunnelling activity. 1.5 The following drainage activities shall be required to be executed in surface works: a) Drainage holes (pressure relief holes) for surface excavation. b) Permanent pressure relief system in the dam foundation from drainage gallery.

1.2

1.3

1.4

1.5

The following exploratory drilling shall be required: a) Probe holes during tunnel excavation with or without coring b) Exploratory holes with or without coring in rock SUBMITTALS Drilling Prior to start of drilling (and / or grouting work) in any working area, Contractor shall give notice of and make available to Project Manager a drilling and/or grouting plan, with 30 days time to review. After the work got commenced and as the sub-surface conditions get disclosed, the drilling and grouting plan may have to be modified. Contractor shall be prepared and equipped for variations in the drilling and grouting work. Contractor shall make drilling logs and other pertinent information available to the Project Manager on completion of each work phase and as needed (Relevant only if Contractor conducts Geo tech investigations) Contractor shall provide to Project Manager Reports of results of each water-pressure test performed within one working day of conducting the tests. The reports shall contain complete records of execution of test as described in this Section.

2.0 2.1 2.1.1

2.1.2

2.1.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 2 OF 17

2.1.4

Contractor shall provide to Project Manager (prior to scheduled use in the field) reports of the effects on the grouting mixture of any additive proposed for use in the drilling water. No additives shall be used without prior approval.. Within 24 hours of completion of any drilling with core recovery, Contractor shall submit, in duplicate, a technical log of the drill hole in a form prescribed by Project Manager . The log shall be in accordance with IS: 4464 and shall include the following data: - (In case Geo-technical investigation is carried by Contractor) a) b) c) d) e) f) g) Date of beginning and end of drilling, Drillhole number, Location, ground E L , coordinates, inclination, direction and length of drillhole, Type and diameter of drilling bit and core barrel used, make of drilling rig and length and diameter of casing, if used, Elevation of ground water levels encountered, including dates and times of measurement, Results of leakage tests and other drill hole tests, if any, A record of the drillers observations on progress of drilling, rate of penetration, speed and uniformity of rotation of bit, action of the drill rig such as jerky, smooth, rough, steady, etc., Length of each core run and the length, or percentage, or both of the core recovered and location and cause of core losses,

2.1.5

h)

i) Any changes in the character of the drilling water or mud, and in case the drilling water was lost (partly or totally), the elevation or depth when this happened, j) k) A simple drillers interpretation and description of the nature of the formation encountered as the drilling progress, Location and nature of cavities, seams, cracks, soft or broken rock, whether filled or open, and any other observation which could give information in connection with the purpose of exploratory drilling, Names of drillers and inspectors.

l) 2.1.6

Geological logging shall be performed by the Engineer-in-Charge. When required by the PROJECT MANAGER, Contractor shall provide assistance during core logging, and in particular with handling of core boxes and cleaning of cores. Colour photographs of the core boxes from each drillhole shall be submitted to the PROJECT MANAGER in 3 copies within 10 days from the completion of the drillhole. Contractor shall submit reports in duplicate giving the results of each water-pressure test performed, within 24 hours of the end of the shift in which the tests were carried out. The reports shall contain the following: a) b) c) d) Location and number of drillhole, Date and time of test performance, Type of test, Pressure readings and water levels before and after testing,

2.1.7 2.1.8

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 3 OF 17

e) f)

Packer rod characteristics and depth of packer(s), Total injected water volume and rate per minute and per linear meter of hole for various pressures applied. A plot showing water take versus increasing and decreasing pressure shall be prepared and both data and plot shall be submitted, Description of all surface water leaks indicating the distance and approximate quantity.

g) 2.1.9

If Contractor intends to use a water-soluble additive to drilling water, he shall submit a notification and a sample of additive to Project Manager for approval 15 days prior to being used. Grouting At least 30 days before start of grouting works, Contractor shall submit detailed proposals with a layout of his arrangements for grouting including specifications of all equipment, tools, all grouting materials, qualification and experience of proposed personnel etc. An overall grouting program shall be drawn up jointly between Contractor and Project Manager Grouting mixes, pressures, pumping rates, and sequencing will be selected, subject to modifications, to meet local conditions encountered during the performance of the work. Grouting works shall be planned in such manner as to run concurrently with other works. This plan shall further be modified in consultation with Project Manager . Prior to each phase of grouting, Contractor shall submit a detailed program for particular grouting works with information relating to the methods he proposes to use and details of grout mixes. No grouting work shall be executed without prior approval by Project Manager . During grouting, Contractor shall keep complete daily records of all grouting operations in prescribed formats and shall be submitted weekly. Results of water pressure tests and grout takes shall be presented in tabular form as well as graphically. The records shall conform to IS: 6066 and contain following: a) b) c) d) e) f) g) Number and location of the drill holes, Results of water-pressure tests, Grouting method, Date, time of commencement of grouting and of each change in grouting operations, Rate of pumping, Grouting pressures and gauge reference number, Water-cement ratio and its variations,

3.0 3.1

3.2

3.3

3.4

h) Separate quantities of cement, sand, bentonite, fly ash, admixtures and chemicals used, i) Connections, if any, with other holes and cracks, as well as any surface leakage of water or grout; crack location, how it was caulked and the success of caulking shall be described and approximate station and offset of each surface leak shall be recorded where it occurs in the dam foundation, j) k) Number of holes and depth of holes left for re-drilling, Time of completion,

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 4 OF 17

l)

Name of the foreman in charge.

3.5 PROJECT MANAGER may seek any additional information deemed necessary to be included in the documents to be submitted to him. 4.0 DEFINITIONS GROUTING is defined as injecting a mixture of cement and water with addition of admixtures, sand, bentonite and fly ash, if required, or similar approved mixture under pressure into overburden or rock mass or between rock/concrete contact through a system of boreholes by means of a pump designed for this purpose. ZONE is part of the impervious curtain grouting or consolidation grouting where all the drill holes have the same depth or the same inclination or where a level for the depths of holes is specified. In a zone, PROJECT MANAGER may adjust and drillholes as required by the topographical and geological conditions to ensure a continuous grouting curtain. STAGE is a section of a drill hole in which grouting or water pressure testing is performed. PACKER GROUTING consists of drilling a hole to its full depth in a single operation, cleaning and washing, water-pressure testing if required and grouting the hole in successive stages in any desired sequence of section which are isolated by use of packers from the un-grouted sections. This method shall generally be used. STAGE GROUTING consists of drilling and grouting a hole by stages. First a hole is drilled to a limited depth, cleaned, subjected to water pressure tests if required and then grouted. Just after the initial set of grout, the hole is cleaned by washing or by other appropriate means. Then the hole is drilled to another limited depth, cleaned, subjected to water pressure tests if required and grouted and so continued in successive stages until satisfactorily grouted to its full depth. FULL DEPTH GROUTING means each hole drilled to full desired depth, washed, pressure tested and grouted in one operation. This method is usually limited to short holes 5 m or less or holes up to 10 m that have only small cracks and joints and there is no risk of surface leakage. SPLIT SPACING consists of progressively closing curtain or consolidation grouting by drilling and grouting holes midway between holes which have previously been drilled and grouted. The spacing between primary and secondary holes may vary from one zone to another depending upon geological conditions encountered. CONSOLIDATION GROUTING is the drilling of shallow holes and grouting of the rock in foundation of the dam, spillway, intake and in rock surrounding the tunnels and shafts. CURTAIN GROUTING is the grouting executed to form a continuous impervious wall. In principle, this curtain shall consist of a single row of holes divided into zones of variable depths, inclinations and spacing. CONTACT GROUTING is drilling and grouting at low pressures required to fill the voids between concrete and rock surface or between concrete and steel lining. OPEN END WASHING is the process of cleaning drill cuttings and sludge from a drillhole by injecting water or water and air at the bottom of the hole and returning the fluid and suspended matter to the top of the hole.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 5 OF 17

GROUTING PRESSURE shall mean the pressure of grout injection as measured at the nearest pressure gauge near collar of hole while the grout is being pumped into the hole. EFFECTIVE PRESSURE shall mean the actual pressure of grout at the packer end, taking into consideration the difference of elevation between the packer end and the nearest pressure gauge or the water table. SUCCESSFUL CONNECTION means the completion of all operations necessary to achieve a proper seating of a packer assembly that can sustain the required pressure without leakage or loss of pressure during pressure water testing or grouting to refusal. GROUT TAKE OR GROUT ABSORPTION is the quantity of materials injected in a hole expressed in units of kg of dry cement/bentonite and of sand. WATER CEMENT RATIO is the ratio of the mass of water to the mass of cement. 5.0 5.1 5.1.1 EQUIPMENT Drilling Equipment Contractor shall have sufficient drilling rigs at the Site for the timely completion of the Works. The drilling rigs shall be in good operating condition and adequate for the satisfactory progress of the work. Internal Combustion engines for operation of drilling equipment will not be permitted for underground work. Drilling equipment shall be capable of drilling at any angle, upward or downward, and shall have the following capacity: Exploratory holes up to 100 m, Dam grouting curtain up to 100 m, Consolidation grouting up to 20 m,

5.1.2

Good modern technology equipment capable also of chemical grouting shall be deployed. 5.1.3 Standard drilling equipment of rotary and percussion type shall be used to perform the drilling. Percussion drilling equipment shall be equipped with water swivel for continuous flushing of the holes during drilling. PROJECT MANAGER may require some of the grout holes and pressure relief holes to be drilled using rotary type drills with core recovery. Rotary type machines shall be capable of drilling NX size holes utilising double tube core barrels equivalent and capable of recovering soft or friable materials with maximum possible core recovery. Equipment and crew shall be made available for drilling exploratory holes as required. All such cores shall be properly stored in wooden boxes and logged for inspection as per the Indian Standard. Drilling units shall be mobile and of size suitable to dimensions of tunnels, galleries and drifts. . Contractor shall provide measuring equipment for checking the actual inclination and alignment of drill holes. Grouting Equipment

5.1.4

5.1.5 5.1.6 6.0

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 6 OF 17

6.1

Grouting equipment required to carry out the work shall include mixers, grout pumps, packers, pipes, grout lines, fittings, pressure gauges, telephones, lighting circuits, trolley grout platforms and miscellaneous supplies. Sufficient grouting equipment in good condition shall be provided to meet the construction schedule and each plant shall be capable of satisfactorily supplying, mixing, stirring, pumping and injecting grout mixes of various viscosities as specified herein. Any grout hole that is lost or damaged due to mechanical failure of equipment or inadequate delivery of grout shall be replaced by another grout hole without loss of time. Grouting equipment for mixing and placing the grout shall be such as to provide a continuous circulation of grout throughout the system and to permit accurate volume and pressure control. It shall be capable of effectively mixing and stirring the grout and forcing it into the hole in a continuous uninterrupted flow at any desired pressure up to the maximum required grouting pressure for a flow rate of 150 litre/min. Grout pumps shall be of the progressive cavity type and be capable of pumping at least 150 litres/min of grout at a maximum discharge pressure of 1,700 kPa (1.7 N/mm2). Grout mixers shall have a minimum capacity of 0.5 m3 and shall be mechanically operated horizontal paddle type or preferably colloidal high speed impeller type. Facilities shall be provided at the mixer for the accurate measurement of grout materials so that mix proportions can be carefully controlled. Sump or holding tanks having a minimum capacity of 0.5 m3 shall be mechanically operated and designed to keep the mixed grout agitated and in suspension. All grout should be discharged from the mixer into the agitator and from the agitator into the pump panel through a 2.36 mm screen to remove lumps and large particles. Water meters shall be calibrated in litres and tenths of litres without by pass so that water can be measured directly in the mixer. A strainer with cleaning valve shall be provided in the water supply line, upstream of the meter to prevent sand and abrasive particles from entering the meters. Pressure gauges of the approved make shall be of such calibration to cover a range of pressures from 0 to 0.5 N/mm2 (500 kPa) and from 0 to 1.5 N/mm2 (1500 kPa), An adequate number of spare gauges shall be provided at each grout plant. Contractor shall provide a standard master gauge against which all other gauges shall be checked periodically for accuracy and satisfactory operation. All the pressure gauges shall be numbered for identification. Packers shall be capable of effectively sealing grout holes at specified elevation and be capable of withstanding without leakage pressures up to maximum grouting pressure. Type of packer to be used shall be of the pneumatically expanded rubber sleeve type. Double packer assemblies separated by up to 3 m of perforated pipe can also be provided. A double line circulating system shall be used and the inside diameter of all lines, walls and connections shall be not less than 25 mm. Hoses and supply lines shall be capable of withstanding pressure 50% greater than those specified for grouting. Grouting headers shall be provided for feeding grout into the holes. The header shall include a supply connection, a connection with a valve to the hole, and a return line with valve. Two number of approved make pressure gauges for the appropriate pressure range shall be installed. One shall be installed to indicate the pressure of the supply at the pump and the other to measure the back pressure at the hole.

6.2

6.3 6.4

6.5

6.6

6.7

6.8

6.9

6.10

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 7 OF 17

6.11 6.12 6.13

Contractor shall furnish, install, maintain and operate satisfactory communication system between grout plants and the holes being grouted regardless of grout area locations. Contractor shall employ competent drilling and grouting supervisors operating personnel, labour, spare tools etc to carry out each phase of the work properly and expeditiously. The grouting units shall be mobile and of size suitable to the dimensions of the tunnels, galleries and drifts. Water Pressure Testing Equipment Washing and water-pressure testing equipment shall include pumps, piping, pressure gauges, valves, seal assemblies and all other accessories, needed to perform the Work. Sufficient number of complete sets of pressure testing equipment to allow simultaneous testing at various drilling and/or grouting locations shall be provided. Pumps furnished shall be of the gear, centrifugal, or other acceptable types, with a minimum output of not less than 0.28 m3/min at 1.5 N/mm2 (1500 kPa) gauge pressure and shall be capable of maintaining constant pressure. Contractor shall supply water storage tanks sufficient for the pumps in addition to flow meters and pressure gauges for calibration and checking. Water-meters and pressure gauges shall be calibrated and certified by an independent laboratory prior to installation at the Site and shall be subject to periodic verification. One pressure gauge and one water-meter shall, after independent checking, remain at disposal of PROJECT MANAGER for further checking purposes. Contractor may be requested to establish, by way of tests, correction graphs for pressure losses occurring in the pipes. Pressure gauges shall be installed directly at the collar of the drill hole. Embedded Pipes and Fittings for Grouting Standard mild steel pipes and fittings for grouting shall be set in the rock and concrete as PROJECT MANAGER may direct, or where shown in Drawings. Pipes and fittings embedded in concrete shall be cleaned of all dirt, grease, grout and mortar immediately before embedding and shall be firmly held in position and protected from damage or displacement while the concrete is being placed. A standard coupling and nipple wrapped to facilitate eventual removal shall be attached to the grout pipe where embedded in concrete. No portion of the pipe shall be allowed to remain within 50 mm of the concrete surface and the resulting recess, after removal of the pipe or fitting, shall be filled with dry-pack mortar. Premature blockage of pipes shall not be allowed. Any pipe that becomes blocked before operation completion shall be cleaned out satisfactorily or replaced. SITE LABORATORY Contractor shall install at site a laboratory equipped for studies and tests related with drilling and grouting works, manned by competent staff, containing equipments and instruments below: - Usual laboratory equipment such as scales, oven, permeability meter etc. - Multi-speed laboratory mixer,

7.0 7.1 7.2 7.3

7.4 7.5

8.0 8.1

8.2

9.0 9.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 8 OF 17

Marsh test cone, Mould for pressure testing the above cubes, variable from 0 to 2 tons,

- Set of sieves for grain size analysis of fines, - Conventional laboratory glassware, including 1 litre beakers and test tubes, - Thermometers and aerometers, and Atterberg limit measuring cups, - A Baroid scale type mud density meter. 9.2 9.3 9.4 This Laboratory shall be located in conjunction with the Cement Quality Test Laboratory covered at Para 5.6.2 under Section B 8 , Concrete PROJECT MANAGER shall have free access to the laboratory and he shall be entitled to carry out any studies and measurements he deems necessary. Contractor shall prepare and test trial mixes to PROJECT MANAGER at least 15 days before start of any grouting. Materials for use in grout mixes shall be tested for compliance with the applicable requirements stipulated in "Materials" of this Section. Tests shall be performed on grout mixes proposed for use in the Works to establish consistencies in mixes, practical mixing ratios; initial and final setting times and such other properties as may affect the quality of grout. During the actual grouting operations Contractor shall carry out tests on grout mixes at the same time as grouting, and shall plot values of viscosity, sedimentation limits, compressive strength, and maximum viscosity possible for the grouting on a diagram. Frequency of testing will be once for each grouting job site or until acceptance criteria have been met. However, if a significant change in the cement source occurs, sampling and testing must be repeated and the new mix approved by PROJECT MANAGER. GROUTING MATERIALS Water used for all drilling, washing and water testing and as an ingredient of grout mixtures shall be fresh, clean and free from deleterious amounts of silt, organic matter, alkali, acids, salts, oil and other impurities. Cement used in the grout mixes shall be PPC cement. Fine cement (Blaine surface area 2 3500 cm /gm) may be specified during the course of work for curtain grout, if so required. Whenever sand is added to the grout mix, it shall consist of clean, hard and durable particles free from lumps or clay and objectionable foreign matter. A supply of 5 cubic metres of sand shall be kept in proximity of the work at all times. Sand shall conform to the following grading requirement: Sieve size (mm) 2.360 1.800 0.600 0.300 0.150 Percentage passing by weight 100 95-100 60-85 30-50 10-30

9.5

10 . 0 10.1

10.2

10.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING
0.075 10.4 10.5 0-5

VOLUME: IV PART: 3 SECTION: B7 SHEET 9 OF 17

Bentonite, conforming to I S 12584 may be required in grout mixes. Approved admixtures shall be used by Contractor in the grout mix to optimise the strength, viscosity, density, decantation, setting time and shrinkage. Only admixtures proved by testing prior to the start of grouting may be used, when approved by Project Manager.. Manufacturer's certificates or guarantees will not be accepted as relieving Contractor of his responsibility for the suitability of any admixture. Contractor shall handle, store and protect all cement and additives in such a manner that these materials will not be subject to deterioration or contamination. Deteriorated or contaminated materials shall not be used in the Works. GROUT MIXES Selection of Grout type : Table below gives as a general guidance for selection of grout type for a particular application which may or may not occur at this project and may require other additives to be determined during grout optimisation process: Objective Void filling Ground Characteristics Grouting Compounds Pure cement (w/c ratio < 0.8%) Narrow or wide joints and fissures filled with sand or clay Wide empty joints or fissures high permeability Injected grout leaks into adjoining open holes. Inflowing water in fissures Crushed rock injected grout leaks to the surface Fine interconnected fissures, medium to low permeability Rock containing many narrow interconnected fissures large permeability Highly fractured rock high permeability slurries

10.6

11.0 11.1

Type of grouting Contact grouting in tunnels Consolidation grouting in tunnels and to assist excavation

Pure cement slurry

Strength

Thick stabilized suspensions

cement

Thick Thixotropic suspensions (bentonite added for thixotropy) Thick thixotropic suspension with fine sand added, additives for quick setting (if required) Thick cement or Cement-bentonite suspensions Stabilized cement bentonite suspensions Thick cement suspensions with some fine or medium sand, addition of bentonite for thixotropy

Curtain grouting below dam

Impermeability

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 10 OF 17

Alluvial grouting below cofferdam 11.2 11.2.1 11.2.2 11.3

Impermeability

Alluvium containing gravel, porous material and boulder

Thixotropic Bentonite cement grout (up to 20% bentonite)

Pure Cement Slurries Water/cement slurry mixes are defined in terms of the W/C (water/cement) ratio by weight. High-turbulence mixing of these slurries shall last at least two minutes after pouring of the full cement weight into the mixer. Use of Bentonite in cement suspension grout Preferred rate of sedimentation of a grout suspension is below 10%. Normal grout mixes dont meet this requirement when the water cement ratio is more than 0.8 To meet the requirement of sedimentation rate below 10%, the grout suspension must be stabilised. As a rule, stabilization is effected by bentonite addition in the range of 1% to 4% of the weight of cement. The relative loss of strength of hardened grout is negligible upto 6% bentonite addition.

11.4

Stable Bentonite-Cement Grouts 11.4.1 Stable bentonite/cement grouts shall be laboratory tested prior to use. The following graphs, in particular, shall be drawn: a) Equiviscosity curves, b) Bleed limit curves, c) Curves of equal mechanical strength, d) Curve of maximum possible viscosity for grouting.

11.4.2

These figures shall be obtained with a mixer which reproduces the high turbulence of the site mixers and with the same materials (cement, bentonite, water) as will be used on the site. Bentonite/cement mixes for grouting shall not bleed more than 5%, expressed in terms of the volume of water visible above the grout after setting and the total volume prior to setting, as measured in a 1 litre, 6 cm diameter test tube. Viscosity shall be measured with a Marsh cone or equivalent method. Unconfined compressive strength after 7 and 28 days shall be measured on 5 cm cubes stored in water. 28 days compressive strength shall be no less than 1 MPa. The time to initial set shall not be longer than 24 hours. Preparation The bentonite/cement grout shall be made by first mixing a bentonite/water parent slurry in a high- turbulence mixer and storing it, once adjusted to the defined W/B ratio, for approximately 24 hours in a large tank where it shall be kept in gentle movement, after which a quantity of parent slurry shall be taken and mixed with additional water and cement in a high-turbulence mixer.

11.4.3 11.4.4 11.4.5 11.5 11.5.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 11 OF 17

11.5.2 11.5.3

The final mixing of the parent slurry with cement shall last at least two minutes after addition of all ingredients. Same mixing drum shall under no circumstances be used for mixing both Bentonite/cement grouts and bentonite/water slurries. Bentonite shall not be suspended in water which contains even the slightest amount of cement. Grout Types Three stable grouts with different batching proportions shall be developed. They shall be the thinnest possible mix (grout A), a mix of average viscosity (grout B), and the thickest possible pumpable mix (grout C. The composition of these mixes for one cubic meter of grout should be approximately as given in the table below: Grout A Water Bentonite Cement Total volume Density Viscosity (Marsh) Bleed 28 day strength 850 l 30 kg 425 kg 1,000 l 1.30 35 s 4% 1.2 MPa Grout B 848 l 40 kg 424 kg 1,000 l 1.31 40 s 2.5 % 1.2 Mpa Grout C 846 l 50 kg 422 kg 1,000 l 1.32 50 s 1% 1.2 MPa

11.6 11.6.1

11.6.2

These compositions are given as a guide only and shall be adjusted to suit the materials used. A greater variety of mixes may be required. General The extent of proposed drilling and grouting programme is tentative. Project Manager may increase or decrease quantum depending on site conditions. Contractor shall provide sufficient pump capacity and storage to ensure a continuous supply of water to all grouting operation at all times at each grouting location. Minimum water pressure in the supply lines shall be 0.35 N/mm2. Sufficient compressed air shall be supplied by the Contractor to perform the work with all equipment using compressed air operating at full capacity, the minimum delivery pressure in the air supply lines shall be 0.70 N/mm2 at all times. During drilling, grouting, washing and pressure testing operations, the Contractor shall keep concrete and rock surfaces free and clean of oil, grease, drill cuttings, grout, cement, excess of water or any kind of waste. At all times during the progress of the work covered by this section, Contractor shall protect all open drill holes from becoming plugged or filled with oil, grease, drill cuttings, grout or waste. Modifications to drilling and grouting techniques may be required as per the foundation and site conditions after which Necessity may also arise of telescopic drilling at certain locales for which equipment and accessories should be available. .

13.0 EXECAVATION 12.1 12.1.1 12.1.2

12.1.3

12.1. 4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 12 OF 17

12.1.5

All drill holes shall be thoroughly washed and cleaned by allowing drilling water to run until the return from the hole is reasonably clean as explained in IS:6066-1984 These shall be protected from being clogged. Clogged holes shall be redrilled and cleaned at Contractor's cost. Unless indicated otherwise, the drill holes shall not deviate from their designed alignment by more than 3% of their designed length. Drilling Percussion Drilling Holes shall be drilled at locations, in the sequence, orientation, inclination and to the depths shown on the Drawings.. Most of the holes for consolidation, curtain or contact grouting and pressure relief will be drilled with percussion drill, which shall be equipped for constant water flushing at the far end of the drilling rod. Holes drilled for contact/consolidation/curtain grouting in various structures shall be 45 mm dia. Holes drilled for pressure relief shall also be 45 mm dia., unless otherwise stated. Use of rod dope, grease or other lubricants on drill rods shall are permitted. No drilling water additives of any kind shall be used without written permission of Project Manager . All holes shall be established to within 250 mm of the specified location. All orientation shall be within 1 degree of the orientation specified. If for any reason the drill hole deviates in inclination or orientation in such a way that it does not satisfy the purpose for which it was intended, Contractor shall correct the deviation or shall drill another hole to satisfaction of Project Manager . Whenever the drill water is lost or artesian flow is encountered drilling operations may be stopped by Project Manager who may require the hole to be grouted before drilling operations are resumed. Contractor is required to record the location, the flow and pressure of any artesian conditions encountered in any drill hole. On completion of drilling and washing of any grout or pressure relief holes drilled through the floor of the galleries, Contractor shall immediately cap the holes with proper removable plugs (wooden or plastic) and shall protect them from entry of dirt or other foreign material. Any grout or pressure relief hole that gets obstructed prior to grouting or installation of elbow, shall be cleaned out or another hole shall be drilled by Contractor. Grout or pressure relief holes shall not be drilled within 12 m of another hole which is being grouted or which has been grouted within the previous 24 hours. No hole shall be drilled through concrete before 5 days after placement of concrete. Drilling for crack grouting in concrete lined tunnels Contractor shall drill holes for crack grouting and sealing of open cold joints, construction joints and cracks in concrete lining as stipulated in Section Concrete. The drilling shall consist of a series of 38mm dia drill holes executed within or along the cracks which have been determined by Project Manager to receive such treatments. Rotary drilling shall be used unless otherwise approved by Project Manager. Washing and Water Pressure Testing

12.1.6 13.0 13.1 13.1.1 13.1.2

13.1.3

13.1.4 13.1.5

13.1.6

13.1.7

13.1.8 13.1.9 13.2 13.2.1 13.2.2

13.3

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 13 OF 17

13.3.1 13.3.2 13.3.3

Immediately before grouting or pressure testing, the hole shall be thoroughly washed with water as explained in IS: 6066 or any other standard practice. For routine grouting operations, simple water tests shall be conducted immediately prior a stage of any grout hole is grouted. A simple water pressure test involves isolating a segment of a hole generally 3 to 5 m in length by means of a single or double packers and pumping in water at constant pressure for period of 15 minutes. Tests shall be carried out as per IS: 6066. Grouting General Grouting Procedure Grout holes shall not be grouted until the concrete / shotcrete within a radius of 12 m from the grout hole has been completed and cured for five days. Full depth grouting shall be limited to 5 m depth of hole in rock, however with latest information about rock geology, experience and pre-grouting results Project Manager may allow full depth grouting up to 10 m depth. For deeper grout holes, more than 5 m length, grouting shall be performed in stages of not more than 5 m length.. Once the grouting of a stage of a hole has been commenced it should be continued without interruption until completion. In general a stage may be considered complete when absorption of grout at the desired limited pressure is less than 2 lit./min. averaged over a period of 10 minutes. As far as practical, a continuous flow of grout should be maintained at the desired pressure and the grouting equipment shall be operated to ensure continuous and efficient performance throughout the grouting operation. The desired changes in the grout mix consistency, rate and pressure of injection, etc shall be effected quickly.. When grouting is interrupted due to plant break down, about 500-1,000 litres of clean water should be run into the hole and allowed to stand. If during injection any hole connects to another one, the grout should be allowed to escape from the coupled hole until it is of the same consistency as that being injected. The coupled hole should then be capped and the combined holes brought up to pressure. After the first hole has been grouted, all the other holes are successively connected to the grouting header to subject them to the full pressure. Grouting shall be stopped if pressure gauges registers a sudden drop or the rate of grout absorption increases abruptly or there is any indication of upheaval, disturbance or leakage. Additional holes may have to be drilled then and grouted in the vicinity or sealing cracks which might have been left due to premature blocking of holes by interruption of grouting operation. It is advisable to begin with a low initial pressure of 0.1 - 0.25 kg/cm2/m of overburden and built up pressure gradually. Pressure shall be raised only when the intake rate falls below 5 lit/min. or as specified otherwise. The true pressure at any depth should take into account the pressure head caused by weight of the grout in the hole as explained in IS: 6066. Control of pressure shall be exercised As per guidelines of IS: 6066.

13. 4 13.4.1 13.4.1.1 13.4.1.2

13.4.1.3 13.4.1.4

13.4.1.5

13.4.1.6 13.4.1.7

13.4.1.8

13.4.1.9

13.4.1.10 13.4.1.11.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 14 OF 17

13.4,1.12 13.4.1.13

Compositions of all grout mixes shall be duly got approved. When pressure does not build up even after the grouting, a thick grout i.e. with water cement ratio lesser than 0.6:1 by weight or by grout with filler such as sand and Bentonite, it is desirable to stop grouting after predetermined limit of consumption is reached. Additional holes shall have to be drilled and grouted in the vicinity of such holes. All grout holes shall be backfilled with grout mix 0.7 water: 1 cement with 3% bentonite or any other approved mix. A minimum 25 mm diameter delivery pipe is lowered to bottom of hole. Grout is pumped in delivery pipe until it flows from the hole, then delivery pipe is slowly withdrawn while pumping continues. If grout still settles after the initial set, holes shall be again backfilled by grout. Contractor shall caulk, dry pack or seal any surface leaks in rock or concrete before continuing grouting operation. In areas of higher grout consumption sand may be required to be incorporated in the mix, the proportions of the sand permitted shall normally not exceed 2 parts of sand for one part of cement with approved plasticizer. Grout mixes which cannot be injected within 2 hours of mixing shall be wasted. Contact Grouting in Tunnels Low pressure contact grouting shall be carried out between concrete lining and rock over the entire length of concrete lined tunnels (Diversion tunnel, spillway tunnel, head race tunnel and other hydraulic tunnels). Contact grouting shall be performed from holes drilled in the overt of concrete lining of the tunnels. 5 to 6 number holes at longitudinal interval of 3 m shall be drilled 300 mm into rock (or as shown in the construction drawings). Washing and water pressure testing is not required prior to contact grouting. In any section of the tunnel, the concrete lining within 90 m of that section shall have been in place for at least 21 days before grouting commences. Contact grouting shall be carried out at low pressure and shall continue until all voids are filled. Vent pipes for the release of air and water during grouting shall be provided in locations directed or approved by Project Manager . After the grouting of any hole is completed, the pressure shall be maintained by means of a stopcock or other suitable device until the grout has set. Check grouting shall be carried out wherever required to verify that voids have been completely filled with grout. Grouting will be regarded as being satisfactory if the pressure can be maintained for at least 5 minutes without further grout take. Contact grouting in steel lined portion of the pressure shafts, manifold and penstocks Low pressure contact grouting shall be carried out between rock and backfill concrete in the crown of steel lined portion of pressure shaft, horizontal portion, manifold and penstocks. Holes shall be drilled 300 mm into the rock through pre-topped holed provided in the steel lining by hydro-mechanical contractor.

13.4.1.14

13.4.1.15. 13.4.1.16

13.4.1.17 13.4.2 13.4.2.1

13.4.2.2

13.4.2.3 13.4.2.4 13.4.2.5

13.4.2.6 13.4.2.7

13.4.3 13.4.3.1

13.4.3.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 15 OF 17

13.4.3.3 13.4.4 13.4.4.1

Work shall be required to be executed in close coordination with Hydro-mechanical contractor. Consolidation grouting Consolidation grouting shall normally be performed in a single stage through a nipple or packer installed at the collar of the hole within the concrete lining, but if geological conditions so dictate multiple-stage grouting either in ascending or descending arrangement shall be performed in the deeper holes. Consolidation grouting at an open air structure shall first commence 7 days after concrete placement. Grouting for rock consolidation in any section of completed underground structure shall not start before 14 days after completion of contact grouting within 100 m of that section. Before grouting, the grout holes shall, rock characteristics permitting, be washed out under pressure till returning water is clear and pressure tested. Grout holes adjacent to a grout hook-up shall be left open during grouting operations to facilitate the escape of air and water from pockets in surrounding rock. Where, during grouting of any hole, grout is found to be flowing from adjacent holes or cracks of any kind, such openings shall be capped temporarily by plugging or caulking. When performing multiple-stage grouting in descending arrangement, the grout which is within the hole shall be removed from each stage except the deepest one, by washing, or by use of a chopping or a "fishtail" bit before the grout sets. In the event of a sudden drop in pressure or a sudden increase in grout take, grouting operations shall be temporarily halted until the crack or opening causing the loss is located and caulked. During this time the drillhole shall be continuously washed to avoid a premature grout set which would inhibit grouting to resume. If such a pressure drop or increase in grout take can be related to hydrofracturing, grout pressure shall be reduced. If surface grout leaks cannot be located and successfully caulked, or cause for pressure loss cannot be determined, within one hour, washing of drillhole will be stopped and grout in rock formation shall be allowed to set for 24 hours. After setting, the drillhole shall be hooked onto again and grouted. If the hole, or stage, does not accept grout the hole shall be redrilled or a replacement hole shall be as directed by Project Manager . If during grouting, there is a communication between the holes, Contractor shall either set packers in the linking holes which shall be bled of accumulated air frequently and grouting continued of one hole continued after another, or he may pressure grout the communicating holes simultaneously. Grouting injection will be deemed to be completed when the take has become 0.03 m3 or less per stage of hole being grouted during 10 minutes at the specified grouting pressure and mixture. After completion of grouting, the packers shall remain in the hole and the pressure shall be maintained until the grout has attained its initial set. Results of water-pressure testing and other information obtained during the performance of grouting will be used for the determination whether the grouting in each section of the Works under consideration is completed in a satisfactory manner, or whether additional grouting in separate drill holes is required. Curtain Grouting

13.4.4.2

13.4.4.4

13.4.4.5

13.4.4.6

13.4.4.7

13.4.4.8

13.4.4.9

13.4.4.10 13.4.4.11

13.4.5

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 16 OF 17

13.4.5.1

In curtain grouting, hole depths, inclinations, sequence of grouting, method of grouting, whether single or multi-stage, in ascending or descending arrangement will be adapted based on information from exploratory drilling or current operations. The holes shall be drilled and grouted by the split-spacing method. Normal sequence of grouting shall be ascending from bottom to top of hole in stages determined from water-pressure tests. Where the permeability exceeds 15-20 Lugeons, grouting shall generally be performed in descending arrangement. When performing the multiple-stage grouting in descending arrangement, the grout that is within the hole shall be removed from each stage except the deepest one, by washing, or by the use of a chopping or a "fishtail" bit before it takes a hard set. Stage length shall be a maximum of 5 m. Unless otherwise directed, air, wash water, and grout pressures shall not exceed 2 bar plus 0.25 bar per linear meter of the depth measured from the collar of the hole to the bottom of the packer. In no cases shall grouting result in heave or hydro-fracturing (sudden increase of take). Grout pressure shall not be released nor packers moved until the grout in each successive stage has achieved an initial set. The curtain grouting shall be performed from one or several grout stations. If several such stations are used, each shall be equipped complete, with mixers, agitator sumps, pumps, gages and measuring devices, and shall have a sufficient supply of grouting materials. In case when the required pressure is not reached even when injecting maximum volume, Project Manager will decide whether the grouting will be interrupted, or the grout mixture is to be changed, or accelerator added. Where grout is found flowing from adjacent holes or cracks, such openings shall be capped temporarily by plugging or caulking. If this does not bring satisfactory results, further grouting shall be interrupted and injected material allowed hardening. Grouting injection will be deemed completed when the take has become 0.03 m3 or less per stage of hole being grouted during 10 minutes at the specified grouting pressure and mixture. After conclusion of grouting program, inclined check holes shall be drilled. Unless otherwise directed, these check holes shall be drilled at spacing of 30 m and two-thirds the depth of the grout curtain. Check holes may also be drilled in areas of complex hydrogeology, which require particular treatment. These holes shall then be filled with grout. Based on results obtained in the check holes, PROJECT MANAGER may order additional grout holes or execute next line of grout holes. General target of permeability of the grouted dam foundation is 5 Lugeons. Closure of Holes and Clean-up Upon completion of grouting work each hole shall be filled with thick grout and connections not embedded in the concrete shall be removed. The drilled holes in the concrete lining shall be reamed or re-drilled (as needed) to a depth corresponding to the two-thirds of theoretical concrete lining thickness, and filled with dry-pack mortar, flush with the concrete surface. In the steel lined section the holes shall be closed as described in Void Grouting between Backfill Concrete and Steel Lining in this section.

13.4.5.2

13.4.5.3

13.4.5.4 13.4.5.5

13.4.5.6

13.4.5.7

13.4.5.8

13.4.5.9

13.4.5.10

13.4.5.11 13.4.6 13.4.6.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION Doc. No TCE.5270A-H-112-601 CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES DRILLING AND GROUTING

VOLUME: IV PART: 3 SECTION: B7 SHEET 17 OF 17

13.4.6.2 13.4.7 13.4.7.1

After completion of the grouting works the internal surface of the concrete or steel lining shall be cleaned and restored to its original condition Crack Grouting in Concrete Lined Tunnels Crack grouting shall be performed to seal the cold joints, construction joints, shrinkage cracks, honeycombs, poorly closed grout holes etc. in the structural concrete linings of underground structures as stipulated in Section Concrete. Crack grouting shall consist of injecting a stable, cement-water mix through holes specially drilled into cracks or joints. Prevention measures shall be taken by plugging the joint with wooden wedges, cardboard, cement-gypsum mortar, or other suitable means to prevent the grout from flowing out of crack.

13.4.7.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
1.0 1.1 SCOPE OF WORK

VOLUME: IV PART: 3 SECTION: B8 SHEET 1 OF 28

Doc. No TCE.5270A-H-112-601

Work under this Section includes all labour, materials, equipment and services related to the concrete work to be carried out under this Contract. Concrete work shall be performed to dimensions shown on Construction Drawings. Lift drawings shall be prepared by Contractor. Approval given by PROJECT MANAGER to Contractor's plants and equipment or their operation or of any construction methods shall not relieve latter of his full responsibility for the proper and safe execution of concrete work or any obligations under this Contract. STANDARDS Unless otherwise specified, the standards and recommendations of Indian Standards Code of Practices shall be followed in respect of all materials, equipment and performances. The following Indian Standards are specifically mentioned: IS: 8112 - 43 Ordinary Portland cement IS: 456 Code of practice for Plain and Reinforced Concrete IS: 383 Coarse and fine aggregates from natural sources for Concrete IS: 2386 (Part-IV) Method of testing of aggregates for Concrete- Mechanical property IS: 5878 (Part-V) Code of practice for Construction of tunnels conveying water : Concrete Lining IS: 516 Method of test for strength of Concrete IS: 1489 Portland Pozzolana Cement Fly Ash based IS: 1199 Method of sampling and analysis of Concrete IS: 457 Code of practice for general construction of plain and reinforced concrete for dams and other massive structures IS:9103 - Concrete Admixtures : Specifications IS: 2505 Concrete Vibrators Immersion type general requirements

1.2

2.0 2.1 2.2

2.3 3.0 3.1 3.1.1

In absence of relevant Indian Standards and specifications the recommendations of "ACI Manual of Concrete Practice" and U.S.B.R. Concrete Manual shall be followed. SUBMITTALS Submittals Before Construction Submittals listed herein are related to items which require the consent of PROJECT MANAGER and are to be submitted by Contractor before the appropriate work may proceed. Within 15 days from date of Order to Commence but before procuring or mobilising the equipment, Contractor shall submit to PROJECT MANAGER updated and detailed plans and descriptions, consistent with those submitted with his Tender and any subsequent amendments and additions agreed to by PROJECT MANAGER and Contractor, of the following: a) Aggregates Processing Plant:

3.1.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 2 OF 28

Doc. No TCE.5270A-H-112-601

Description, flow diagrams and drawings in sufficient details to indicate layout, type and capacity of crushing, screening, washing, conveying and other aggregate processing and handling equipment. b) Batching and Mixing Plants: Concrete Mixers of 14/10 or 10 / 7 capacity. Type, capacity, numbers and location where these are to be placed. Aggregate supply and carriage details. d) Transit Mixers, Concrete pumps, Placing boom etc for Placing of Concrete: Details of equipment and methods for transporting concrete from Batch plant or mixers to the final point of placing, including numbers, type and capacity of transport vehicles, concrete pumps, vibrators, and details of standby plants to be installed. e) f) Mode and methodology of concrete curing, Sampling and Testing of Materials: List and details of equipment for sampling and testing, detailed program for quality control of concrete work, and qualification and experience of the proposed personnel. 3.1.3 At least 15 before commencing any concrete work, Contractor shall submit to PROJECT MANAGER following information based on the results of the preliminary material testing: a) b) The source, analysis, method of delivery, and storage of cement, aggregate, sand and water for concrete manufacture, Any admixtures and pozzolans proposed to be used, their manufacturers, information about chemical names of the principal ingredients and effects of under or over dosage. Likewise , of any accelerator also, full details as type, dosage, influence on construction and cost savings involved, Details of materials for formwork and surface finishes, treatment of construction joints, and construction techniques which the Contractor proposes to use in order to achieve the required concrete surfaces and allowable tolerances. System, methods, and equipment for prestressing steel and grouting of cables in pre-stressed concrete elements.

d)

e) 3.1.4

At least 15 days prior to procuring or despatch to the Site of the particular item of work to which the submittal relates, Contractor shall submit the following: a) b) Details of curing compounds, if any, Details of epoxy mortar for concrete repair.

3.1.5

Drawings showing location of construction joints now proposed which differ from those shown in Drawings, including formwork and reinforcement details These shall be submitted 15 days prior to commencement of work on the particular structure. Submittals During Construction Contractor shall provide to PROJECT MANAGER a weekly placing scheduling giving the detailed location of the pours, the approximate extent of pours, and the date on which the concrete will be placed. This weekly programme of concrete placement shall be

3.2 3.2.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 3 OF 28

Doc. No TCE.5270A-H-112-601

submitted to PROJECT MANAGER for his acceptance at least 2 days prior to the commencement of the week. 3.2.2 Before start of concrete placement, Contractor shall prepare and submit a checklist regarding all preparations for the specified work such as rock surfaces and foundations, cleaning, formwork, reinforcement, embedding, and PROJECT MANAGER, on being satisfied, will permit to commence concrete placement. Contractor shall keep and make available to PROJECT MANAGER records of the date, amount, and storage location of each delivery of cement and of the part of the Works in which it was used and shall provide facilities for checking the stock of cement. During performance of the concrete work, Contractor shall keep a diary where he shall record construction procedures related to concreting. These contain at least the following: a) b) c) d) e) f) g) i) . 4.0 4.1 4.1.1 CONSTITUENTS OF CONCRETE Cement Contractor shall supply Portland Pozzolana Cement (PPC) conforming to IS:1489 Part-I. Percentage of fly ash will be 30% in PPC. Average compressive strength of not less than 3 mortar cubes tested as per IS 4031 (Part 6): 1988 at 672 + 4 hours shall not be less than 43 MPa. Cement shall be procured from the cement sources/plants approved by PROJECT MANAGER. At least two sources/plants shall be selected out of those intimated by the Contractor so that one is a standby for any eventualities. Each consignment of cement delivered shall have a test certificate of manufacturer in quadruplicate. Project Manager will have right to attend the sampling and testing at manufacturers plant at any time. If delivery is not directly from manufacturer, the intermediate storage and delivery arrangements shall be subject to approval of Project Manager Cement which does not comply with relevant IS Code or is damaged in consignment, handling or storage shall be promptly removed from the Site. All facilities for transport and storage shall ensure easy access for inspection. Commencement and termination of concreting of various parts of the structures, Quantities and quality of aggregates and cement provided, and the storage from which they were drawn, Temperature of air, water, cement, aggregates, and concrete, Meteorological conditions and humidity of air, Sampling and testing performed and summary of results, Personnel employed during various stages of the concreting operation and name of the responsible inspector or foreman, Equipment used, Any special material or procedures employed.

3,2,3

3,2,4

4.1.2

4.1.3

4.1.4 4.1.5

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 4 OF 28

Doc. No TCE.5270A-H-112-601

4.1.6 Cement bags shall be stored in weatherproof buildings with a raised, well ventilated wooden floor, and placed so that each consignment can be segregated if required and used in order of its age. Bags shall not be stacked more than 1.5m high. Cement shall not be stored out of doors, except for immediate use, and in such event shall be protected during storage and handling by waterproof covers and a raised floor. Unused cement shall be placed back into the storage buildings. 4.1.7 Arrangements shall be made such that stocks of approved cement are adequate to meet the programme of work at all times. Programme shall allow time for testing and approval of each consignment before such cement is incorporated in the work. Cement shall be preferably used in same order in which it has been received at the Site. Storage of cement shall be limited to 90 days. Cement that has been in storage for longer than these periods or which may have absorbed moisture or become lumpy shall not be used unless it has been re-tested. Cement from different mills or of different makes shall be stored separately.

4.1.8

4.1.9 Temperature of cement upon arrival to the Site shall not exceed 70 and when entering the C mixers shall not exceed 50 unless otherwise approved. C 4.1.10 Fly ash (pozolana) shall not be mixed with cement at place other than ctory/manufacturing unit. Fly ash (pozolana) mixed at factory shall conform to IS:3812 and IS:1344.

4.1.11 Contractor is solely responsible for the timely supply of cement meeting the requirements of these Specifications and the Works. The delay due to the lack of suitable cement will not give the Contractor any right for the extension of time for the Completion of Works or any claims resulting therefrom. 4.2 4.2.1 AGGREGATE General

4.2.1.1 Unless otherwise specified, concrete aggregates shall conform to the requirements of IS:456 and IS:383. They shall be tested in accordance with the provisions of IS:2386. 4.2.1.2 Aggregates shall consist of clean, hard, dense, durable, uncoated materials and shall have a stable moisture content and grading when delivered to batching plant. Shall not contain substances which may impair quality of concrete, attack reinforcing steel or reduce bond. 4.2.1.3 Use of aggregates containing minerals which can cause alkali reactivity shall be permitted with use of Portland Pozzolana Cement conforming to IS 1489. Presence of such minerals in stones to be used as aggregates shall be determined by testing. 4.2.1.4 Shape of the particles shall be generally spherical or cubical. The amount of flat or elongated particles shall not exceed 25% by weight. A flat or elongated particle is defined as one in which the width to thickness, respectively length to width ratio is greater than 3. Rock which break down into such shape, regardless of the type of processing equipment used, will not be approved for use in the production of aggregates. 4.2.1.5 Provisions for crushing and processing of material in accordance with IS:383 to meet the gradation and other requirements to work out amount of aggregate required for concrete manufacture shall be made. Proper arrangements for crushing, screening, washing, benefaction of aggregate, blending of crushed and natural aggregates all shall be made.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 5 OF 28

Doc. No TCE.5270A-H-112-601

4.2.1.6 Handling, transporting, and stockpiling of aggregates shall be such that there will be a minimum amount of fines resulting from breakage and abrasion of material resulting from free fall and improper handling. 4.2.2 Source

4.2.2.1 Coarse and fine aggregates shall be produced out of material obtained from required excavation for Permanent and Temporary Works and from approved quarry and borrow areas shown in Tender Drawings and described in Information to Tenderers or from other sources as may be designated or approved during the course of the work. 4.2.2 2 Alternative sources or supply agency developed by Contractor shall be subjected to approval by Project Manager Contractor shall carry out tests to furnish satisfactory evidence that aggregates from such alternative sources comply with the requirements of this Section. 4.2.2.3 Approval of source for supply does shall mean acceptance of all materials taken from that source. Project Manager may reject certain localised areas, strata, or channels within the approved areas and zones, when the material is unsatisfactory for use. 4.2.3 Fine Aggregates 4.2.3.1 Term "fine aggregate" is used to designate aggregate in which the maximum size of particles is 4.75mm. The gradation of fine aggregate shall be as per IS:383 4.2.3.2 The percentage of deleterious substance in the fine aggregate shall conform to IS:383, except that the fine aggregate shall contain not more than 0.1% by weight of deleterious (reactive) ferrous sulphide. The total percentage of deleterious substance must not exceed 5% by weight. 4.2.3.3 Fine aggregate having specific gravity of less than 2.6 shall be rejected. Fine aggregates, when subjected to soundness test with a solution of sodium sulphate, after five cycles of tests, shall not suffer a loss of weight in excess of 10 per cent. 4.2.3.4 Fine aggregate, upon delivery to the batching plant, shall have a uniform and stable moisture content. The amount of moisture shall be less then 6% by weight, and shall not vary by more than 0.5% per hour. 4.2.4 Coarse Aggregates 4.2.4.1 Term "coarse aggregate" is used to designate aggregate which is retained on sieve opening 4.75mm. The coarse aggregate shall be well graded and its gradation will be decided based on the laboratory tests to obtain dense mass of concrete. . 4.2.4.2 Coarse aggregates shall be stored separately in stockpiles or bins in such a manner to avoid intermixing of different size of aggregates. The storing shall be done in following sizes: 4.75-10 mm 10-20 mm 20-40 mm 40-80 mm

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 6 OF 28

Doc. No TCE.5270A-H-112-601

4.2.4.3 Percentage of deleterious substance in the coarse aggregate shall conform to IS:383, except that the coarse aggregate shall contain not more than 0.3% by weight of deleterious (reactive) ferrous sulphide. 4.2.4.4 When subjected to following tests as specified in IS:2386 (Part IV), the coarse aggregate shall comply with following requirements: High Performance Concrete (a) Aggregate Crushing Value (b) Aggregate Impact Value (c) Los Angles abrasion value Less than 30% Less than 30% Less than 30% All Other Concrete Less than 45% Less than 45% Less than 50%

4.2.4.5 When subjected to sodium sulphate soundness test, coarse aggregate shall not suffer a loss of weight in excess of 12% after five cycles. 4.2.4.6 Coarse aggregate shall be hard, dense, durable, uncoated rock fragments. Rock having an absorption greater than 3% or specific gravity less than 2.5 shall not be used. 4.2.4.7 Aggregate delivered to the batching plant shall have uniform, stable moisture content. 4.2.4.8 The nominal maximum aggregate size in relation to the structure dimension shall not be larger than: a) b) c) 4.2.5 0.20 of the narrowest dimension between the side of forms, 0.75 of the minimum clear spacing between the reinforcing bars, 0.25 of the slab depth.

Aggregate Storage

4.2.5.1 Aggregates shall be stored in a manner so that each size of aggregate is stored separately in free-draining piles in a manner that reduces breakage, deterioration, contamination and segregation to a minimum. 4.2.5.2 Moisture content of aggregates shall be controlled as far as practicable, by wetting the stockpiles and by adequate drainage. All aggregate shall remain in a free-draining stockpile for at least 12 hours prior to use. 4.2.5.3 Preparation of stockpile areas, storage of processed aggregates and disposal of any rejected material shall at all times be subject to the approval by PROJECT MANAGER. 4.2.5.4 Materials shall be removed from stockpiles by methods which minimise segregation and crushing. No fine aggregate from 500 mm in the bottom of stockpile shall be used for mixing concrete. 4.2. 6 Water 4.2.6.1 A reliable and adequate water supply shall be installed and maintained by the Contractor for washing of aggregates, manufacturing and curing of concrete. The water shall be clean and free from harmful quantities of oil, acids, alkalis, sugar, salt, silt and other organic matters and shall conform to IS:456. 4.2.6.2 Water shall contain not more than 1,000 mg/l of sulphates (SO4), not more than 100 mg/l of chlorides (Cl), and shall have a turbidity limit of not more than 1,000 ppm.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 7 OF 28

Doc. No TCE.5270A-H-112-601

4.2.6.3 Adequate water storage shall be provided at the batching plant to ensure smooth concrete production. Quality of water shall be got pre checked. Requirement of settling pond may be got pre assessed.. 4.2. 7 Admixtures

4.2.7.1 Admixtures proposed by Contractor are subject to approval of PROJECT MANAGER All admixtures shall be manufactured by a reputable company(ies), supported by a fully staffed technical service organisation and research group. Following may be required from time to time: a) b) c) Superplasticizer meeting requirement of ASTM C-494, Type F. Air-entraining agent, (complying to IS 9103 : 1999) Accelerating agent in the concrete, mortar or grout to increase the rate of hydration, shorten the setting time or increase the rate of hardening or strength development, (complying to IS 9103 : 1999)

4.2.7.2 Admixtures shall be stored and handled so as to avoid contamination or damage to their properties by temperature or moisture changes or other influences. 4.2.7.3 Contractor shall be liable for any damages and difficulties resulting from the selection and use of admixtures such as delay in concrete placing or damage to concrete during forms removal, and shall not be entitled to any time extension or claims resulting herefrom. 5.0 5.1 5.1.1 5.1.2 5.1.3 CONCRETE MIX DESIGN General Denomination of concrete classes is based on the nominal cube compressive strength (in Newton per square mm) and maximum aggregate size. The cube compressive strength is defined as the strength as measured at 28 days. The strength shall comply with the requirements of IS:456. The following table shows, in general, the anticipated classes of concrete required in various sections of work. The specific class of concrete to be used in each area will be shown on the Construction Drawings or designated by PROJECT MANAGER. Max. size of aggreg. (mm) M30 M25 M25 M20 20 20 40 20 Nominal cement content (kg) 350 325 300 300 Max. slump (mm) 120 120 120 120 28-day strength (N/mm ) 30 25 25 20 Selected locations for Second Stage Concreting around Embedded Parts Around Penstocks, Turbine parts and Draft Tubes, Precast Units etc Lining of Hydraulic Tunnel and Shafts, Beams, Columns, Slabs, Footings, etc. Various Unspecified Locations
2

Class of concrete

Location

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
M20 40 275 125 20

VOLUME: IV PART: 3 SECTION: B8 SHEET 8 OF 28

Doc. No TCE.5270A-H-112-601

Concrete Lining of Access Tunnels, Adits, Backfill behind Steel Liner

M15

40

200

120

15

Backfill concrete behind Ribs, Steel support

5.1.4

One month prior to start of any concreting job, Contractor shall start the testing of materials, propose the composition of concrete mixes and prepare trial mix of each of the proposed concrete class. He shall prepare the trial mixes with cement, water, aggregates and admixtures intended for Work and which conform to requirements specified in this Section. Contractor shall determine, in accordance with IS standards and/or ACI Manual of Concrete Practice, the mix proportions for the designated classes of concrete and submit test reports for approval. This preliminary test program shall include the determination of following parameters: a) b) c) d) e) f) g) h) i) j) k) l) m) Cement properties, Characteristics of aggregates, Mix water properties, Admixture properties, Proportion of aggregate ranges in the mix, Proportion of uncrushed to crushed aggregates, Cement content, Water-cement ratio (W/C), Workability of concrete mixes, Compressive and tensile strength, Entrained air, Density, Water-tightness.

5.1.5

5.1.6

These tests shall be carried out until the concrete mixes show appropriate strength, workability, density, and water-tightness without the use of excessive cement and water. The actual cement content in the mix design shall be optimized and justified by using cement of various manufacturers during trial mix design To carry out these preconstruction tests, full scale machine-mixed test batches shall be made and test samples taken therefrom. Tests shall be made in ample time so that complete and acceptable results are available before concreting of structures. Test samples shall be made in accordance with IS:1199 and tested in accordance with IS:516. The test results shall be analysed in accordance with IS:456.

5.1.7

5.1.8

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
5.1.9 5.1.10

VOLUME: IV PART: 3 SECTION: B8 SHEET 9 OF 28

Doc. No TCE.5270A-H-112-601

Mixes for different classes of concrete shall be approved by Project Manager . During the progress of the work, the mixes may be changed whenever, such change is necessary or desirable to secure the required strength, workability, water-tightness, density, economy, or to limit shrinkage. Contractor shall not change the approved mix proportions without written permission of Project Manager .. Water to be added to the mix shall be adjusted to compensate for any variation in the free moisture content of the aggregate as they enter the batch plant. Water beyond the specified water-cement ratio shall not be added without the written permission of Project Manager . QUALITY CONTROL

5.1.11

5.2

5.2.1

General
advance. Aside from Contractor's testing program, former will make control test to the extent as he deems necessary. Former shall give all required assistance in sampling and provide for the proper storage and transport of the specimens to be tested by Project Manager .

5.2.1.1 Contractor shall inform schedule of his concrete testing programme to Project Manager in

5.2.1.2 Contractor shall make such arrangements or purchase a new equipment should the test results prove that changes in the aggregates or concrete plant are necessary to obtain required concrete quality. 5.2.2 Site Laboratory 5.2.2.1 Contractor shall build, equip, and operate the site laboratory in which the tests included in the Quality Control Programme will be carried out. In some cases where special tests are required, they will be made in other specialised laboratories after approval by PROJECT MANAGER.. 5.2.2.2 The laboratory shall be equipped with all the necessary equipment to carry out the tests indicated below. a) Tests on aggregates as per IS 2386 (Parts I, II, III, IV) - Sieve analysis - Compressive strength - Specific gravity - Water absorption - Flakiness - Sand equivalent - Soundness and organic matter - Los Angeles abrasion b) Tests on cement - Equivalent alkaline content (IS 4032) - Specific Blaine surface (IS 4031 (6)) - Standard Mortar Compressive Strength (IS 4031 (6))

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
- Shrinkage (IS 4031 (10)) - Heat of hydration (IS 4031 (9)) - Setting time IS 4031 (5)) c) Tests on fresh concrete - Consistency through slump test (IS 1199) - Workability

VOLUME: IV PART: 3 SECTION: B8 SHEET 10 OF 28

Doc. No TCE.5270A-H-112-601

- Heat of hydration using thermometers, cells and recording instruments d) Tests on hardened concrete - Compressive strength on all classes of concrete (IS 516) - Shrinkage IS 4031 (10)) 5.2.2.3 This site laboratory shall be located in conjunction with the one for drilling and grouting covered in para 9.2 earlier under Section B.7. This shall be properly air-conditioned and equipped with temperature and relative humidity recording instruments. 5.2.3 Concrete Sampling and Testing 5.2.3.1 Aggregates Following tests will be carried out by taking samples from stores at the rate of one for every 100 m3 of produced concrete ( cumulative of all concrete classes) and once a week at the mimnimum. : - Sieve analysis - Sand equivalent - Cleanliness of gravel - Flakiness of gravel - Los Angeles abrasion - Crushing Value - Impact Value 5.2.3.2 Cement 5.2.3.2.1Quality control of cement shall first take place at the cement factory. This will be exercised by the factory itself under the supervision and the follow-up of the Contractor who shall submit copies of test results of cement to Project Manager for final approval. The quality control program will be established jointly with the Contractor and shall be submitted for the approval of Project Manager . To ensure that this quality control program is properly conduced, the Contractor shall post at the factory one of his officials, when necessary 5.2.3.2.2 The following tests will be carried out at both laboratories and compared : - Setting time, - Expansion

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
- Specific Blaine surface - Equivalent alkali content - Standard mortar compressive strength - Heat of hydration

VOLUME: IV PART: 3 SECTION: B8 SHEET 11 OF 28

Doc. No TCE.5270A-H-112-601

5.2.3.2.3 Furthermore, each week, a sample of cement shall be taken at the batching plant and the following tests shall be carried out: - Setting time, - Specific Blaine surface, - Standard mortar compressive strength at 3, 7 and 28 days. 5.2.3.3 Admixtures 5.2.3.3.1 Admixtures to be used for concrete production shall be tested for their suitability with the cement and other materials under actual working conditions. Each shipment of admixtures shall be tested for density and dry extract. 5.2.3.3.2 Admixtures older than 12 months, after their fabrication, shall be tested for deterioration. 5.6.3.3.3. Shipment of which the tested sample has not pass the criteria shall be rejected. 5.2.3.4 Water A sample of water will be taken from the concrete batch plant every 3 months and submitted to chemical analysis as described in IS 3025. 5.2.3.5 Fresh Concrete 5.2.3.5.1 The following tests shall be carried out by the Contractor on fresh concrete samples: - Consistency (slump tests) on all concrete classes (sieved at 40 mm for 80 mm size of aggregate concrete), - Air content, - Temperature. 5.2.3.5.2 5.2.3.5.3 5.2.3.5.4 5.2.3.5.5 These tests shall be carried out at the beginning of manufacturing of the concrete for each work or part of the work and for large quantities once every 100 m3. All consistency tests shall be determined based on that portion of total sample which passes a 40 mm size. Air content shall be determined in accordance with the established standard. One air test (0.006 m3 capacity bowl) is required at the beginning of each shift, whenever a class change occurs, whenever air test results are deviating from specifications and at 500 m3 intervals for each class of concrete in production. Routine air tests as noted above will be determined on that portion of the total sample which passes a 40 mm sieve size.

5.2.3.5.6.

5.2.3.6 Hardened Concrete 5.2.3.6.1 Set of six samples for compressive strength tests at 7 and 28 days will be taken and tested for each part of Work, being defined as the volume poured in one concreting operation.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 12 OF 28

Doc. No TCE.5270A-H-112-601

5.2.3.6.2Compressive strength specimens shall be prepared by Contractor and performed in accordance with Indian Standards and Code of Practice. 5.2.3.6.3 All coarse aggregate larger than one quarter the minimum dimension of the mould will be removed by wet screening. Portions of samples of concrete used for slump, air content, unit weight, etc. will not be used to mould specimens for compressive strength testing. 5.2.3.7 Analysis of Results 5.2.3.7.1 The test results will include the different components analyses, the values obtained on fresh and hardened concrete and the characteristics of the corresponding batch given by the printer of the batching plant. 5.2.7.2 Contractor shall present regularly to PROJECT MANAGER a synthesis of all the results in the form of tables, charts, statistical analyses (weekly and monthly reports). 5.2.3.7.3.The frequency and time schedule of these tests given above shall be governed by the quantum of concrete scheduled each week. 5.3 5.3.1 ACCEPTANCE CRITERIA Concrete Components

5.3.1.1 The measured values shall be within the specified range of values indicated above. 5.3.2.2 Any unsuitable material should be eliminated and the concrete manufacturing be suspended until the Contractor justifies that the replacing component is acceptable. 5.3.2 Fresh Concrete 5.3.2.1 Any controlled batch which will not satisfy the specified conditions in terms of consistency, air content and temperature, will be eliminated and concreting suspended until it is shown that corrections brought to the following batches are satisfactory. 5.3.3 Hardened Concrete 5.3.3.1 The acceptance criteria for hardened concrete shall be as per the clause 15 of IS:456. 5.3.3.2 If analysis of test cube results indicate poorer concrete in the structure over that specified in clause 15 of IS:456, PROJECT MANAGER will order Contractor to provide core tests from samples from specified location and number of samples. Contractor shall comply with directions. 5.3.3.3 In case the concrete cores fail to meet the specifications and PROJECT MANAGER is not satisfied with various tests results and quality, he will then direct for removal or subsequent suitable strengthening measures for such works. 6.0 6.1 6.2 6.2.1 BATCHING AND MIXING General The quantities being less, the use of Batching Plant is not visualised. Mixing Concrete shall be mixed in a power-driven stationary batch mixers of approved type and size. They shall be kept clean and in proper working order. The mixing blades in the drum shall be replaced when worn by 10% of their design dimensions.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
6.2.2 6.2.3 Movable truck mixers shall not be permitted for mixing concrete mixes.

VOLUME: IV PART: 3 SECTION: B8 SHEET 13 OF 28

Doc. No TCE.5270A-H-112-601

Batching plant shall be provided with a bypass such that the mix materials can be discharged directly into a transit mixer drum. This bypass is to be used only in emergency and with permission of PROJECT MANAGER.. The mixing equipment shall be capable of combining the aggregate, cementing materials, water and other ingredients, within the time hereinafter specified, into a thoroughly mixed and uniform mass, and of discharging the mixture without segregation. The mixers shall be so charged that some water will enter in advance of cement and aggregate and all materials shall continue to flow in as rapidly as possible. The construction of the mixers should prevent loss of materials during charging. The mixers shall not be charged beyond their rated capacities and the entire contents of the mixer shall be discharged before recharging. Unless otherwise authorised by Project Manager for mixers of 1m3 capacity or less, the mixing of each batch shall continue for not less than +1.5 minutes as specified in IS:456 (but not more than 5 minutes when mixing air-entrained concrete) after all materials, except the full amount of water, are in the mixer. For mixers of larger capacity, minimum mixing time will be increased by 15 seconds for each additional 0.5 m3. Mixing time shall be increased when the charging and mixing operations fail to result in the required uniformity of composition and consistency within the batch and from batch to batch.

6.2.5

6.2.6

6.2.7 6.2.8

6.2.9.

6.2.10. Arrangement for controlling, measuring and mixing operations shall be such that the operator may observe the concrete discharging from the mixer. 6.3.11 Each mixer shall be equipped with a mechanically or electrically operated timing and signalling device for indicating and assuring the completion of the required mixing period and for counting the batches. Defective mixers shall be promptly replaced. Each mixer shall be cleaned after each period of continuous operation and shall be maintained in such a condition that the mixing action will not be impaired. Where distance between batching plant and a concrete pour is such that it would cause deterioration of mixed concrete in transit, dry batching may be permitted using transit mix trucks in accordance with IS:457. Water shall be added not later than 30 minutes after batching.

6.2.11 6.2.12

6.2.13) On no account shall any addition be made to any component of a concrete batched once that batch has been mixed and discharged from the mixer, whether for the purpose of re tempering or for any other reason. :: 7.0 7.1 CONVEYING Method and facilities for concrete transport shall be selected by the Contractor within the limitations of these Specifications, and he shall be responsible for adequacy and suitability of the transporting system. Time elapse between mixing and the initial set of the concrete shall be taken into consideration. Concrete transporting methods and facilities shall be such that will prevent segregation of coarse aggregate, excessive loss of slump, and loss of ingredients. Equipment such as buckets, cars, conveyers and pumping equipment which may be used for conveying

7.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 14 OF 28

Doc. No TCE.5270A-H-112-601

concrete, shall be of such size, design and condition as to ensure an even and adequate supply of concrete at the placement area. 7.3 Use of chutes to convey concrete will not be permitted, except that chutes less than 3m in total length may be used immediately adjacent to or in the forms with acceptance of Project Manager Where chutes are used, they shall be so constructed and arranged as to permit continuous flow of the concrete without separation of the ingredients. There shall be no vertical drop greater than 1.5m, except where equipment satisfactory to Project Manager is used to confine and control the falling concrete. Concrete may be dropped through flexible elephant-trunk chutes, provided methods are used at the lower end to retard the speed of the falling concrete and prevent it from segregating. Where it is necessary to drop concrete from more than 1.5m it shall fall into a hopper with a capacity of 1m3 more than the total capacity of the full trunk. Buckets for transporting concrete shall be manufactured as low slump concrete buckets. All conveying plant shall be supported independently of the forms. Conveying plant shall be kept free from hardened concrete and foreign materials, and shall be cleaned at frequent intervals. PLACING General In order to reduce bleeding, slump shall not be higher than necessary to achieve proper placement and consolidation. Concrete shall be placed before initial set has occurred, i.e. 60 to 90 minutes after adding water to the mix. No concrete shall be placed when the atmospheric conditions are such that proper placing and hardening of concrete are not guarantied. Specifically, Contractor shall be responsible for meeting the hot and cold weather concreting requirements and for postponing concreting whenever such requirements cannot be met or, based on weather forecast, probably cannot be met. Preparation for Concrete Placing Concrete shall not be placed until all formwork, installation of embedded parts, reinforcing steel and surfaces on which concrete is to be cast have been accepted by Project Manager . All surfaces of forms and embedded items that have become deposited with dried material from concrete previously placed shall be cleaned of all such material before the surrounding or adjacent concrete is placed. Concrete shall not be placed in any structure until all water entering the space to be filled with concrete has been properly cut off or diverted by pipes and carried out of forms to clear of work. Water shall not be allowed to stand on any concrete surface until it has attained its final set. Water flow over concrete, which injures the surface finish will not be allowed. Pipes, conduits, dowels and other items to be embedded shall be so positioned and supported prior to concrete placement to be stable and provide sufficient clearance (50 mm min.) between said items and steel reinforcement to allow proper concreting. Securing such items in position by wiring or welding to reinforcement is not permitted.

7.4 7.5

7.6 6.7 7.8 8.0 8.1 8.1.1

8.1.2

8.2 8.2.1 8.2.2

8.2.3.

8.2.4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
8.2.5

VOLUME: IV PART: 3 SECTION: B8 SHEET 15 OF 28

Doc. No TCE.5270A-H-112-601

Where excavated surfaces which are to form the foundations for structural concrete, are absorptive or likely to become otherwise unsuitable, or where shown in Drawings, Contractor shall place a 'blinding course' consisting of a layer of Class M10 or M15 concrete 50 to 100 mm thick, uniformly over the foundation such that the upper surface is at grade elevation. Blinding concrete shall be placed before installing reinforcement or formwork. Immediately before concreting, forms and all other surfaces which will be in contact with fresh concrete shall be cleaned of all loose material and debris including shavings, wood chips, sawdust, pieces of wire, nails, fragments of hardened concrete and mortar. Clean-out holes which may be needed for this purpose shall subsequently be securely closed in order to obtain the required surface finish. Use of compressed air for cleaning will be allowed only if adequate precautions are taken to avoid the deposition of suspended oil on construction joint surfaces, reinforcement or other items which are to be bonded to concrete. Contractor shall have protective coverings available for fresh concrete surfaces if there is a possibility of rain, hail, sleet, or snow. Rock surfaces against which concrete is to be placed shall be clean and free from oil, standing or running water, mud, loose rock, objectionable coating, debris, and loose or unsound fragment. Faults, fissures and seams shall be cleaned to sound rock, and if directed, backfilled with dental concrete, shotcrete or dry-pack as appropriate. Immediately before concrete is placed, all surfaces shall be cleaned thoroughly by the use of high velocity air-water jets, sweeping with brooms, wet sandblasting, bush-hammering, or other satisfactory means including combinations of the above. Rock surface against which concrete is to be placed shall be kept wet for at least 12 hours during the 24-hour period prior to placing concrete and shall be in a damp condition at the time of placing, with all pools of water removed. a) The excavated cross section profile shall be carefully checked to ensure the minimum lining thickness requirements and if necessary it should be corrected, b) All loose rock which has been trapped by the wire mesh covering over the excavated surface shall be cleared and the mesh be repaired and if necessary replaced, c) All timber supports, large wooden wedges used during the initial assembly and erection of steel supports shall be removed, d) Inverts of tunnel and shafts shall be totally cleaned of debris leaving sound rock Wherever required the Contractor shall use mechanical tools to loosen and remove all loosened and blast damaged rock.

8.2.6

8.2.7

8.2.8 8.2.9

8.2.10

8.2.11

8.2.12 Before placing the concrete for tunnel lining the following requirements should be met:

8.2.13 8.3 8.3.1

Before any concrete is cast against previously placed concrete, the surface of the old concrete shall be prepared as described in sub-section "Construction Joints". Placing and Compaction Concrete shall be carefully placed in designated position. Where dense reinforcement or deep forms may cause segregation of concrete while placing, suitable methods shall be used to prevent segregation. The free fall of concrete shall not exceed 1.5 m.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
8.3.2 8.3.3 8.3.4

VOLUME: IV PART: 3 SECTION: B8 SHEET 16 OF 28

Doc. No TCE.5270A-H-112-601

Concrete shall be placed directly in its permanent position and shall not be worked along the forms to that position. Vibrators shall not be used to move concrete laterally. Addition of water into concrete after batching to compensate for stiffening of the concrete before placing shall not be permitted. All concrete, with exception of concrete tunnel lining, shall be placed in continuous approximately horizontal layers. The thickness of the layers shall not exceed 400 mm for mass concrete, and 500 mm for structural and all other concrete. Each layer shall be soft when a new layer is placed upon it so that no seams or planes of weakness within the section can form, and the two layers shall be made monolithic by penetration of vibrators. Project Manager reserves right to order a reduced thickness of layers where the layers as stated above cannot be placed in accordance with the requirements of these Specifications. Time interval between successive lifts of mass concrete shall be determined by Project Manager.. Nevertheless a minimum of 72 hours shall elapse between successive lifts. No concrete shall be placed under water, all the more in running water, except where shown on the Construction Drawings or specifically directed. Water shall not be allowed to rise over freshly poured concrete until final set has been achieved. Each layer of concrete shall be consolidated to the maximum practicable density, be free from pockets of coarse aggregate, completely fill all recesses in forms and around embedded parts, and be free of all voids. The concrete shall be compacted and worked into all corners and angles of the forms, around reinforcement and embedded items without permitting the component concrete materials to segregate. No layer of concrete shall be placed until the previous layer in the same lift has been thoroughly consolidated. Each layer of concrete within a lift shall be covered with fresh concrete as soon as possible, but certainly within the period when the lower layer is still capable of being reverberated so that successive layers can be thoroughly worked together.

8.3.5 8.3.6 8.3.7

8.3.8

8.3.9

8. 3.10 Maximum permissible time between the placing successive layers in a pour shall not exceed initial setting time of cement or 45 minutes, whichever is less and shall be reduced to suit the temperature, humidity and job conditions. Concrete shall not be piled up in the forms in a manner that causes movement of the unconsolidated concrete, or permits mortar to escape from the coarse aggregate. 8.3.11. The concrete lining in tunnel shall be handled in one continuous pour in crown with construction joints normal to tunnel axis over the full cross section, or continuous placing may be adopted with a sloping joint corresponding to natural angle of repose at end of each concreting cycle. 8.3.12 Concreting of lining shall be carried out by concrete pump using methods which do not cause segregation or requiring remixing of the concrete. Point of discharge when concreting the crown above the springing line shall be kept buried sufficiently to allow enough pressure to be built up to completely fill the crown including areas of over break in crown if any. Concrete shall be consolidated with the aid of approved immersion type mechanical vibrators complying with IS:2505 or electric or air driven vibrators operating at a speed of at least 7,000 cycles/minute when immersed in the concrete. The vibrating equipment shall at all times be adequate in number of units and power to penetrate concrete as it is being placed, to the satisfaction of PROJECT MANAGER. Vibrators with flexible operating shafts shall be used

8.3.13

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 17 OF 28

Doc. No TCE.5270A-H-112-601

for reinforced concrete and for concrete in restricted forms. At least one extra vibrator in working condition shall be constantly on hand at each point of placement for emergency use. 8.3.14 8.3.15 Application of vibrators shall be made systematically and at such intervals that zones of influence overlap and the concrete is properly compacted. Every vibrator shall be operated in a near vertical position and the vibrating head shall be allowed to penetrate under the action of its own weight. In consolidating each layer of concrete, the vibrating head shall be allowed to penetrate and revibrate the concrete in the upper portion of the underlying layers. Extreme care shall be taken to ensure that the vibrators do not touch or disturb the reinforcing, embedded steel or forms. To ensure even and dense surfaces which are free from aggregate pockets, honeycombing or air holes, it may be necessary to supplement internal vibration with hand-spading along the boundaries of the concrete and around embedded parts while the concrete is plastic under the vibratory action, should slip forms be used, the equipment and methods shall be such that the finished concrete will be well consolidated and homogeneous. Contractor shall use any or all of the above methods of consolidation, if required, to produce the necessary finish. Form vibrators shall not be used unless the forms are designed for form vibration and unless specifically authorised by PROJECT MANAGER.. Pumping Concrete Positive displacement pumping or other approved methods may be used to place concrete in locations approved by PROJECT MANAGER. The type and arrangement of equipment shall be subject to approval, and the equipment shall be operated only be experienced persons. Pneumatic placing will not be allowed. The equipment and its method of operation shall allow the concrete to enter the forms at a low velocity. Concrete pumps and auxiliary equipment shall be in good condition and shall be maintained as such throughout the duration of the work. Thorough washing down of all parts that come in contact with concrete shall be performed after each concreting operation. Pump lines shall consist of rigid steel pipe or flexible pipe made of rubber, spiral-wound flexible metal or plastic, or combination of both. Use of aluminium pipe for pump lines shall not be permitted. Couplings shall be leak proof and strong enough to withstand handling during erection and poor support along the lines. They shall provide a full internal cross section with no constrictions of the smooth flow of concrete. Immediately prior to the start of all concrete pumping, the pump and pump lines shall be primed by pumping an approved grout mixture through the equipment. Concrete pumping operations shall be planned in such a way that concrete does not set before the succeeding layer is place thereon. An adequate supply of fresh concrete shall be provided at all times. When placing the concrete by pumping in tunnel lining, sides of lining shall be brought up evenly through windows prepared in formwork and care shall be taken equal pressure is maintained on the formwork. Crown shall be filled through the slick line running along the top of the formwork. This line shall be deeply buried in the concrete at all times. Identifications marks to indicate the depth of burial shall be provided. The buried pump line shall be withdrawn from the form gradually as the placement is completed. Air boosters shall not be permitted until slick lines are buried at least 1.5 m into fresh concrete.

8.3.16

8.3.17

8.4 8.4.1

8.4.2

8.4.3

8.4.4 8.4.5

8.4.6

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
8.5 8.5.1 Concrete in Block outs, Second Stage in Restricted Locations, etc.

VOLUME: IV PART: 3 SECTION: B8 SHEET 18 OF 28

Doc. No TCE.5270A-H-112-601

All concrete required to be placed in block outs to permit the installation and adjustment of mechanical and other equipment, around formed holes and second stage concrete in other locations shall be included in respective concrete as described in these Specifications. Concrete surfaces of block outs and first stage concrete at other locations shall be chipped and roughened as described herein before second stage concrete is placed at such locations. Exceptional care shall be taken to placing concrete in block outs in order to ensure satisfactory bond with concrete previously placed and to secure complete contact with all metal works in the block outs. Roughening of first stage concrete surfaces shall be attained by chipping or sand blasting in such a manner as not to loosen, crack or shatter any part of concrete beyond the roughened surfaces. After being roughened, the surfaces of concrete shall be cleaned thoroughly of loose fragments, dirt and the objectionable substances and shall be sound and hard to ensure good mechanical bond between the existing and new concrete. Second stage concrete shall be placed in lifts of not more than 3.0 m and concrete placement rate shall not exceed 1.5 m per hour except as otherwise approved by Project Manager . FINISHING OF CONCRETE General Quality of surface finish shall be in accordance with requirements for particular class of finish specified hereunder. Finished surfaces of concrete shall be free from honeycombs, segregation, loss of cement or fine material, from damage due to stripping of forms, from boltholes, abrupt irregularities caused by movement of forms or components, loose knots and similar features, and bulges or depressions in the general plane of the surface. Only one type of formwork shall be used for all parts of a concrete structure which is visible from any direction. Classes of finish shall be as shown in Construction Drawings or as directed by Project Manager . Formed Surfaces Classes of finish for formed surfaces are designated by the use of symbol F and the shape of the formwork panels required for concrete work shall be either plane (F1, F2, F3) or curved (F1C, F2C, F3C). Formed surfaces should be given a Class F 4 finish, but with steel forms only. Surface finishes and other variations in finishing of concrete shall conform to the tolerances indicated below: Type of finish General areas of application and method of forming Tolerances (in mm)

8.5.2

8.5.3

8.5.4

8.5.5

8.5.6

9.0 9.1 9.1.1

9.1.2 9.1.3 9. 2 9.2.1

9.2.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
F1, F1C

VOLUME: IV PART: 3 SECTION: B8 SHEET 19 OF 28

Doc. No TCE.5270A-H-112-601

Formed surfaces of construction joints and other surfaces +25 which will not be permanently exposed. The surface will require no treatment after form removal other than repair of -10 defective concrete and specified curing, or treatment as specified for construction joints. All permanently exposed formed surfaces. Immediately on +10 the removal of forms all unsightly ridges or fins shall be removed; all holes left by removal of ends of form rods shall -10 be neatly filled with mortar and surfaces treated to meet the required tolerances by tooling and rubbing. Formed surfaces which will be exposed to flowing water. +3 These surfaces shall be hard, smooth and dense, free from offsets, pits, voids, air holes and irregularities and shall be -3 chipped, ground and thoroughly cleaned as necessary to conform to the required tolerances. Formed surfaces where accurate alignment, evenness, density are of vital importance for preventing destructive effects of water. Surface shall not be rubbed except for clearing by wire brushing and grinding off thin fins or small projections. Poor areas with pits and voids be treated by carborundum brick or other abrasive as described under F 3. + or 3 mm

F2, F2C

F3, F3C

F4,

9. 3 9.3.1

Unformed Surfaces Classes of finish for unformed concrete surfaces are designated by use of symbol U and shall be finished by screeding, floating and trowelling. Those subjected to a high water velocity should be finished with a steel trowel finish with no abrupt edges, pits or roughness. Surface finishes and other variations in finishing of concrete shall conform to the tolerances indicated below. Type of Finish U1

9.3.2

General areas of application and method of forming

Tolerances (in mm)

Unformed, screeded surfaces which will be covered by fill materials. +10 Finishing shall consist of sufficient levelling and screeding to produce -10 an even, uniform surface meeting the required tolerance.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
U2

VOLUME: IV PART: 3 SECTION: B8 SHEET 20 OF 28

Doc. No TCE.5270A-H-112-601

Unformed surfaces not concealed by fill. Floating by means of hand or +5 power-driven equipment shall be started as soon as the screeded surface has stiffened sufficiently, and shall be the minimum necessary -5 to produce a surface that is free from screed marks and that is uniform in texture. Unformed, screeded surfaces which will be exposed to flowing water. +3 This finish shall be applied by steel troweling after the concrete has hardened enough to prevent excess of fine materials and water from -3 being worked to the surface, free from blemishes, ripples and trowel marks. After the surface has nearly hardened, it shall be trowelled once more until the surface is hard and glossy in appearance.

U3

9.3.3

Interior surfaces shall be sloped for drainage where shown in Construction Drawings. Exterior surfaces, which will be exposed to weather shall be sloped for drainage even if there is no such indication in Construction Drawings. In such case the slope shall be at least 2% but not exceed 3%. Tolerances for General Concrete Structures General Areas of Application Variations of the constructed line or In 6 metres outlines from established position in plan In 12 metres In 24 metres or more Variations of dimensions to individual In buried construction structural features from established position Variations from the plumb, from the In 3 metres specified batter or from the curved surface of all structures, including the In 12 metres or more lines and the surfaces, walls and vertical In buried construction joints Variations from the level or from the In 3 metres grades indicated on the drawing In 12 metres or more In buried construction Variation in cross sectional dimensions of columns, beams, buttresses, piers and similar members and variation in the thickness of slabs, walls and similar members Tolerances in mm 12 mm 20 mm 30 mm Twice the above amount

9. 4

12 mm 30 mm Twice the above amount 6 mm 12 mm Twice the above amount -6 mm +12 mm

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
Variation from plumb and level for sills Not greater than: and side walls for radial gates and similar watertight joints 9.5 Bush Hammer Finish

VOLUME: IV PART: 3 SECTION: B8 SHEET 21 OF 28

Doc. No TCE.5270A-H-112-601

3 mm/3 m

9.5.1 Bush hammer finish shall be applied on surfaces as directed by PROJECT MANAGER. Bush hammering shall not commence until at least a month after concrete placement. Electrically driven tool shall be used for bush hammering and this shall have a head 3 cm2 with 16 pyramid shaped teeth. Surfaces shall be finished at a rate of 250 to 400 cm2/minute indenting the concrete surface approximately 2 mm. 10.0 10.1 CONSTRUCTION JOINTS IN CONCRETE STRUCTURES Construction joints are defined as concrete surfaces on or against which concrete is to be placed and to which new concrete is to adhere and which have become so rigid that the new concrete cannot be incorporated integrally with that previously placed. Construction joints shall be located in positions shown in Construction Drawings and Contractor shall not be permitted to form any additional joints or deviate from the joints indicated in Drawings without the written authorisation of EIC. Necessary rearrangement of steel reinforcement arising from such modifications shall be to the Contractor's debit. Horizontal construction joints shall be arranged, where possible, to coincide with joints in the formwork. Joints at exposed surfaces of concrete shall be straight and continuous. Feather-edged construction joints will not be permitted. Faces of vertical joints shall be shuttered with expanded metal or other approved rough material. Expanded metal shall be removed as far as possible, before the adjacent lift is poured. If required, the surface shall be cleaned by wet sandblasting and roughened by light bush-hammering. Surface of construction joints upon which new concrete is to be placed and to which new concrete is to adhere shall be clean, rough, and free of water. The laitance, loose or defective concrete and foreign material shall be removed from surface of existing concrete. The portion should be dry when successive lift is placed. Surface of the hardened concrete shall be cleaned and roughened by wet-sandblasting and washing thoroughly with air-water jet. Care shall be taken to prevent undercutting of aggregate in the concrete during sandblasting. Wet-sandblasting equipment shall be operated at an air pressure of approximately 7 bars. Sand to be used for blasting shall be dense, hard, not easily broken and sufficiently dry. In lieu of wet-sandblasting, Contractor may propose high-pressure water blasting utilising pressures not less than 400 bars, provided that such high-pressure water blasting produce equivalent results to those obtainable by wet-sandblasting. Horizontal surfaces of construction joints may be treated by cutting with an air-water jets ("green-cutting") This shall be done after initial set has taken place but before concrete has become too hard for effective cutting. Fresh concrete surface shall be cut with air-water jets to remove all laitance and to expose clean, sound aggregate. After cutting, the surface shall

10.2

10.3 10.4 10.5

10.6

10.7

10.8 10.9

10.10

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)

VOLUME: IV PART: 3 SECTION: B8 SHEET 22 OF 28

Doc. No TCE.5270A-H-112-601

be washed with clean water. Care shall be taken that the treated surface does not become contaminated before new concrete is placed upon it. If it becomes and so a satisfactory joint with newly placed concrete is not ensured, it shall be cleaned by wet-sandblasting. 10.11 10.12 Water used in cutting, washing and rinsing of concrete surfaces shall be disposed in such a way that it does not stain, discolour or affect exposed surfaces of structures. When necessary, as determined by PROJECT MANAGER, structural concrete placement in forms shall be started with an over sanded mix with 19 mm maximum size aggregate, an extra 50 kg of cement per cubic meter and a 100 mm slump. This mix will be referred to as a starter mix and shall be placed approximately 50 mm deep. Disturbance of the surface at a joint during the early stages of hardening shall be avoided, and traffic on concrete will not be permitted until the concrete has hardened sufficiently to withstand such treatment without injury. All construction joints shall be kept continuously moist until they are covered with concrete, provided that, if it becomes necessary to delay the placement of new concrete on or against a construction joint for an extended period, moist curing of the surface of the joint may be discontinued at the expiration of the regular prescribed curing period. If the moist curing is so discontinued, it shall be resumed before 24 hours of new concrete placement on the joints. CURING AND PROTECTION OF CONCRETE Equipment for concrete curing and protection shall be readily available at each site of placement before placement is started. Curing water temperature shall not exceed 25oC. Exposed surface of concrete which have been finished as specified shall be protected from direct rays of sun for at least 2 days after placing. Fresh placed concrete shall be protected from damage by rainfall. Exposed surfaces shall be kept moist or moisture in concrete shall be prevented from evaporating for at least 14 days after placing by continuously sprinkling or spraying with water.. Care shall be taken not to disturb the steel reinforcement projecting from any placement for at least 24 hours after the completion of such placement. PROJECT MANAGER may permit the use of curing by means of membrane forming compounds. Sealing compounds proposed by Contractor will be subject to sampling and testing.. Curing compounds shall be applied according to the manufacturer's recommendations to provide a continuous uniform membrane over all area. Curing compounds shall be applied only after moist curing has been carried out for at least 24 hours. Curing membranes shall be protected from damage at all times. Curing compound shall not be used on any unformed surface where the irregularities in that surface would prevent the membrane forming an effective seal, on any surface which has a temperature lower than manufacturer's recommended application temperature, on any surface where a bond is required for additional concrete, or where a bonded surface coating is to be applied. Where a curing compound is placed on a surface where a bond is required, it shall be removed by sand blasting or by other means.

10.13

10.14

11.0 11.1 11.2

11.3

11.4 11.5

11.6

11.7

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
11.8

VOLUME: IV PART: 3 SECTION: B8 SHEET 23 OF 28

Doc. No TCE.5270A-H-112-601

Concrete poured in tunnels to form tunnel linings shall be cured by membrane curing, as described above. Curing compounds used in tunnels shall not contain solvents which may create hazardous conditions. Curing compounds used for surfaces exposed to atmosphere shall degrade completely when exposed so beyond 3 months. They should remain at least 80% impermeable for one month after application. REPAIR OF CONCRETE General Repair of damaged or defective concrete shall be performed by skilled workmen only, and in the presence of Project Manager . No repair work shall be carried out until he has inspected the location of proposed repair and accepted the method of repair proposed.. Contractor shall correct all imperfections on the concrete surface as necessary to produce surface that conforms to the requirements specified. Where concrete is exposed to flowing water or to weather, porous and fractured concrete and surface concrete to which additions are required to bring it to prescribed lines shall be removed by chipping openings into the concrete a minimum of 75 mm below the reinforcing or to depth required by Project Manager if sound concrete is not encountered at 75mm. Repair areas shall be formed and area filled with fresh concrete. If concrete section to be repaired contains no reinforcement, concrete shall be chipped to minimum depth of 100mm. The chipped openings shall be sharp edged and keyed and shall be filled to required lines with fresh concrete or patching mortar. Where concrete is used for filling, the chipped openings shall not be less than 75 mm in depth and the fresh concrete shall be reinforced and doweled to the surface of the openings. Dry pack mortar for patching shall consist of 1 part cementing material, 2 parts by volume of regular sand, and just enough water so that after thorough mixing of the ingredients the mortar will barely held together when compacted by squeezing with the hand. The mortar shall be fresh when placed, and any mortar that is not used within 1 hour after preparation shall be wasted. Just prior to mortar application, the surface to which the mortar is to bond shall be kept wet for at least 2 hours, then scrubbed with a small quantity of cement grout using a wire brush. When repairs are more than 25 mm deep, the mortar shall be applied in layers not more than 20 mm thick to avoid sagging. After each layer, except the last is placed, it shall be thoroughly roughened by scratching with a trowel to provide an effective bond with the succeeding layers. The last or finishing layer shall be smoothened with a trowel to form a continuous surface with the surrounding concrete. All patches on exposed surface shall be neat and smooth and as nearly as possible of the same colour as the adjoining concrete. All patches shall be thoroughly bonded to the surfaces of the chipped openings shall be cured and shall be sound, free from shrinkage cracks and drummy areas. For concrete surfaces where high velocity flows may occur, repairs to surfaces having F3 and U3 finishes shall be bonded with an approved brand of epoxy adhesive and used in accordance with the manufacturer's instructions. (8) All repairs to the surface of concrete required for flowing water shall be ground smooth to meet the tolerances specified for that surface.

11.9

12.0 12.1 12.1.1

12.1.2 12.1.3

12.1.4

12.1.5

12.1.6

12.1.7

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
13.0 13.1 Sealing Work in Concrete Lining of Underground Structures

VOLUME: IV PART: 3 SECTION: B8 SHEET 24 OF 28

Doc. No TCE.5270A-H-112-601

Contractor shall carry out sealing work to reduce water inflow and water losses through, and to guarantee the normal water-tightness of the concrete lining of underground structures according to criteria stated hereafter and as requested by PROJECT MANAGER. Work shall consist of sealing cold joints, construction joints, shrinkage cracks both vertical and horizontal, honeycombs and poorly grouted or sealed grout holes. Work shall be performed intermittently, whenever water inflows are observed and measured, wide cracks are discovered (especially after performance of tunnel pressure testing) or future permeability is doubtful. The sealing work shall be carried out when following phenomena are encountered: a) b) c) Water inflow equals or exceed 1 l/min measured at each single inflow source, Any water inflow from grout holes and through honeycombs is unacceptable, Cracks or joints, regardless whether they are dry or wet, of width greater than: - 0.2 mm in tunnels and shafts containing reinforcing steel - 0.5 mm in un reinforced stretches of tunnels or shafts d) Areas of porous concrete (e.g. due to poor vibration) where depth of porosity is obviously deeper than superficial. Crack or joint 0.2-0.6 mm wide shall be repaired as stipulated in the Section "Drilling and Grouting". Crack or joint wider than 0.6 mm shall be repaired as under (1) above, followed by cutting a groove 25x25 mm along the joint or crack and subsequent filling with an epoxy mortar. Wet joint may also be sealed by applying the "Oberhasli Method", which consists of cutting a groove as for the dry joint and by collecting the seepage water into one or several flexible plastic pipes. As soon as the groove is without running water is shall be filled with a quick-setting mortar and, after its hardening, followed by pumping the cement-Bentonite-water slurry through the plastic pipes. Areas of porous concrete shall be grouted under high pressure (30 bar) with cement grout mix W/C=0.7, by weight, containing suitable water-reducing airentraining admixture. Grout holes shall be drilled at 500 mm spacing until the rock. After grouting, the area shall be repaired with epoxy mortar. Grout holes filled only with water/cement mix shall be redrilled up to 2/3 of the theoretical lining thickness and filled with dry-pack mortar.

13.2

13.3

13.4

The sealing work shall be executed as follows: a) b)

c)

d)

e) 14.0 14.1 14.1.1 14.1.2

Particular Requirements for Individual Concrete Structures Concrete Linings of Tunnels and Shafts Contractor shall propose the sequence of the casting operations for tunnel and shafts and get same approved from PROJECT MANAGER. As this is a small section tunnel, lining shall be carried out in sections. When job is commenced, no interruption shall be allowed.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
14.1.3

VOLUME: IV PART: 3 SECTION: B8 SHEET 25 OF 28

Doc. No TCE.5270A-H-112-601

Number of vertical construction joints shall be reduced to minimum. Inclined construction joints will have the naturally running slope of placed concrete. In addition to treatment as specified in aforesaid "Joints in Concrete Structures", in case of inclined construction joints, the concrete in the crown and the invert shall be removed prior to placing of the next stage to avoid an acute angled construction joints relative to the inside surface of the tunnel lining concrete. Prior to concreting, rock surface shall be cleaned and shall be free from oil, mud, loose rock, objectionable coating, debris and loose or unsound fragments. All surfaces shall be cleaned with air-water jets or by other satisfactory means. Particular attention shall be given to draining the flowing water and removal of standing water at place of concreting. PROJECT MANAGER will determine extent of steel reinforcement required in concrete lining, based on results of rock mechanics test, if any, performed in excavated tunnel. Generally reinforcement will be used where weak rock and/or high permeability is encountered and crack Backfill Concrete Behind Steel Liners No windows for introduction of vibrators will be provided in the permanent tunnel / shaft steel liners. Working space has been provided at the crown of the tunnel to permit access for necessary vibration of backfill concrete. Special care shall be taken to ensure compaction of concrete and complete filling of the space beneath the steel lining and crown, following the procedure specified in portion "Pumping Concrete". Concrete used for backfilling behind the steel lining shall be Class M20/A40. Prior to concreting, the rock surface shall be cleaned and shall be free from oil, standing or running water, sand, loose rock, objectionable coating, debris and loose or unsound fragments. All surfaces shall be cleaned with air-water jets or by other satisfactory means. Particular attention shall be given to the drainage of flowing, and the removal of standing water where concrete will be placed. Contractor shall co-operate closely with the supplier of all the steel-linings during their erection prior to backfilling. Embedding concrete around steel liners shall be spaced at a maximum rate of rise of 150 mm per hour, unless reliable bracing has been installed to prevent uplifting of pipes. In no case, differential level of concrete on either side of liner may exceed 150 mm during placing. Installation of subsequent steel liner units shall not proceed until either 24 hours have elapsed since placing of the backfill concrete, or the concrete has been shown to have obtained 20% of it's required 28-days cylinder compressive strength. Concrete in the Power Cavern

14.1.4

14.1.5

14.2 14.2.1

14.2.2 14.2.3

14.2.4 14.2.5

14.2.6

14.3

14.3.1 Contractor shall place all required concrete in the power cavern in accordance with the requirements of these Specifications, as shown in Drawings or as directed by Project Manager . Concrete for the transformer cavern is included under this heading. 14,3.2 The levels of the floors in the power cavern and the dimensions of the concrete elements such as beams, columns, floors, walls and openings as shown on the Tender Drawings are typical only and may be changed in the final design to suit the actual shapes and sizes of the equipment to be installed in the power and transformer caverns.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
14.3.3

VOLUME: IV PART: 3 SECTION: B8 SHEET 26 OF 28

Doc. No TCE.5270A-H-112-601

Blockouts, holes, pipes, pits, pedestals and embedded metalwork for equipment, cables, anchor bolts and other accessories are not fully detailed in Tender Drawings and may be changed in number, location or size in the final design. Contractor shall cooperate closely with the supplier of the mechanical and electrical equipment during equipment installation and its embedding, including provision of bracing and ties necessary to maintain all equipment in their correct position during placement of the surrounding concrete. Concrete slabs to be covered with a floor finish or tiles shall be left at a sufficient depth below the finished floor elevations to permit placing of the required thickness of floor finish or tiles, and proper allowance shall be made for the finish when anchor bolts, pipes and other metalwork are placed. Concrete slabs forming floors shall be carefully screeded to the design levels. Special Requirements For Embedding Turbine Parts In Concrete At least two weeks prior to placement, Contractor shall submit to Project Manager for approval his proposed method of placement of concrete embedding of turbine parts. Contractor shall ensure that there will be no delay in placing concrete after any part of the turbine has been put in position and accepted for concrete placement. Concrete for supporting and encasing turbine parts in the structure shall be placed in stages, places and sequence as the erection procedure requires. Delay in concrete placement will be necessary at times to permit checking, adjusting and grouting operations to ensure proper installation of the draft tube liner and spiral case. Contractor shall construct erection pedestals for placing and aligning draft tubes, penstocks and spiral casings and provide setting anchors, reinforcing steel, and dowels as indicated in Drawings. The units to be embedded shall be checked for alignment immediately before, during and after concrete placing operations. If directed, Contractor shall fill spiral case with water under pressure during concrete placing. Pressure, temperature and duration of water circulation shall be got pre approved. Extreme care shall be exercised in concrete placing around the various parts of turbine to ensure that unbalanced loading and impact from placing concrete will not cause distortion or dislocation of parts. Both during and after placing of a lift, careful checks shall be made to see that draft tube liner, stay ring, spiral casing and other parts requiring accurate setting have not displaced. Vibrators shall not be used within 30 mm of the spiral casing or anchor bars. Unless otherwise specified or shown on the Construction Drawings, concrete class M30/A20 with the addition of an approved non-shrink agent shall be used for embedding of equipment in second stage concrete. Rate of placing and maximum depth of lifts shall at all times be got pre decided. Evidence of displacement or threatened displacement of equipment which has been set in proper position shall demand immediate corrective measures. This may include but not be limited to, change in depth, sequence and time required between lifts and removal of concrete already placed.

14.3.4

14.3.5

14.3.6 14.4 14.4.1

14.4.2

14.4.3

14.4.4 14.4.5

14.4.6

14.4.7

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
14.4.8

VOLUME: IV PART: 3 SECTION: B8 SHEET 27 OF 28

Doc. No TCE.5270A-H-112-601

Draft tube liner encasement concrete shall be placed simultaneously all around the perimeter of the liner at a rate of not more than 750 mm per hour. The difference in level of fresh concrete in any lift shall not exceed 300 mm. Spiral case encasement concrete shall be placed at a rate not exceeding 150 mm per hour at any time during concreting, the difference in level of fresh concrete shall not exceed 150 mm. During concreting placement level and stay ring levels shall be checked continuously.

14.4.9

14.4.10 Any damage or displacement of embedded parts caused by too rapid or careless placement of concrete or non conformity with these specifications shall be corrected or replaced by Contractor as required. 14.4.11 Any pipes used to fill or grout the space remaining beneath the stay ring or spiral case shall be supported independently and not welded to the equipment. 14.4.12 Grouting of stay ring shall be through threaded grout holes in stay ring and to specified pressure. Grouting shall be made not less than 4 weeks after the concrete around the stay ring is completed and shall conform to requirement of the turbine manufacturer. 14.4.13 At any point where inspection (e.g. by sounding) indicates that a cavity exists between steel liners and the surrounding concrete, Contractor shall drill and tap the liners to provide additional grouting points. Backfill grouting shall be performed after concrete has cooled and achieved sufficient strength, to resist the grouting pressures. After grouting, all grout holes shall be sealed by welding. 14.5 14.5.1 Other Parts Embedded In Concrete Anchors, anchor bolts, structural shapes, plates shapes, plates for gates, hoists, valves, machinery etc. and other miscellaneous parts shall be installed in concrete. Wherever practicable, anchors shall be installed before the concrete is placed. Except as otherwise specified, drilling and installation of anchors in the concrete after concrete is placed, will not be permitted. Before being placed in position, all anchors and embedded parts shall be thoroughly cleaned of rust, grease, paint, splashed concrete, or other coatings that will reduce bond. Where such installation of anchors is not practicable before concrete is placed, formed openings shall be provided and anchors grouted into openings at a later time in a technically acceptable manner. Embedded anchors shall be supported during embedding and embedded so that the tolerances specified will not be exceeded. Care shall be taken not to disturb or displace embedded items during concrete placement. Concrete may be placed around embed components in locations and to the dimensions shown in Construction Drawings. Method of placement and rates of placing concrete shall be got pre approved. Care shall be exercised that such parts are not damaged or disturbed while concrete placing operations. Concrete in Blockouts for Equipment Embedding Contractor shall form block outs, place reinforcement and concrete as shown in Construction Drawings and in such manner as to ensure good bond with the existing concrete, to secure complete contact with the metalwork to be embedded in the blockout concrete and to avoid displacement of the metalwork. Block out concrete includes concrete designated in Construction Drawings or by Project Manager as second stage concrete.

14.5.2

14.5.3

14.6 14.6.1

14.6.2

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES CONCRETE (Excluding Formwork, Reinforcement, and Joints)
14.6.3

VOLUME: IV PART: 3 SECTION: B8 SHEET 28 OF 28

Doc. No TCE.5270A-H-112-601

Before placing concrete, all parts to be embedded shall be checked to ensure that they are firmly fixed in their required position. Surfaces of blockouts or holes shall be thoroughly cleaned and wetted. Oil or grease shall be removed by brushing and chipping to a sufficient depth, or by application of approved chemicals and flushed with clear water. The parts to be embedded shall be cleaned of rust, mill scale, paint, oil or grease before they are set into place. Where bond between metal parts and concrete or grout is not desired, approved material such as flake graphite or paraffin shall be applied to the metal parts. The metal surfaces shall be wetted before placing the concrete or grout. Only non-shrink self compacting concrete containing approved admixtures shall be used for concrete in second stage and in blockouts for equipment embedding as shown on the construction drawing. Grouting of the Equipment Bearing Plates and Anchors Limited spaces and small blockouts where equipment bearing plates, anchors, rails, etc., are placed shall be grouted under pressure. Grouting shall be performed using non-shrink cement-based grout or non-shrink epoxy grout as proposed by Contractor and approved. All mixing and grouting shall be performed in accordance with the manufacturer's recommendations and shall be tested prior to grouting. Technical service by manufacturer shall be organised by Contractor. Before placing grout, the surfaces of the base concrete to which the grout will be bonded shall be roughened and cleaned of all laitance, loose or defective concrete, any coatings or other foreign material, followed by thorough washing with water. Forms for grouting shall be installed where necessary and care shall be taken that the grout fill all spaces under the plates leaving no voids. The exposed surfaces of the grout shall be cured as recommended by the manufacturer and no loads shall be applied until the grout has reached the design strength. Precast Concrete Precast concrete shall be produced in an enclosed area separate from other construction works. Precast units shall generally conform to the other parts of the same technical specifications where applicable and as required by PROJECT MANAGER. Precast units shall be protected at all times from damage at the place of fabrication and during handling, storage and erection. Precast concrete units shall be placed in their correct relative location and temporarily braced and secured to prevent collapse or distortion of the structure until completion of Work to satisfaction of PROJECT MANAGER. Following removal of formwork, any hole, voids or other blemishes in the surfaces of precast concrete units which are to be exposed shall be patched and a smooth rubbed finish provided. Rubbing shall be done with a corborumdum stone and a mixture of Portland cement and water.

14.6.4

14.6.5

15. 0 15.1 15.2

15.3

15.4

16.0 16.1

16.2 16.3

16.4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES FORMORK

VOLUME: IV PART: 3 SECTION: B9 SHEET 1 OF 4

Doc. No TCE.5270A-H-112-601

1.0

SCOPE OF WORK Work under this Section shall comprise supply of all labour, plant and material and the performance of all work necessary for the design, fabrication, supply, erection, maintenance and removal of formwork and falsework to form concrete structures as shown on the Construction Drawings or as otherwise directed by Project Manager ..

2.0

DEFINITIONS For the sake of clarity, the terms used in this Section are defined as follows: a) b) c) "Forms" or "Formwork" shall mean the moulds into which concrete is placed, "False work" or "Shoring" shall mean the structural supports and bracings for forms used in any part of the Works, "Curved forms" shall mean any form not composed of plain surface and limits of curved forms shall not extend beyond the lines of tangency or intersections with flat surfaces.

3.0 3.1

SUBMITTALS At least 15 days in advance of any concrete work being carried out at the Site, Contractor shall submit details of materials for formwork and surface finishes, and construction techniques which he plans to achieve in the concrete surfaces and allowable tolerances. Likewise, he shall provide details and schedules of steel formwork, related shop drawings for tunnel lining and also structural computations of the formwork construction. Review by Project Manager of Contractor's drawing and calculations shall not relieve Contractor of his responsibility for the adequacy of form and falsework, or for the safety of persons or property, for the successful completion of the work. MATERIALS Materials used for form sheathing and lining shall be wood, steel, plywood, or fibreglass. All materials used in formwork construction shall be of adequate strength and quality for their intended purpose and shall be satisfactory to Project Manager .. Timber shall be sound, straight, free from warp, decay and loose knots and shall be dressed smooth. Except as expressly approved by Project Manager , timber brought for use as forms, shoring or bracing shall be new material. Plywood as form shall be mill-oiled and edge-sealed, non-warping, non-wrinkling and manufactured with special water proof glues. Plywood sheets shall be of uniform width and length. Surface of steel of steel lined forms shall be smooth. Forms with dents, buckled areas or other surface irregularities shall not be used. Forms for concrete surfaces exposed to flowing water (other than tunnel lining) shall be lined with sanded, uncoated, plywood veneer. Steel or impermeable plastic liners will not be permitted. Rough sawn boards may be used only for lowest grade of surface finish (F1). Reuse of forms will be allowed only if they are thoroughly cleaned and repaired and capable of producing the finish required for concrete. Damaged or deteriorated forms through use shall not be used. Timber or plywood forms repaired with metal patches shall not be used.

3.2

4.0 4.1

4.2

4.3

4.4 4.5

4.6 4.7

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES FORMORK

VOLUME: IV PART: 3 SECTION: B9 SHEET 2 OF 4

Doc. No TCE.5270A-H-112-601

4.8

Where required, expanded metal fixed to the formwork shall be used in vertical construction joints.

5.0 5.1

FORM TIES Type, number and positions of internal formwork supports and ties shall be got pre approved. Form inserts and similar permanently embedded items shall be accurately located and securely fastened in place. Number and location of form ties and bolts shall be such as to ensure tight fitment against concrete previously placed and remain in tight contact during operations. The whole or part of such formwork supports and ties shall be removed without damage to the concrete so as to leave no part embedded nearer the surface of the concrete than the designed cover of the reinforcement or 50 mm in the case of unreinforced concrete. Only metal portions of formwork supports and ties shall be allowed to remain in place. Through-bolts will not be permitted in water retaining walls. Holes left after the removal of supports and ties shall be filled as described in Section "Concrete - Repair of Defective Concrete", and shall be finished off neatly to the standard of the concrete surface. Such filling shall be adequately cured. DESIGN Contractor shall be solely responsible for the adequate design, construction and maintenance of any and all formwork and falsework required in the Works. Forms shall be designed to permit the concrete to be deposited as nearly as is practicable directly in its final position, and to allow inspection, checking the cleanup of the formwork and reinforcement to be completed without delay. Formwork and falsework shall be designed, fabricated, erected and removed in accordance with the applicable provisions of the recommended practice for concrete form of IS:456. All falsework shall be designed to withstand safely all live and dead loads which might be applied to the falsework during all stages of construction, service and removal. For the purpose of formwork and falsework design, Contractor shall assume a value of 2.5 t/m3 for the density of concrete. Detailed drawings of shoring and formwork shall be prepared by Contractor . The calculations and drawings shall show the size and specification of the formwork, including the type and grade of all materials used in the construction, design loads on the formwork supports, horizontal forces imposed on the false work and used for design purpose, and details of splices and connections, including nailspikes and other fasteners. If mechanical equipment such as concrete buggies, screeding machines, etc. are to be used, this information shall be shown on these drawings. ERECTION OF FORMWORK Formwork and falsework shall be constructed only after the formwork drawings are got accepted by PROJECT MANAGER. One set of which shall be kept at the Site at all times. No change will be allowed without prior written acceptance of EIC.

5.2

5.3 5.4

6.0 6.1

6.2 6.3 6.4 6.5

7.0 7.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES FORMORK

VOLUME: IV PART: 3 SECTION: B9 SHEET 3 OF 4

Doc. No TCE.5270A-H-112-601

7.2

Formwork shall be erected and maintained such as to confine the concrete without loss of mortar and produce required finished surfaces. Forms shall be set and maintained within the specified tolerance limit such that the complete concrete surfaces are within these limits. Forms for concrete against which backfill is to be placed or which will not be exposed to view may be constructed of smooth tight boards not less than 25 mm nominal thickness. Forms for concrete exposed to view shall be constructed of steel or plywood that is smooth and defect free with matched and sanded joints to give a symmetrical pattern over entire area. Chamfer strips, 35 mm X 35 mm shall generally be used on all exposed corners. Forms considered unsafe or inadequate in any manner shall rejected and replaced.. An adequate number of temporary clean-out holes or short pipes shall be provided in the forms to secure the draining of rainwater. When a second lift is placed on hardened concrete, the number, location and tightening of ties at the top of the old lift and bottom of the new shall be such as to prevent any damage to concrete. The form of a new lift shall overlap the hardened concrete by 100 mm, to prevent abrupt irregularities. Forms for sloping concrete surfaces shall permit their placing board-by-board or panel-bypanel immediately ahead of concrete placement so as to enable access for placement, vibration, and inspection of the concrete. All form surfaces shall be thoroughly cleaned before erection and shall be lubricated with a non-staining mineral oil. All excess shall be wiped off the forms prior to placement of concrete. Oil shall not be allowed to come into contact with reinforcement steel or other embedded items. Immediately before concrete placement, all forms shall be inspected to ensure that they are properly placed, sufficiently rigid, clean, tight, properly surface treated and free from excess of oil or other foreign materials. The formwork for the gate groove areas shall be accurately drilled to be held with first stage anchor couplings/plates to be embedded in primary concrete. Both shall be fixed through formwork into the first stage anchors couplings/plates to ensure that the couplings/plates remain flush with primary concrete face and the couplings do not get plugged. TUNNEL FORMWORK Steel faced forms shall be used to achieve the F3C finish required on the hydraulic tunnels lining surface. The forms shall be fitted with ample windows at appropriate spacing and locations to allow the introduction of vibrators and to carry out inspections and any other work needed behind the form. Formwork shall allow for continuous concrete pouring of the whole face. It shall be of rigid construction, non-deformable due to working loads imposed upon it. Once installed in the position the form shall maintain it without displacement during concrete placement. Formwork shall be constructed in such a way that no abrupt irregularities arise at vertical construction joint. The joint in formwork shall overlap the vertical construction joint at least 500 mm and one formwork element remains in contact with placed concrete while others are being stripped down and installed for following concreting stages. Windows shall be provided in each side about the midheight at tunnel and crown on alternate sides of centreline. These shall be at least 600 mm in the least dimension and shall be spaced at a intervals not exceeding 2.5m.

7.3 7.4

7.5 7.6 7.7

7.8

7.9

7.10

7.11

8.0 8.1

8.2

8.3

8.4

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES FORMORK

VOLUME: IV PART: 3 SECTION: B9 SHEET 4 OF 4

Doc. No TCE.5270A-H-112-601

9.0

FINISHED TOLERANCES Forms shall be so constructed that the finished concrete surfaces shall be of uniform texture in accordance with the types of finish specified in Section "Concrete".

10.0 10.1

REMOVAL OF FORMWORK Removal of forms shall be performed with care so as to avoid injury to the concrete and as soon as permissible in order to avoid delay in curing and repair of surface imperfections. Forms shall not be removed without the consent of the Engineer. Forms shall not be removed until the concrete has attained sufficient strength to prevent damage to concrete. Damaged concrete shall be repaired or treated as soon as possible, but not before Project Manager has inspected this and agreed to the repairs. Time elapse between completion of concrete placing and removal of forms shall generally be in accordance with IS:406, but not less than following: Undersides of beams, deck type slabs, undersides of openings generally Piers, columns and walls - lifts 2 m and under - lifts over 2 m Tunnel linings Mass concrete Removing time for propping under beams, slabs etc., will be taken as per IS:456. 24 hours 48 hours 16 hours 24 hours 7 days

10.2

10.3

10.4

These are only indicative. Governing rule to be observed is 28-day compressive strength to be determined by cube test, described in Section "Concrete - Test During Execution of Work". When fixing the minimum period for formwork removal, shrinkage and creep of the concrete shall be taken in to consideration. Considering the weather conditions and type of pour, the minimum elapsed required for formwork removal may be modified for individual pours, and in case of formwork for beams and deck slabs it shall remain in place until concrete has developed the specified design strength. Forms shall be removed so as to avoid cracking, spalling, peeling, breaking of edges or surfaces or other damage to concrete. If it is necessary to use wedges, only wooden wedges shall be used against the concrete. Damaged concrete shall be repaired or treated as soon as possible, but not before Project Manager has inspected such damage and agreed to the remedial works.

10.5

10.6

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIOS ACTIVITIES REINFORCING STEEL

VOLUME: IV PART: 3 SECTION: B10 SHEET 1 OF 3

Doc. No TCE.5270A-H-112-601

1.0

SCOPE OF WORK Contractor shall furnish, fabricate, and install all reinforcement steel as shown on the approved detailed reinforcement drawings and bar lists prepared on the basis of EI C's Construction Drawings. Work shall further include the furnishing and installation of all tie wires, clips, supports, chairs, spacers, couplers and other appurtenances necessary to produce finished concrete structures.

2.0 2.1

STANDARDS Cutting, bending, cleaning, placing and fastening in position and testing shall conform to the requirements of the following Indian Standards (latest edition): IS:432(Part 1) specifications for mild steel and medium tensile steel bars and hard drawn steel bars for concrete reinforcement IS:456 Code of practice for plain and reinforced concrete IS:1786 Specifications for high strength deformed steel bars and wires for concrete reinforcement IS:2502 code of practice for bending and fixing of bars IS:2571 code of practice for welding of mild steel bars IS:13920 code of practice for Ductile detailing of reinforced concrete structures

2.2 2.3 3.0 3.1

Tolerances for reinforcement placing and fastening in position shall be in accordance with IS:456. In case of a conflict between the above Standards and the Specifications given herein, these Specifications shall take precedence. SUBMITTALS Within 15 days from Order to Commence but before procuring to the Site the equipment, Contractor shall submit to PROJECT MANAGER an updated and detailed plans and descriptions of the equipment proposed for fabrication of reinforcing steel, consistent with those submitted with his Tender and any subsequent amendments and additions agreed to with PROJECT MANAGER During progress of work, PROJECT MANAGER will prepare reinforcement drawings which will indicate the main structural reinforcement required in the particular structure. Contractor shall notify to PROJECT MANAGER at least four weeks before such drawings are required for each section of work. Based on these drawings, Contractor shall prepare the detail bar bending schedules. All bars shown in reinforcement drawings shall be identifiable on the bar lists and all bars shall be defined and dimensioned in clear unambiguous way. Contractor shall be responsible for correctness of these drawings and bar lists. He shall also submit to PROJECT MANAGER blue prints and transparencies of reinforcement drawings and bar lists as stipulated in the Conditions of Contract. MATERIALS All deformed reinforcing bars shall be high yield strength, deformed steel bars conforming to IS:1786 Grade Fe500.

3.2

4.0 4.1

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIOS ACTIVITIES REINFORCING STEEL

VOLUME: IV PART: 3 SECTION: B10 SHEET 2 OF 3

Doc. No TCE.5270A-H-112-601

4.2 4.3 5.0 5.1

All plain reinforcing bars shall be mild steel and medium tensile strength steel conforming to IS: 432( Part 1)

bars

Wire for tying reinforcing steel shall be black annealed iron wire, or acceptable equivalent, with a diameter not less than 1.6 mm. STORAGE Reinforcing steel shall be stored above the ground in separate groups according to size and length. Reinforcing steel which has been cut and bent according to schedules approved schedules shall be marked with a bar number shown on the schedule by using weatherproof tag or by placing in marked bins and shall be stored in such a manner as to be readily accessible when required and to facilitate inspection. Reinforcement fabric supplied in rolls shall be straightened into flat sheets before being placed. FABRICATION Contractor shall cut and bend all reinforcing steel in accordance with bar schedules supplied by himself, duly approved by PROJECT MANAGER. Reinforcing steel bars shall be cut and bent at site or at a fabricator's plant in a workmanlike manner as per Indian Standards. Nevertheless, bar-bending machine and a representative stock of reinforcing steel shall be maintained at the Site, sufficient to allow minor revisions and additions to be carried out as required by PROJECT MANAGER.. Bars shall be bent cold at temperature greater than 5 Bending below that temperature or C. warm-bending will only be permitted when adequate precautions are taken to comply with the corresponding direction issued by the steel manufacturer for such bending. Reinforcing steel shall not be straightened or rebent in a manner that will damage the materials. Temporary bending and subsequent straightening of bars partially embedded in concrete shall not be permitted, except when shown on the Construction Drawings or with approval of PROJECT MANAGER. Bars with kinks or bends other than those indicated on the Drawings and schedules shall not be used. Reinforcement bars, other than tie bars, shall not be spliced at points other than those shown I n Construction Drawings. On occasions when it becomes necessary to alter the position of such splices, the new position and the type of splice shall be subject to the approval of PROJECT MANAGER. If necessity arises of welding of reinforcement, provisions of IS-2751 and Indian Standard recommendations for welding cold worked steel bars for reinforced concrete shall be followed. Couplers (BARTEC or equivalent) shall be used for splicing the reinforcing bars of 32 mm diameter and more as indicated in the Construction Drawings. Patent reinforcement splicing methods shall be used MANAGER. only with approval of PROJECT

5.2 6.0 6.1 6.2

6.3

6.4

6.5

6.6 6.7 6.8 6.9 6.10

Contractor shall not weld any item to reinforcing steel except as approved by PROJECT MANAGER and in such case, shall adapt only accepted procedures. Reinforcing bars available from the rejected concrete structures shall not be used without prior specific approval by PROJECT MANAGER. PLACING

7.0

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIOS ACTIVITIES REINFORCING STEEL

VOLUME: IV PART: 3 SECTION: B10 SHEET 3 OF 3

Doc. No TCE.5270A-H-112-601

7.1 7.2 7.3

Before placing in position, the reinforcing steel shall be thoroughly cleaned of loose mill scale, rust, grease, paint, splashed concrete now dried or other coatings that would reduce bond. Reinforcing steel to be incorporated in the works shall be placed accurately in positions shown in drawings and shall be held firmly in place during the placing and setting of concrete. Reinforcing steel shall be so placed that there will be a clear distance of at least 50 mm between the reinforcing steel and anchor bolts or embedded metal work, if not shown otherwise on the drawings or required otherwise by PROJECT MANAGER. Reinforcing steel shall be maintained in position by the use of small concrete blocks, steel chairs, steel spacers, steel hangers and other steel supports and ties, acceptable to PROJECT MANAGER.Wood supports or spreaders shall never be used. All intersections shall be securely tied except those where the bar spacing is less than 300 mm in each direction, where only alternate intersections need be tied. Binding wire and steel supports shall not be carried to permanently exposed surfaces and are bound by same technical requirements with regard to concrete cover as for reinforcing steel. All reinforcement shall be inspected in place and approved by PROJECT MANAGER before placing concrete. Concrete placed in violation of this provision may be rejected and removal required. TOLERANCE ON PLACING OF REINFORCEMENT Unless otherwise specified by PROJECT MANAGER or shown in drawings, reinforcement shall be placed within the following tolerances: a) Protective cover: For cover up to 50 mm For cover 75 mm and more b) Spacing: For effective depth 200 mm or less For effective depth between 200 and 2000 mm For effective depth more than 2000 mm + 10 mm + 15 mm + 25 mm + 6 mm + 12 mm or 1/3rd of specified cover whichever is less

7.4

7.5 7.6

8.0

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES WATERSTOPS AND JOINTS

VOLUME: IV PART: 3 SECTION: B11 SHEET 1 OF 3

Doc. No TCE.5270A-H-112-601

1.0 SCOPE OF WORK 1.1 Work under this Section include all labour, materials and equipment required for supply, fabrication ( if any), storage, handling, placing and splicing of metal sealing strips and PVC/Rubber Water stops and other components to be incorporated in the movement joints in concrete structures as shown in Construction Drawings or as required by Project Manager . The work shall include all the necessary supports and ties required for placing waterstops and other materials. STANDARDS Material, testing, placing and sealing of joints shall conform to the requirements of the following Indian Standards (latest edition): IS:456 IS:290 IS:8543 IS:1834 Code of practice for plain and reinforced concrete Specifications for coal tar Black Paint Methods of Testing of Plastics Specifications for Hot applied sealing compounds for joints in concrete

1.2

2.0 2.1

IS:1838 Specifications for Preformed fillers for Expansion joints in concrete pavement structures IS:3400 2.2 Methods of tests for Vulcanised Rubbers IS:13360 Plastics - Methods of Testing In case of conflict between above Standards and Specifications given herein, these Specifications shall take precedence. SUBMITTALS At least 4 weeks prior to procuring or dispatch to the Site of the particular item of work to which the submittal relates, Contractor shall submit to Project Manager the details covering the properties and performance, including the certified copies of reports of all tests made by manufacturers, along with material samples of the products, of: a) b) c) d) PVC Waterstops, Joint fillers, Joint sealing compounds Joint Sealant.

3.0

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES WATERSTOPS AND JOINTS

VOLUME: IV PART: 3 SECTION: B11 SHEET 2 OF 3

Doc. No TCE.5270A-H-112-601

4.0 4.1

MOVEMENT JOINTS IN GENERAL CONCRETE STRUCTURES Term movement joint comprises of both the expansion and contraction joints in concrete structures. Movement joints shall be constructed at such locations and to such dimensions as shown in Construction Drawings. Contractor shall supply and install various joint components as specified herein and as shown in Construction Drawings and in accordance with manufacturers recommendations. No fixed metal embedded in the concrete shall be continuous through a movement joint except where expressly shown on Construction Drawing. Expansion joints may be comprised of the following elements: a) b) c) d) PVC waterstop, Joint filler, Joint sealing compound (asphalt seal), Bituminous coating.

4.2 4.3

4.4

Contraction joints may be comprised of the following elements: a) PVC waterstop, b) Bituminous coating, or other approved bond breaker.

12.5 (1)

MATERIALS Waterstops shall be made of extruded polyvinyl chloride ( PVC) conforming to IS: 15058.Material for waterstops shall be clean, homogeneous and free from porosity and other imperfections. Waterstops will have minimum width of 230 mm for joints in general and 300 mm for concrete dam. Minimum wall thickness shall be 8 mm. Wings of PVC water stop shall be provided with corrugations or bulbs to achieve good bond. PVC water stops in expansion joints shall be provided with hollow centre bulb. Storage of material prior to placement shall be made in such a way as not to alter the properties of the material during storage. Water stops shall be stored so as to permit free circulation of air around them. All materials shall be protected from contact with oil and grease. Water stops shall be stored in a place protected from the direct rays of Sun or to any other heat source. Water stops shall be joined and fixed in place as per manufacturer's recommendations to form a continuous watertight barrier. All cross-pieces, T-pieces and corner-pieces shall be factory produced and joints shall be welded with approved, thermostatically controlled electric heat equipment. Temperature at which the splices are made shall be sufficient to melt but not char the plastic material. Splices shall be neat with their ends joined in true alignment. A mitre-box guide and portable knife shall be provided for cutting the ends to be joined to ensure good contact between joined surfaces.

12.5.1 PVC Waterstops

(2) (3) (4)

(5)

12.5.2 Joint Filler Bituminous fibre sheet shall be 12 mm thick and shall conform to IS 1838 (Part 1) for preformed expansion joint fillers for concrete paving and structural construction (nonextruding and resilient bituminous types).

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES WATERSTOPS AND JOINTS

VOLUME: IV PART: 3 SECTION: B11 SHEET 3 OF 3

Doc. No TCE.5270A-H-112-601

12.5.3 Joint Sealing Compound (asphalt seal) Joint sealing compounds shall be as per the specification for hot-applied sealing compounds for joints in concrete (IS: 1834). 12.5.4 Bituminous Coating Bituminous coating shall consist of two (2) layers of coating as per IS: 290. 12.5.5 Joint Sealant Joint sealant shall be as per IS: 11433. 12.6 (1) EXECUTION Where grouting is not required, the movement joints shall be formed with F1 finish, explained in part Formed Surfaces under CONCRETE in these Specifications. If grouting is required, joints shall be formed with F2 finish as specified in section Concrete. Contractor shall supply all necessary supports and ties required for placing the Metal sealing strip and water stop and shall position it so that its central axis coincides with the joint centre. Care shall be taken that metal sealing strip and water stop does not bend or deflect during concreting. Concrete adjacent to metal sealing strip and water stop shall be thoroughly worked to ensure full contact with metal sealing strip and water stop but without damaging it. PVC materials shall be protected from sunlight until installation is completed. In structures founded on rock, metal sealing strip and water stops shall be sealed 500 mm minimum in drilled or excavated slot below effective foundation surface, and the space around metal sealing strip and water stop in the slot shall be filled with non-shrink grout. Prior to commencement of concrete placing, metal sealing strip and water stops placed shall be inspected by PROJECT MANAGER. Before casting second part of a movement joint, whole surface shall be covered with bituminous coating, bituminous fibre sheet joint filler or other approved bond breaker as shown in Construction Drawings. Before applying joint sealant, the joint shall be raked out to specified depth and all laitance, dirt, oil and foreign matter shall be removed by sandblasting, compressed air, grinding discs, or other effective means and the concrete surfaces coated with an approved suitable primer. Joint sealant shall be placed after the concrete curing period in accordance with manufacturer's instructions. Concrete surface temperature shall not be higher than 30 at C the time of placing and this shall be surface dry. After placing, sealant shall be protected from effects of water for minimum of ten hours. Sealant that becomes unbonded from the concrete, or cracks, or shows any other defects before final acceptance of the work shall be replaced by Contractor.

12.6.1 Movement joints in General Concrete Structures

(2)

(3)

(4)

(5)

(6)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 1 OF 7

Doc. No TCE.5270A-H-112-601

13.1 (1)

SCOPE OF WORK Work in this Section include all labour, materials and equipment required for the supply, fabrication, and installation of various metal works as shown in Construction Drawings. Specifications contained hereunder are applicable for all metal works to be carried out under this Contract. Furthermore, the Contractor shall install metal works supplied by others. This Section covers the following items: a) b) c) d) e) f) g) h) j) Steel pipes Miscellaneous steel sections Watertight steel covers, frames, and gratings Handrails Railing Ladders, handles, and climbing irons Erection hooks Steel anchorings Metal works supplied by others

(2)

(3) (4) 13.2 (1)

Unless otherwise stated, all miscellaneous metalwork shall be fabricated from carbon steel sections, plates and bars conforming with IS:2062. Unless otherwise stated or shown, all miscellaneous metalwork shall be painted as specified hereinafter. Where specifically so stated, steelwork shall be hot-dip galvanised. SUBMITTALS Contractor shall supply certificates of compliance with specified Indian Standards or other relevant standards for all materials supplied to Works. Manufacturers catalogues and samples of materials proposed for incorporation in the Works shall be submitted as requested by Project Manager . From the information given in Tender and Construction Drawings, Contractor shall prepare, prior to actual manufacture, his own shop drawings showing plans and sections of all parts, assemblies, connections and supports for all metalwork shown in Construction Drawings. Two copies of each drawing, calculation sheet and schedule of materials shall be submitted for approval. Project Manager will return these within 15 days either approved or with requests for modifications. Within 7 days, Contractor shall revise the drawings, calculations and schedules accordingly and return a new set (again in two copies) of these for the final approval. After final approval, the Contractor shall deliver one transparency and two copies of the documents to PM. Approval of shop drawings and calculations shall not in any way relieve the Contractor of his responsibility and obligations under this Contract, particularly those relating to the adequacy and accuracy of the final product. Any materials ordered or fabrication work performed, before Contractor's drawings are approved will be at his own risk.

(2)

(3) (4)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 2 OF 7

Doc. No TCE.5270A-H-112-601

(5)

Contractor shall not be entitled to any time extension based upon the rejection of his designs or detail drawings if these fail to conform to sound engineering practises or to the stipulations contained in these Specifications. FABRICATION The work shall be shop fitted and shop assembled where possible, and shall conform to the details on approved Contractor's shop drawings. Workmanship shall conform to the best modern shop and field practice. All joints and intersecting members shall be accurately fitted and all work shall be fabricated in true planes (to tolerances as provided on drawings) with adequate fastenings. Plates and steel sections shall be perfectly straight with smooth surfaces. Edges shall be sharp, clean and without burrs after the cutting. Thick plates may be flame cut, provided that the material is not damaged and that the edges of the cut are ground clean or machined. Plates shall be cold-rolled. Correction of bent members by heavy blows shall be avoided. Special care shall be taken when hot-rolling becomes necessary. All members shall be carefully and accurately assembled by welding, screws, bolts, or rivets as approved. The joints shall be filled, milled, or machined as necessary to provide closed and perfect connections. All frames shall be provided with suitable bracing to maintain alignment during transport. Units shall not be subject to overstressing during transport and erection. Hammering which would injure or distort the members will not be tolerated. All fastenings, anchors and accessories required for fabrication and erection of the work shall be provided. Exposed fastenings shall be kept to an absolute minimum evenly spaced and neatly set out. Wood plugs shall not be permitted. Contractor shall check the actual dimensions and shapes of existing concrete openings before fabricating steel frames and metal supporting parts of steel covers and gratings. WELDING All welding shall be carried out by experienced welders using the shielded-arc method as described in the SP12 ISI Handbook for Gas Welders and ISI Handbook of Manual Metal Arc Welding for Welders. Welding rods shall be of the heavily coated type designed for all position welding, and the size, type and manufacture of the rods shall require the consent of Project Manager . All welding shall be continuous along the entire line of contact, except where tack welding is permitted. Bevelling of materials shall be done as shown in approved shop drawings and shall be finished to a smooth and true finish with an automatic gas cutter or grinder. Use of manual gas cutters shall require the consent of Project Manager . The surface of the working materials shall be free from slag, moisture, rust, oil, paint or other impurities. Mill scale which cannot be removed with a stiff wire brush may however remain. The face of welds shall be smooth and form a uniform bead. Size and thickness of weld shall nor be less than specified, nor shall there be an excessive build-up or marked irregularities in the surface appearance. Blow holes, slag, overlap, undercut and unsatisfactory melting of welded joints shall be removed with grinders or by other means and then rewelded. Due care shall be taken to protect the surrounding part from any injury or damage. Deformation of members resulting from welding shall be repaired by an approved mechanical method.

13.3 (1) (2)

(3)

(4)

(5)

(6) 13.4 (1)

(2) (3)

(4) (5)

(6)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 3 OF 7

Doc. No TCE.5270A-H-112-601

(7) (8) (9)

Steel which has been previously galvanised shall not be welded. Welding of aluminium shall be done employing a "parent metal" or other approved filler rods. Surfaces which have been previously treated such as anodising shall not be welded. The Contractor shall propose the type and carry out the non-destructive testing of the welds as approved. All joints which are to be watertight shall be tested by dye penetrant. SURFACE FINISH AND CORROSION PROTECTION All metal components other than stainless steel, aluminium, embedded parts and those that are required to be galvanised, shall be prepared, primed and painted in the shop prior to erection. Paints used for both prime and finish coats shall be two component epoxy based, shall be obtained form the same manufacturer and shall be the best quality of their kind. They shall be suitable for application in environments where the relative humidity may exceed 90%. The Contractor shall submit samples of all paints he proposes to use to PROJECT MANAGER, who will select the colour of the finish coats. Prior to painting, steel surfaces shall be sandblasted down to rust degree SA 2-1/2 according to SIS Standard 055900, to remove all mill scale, weld splatter, rust and any other deleterious material. Oil and grease shall be removed by an approved solvent. The surface shall be wiped clean of any dust prior to priming. Immediately after cleaning, steelwork shall receive two coats of two component zinc epoxy primer, each of dry film thickness 0.05 mm. Any primer applied surface that shows signs of rusting, flaking, powdering or peeling of the prime coat, or any finish coat, shall be sandblasted to remove the paint bare to the metal as described above and repainted. After priming, steelwork shall receive a further two coats of two component epoxy based paint, each of dry film thickness 0.08 mm. The total theoretical thickness of paint applied, including prime coats, shall be 0.26 mm, but in no case less than 0.22 mm. Painting work shall be carried out as per manufacturers recommendations in a clean dust-free environment with temperature and humidity controlled. All the surrounding works shall be protected from falling paint stains in appropriate manner or over spray. All smeared and damaged surfaces shall be cleaned or repaired. After erection of painted miscellaneous metalwork,Contractor shall make good any damage to paint coating. Project Manager may direct removal of such items, badly damaged. These may be returned to the shop and repainted. All steel assemblies required to be galvanised shall, after the steel has been thoroughly cleaned of rust and scale, be galvanised in accordance with IS:4759 (Hot dip zinc coating on 2 structural steel and other allied products). The zinc coating shall be 350 g/m minimum. Any galvanised parts that becomes warped during galvanising operation shall be straightened. Bolts, nuts and similar threaded fasteners, after being properly cleaned, shall be galvanised in accordance with ASTM Specification A 153 "Spec, for Zinc Coating (Hot-Dip) on Iron and Steel Hardware". Threads on galvanised bolts and nuts shall be formed with suitable taps and dies such that they retain their normal clearance after hot-dip galvanising.

13.5 (1)

13.5.1 Painting

(2)

(3)

(4)

(5)

(6)

(7)

13.5.2 Galvanised Steelwork (1)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 4 OF 7

Doc. No TCE.5270A-H-112-601

(2)

After installation on the final place all areas of damage to the galvanised coating shall be sandblasted and prepared and given 2 coats of approved zinc rich paint. Preparation of steelwork surface and application of paint shall be in accordance with the paint manufacturers instructions. Contractor shall supply certificates of compliance with the above standards for all galvanised material delivered to the Site. Fasteners for miscellaneous metalwork including bolts, anchor bolts, cap screws and nuts shall be of stainless steel unless otherwise stated or shown. Studs and anchors fixing metalwork to concrete will be of stainless steel. These shall be expanding anchor type (e.g. Nelson or Hilti). Grouted or resin types shall need consent of Project Manager . All aluminium parts exposed to view shall have an anodising finish of uniform appearance and shall be free from marks and blemishes. Sulphuric acid shall be employed as electrolyte for anodising unless otherwise directed. The coating thickness shall be 0.02 mm. INSTALLATION All items of miscellaneous metalwork shall be installed in correct position and alignment. Damaged or defective materials shall not be installed. Damaged or defective areas of paint or galvanising shall be cleaned and repaired as directed by Project Manager . Metalwork to be embedded in concrete shall be located accurately and shall be held in correct position and alignment during concrete placing and setting of the concrete. Unless otherwise provided, the anchor bolts shall be set and held in position before concrete is placed. Where it is impractical to embed anchor bolts or anchors for a comparatively light metalwork before concrete placement and where it is necessary to anchor in parts but inserts or anchor bolts have not been provided, holes shall be drilled in concrete and approved expansion anchors shall be installed. All anchor holes shall be straight, true to diameter and fitting with recommended of respective manufacturer. When drilling water is used, concrete surface permanently exposed shall be immediately cleaned to prevent discoloration by water and cuttings. Supports and base plates shall be levelled or aligned accurately and rigidly secured in place. Adjustment with steel shims shall be done as necessary. All spaces under the supports or base plates shall be filled with concrete or shall be grouted as specified in the Section "Concrete". Each complete unit shall be serviced and tested after installation. The servicing shall include lubricating, adjusting, cleaning all parts, and all other work and material required for operation. After each unit has been serviced, it shall be given an operation test, and adjustments shall be made until the operation of the unit is approved by Project Manager . METALWORKS SUPPLIED AND INSTALLED BY THE CONTRACTOR

(3)

13.5.3 Fasteners (1) (2)

13.5.4 Anodising (1) (2) 13.6 (1)

(2) (3)

(4)

(5)

13.7

13.7.1 Steel Pipes

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 5 OF 7

Doc. No TCE.5270A-H-112-601

(1) (2)

Contractor shall supply and install steel pipes of various diameters and fittings in the positions shown on the Construction Drawings or as directed by Project Manager .. Steel Pipes used shall be ERW (Electric Resistance Welded) of Steel grade Fe 410 as specified in IS 3589. The thickness of pipes shall generally be as below : Outer Dia 219.1 323.9 Thickness 4.5 mm 4.5 mm

Pipes of other diameters and with different thickness may also be required. (3) (4) (5) Weight of the pipe shall be calculated as per Table 5 of IS 3589. Pipes shall be carefully fastened and supported within the shuttering, in order to avoid any movement when pouring concrete. Pipes where not cast into concrete shall be adequately supported by galvanised mild steel holderbats or other approved means. The distance between pipe supports shall nor exceed 2.0 meters. Contractor shall supply and install all small galvanised steel sections such as edge protection, angles, frames, bearing plates, brackets, beads at plastered corners, etc., of various dimensions. Bolts, screws, anchors and other accessories for interior or exterior purposes shall be included. 13.7.3 Watertight Steel Covers, Frames, and Gratings (1) Contractor shall supply and install all watertight steel hatch covers, frames, gratings for cable channels, drains etc., as required by Project Manager as shown in Tender Drawings.. All items shall be fabricated according to shop drawings prepared by the Contractor in the course of Works. Covers shall be manufactured from 6 mm steel checker plate with reinforcing steel sections where required, steel flats and lifting handles. Supporting frames shall consist of steel angles and welded steel flats provided with continuous watertight rubber seal. Frames shall be adjusted during installation to ensure a good fit and water tightness of the cover. The covers shall be placed flush with finished floors. Steel gratings shall consist of 25 mm deep by 2 mm thick welded steel flats. Mesh size shall be 30x30 mm. Frames and steel sections as supports for gratings shall consist of steel angle or channel sections fixed in the concrete. Frames shall be adjusted during installation to ensure a good fit and even bearing for the grating. Gratings shall be placed flush with finished floors. Steel covers, frames and reinforcing members for supporting gratings shall be painted as specified above in this Section. Gratings shall be hot-dip galvanised and shall be fixed to support platforms using stainless steel screws and fittings. Contractor shall supply and install in the buildings handrails fabricated from galvanised steel pipes supported on welded steel flats and steel plates as shown on the Tender Drawings and as specified herein. Material for steel pipes shall be of standard weight and shall conform to

13.7.2 Miscellaneous Steel Sections

(2)

(3)

(4)

13.7.4 Handrails (1)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS

VOLUME: IV PART: 3 SECTION: B12 SHEET 6 OF 7

Doc. No TCE.5270A-H-112-601

IS:4736. All items shall be fabricated according to shop drawings prepared by the Contractor in the course of Works. (2) Handrails shall be installed following the slopes and in the positions shown on the Construction Drawings and shall be supported to avoid movement when placing concrete in the blockouts. Handrails shall be painted as specified above in this Section. The Contractor shall supply and install steel pipe railings as shown on the Tender Drawings. Railings shall consist of welded galvanised steel pipes conforming to IS:4736. All items shall be fabricated according to shop drawings prepared by the Contractor in the course of Works. Railings shall be installed both indoor and outdoor, horizontal or inclined in the positions shown on the Construction Drawings and shall be supported to avoid movement when placing concrete in the blockouts. Steel pipe railings shall be painted as specified above in this Section. Contractor shall install ladders and climbing irons fabricated out of steel flats and plain round bars as shown in Tender Drawings. Ladders may have protection cages as required for safety of personnel. Fixings and fittings shall be of stainless steel. All items shall be fabricated according to approved shop drawings and all these shall be painted as specified. Contractor shall install steel erection hooks as required by Project Manager Erection hooks shall be formed out of structural steel conforming to IS:2062 and IS:8500. These shall be hot bent and firmly held during placing of concrete. These shall be later galvanised in specified manner. Contractor shall supply and cast into concrete steel anchorings as required by Project Manager or when shown in Construction Drawings. Anchorages shall consist of 150 mm long, 16 mm diameter anchors made of mild steel conforming to IS:432 (Part I). Steel anchorings shall require no surface treatment. Where anchoring is to be done after concreting either for convenience or per specification or drawings, same shall be grouted by cement grout.

13.7.5 Railing (1)

(2)

13.7.6 Ladders, and Climbing Irons (1)

13.7.7 Erection Hooks (1)

13.7.8 Steel Anchorages (1)

(2) (3)

13.7.9 Steel Liner in Spillway Gates Inlet (1) The Contractor shall design, furnish and install the steel liners in the entrance upper curves of the spillway inlets as shown on the Tender Drawings. The minimum thickness shall be 16 mm. The properties of steel shall be as per IS8500. All steel shall be fine grained, fully killed, not subject to brittle fracture, non-ageing and highly weldable. The liners shall be designed with the following objectives: a) b) Lining shall resist all forces resulting from the water loads, Lining shall resist the external water load, because of seepage corresponding to the reservoir water level,

(2) (3)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES METALWORKS
Lining shall resist the loads due to encasing in the concrete. Compression/tension Shear 0.45 yield point 0.35 yield point

VOLUME: IV PART: 3 SECTION: B12 SHEET 7 OF 7

Doc. No TCE.5270A-H-112-601

c) (4) a) b) (5) 13.8 (1)

The design stresses shall conform to those given in the relevant IS, but not more than:

Contractor shall co-ordinate the fabrication, welding and corrosion protective treatment with the Lot 4-contractor. Metalworks Supplied by Others Anchorings and conduits furnished by suppliers of hydro and electro-mechanical equipment shall be installed locations shown in Construction Drawings in concerned drawings prepared by others and approved by Project Manager .. Pieces to be incorporated in the concrete shall be furnished and stored in the warehouse of the Contractor at the Site. Every piece handled over to the Contractor shall have a handover card on which the following is stated: a) b) c) d) e) Installation site, Number of pieces, Number of reference drawings, Weight of the pieces, without packing, Special connections for fixing if necessary.

(2)

(3)

Contractor shall transport these items from warehouse to installation site and fix it stiffly behind the formwork with due precision before concreting. It is the responsibility of the supplier to check the correct fitment of these pieces behind the formwork before concreting takes place.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 1 OF 13

Doc. No TCE.5270A-H-112-601

1.0 1.1

SCOPE OF WORK Work under this Section includes all labour, materials and equipment, and performance of all operations required for the execution of the finishing and architectural works inside or outside of buildings, rooms or chambers to be constructed under this Contract. Mainly it refers to the buildings of Power House, Switch yard and Valve house. This Section covers the following items: a) b) c) d) e) f) g) h) i) j) k) l) m) Masonry walls Wall, floor and roof finishes Tile works Suspended ceiling Bituminous waterproofing membranes Doors and louvers Windows and sunblinds Glass and glazing Painting works Carpentry and joinery Caulking and damp-proofing Perforations and cuts in the finished concrete and masonry Temporary closures and protection

1.2

1.3 1.4 1.5

The building and architectural works not specified herein shall be defined by the Contractor during the course of the Work. All materials and equipment which will become a part of the Permanent Works shall be new and of good quality. If Specification and Annexure. do not contain particulars of materials and works which are obviously necessary for the proper completion of the work and the intention to include such is nevertheless to be inferred, all such materials and works shall be supplied and executed by Contractor, but being a Fixed Price Contract, not reimbursable. Similarly, Contractor shall supply, place and attach to the structure all timber, metal or other accessories necessary for the proper completion of the work. All incidental flashings, damp proofing, weather seals and other approved components necessary to render the buildings completely watertight and weatherproof shall be provided.. Contractor shall furnish, erect and maintain during the work as required all scaffolding, walkways and other temporary structures required for the execution of the works.

1.6 1.7 1.8

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 2 OF 13

Doc. No TCE.5270A-H-112-601

1.9

Contractor shall collect and dispose of all material, debris and rubbish as it accumulates from time to time as the work proceeds. On completion of this work, the Contractor shall thoroughly clean interior and exterior of the buildings and the other works. SUBMITTALS With his bid, Contractor shall propose an experienced architect in architectural services related to hydraulic projects who shall be responsible for the following: Planning and detailing of architectural works of powerhouse complex and dam complex based upon the general layouts given by the owner and the technical specifications. Preparing shop and detailed drawings and measuring schedules for various buildings and submit to Project Manager for approval. Providing expert advice to the owner on patented products like wall finishes, doors and windows and other related material. Work as a coordinator between contractor and the owner in respect of architectural works. Coordinate with water supply consultant for design/layout of sanitary items, water supply and sewerage system. Assist the owner in the supervision of architectural work being executed by the contractor and suggest changes as required.

2.0 2.1

2.2

Contractor shall prepare and submit for approval at least 28 days prior to the date he wishes to place or confirm purchase order: a) b) c) d) Lists and schedules of materials to be purchased, Manufacturers' catalogues for the various items specified in this Section, Samples of materials and hardware with specimens of workmanship, Colour and finish for the various items specified in this Section.

3.0 3.1 4.0 4.1

NOMINAL SIZES Contractor shall allow for variations between nominal sizes and actual sizes where such variation is within the required tolerances or is normal trade practice. FINISHING WORKS Finishing work shall not commence until each or all of the following conditions have been met to the satisfaction of Project Manager . a) b) c) Area concerned and such adjacent areas, which may affect the finishing work, have been weatherproofed, All construction including installation of permanent plant, fittings and equipment has been completed, Concrete or other materials have dried out sufficiently. Test for dryness may be conducted if necessary beforehand.

5.0 5.1

MASONRY WALLS General

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 3 OF 13

Doc. No TCE.5270A-H-112-601

5.1.1

Contractor shall construct masonry walls where shown on the Construction Drawings or as directed by Project Manager . All masonry walls shall be constructed after the structural concrete work has been completed. The work shall include, but not limited to, the brickwork. Materials Masonry units shall be bricks, samples duly submitted to Project Manager for approval. Cement, sand and water shall be as specified in the relevant section of "Concrete". Masonry units shall have a moisture content (expressed as a percentage of total absorption) of not more than 30% at time of delivery. Units made from cinder aggregate shall not be used. All bricks shall be adapted to the wall thickness shall be got approved.. All bricks shall be uniform in size and shape, deep red in colour and sufficiently well burnt. They shall be clean and free from flaws, cracks and under burnt lumps or defects of any kind. The bricks may be local product available in the vicinity of Site, but the quality shall conform to a requisite standards.. The mortar shall be thoroughly mixed until uniform in colour and shall be used before it has taken initial set. Mortar, which has partially set, shall not be used, nor shall more water be added to it. Execution The masonry units shall be laid on horizontal courses, true to line and plumb, and vertical joints shall be staggered with respect to those in the courses next above and below. No broken bricks and blocks, except as are required as closures for the proper sizing of courses, cracked or misshapen bricks will be used in the works. Corners, and at edges of framed openings, bricks shall have finished return ends. All exposed bricks, which are to be cut, shall be cut with a carborundum wheel. All units shall be laid with full buttered ends and side joints, and shall be shoved to bear on a full bed of mortar. All joints shall be 10 mm and cut flush, except that joints in areas to be plastered shall be raked 7 mm to provide a mechanical joint for the scratch coat. After initial set exposed joints shall be burlap rubbed. The bricks shall be dampened before scratch or setting bed is placed. The thickness of mortar setting bed shall not exceed 20 mm. The masonry units shall be stored on platforms to prevent contact with soil and water and shall be covered with non-staining tarpaulins for protection against the elements. WALL, FLOOR AND ROOF FINISHES General

5.1.2 5.2 5.2.1 5.2.2 5.2.3 5.2.4 5.2.5

5.2.6

5.3 5.3.1

5.3.2

5.3.3 5.3.4 5.4 5.4.1

5.4.1.1 Contractor shall install finishes on walls, floors and roofs according to his shop drawings as approved by PROJECT MANAGER. 5.4.1.2 The work shall include, but not limited to, the following : a) b) c) d) Plastering Floor finish Roof finish (cement mortar) Special floor finish (Granolithic concrete )

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 4 OF 13

Doc. No TCE.5270A-H-112-601

5.5 5.5.1 5.5.2 5.5.3 5.5.4

Materials Cement, sand and water shall be as specified in the relevant section of "Concrete". Waterproofing and epoxy resin shall be approved by Project Manager and shall be used in perfect accordance with the manufacturer's instructions. Mortar shall be thoroughly mixed until uniform in colour and shall be used before it has taken initial set. Mortar, which has partially set, shall not be used, nor shall more water be added. Cement mortars shall be composed as follows: a) For wall plastering: b) For flooring finish: c) For waterproofing of floor & walls: 350 kg cement per 1 m3 sand and water, 500 kg cement per 1 m3 and water, 600 Kg cement 1m3 sand and water, and waterproofing agent in accordance with the manufacturer's instructions, 450 kg cement per 1 m3 sand and water.

d) For roof finish: 5.6 5.6.1 Execution

Concrete surfaces, which are to receive a rendering coat, shall be roughened, scratched and free from all laitance, scum. Loose carbonate scale, loose aggregate, dirt and other foreign matter and shall be kept thoroughly wet for 24 hours prior to the application of mortar. All masonry and concrete surfaces to which cement mortar is to be applied without furring shall receive one coat of epoxy resin type bonding agent or other approved agent. The various finishes shall be executed as follows: a) Exterior wall plastering On exterior wall plaster shall be applied, by hand or mechanically, to a total thickness of 25 mm. Interior wall plastering On interior walls plaster shall be applied by hand or mechanically, to a total thickness of 15 mm.

5.6.2 5.6.3

b)

5.7 5.7.1 5.7.1 5.7.2

TILE WORKS FLOORS AND WALLS General Contractor shall install tiles on walls and floors as given in Annex-I (Room schedule) and according to his shop drawings as approved.. Work shall include, but not limited to, the following : a) b) c) d) e) f) g) Terrazzo tiles Ceramic wall tiles Vitrified ceramic tiles Grantlithic flooring Kota stone Pre-polished granite tiles Acid-proof tiles.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 5 OF 13

Doc. No TCE.5270A-H-112-601

5.7.3

Contractor shall submit samples of tiles for approval by PROJECT MANAGER with respect to quality and colour. Tile samples shall include the manufacturers full colour and texture range of specified series. The detailed execution procedure has been highlighted in Annex-II. SUSPENDED CEILING (MACHINE HALL) Contractor shall supply the suspended ceiling in main machine hall

5.8

5.8.1 General 5.8.1.1 Supplying and installation of supporting structure for suspended ceiling like hangers (suspenders), plates to be attached with Rock bolts, turn buckles, purlins and other accessories like gutters, spouts, roof drains etc complete in all respect. 5.8.1.2 Supply and installation of materials and installation of Trackdeck Hi-Rib or equivalent roofing sheets. 5.8.1.3 Supply and installation of Structural steel for walkway for inspection and maintenance of machine hall crown. The detailed execution method is enclosed in Annex-III 5.9 FALSE CEILING The contractor shall provide the false ceiling in Dam control room, powerhouse control room and GIS room. General (1) (2) (3) 15.10 (1) (2) (1) Supply and installation of materials and installation of suspension system components, hangers and fastening devices. Supply and installation of materials and installation of ceilings tiles and panels. Supply and installation of sound absorbent materials.

5.9.1

The detailed execution of false ceiling is enclosed in Annex-IV. BITUMINOUS WATERPROOFING MEMBRANES The Contractor shall supply and install bituminous waterproof membranes on roofs and floors with or without thermal insulation as directed by the Engineer-in-Charge. Membranes on roofs shall include protective mortar, roof drain and downspouts. Bituminous waterproof roofing shall consist of 3-ply built-up roofing layers applied as follows: 3-ply built-up roofing Asphalt primer Asphalt compound 1st layer felt Asphalt compound 2nd layer felt square meshed 0.4 l/m2 1.5 kg/m2 39 kg / 42 m2 roll 1.5 kg/m2 35 kg / 21 m2 15.10.1 General

15.10.2 Materials

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK
or perforated fibreglass felt Asphalt compound 3rd layer felt Asphalt compound Plastic sheet protection 15.10.3 Thermal Insulation (1)

VOLUME: IV PART: 3 SECTION: B13 SHEET 6 OF 13

Doc. No TCE.5270A-H-112-601

28 kg / 10 m2 roll 2.0 kg/m2 35 kg / 21 m2 roll 2.1 kg/m2 one layer

Thermal insulation shall be provided in the form of thermal insulation panels laid directly on the bituminous roofing felt covering the cement mortar screed. The thermal insulation material shall in turn be covered with a second layer of bituminous roofing felt. Panels for thermal insulation shall be of synthetic insulating material having a density of approximately 30 kilograms per cubic meter. The panels shall have a thickness of 30 mm. organic material like cork shall not be permitted. Consideration shall be given to the chemical composition of panels, with regard to any possible chemical reaction with bitumen. Insulating panels shall be laid with staggered joints and with their joints coated with bituminous paint. They shall then be covered by a layer of bituminous roofing felt. Joints in bituminous roofing felt shall consist of a minimum overlap of 100 mm sealed with a layer of hot bituminous paste. Roofing felt shall be laid such that it overlaps the insulation layer and joins with the roofing felt beneath the insulation layer. The 2 layers of felt shall be joined together to completely surround and seal the insulation layer on all sides and edges.

(2)

(3)

15.10.4 Execution (1) Concrete roof slabs shall be prepared to receive bituminous 3-ply built up roofing by first laying a 1:3 cement mortar to form the slopes. The thickness of the screed shall vary between 20 mm (minimum) and 120 mm (maximum) thickness. The surface of the concrete slab prior to the laying of the screed shall be prepared in accordance with the requirements for concrete construction joints as specified in Section "Concrete". After laying, the surface of the cement mortar screed shall be compacted with a screed board prior to receiving a wood float finish. External and internal angles shall be finished with a rounded surface of minimum radios 50 mm. The cement mortar screed shall be allowed to cure for a minimum period of 3 weeks before covering with the specified insulation and waterproofing layers. A layer of bituminous roofing felt, thermal insulation panels and a second layer of bituminous roofing felt shall be placed over the cement mortar screed as specified above. 3-ply built-up roofing shall then be applied follows: a) Asphalt primer shall be evenly applied in accordance whit the manufactures recommendations over the surface of the bituminous roofing felt covering the thermal insulation panels. Asphalt compound shall then be evenly poured and sprayed over the asphalt primer. Compound heated to a temperature exceeding 140 degree C above the melting point shall not be used. Asphalt felt, roofing and special roofing shall be laid over each respective asphalt compound with care to avoid bulges. The sides and ends of these sheets shall be provided with an overlap of at least 90 mm. The joints shall be completely watertight.

(2) (3)

b)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 7 OF 13

Doc. No TCE.5270A-H-112-601

c)

The whole surface shall be covered by plastic sheet protection in order to allow the movement of the top protective mortar screed without damaging the 3-ply built-up roofing. Care shall be exercised when carrying out roofing work surrounding anchor bolts, parapets and roof drains to prevent leakage.

(4)

The top protective screed shall be placed in two 25 mm thick layers with wire mesh laid in between. Wire mesh shall consist of 0.9 mm diameter galvanised steel wire with a mesh size of 25 mm or similar approved. The roof drain shall be made of cast iron, heat coated with asphalt. Care shall be exercised in fitting the surrounding waterproofing works to the drains for preventing any damage to the waterproofing membrane. Caulking shall be applied as required. Roof drain grates shall be convex in profile at least as high as the pipe diameter and the total area of the openings of the gratings shall be 1.5 times the cross sectional area of the drain pipe. Grates shall be fixed with non-corrosive screws. Roof drain shall have two flanges. The bottom flange shall be integral with the drain body and shall be set to the top surface of the surrounding concrete. The top flange shall be adjustable to permit this flange to be set to the finished roof elevation. The two flanges shall be provided to allow seepage to drain from beneath the top flange. Downspouts shall be provided as shown on the Tender Drawings. Downspouts shall be 100 mm in diameter polyvinyl chloride pipes provided with adaptable fittings. The downspouts shall be securely fixed to the walls with steel ring suspenders at adequate intervals. Flexible joints shall be synthetic rubber, 4-ply approximately 80 cm in length and shall be provided at expansion joint of each downspout. The flexible joints shall be tightly connected to both ends of the downspouts with adequate metal bands. ALUMINIUM DOORS, WINDOWS AND ROLLING SHUTTERS Fabrication The Contractor shall supply and install aluminium doors as required. They shall be installed in accordance with approved Contractors shop drawings. All aluminium doors, frames and hardware shall be to the approval of the Engineer-inCharge. Prior to fabricating or ordering the aluminium doors, the Contractor shall check the actual dimensions and shape of existing concrete openings. The detailed execution of Aluminium doors and windows is enclosed in Annex-V.

15.10.5 Roof Drain (1)

(2)

(3)

15.10.6 Downspout (1)

(2)

15.11

15.11.1 Aluminium Doors 15.11.1.1 (1) (2) (3) (4) 15.11.2

Rolling Shutters (1) (2) The contractor shall supply and install steel rolling shutters as required. These shall be installed in accordance with contractors approved shop drawings. Prior to fabrication or order of the rolling shutters the contractor shall check the actual dimensions of existing openings.

15.11.2.1 Fabrication

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 8 OF 13

Doc. No TCE.5270A-H-112-601

(3)

The rolling shutter shall be of approved make, made of required size of M.S. laths interlocked together through their entire length and jointed together at the end by end locks mounted on specifically designed pipe shaft with brackets, side guides and arrangement for inside and outside locking with push and pull operation complete including wire springs and M.S. top cover of required thickness. The rolling shutter may also required to be fitted with motorised arrangement and related works.

(4) 15.12

GLASS AND GLAZING (1) (2) (3) (4) (5) (1) Each glass sheet shall bear the manufacturers label showing its grade, thickness and type. Labels shall remain until the glass has been set and inspected. When glass is not cut to size by the manufacturer, the contractor shall furnish an affidavit certifying the grade, thickness, type and manufacturer of the glass supplied. Glass shall be heat-tempered, safety glass 16 kg/m2 and of 6 mm thickness, free from any distortion or imperfection. Sealant and glazing compound shall be compatible with the frame as recommended by the manufacturer. Glazing beads and seals shall be black neoprene or vinyl chloride. All single glass panel shall be accurately shop-cut to size of opening with allowances for maximum grip on all edges. Concealed edges of glass shall be clean, straight cut and free from chips and fissures. Glass shall be set with equal bearing on entire width of pane and shall not move nor rattle. Glass and glazing system shall be installed complete with all stops, blocks, channels, beads, sealants and glass to form a watertight installation in accordance with the manufacturers recommendation. After installation, all exterior glazing shall be given a leak test by flooding the glazing from bottom to top using 20 mm hose with nozzle. Any defective work shall be repaired or replaced by the Contractor to the satisfaction of the Engineer-in-Charge. All glass shall be cleaned at the completion of the work. Any defective, cracked or scratched glass shall be replaced.

15.12.1 Materials

15.12.2 Installation

(2)

(3)

(4) 15.13

PAINTING WORKS (1) The work includes preparing and painting various surfaces as directed by the Engineer-in-Charge, including protection and finish painting of metal surfaces, except those metal surface specified under the Technical Specifications for equipment supplied by others. The Contractor shall provide all labour, materials, supplies, equipment and scaffolding to perform all operations necessary to complete the work.

15.13.1 General

(2)

15.13.2 Materials

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 9 OF 13

Doc. No TCE.5270A-H-112-601

(1) Colour of paints shall be in accordance with the colour schemes selected by PM .Exact tones of the colour selected shall be in accordance with the samples supplied and applied on test areas in the Works approved by Project Manager. (2) (3) All paint materials shall be delivered to the Site in their original containers, with labels intact and seals unbroken. All paints shall be of well known registered brands. All tinting colours and thinning materials shall be of the same brand as the oil paint specified for the particular area. Tinting colours for oil paint shall be colours-in-oil, ground in pure linseed oil of the best grade. With the exception of ready mixed materials in original containers, all mixing shall be done at the Site. The Contractor is responsible to ensure that the storage and handling of paint material complies with the requirements of pertinent codes and fire regulations. Proper containers placed outside of the building shall be provided and used for painting wastes, which shall be properly disposed of or removed from the premises at the close of each days work. No plumbing fixture shall be used for this purpose. The Contractor shall provide for the purpose of maintenance one unopened 4-liter can of each type and each colour of paint used, on completion of the work. Concrete and masonry work shall be left for one month and any surface defects repaired before painting. Cracks, holes and other defects in plaster shall be filled or patched with an approved filling compound. The filling shall finish flush with and in the same plane as the adjoining surface. Where patches in cement plaster are required, the surfaces shall be coated with an approved bonding agent, the defects filled with an approved mortar mix for patching, and the patched areas finished to match the texture of the cement plaster. Plaster surfaces that will be painted for the first time shall be uniformly coated with a solution composed of 1 kg of zinc sulphate to 4 litres of water, to which shall be added 28 g of dry sienna to each 4 litres of zinc sulphate solution. 24 hours after application of the zinc sulphate solution, the surfaces shall be thoroughly washed with clear water and allowed to dry thoroughly. Metal surfaces to be painted shall be clean and thoroughly dry before painting. Rust, loose scale, oil, grease and dirt shall be removed with approved solvents, wire brushing or sanding. Metal welds and blisters shall be ground and sanded smooth, pits and dents filled and imperfections corrected so as to leave a smooth surface. Wood surfaces to receive paint shall be cleaned of all dirt, grease, dust or any other deleterious matter. All surfaces shall be thoroughly sanded and all nail holes, cracks and any other defects shall be coloured to match the colour of the finish paint. The finish surfaces shall be smooth, level and uniform, free from any stains and shall be uniform in colour and shade. The Contractor shall be responsible for and shall rectify any surface finish which in the opinion of Project Manager is unsatisfactory to receive paint.

(4) (5)

(6)

15.13.3 Preparation of Surfaces (1) (2)

(3)

(4)

(5)

15.13.4 Workmanship

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 10 OF 13

Doc. No TCE.5270A-H-112-601

(1)

All paint shall be applied by brush unless spray painting or other method is specifically approved by the Engineer-in-Charge. Spray-painting equipment shall be adequate for the work to be performed and shall have suitable air pressure and paint flow controls. Material shall be applied in accordance with the manufacturers printed directions. Any thinning that may be required shall be added only with the approval of the Engineer-inCharge and then with an approved type of thinner and in the amount recommended by the paint manufacturer. One liter of paint as originally supplied by the manufacturer shall not cover a greater area when applied by spray gun than when applied unthinned by brush. Deficiencies in film thickness shall be corrected by the application of additional coat(s). Application on masonry surfaces may vary according to surface texture but in no case shall the manufacturers coverage rate be exceeded. On porous surfaces, it shall be the Contractors responsibility to achieve a finish comparable to the manufacturers coverage rate by decreasing the coverage or applying additional coats of paint.

(2)

(3)

(4) Painting shall be equal in quality to the samples as submitted to and approved by Project Manager and shall not be done during rain, fog or mist or in any time unsuitable for the job.. (5) Contractor shall remove all lighting fixture, including canopies, surface hardware and similar items before painting; safely store them and replace them when painting is complete. Dripped, spilled or splattered paint shall be cleaned up promptly. Drop cloths shall be laid to completely cover flooring and all other work items during painting, and shall remain in position until the paint work is dry, finished and inspected. Premises shall at all times be kept free from an accumulation of waste material and rubbish. On completion of the painting, all tools, scaffolding and surplus materials shall be removed from and about the building, ready for inspection by Project Manager . All the surrounding works shall be protected in a suitable manner from paint drops and overspray. All smeared and damaged surfaces are cleaned or repaired to satisfaction of EIC. 7.0 CARPENTRY AND JOINERY (1) The work to be done under this Section includes the furnishing of all labour, materials, equipment, tools and other incidentals for all carpentry and joinery works. Shop drawings showing all essential dimensions and details of construction for millwork shall be got approved before actual construction. All carpentry and joinery works shall be performed and completed in a workmanlike manner in accordance with generally accepted modern practice in carpentry, notwithstanding any omission from these Specifications. Lumber and woodwork shall be covered and protected from the elements until used. Buildings shall be thoroughly dry before the finish is placed on them. As far as practicable, nailing shall be done in concealed places, and all nails in exposed woodwork shall be set. All lumber shall be surfaced on four sides. Exterior and interior shall be dressed and smooth. Finishing woodwork shall be hand-smoothed and sanded at the site as 15.14.1 General

(6)

(7)

(2)

(3)

(4)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 11 OF 13

Doc. No TCE.5270A-H-112-601

necessary to produce the proper finish. All dents on surfaces and counter sunk nails or screws shall be filled with acceptable wood filler before sanding of surfaces. (5) (6) When practicable, millwork shall be fabricated in the shop, doweled, mortised and sanded to a smooth surface, and delivered to the site ready to be secured in place. All cuttings, framings and fittings necessary for the accommodation of other works shall be provided. All lumber to be incorporated into the Works shall be sound stock delivered dry and fully protected at all times from injury and dampness. Kinked, split, knotted, broken, insect bored, or otherwise damaged pieces will not be allowed. Gradation shall be select, defined as selected lumber, generally clear, high quality, of good appearance, and suitable for use without waste and for natural finish. Cabinets, closets and other wood furniture shall be constructed as shown on the shop drawings. Toilet partitions and doors shall be pre-fabricated units. The Contractor shall prepare shop drawings and submit them for approval. Nails shall be smooth shank, zinc-coated steel wire nails. Putty for woodwork shall be of the color to match wood finish where exposed, and shall be subject to the approval of Project Manager . Glue shall be an approved phenol-resorcinol base glue.

15.14.2 Materials (1)

(2) (3)

(4) (5) (6)

15.14.3 Seats, Slats, Cabinets, Toilet Partitions Doors, slats, cabinets, shall be installed as shown on the approved shop drawings complete with all necessary hardware. All fastenings shall be concealed where practicable. Counters and cabinets shall be fitted neatly with a high degree of craftsmanship, installed in a rigid and substantial manner and scribed to joining surfaces. Prefabricated toilet partitions and doors shall be provided with a 300 mm floor clearance. 15.14.4 Miscellaneous Wood Formwork (1) (2) (3) Miscellaneous wood formwork as may be required for the completion of the work shall be provided by the Contractor. Exterior and interior staging shall be erected by the Contractor, and maintained in safe condition. Edges of sills, projected masonry courses, concrete steps, and masonry liable to be damaged during construction shall be protected with temporary wooden covers.

15.14.5 Dimensions The sizes shown for wood on the Tender Drawings are the nominal sizes. All dressed lumber after planning shall not vary from the indicated dimensions by more than 10%. Thickness and width of lumber shall be uniform throughout its length. Lumber shall not be delivered to the Site in lengths shorter than 2.5 m. 15.14.6 Wooden Built-in Parts (1) For the wooden components which will be concealed after installation, e.g. built-in cupboards, wardrobes or wall linings, either the type of wood specified for the unconcealed structural components (spruce, fir, pine or wood of at least equal quality)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 12 OF 13

Doc. No TCE.5270A-H-112-601

or an equally suitable material may be used at the Contractor's own choice, unless otherwise specified. (2) (3) The timber shall be in a suitable condition so that the components made of it will neither crack, warp nor twist. The moisture content of timber assemblies when leaving the manufacturer's works shall be as follows (referred to the over dry weight): 15.15 8 - 12 % for interior finish components 10 - 15 % for structural parts in permanent connection with the outside air.

Proof of this moisture content shall be furnished to Project Manager . CAULKING AND DAMP PROOFING Contractor shall supply all labour, materials and equipment necessary to complete the caulking and damp proofing of the buildings. The work shall consist of, but not be limited to the following: a) b) c) 15.15.2 Materials (1) (2) Joint backing shall be polyethylene foam, neoprene or butyl rope. Oakum, bituminous or impregnated metals will not be permitted. Caulking material shall be elastic, non-corrosive and water resistant polysulphide liquid polymer which when set shall be firm but not brittle. It shall be delivered in original sealed containers and applied in accordance with the manufacturers directions. The color shall be grey and the material characteristics shall permit concave tooling when in place. Damp-proofing shall be of a clear silicon formulation for application to exterior masonry surfaces. Application of caulking material shall be done in accordance with the manufacturers directions, and only by tradesmen fully experienced in this type of work. Joints, reglets and openings to be caulked shall be clean, dry and free of dust and foreign matter, and a joint cleaner shall be used where necessary. Deep joints shall be packed tightly with joint backing to not less than 10 mm from the surface. Joint backing shall be provided by the caulking material supplier, and joint primer applied as required by the manufacturers instructions. Excess caulking material shall be cleaned from all surfaces adjacent to and in proximity of the work area, and the joint left smooth and clean. Masonry control and expansion joints, Caulking for roof penetrations and masonry wall openings such as for windows and doors, Damp proofing the outside surfaces of all exterior concrete hollow block Q 15.15.1 General

(3)

15.15.3 Caulking and Jointing (1) (2)

(3)

15.15.4 Damp-proofing

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES BUILDING AND ARCHITECTURAL WORK

VOLUME: IV PART: 3 SECTION: B13 SHEET 13 OF 13

Doc. No TCE.5270A-H-112-601

(1)

Surface shall be cleaned of oil, dirt and foreign matter, and prepared in accordance with the manufacturers instructions before application of the damp proofing material. The concrete shall have been completely cured and the surface kept dry at the time of application. Surfaces shall receive two heavy coats of damp proofing. The first coat shall be carefully applied so that untreated air-bubble depressions in the surface shall be completely filled and the second coat shall ensure a 100% coating of the surface. Particular care shall be taken to apply the damp proofing at all construction and other joints.

(2)

15.16

MEASUREMENT AND PAYMENT (1) Payment for building and architectural works will be made as lumpsums entered in the schedule, provided for the following structures : a) Powerhouse caverns including powerhouse control building b) Switchyard building including DG building c) Dam control building The lumpsum quoted shall include the entire cost of labour, furnishing of materials and installation for various architectural items described in these technical specifications including brick masonry, cement plasters, flooring, railings, doors, windows and all necessary sanitary items. (2) Measurement for suspended ceiling in the underground powerhouse machine hall shall be of the actual area of the suspended ceiling installed. Payment shall be made at the unit price per sqm entered in schedule which shall include, the cost of hangers (suspenders), the plate attachment with the rock bolts, the purlins and the roofing sheet, as supplied and installed at site complete in all respect. The steel works involved in the fabrication and installation of walkway in the roof of powerhouse is also included. Measurement for payment for rendering Architectural design and supervision services shall be done in number of weeks the architect actually put in (including the time put in his office) during the two phases namely planning and design phase and supervision at site. The week shall comprise of five to seven days working in continuation. The continuous work of 3 days shall comprise half week. Payment will be made at the appropriate unit price per week entered in the BOQ, which shall include besides other things the necessary visits required to be made to site both during planning and design phase and during supervision phase.

(3)

15.17

EXCLUSIONS (1) (2) Concrete, formwork and reinforcement for the construction of buildings shall be paid separately and not included in the Lump Sum for building and architectural works. All lighting and illumination works for dam control building shall be paid for under Section B.20 E & M Equipments and not included in the Lump Sum for building and architectural works. For powerhouse cavern and switchgear building, these are covered under scope of E & M package.

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES MISCELLANEOUS AND ANCILLARY WORKS

VOLUME: IV PART: 3 SECTION: B14 SHEET 1 OF 3

Doc. No TCE.5270A-H-112-601

16.1

SCOPE OF WORK (1) The work under this section includes all labour, materials and equipment, and performing all operations required for the execution of miscellaneous or complementary works described herein. This sections covers the following items: a) b) c) d) (3) Fencing and gates, Concrete pipes, Concrete cable channels Weepholes

(2)

The extent, type and dimensions of the miscellaneous and ancillary works are shown on the Tender Drawings or shall be as required by Project Manager .

16.2

FENCING AND GATES (1) The Contractor shall supply and install chain link fences and gates at the locations and to the dimensions as shown on the Construction Drawings or as directed by Project Manager.. They shall be constructed according to approved Contractor's shop drawings showing details of all fencing components, fittings, materials, accessories and construction. Fencing shall be manufactured by a reputable company regularly engaged in the manufacture of chain link fencing, to be approved by Project Manager.. Zinc coated steel wire fence material shall meet the requirements of IS:2721. Chain link fabric shall be 4 mm steel wire woven in a 50 mm mesh and hot-dip galvanised after weaving. Posts, tap and brace elements, and gate frames shall be of hot-dip galvanised standard weight seamless steel pipes conforming to IS: 4736 and shall have following minimum outside diameters: (5) Intermediate posts: 50 mm Top and brace: 40 mm Corner and pull posts: 75 mm Gate posts: 100 mm

(2) (3)

(4)

Gate frames/brace: 60/32 mm Intermediate posts shall be placed every 3 to 3.5 m. Pull posts shall be executed every 15 m. Every post shall be equipped with pipe head covering and fastenings for wire tensioning. Posts shall be set plumb and in alignment. Chain link fabric for gates shall be as specified for fences. Each gate leaf shall be equipped with one pair of heavy hinges that will allow a full gate opening between gate posts. The hinges shall be designed to not twist or turn under gate action and shall allow the gate to swing a full 180 degrees. Hinges shall be of hot-dip galvanised ductile iron or malleable iron. Gates shall be equipped with a heavy latching device and cylinder door lock. Locking bars to secure gates in open and closed position shall be provided. Double wing gates

(6)

(7)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES MISCELLANEOUS AND ANCILLARY WORKS

VOLUME: IV PART: 3 SECTION: B14 SHEET 2 OF 3

Doc. No TCE.5270A-H-112-601

shall be provided with one safety stop fixing the wing in its closed position by means of a vertical shaft. The locks and other rotating materials shall be brass or bronze. (8) (9) Barbed wire on the top of the fence shall be 3-strand 4-point wire, tack-welded to extension arms at the top of each post. Posts shall be set concrete M15/40 compacted so that no movement will occur after installation of the fence. Posts shall be set in blockouts and grouted. The blockouts shall be protected from standing water and freezing. Curb stone laid in concrete M15/40 shall be provided along the whole length of the fencing.

(10)

16.3

CONCRETE PIPES (1) The Contractor shall supply and install prefabricated concrete pipes, either full section or perforated, at the locations and of diameters as shown on the Construction Drawings or as directed by the Engineer-in-Charge. The following types of concrete pipes are envisaged to be installed in the Works: (3) Type 1: Concrete pipe fully embedded in concrete Type 2: Drain pipe on concrete / sand base

(2)

The Contractor shall furnish concrete pipes of the best possible quality to be found on the local market and shall be PN-3 Reinforced concrete (medium duty) conforming to IS 4589. The sand bedding shall comply with the requirements for fine aggregates stipulated in the Section "Concrete". The drainage layer shall consist of crushed rock or gravel of minimum diameter 35 mm. The concrete for the base or embedding shall be M15/40 or M20/40. The pipeline shall be aligned to the slope and direction shown on the Construction Drawings or as directed by Project Manager . The joints between pipes shall be sealed with cement mortar and cleaned immediately after matching of the pipes. After installation of the perforated drain pipes, filter and drainage layers shall be placed and tamped around the pipe with all care as not to displace them, especially in the case of sand bedding. All laid pipe systems shall be tested after the trenches have been backfilled by pulling or flushing a ball 2 cm smaller than the pipe diameter through each segment of the system.

(4)

(5)

(6)

16.4

CONCRETE CABLE CHANNELS (1) The Contractor shall supply and install the concrete cable channels (cable ducts) where shown on the Construction Drawings or where directed by the Engineer-inCharge. They will principally be used for electrical inter-connections between various locations, but may be used for other purposes as well. The channels shall be composed of precast concrete elements manufactured either at Site or by an established manufacturer of similar items. They shall include all necessary special parts such as covers, lifting hooks, angles, bends, and blockouts for the passage of the cables.

(2)

THE TATA POWER COMPANY LIMITED BHIRA 100MW-AUGMENTATION SCHEME INCLUDING MULSHI LAKE SUB-STORAGE UTILIZATION CIVIL & HYDRO-MECHANICAL WORKS TECHNICAL SPECIFICATIONS ACTIVITIES MISCELLANEOUS AND ANCILLARY WORKS

VOLUME: IV PART: 3 SECTION: B14 SHEET 3 OF 3

Doc. No TCE.5270A-H-112-601

(3)

Channels shall be manufactured of a concrete class M25/20 and shall be sufficiently reinforced to prevent shrinkage cracks, transport caused stresses, and traffic loads where relevant. The elements shall be provided with groove and tongue for fitting and connecting. Channels shall be laid and adjusted on a layer of fine sand with an average thickness of 60 mm.

(4)

16.5

PVC PIPES (1) (2) PVC Pipes of various sizes may be required for various application. PVC Pipes used shall conform to IS:4985 ( Unplasticised PVC pipes for potable water supplies). PVC Pipes used shall be Class 4 i.e working pressure 8 kg/cm2 as per Table 5 of IS 4985 The pipes may be required to be embedded in Concrete, embankment or any other material.

(3)

Das könnte Ihnen auch gefallen