Sie sind auf Seite 1von 28

CHAPTER-VI PRELIMINARY AND MAINTENANCE WORKS - Standard Data (STORED WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)

For the Year:2012-13 Index- code IRR-PMW IRR-PMW-1 IRR-PMW-1-1 PRELIMINARY & MAINTENANCE WORKS - DATA RATES JUNGLE CLEARANCE : Clearing thin jungle growth ( more than 50 percent open space ) including bushes upto 30 cm / parthenium and other weeds including burning or disposing off the same as directed etc., complete.

IRR-PMW

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

1000 sqm Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description Day Day Total cost of Labour 0.90 0.14 0.10 1.00

Unit

Quantity 0.50 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 750.00 900.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 1000.00 sqm (A+B+C+D)/1000.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 900.00 900.00 126 1026.00 1.00

IRR-PMW-1-2

Clearing thick jungle growth ( less than 50 percent open space ) including bushes upto 30 cm / parthenium and other weedsincluding burning or disposing off the same as directed etc., complete.

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

1000 sqm Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description Day Day Total cost of Labour 1.40 0.14 0.20 1.60

Unit

Quantity 0.50 5.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 1250.00 1400.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT:

297

A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 1000.00 sqm (A+B+C+D)/1000.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1400.00 1400.00 196 1596.00 1.60

IRR-PMW

IRR-PMW-1-3

Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girthincluding excavation, stacking the materials neatly and levelling the surface etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 18 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 31.90 0.14 4.50 36.40

Quantity 0.25 2.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 500.00 575.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 18.00 Nos. (A+B+C+D)/18.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 575.00 575.00 80.5 655.50 36.40

IRR-PMW-1-4

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 mand upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 8 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 71.90 0.14 10.07 82.00

Quantity 0.25 2.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 500.00 575.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total

Rs: Rs: Rs: Rs:

0.00 0.00 575.00 575.00

298

D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each

8.00 Nos. (A+B+C+D)/8.0

14.00% Rs: Rs: Rs.

80.5 655.50 81.90

IRR-PMW

IRR-PMW-1-5

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling the area etc., complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 5 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 230.00 0.14 32.20 262.20

Quantity 0.50 4.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 1000.00 1150.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 5.00 Nos. (A+B+C+D)/5.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1150.00 1150.00 161 1311.00 262.20

IRR-PMW-1-6 DATA:

Additional rate for every 0.5 m increase in girthof tree stump / stumps of bamboo cluster beyond 5 m.

RATE ANALYSIS A. MATERIALS: Sl No 1

UNIT :

7 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 40.70 0.14 5.70 46.40

Quantity 0.22 0.88

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 66.00 218.75 284.75

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 7.00 Nos. (A+B+C+D)/7.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 284.75 284.75 39.865 324.62 46.40

299

IRR-PMW-1-7

Cutting and stacking bamboos excluding removing stumps and roots etc., complete with initial lead upto 50 m and all lifts.

IRR-PMW

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

150 Nos.

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour 9.30 0.14 1.30 10.60

Quantity 0.50 5.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 1250.00 1400.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 150.00 Nos. (A+B+C+D)/150.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1400.00 1400.00 196 1596.00 10.60

IRR-PMW-1-8

Cutting and removing jauliflora bushes upto 1.5 m girthexcluding removal of stumps and including burning or disposing off the materials as directed with initial lead upto 50 m and all lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 100 Nos.

DATA:

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 9.00 0.14 1.30 10.30

Quantity 0.50 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 750.00 900.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 100.00 Nos (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 900.00 900.00 126 1026.00 10.30

IRR-PMW-1-9

Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girthexcluding removal of stumps and including burning or disposing off the materials as directed with initial lead upto 50 m and all lifts.

300

IRR-PMW

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

50 Nos

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 18.00 0.14 2.50 20.50

Quantity 0.50 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 750.00 900.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 50.00 Nos (A+B+C+D)/50.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 900.00 900.00 126 1026.00 20.50

IRR-PMW-1-10

Cutting trees above 0.3 m and upto 0.6 m girthexcluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

14 Nos.

particulars Use rate of ropes etc LS

Unit

Quantity 0.25 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 130.00 0.00 Rs:

Amount in Rs. 32.50 0.00 32.50

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 58.90 0.14 8.20 67.10

Quantity 0.25 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 750.00 825.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 14.00 Nos. (A+B+C+D)/14.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

32.50 0.00 825.00 857.50 120.05 977.55 69.80

IRR-PMW-1-11

Cutting trees above 0.6 m and upto 1.2 m girthexcluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No

RATE ANALYSIS

UNIT :

4 Nos.

particulars

Unit

Quantity

Rate in Rs.

Amount in Rs.

301

Use rate of ropes etc

LS Total cost of Materials

0.25 0.00

130.00 0.00 Rs:

32.50 0.00 32.50

IRR-PMW

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 206.30 0.14 28.90 235.20

Quantity 0.25 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 750.00 825.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 4.00 Nos. (A+B+C+D)/4.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

32.50 0.00 825.00 857.50 120.05 977.55 244.40

IRR-PMW-1-12

Cutting trees above 1.2 m and upto 1.8 m girthexcluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

2 Nos.

particulars Use rate of ropes etc LS

Unit

Quantity 0.25 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 130.00 0.00 Rs:

Amount in Rs. 32.50 0.00 32.50

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 412.50 0.14 57.80 470.30

Quantity 0.25 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 750.00 825.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 2.00 Nos. (A+B+C+D)/2.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

32.50 0.00 825.00 857.50 120.05 977.55 488.80

IRR-PMW-1-13

Cutting trees above 1.8 m and upto 2.4 m girthexcluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

1 No.

particulars Use rate of ropes etc LS

Unit

Quantity 0.25 0.00

Total cost of Materials B. MACHINERY: Sl No

Rate in Rs. 130.00 0.00 Rs:

Amount in Rs. 32.50 0.00 32.50

Description

Unit

Quantity

Rate

Amount

302

NIL Total hire charges of Machinery

0.00 0.00

in Rs. 0.00 0.00 Rs:

in Rs. 0.00 0.00 0.00

IRR-PMW

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour 825.00 0.14 115.50 940.50

Quantity 0.25 3.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 750.00 825.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 1.00 No. (A+B+C+D)/1.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

32.50 0.00 825.00 857.50 120.05 977.55 977.60

IRR-PMW-1-14

Cutting trees above 2.4 m and upto 3.0 m girthexcluding removal of stumps and including stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

1 Nos.

particulars Use rate of ropes etc LS

Unit

Quantity 0.50 0.00

Total cost of Materials

Rate in Rs. 130.00 0.00 Rs:

Amount in Rs. 65.00 0.00 65.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour 1325.00 0.14 185.50 1510.50

Quantity 0.25 5.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 75.00 1250.00 1325.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 1.00 Nos. (A+B+C+D)/1.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

65.00 0.00 1325.00 1390.00 194.6 1584.60 1584.60

IRR-PMW-1-15

Additional rate for cutting tree for every 0.5 m increase in girthof tree beyond 3 m.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

1 No

particulars Use rate of ropes etc LS

Unit

Quantity 0.15 0.00

Total cost of Materials

Rate in Rs. 130.00 0.00 Rs:

Amount in Rs. 19.50 0.00 19.50

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

303

IRR-PMW

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour 467.50 0.14 65.50 533.00

Quantity 0.10 1.75

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 30.00 437.50 467.50

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 1.00 No (A+B+C+D)/1.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

19.50 0.00 467.50 487.00 68.18 555.18 555.20

IRR-PMW-1-16

Cutting and burning or disposing off Apu / Jondu from marshy areasas directed with initial lead upto 50 m and all lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 UNIT : 1000 sqm

DATA:

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

C. LABOUR: Sl No 1 2 work inspector mazdoor

Description Day Day Total cost of Labour 3.30 0.14 0.50 3.80

Unit

Quantity 1.00 12.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 300.00 3000.00 3300.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 1000.00 sqm (A+B+C+D)/1000.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 3300.00 3300.00 462 3762.00 3.80

IRR-PMW-2 IRR-PMW-2-1

PRELIMINARY WORKS : Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead upto 10 m and lift upto 3 m.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

10 cum

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR:

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

304

Sl No 1 2 work inspector mazdoor

Description

Unit Day Day Total cost of Labour 165.00 0.14 23.10 188.10

Quantity 0.50 6.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 150.00 1500.00 1650.00

IRR-PMW

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-2-2 10.00 cum (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1650.00 1650.00 231 1881.00 188.10

Earthwork excavation for trial pits / borrow pits and other investigation works in soft rock including disposing off the excavated rock as directed with lead upto 10 m and lift upto 3 m.

DATA: A. MATERIALS: Sl No 1

RATE ANALYSIS

UNIT :

10 cum

particulars NIL

Unit

Quantity 0.00 0.00

Total cost of Materials B. MACHINERY: Sl No 1

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 work inspector Crowbarman mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Day Total cost of Labour 231.00 0.14 32.30 263.30

Quantity 0.50 1.00 7.50

Rate in Rs. 300.00 285.00 250.00 Rs:

Amount in Rs. 150.00 285.00 1875.00 2310.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-2-3 10.00 cum (A+B+C+D)/10.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 2310.00 2310.00 323.4 2633.40 263.30

Conducting geophysical investigation studies by electrical resistivity methodin stages of 5m for sub-surface details such as depth of formations, shear zones, classification of strata, depth of water table etc., including cost of all materials, equipments, labour, analysing and reporting the details of field studies conducted etc., complete excluding cost of transportation arrangements.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars Sundries ( misc. consumables ) Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 5.00 0.00 20 Stages Rate in Rs. 36.00 0.00 Rs: Amount in Rs. 180.00 0.00 180.00

Description Hour

Unit

Quantity 8.00

Electric resistivity meter Battery / charging cost etc @

Rate in Rs. 103.40 Rs:

20% Total hire charges of Machinery

Amount in Rs. 827.20 165.44 992.64

C. LABOUR: Sl No 1 2

Description Geophysist / Geologist Graduate Engineer Day Day

Unit

Quantity 2.00 1.00

Rate in Rs. 600.00 600.00

Amount in Rs. 1200.00 600.00

305

3 4

Lab Assistant mazdoor

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Day Day Total cost of Labour 157.50 0.14 22.10 179.60

1.00 4.00

350.00 250.00 Rs:

350.00 1000.00 3150.00

IRR-PMW

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per stage 14.00% Rs: 20.00 Stages Rs: (A+B+C+D)/20.0 Rs.

Rs: Rs: Rs: Rs:

180.00 992.64 3150.00 4322.64 605.1696 4927.81 246.40

IRR-PMW-2-4

DATA:

Drilling 80 mm dia hole through over-burden using casing shoe bitvertical or inclined upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water charges, reaming, collection of wash samples at suitable intervals, logging and lebelling, supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc., complete for depth upto 30 m from surface. Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per Rm by 10 percent. 2. For providing HDPE or light black MS casing pipes add the cost of pipe per Rm. RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 particulars Use rate of casing shoe bit Use rate of reamer shell Use rate of extension rod set 16.5 m Use rate of honne core box Total cost of Materials B. MACHINERY: Sl No 1 2 3 Unit Rm Rm Rm Rm UNIT : Quantity 3.00 3.00 3.00 3.00 3.00 Rm Rate in Rs. 111.11 27.78 1.65 226.11 Rs: Amount in Rs. 333.33 83.33 4.95 678.33 1099.95

Description

Unit Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 1.00 1.00 2.00 2.00 2.00

Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries ( samplers etc )

Rate in Rs. 329.30 189.80 11.10 63.30 36.00 Rs:

Amount in Rs. 329.30 189.80 22.20 126.60 72.00 739.90

C. LABOUR: Sl No 1 2 3

Description Crew for Core drilling machine Crew for Pump mazdoor

Unit Hour Hour Day Total cost of Labour 285.60 0.14 40.00 325.60

Quantity 1.00 2.00 2.00

Rate in Rs. 199.70 78.60 250.00 Rs:

Amount in Rs. 199.70 157.20 500.00 856.90

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per IRR-PMW-2-5 Rm 3.00 Rm (A+B+C+D)/3.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

1099.95 739.90 856.90 2696.75 377.5443583 3074.29 1024.80

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bitvertical / inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water charges, collection of core samples, logging and lebelling, supplying honne wood core box including cement grouting ( excluding cost of cement for grouting )and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface. RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 UNIT : 3.00 Rm

DATA:

particulars Use rate of diamond core bit Use rate of reamer shell Use rate of double tube core barrel Use rate of extension rod set 16.5 m Use rate of honne core box

Unit Rm Rm Rm Rm Rm Total cost of Materials

Quantity 3.00 3.00 3.00 3.00 3.00

Rate in Rs. 800.00 83.33 216.67 22.00 508.75 Rs:

Amount in Rs. 2400.00 250.00 650.00 66.00 1526.24 4892.24

306

B. MACHINERY: Sl No 1 2 3

IRR-PMW

Description

Unit Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 8.00 8.00 16.00 16.00 5.00

Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries

Rate in Rs. 329.30 189.80 11.10 63.30 36.00 Rs:

Amount in Rs. 2634.40 1518.40 177.60 1012.80 180.00 5523.20

C. LABOUR: Sl No 1 2 3

Description Crew for Core drilling machine Crew for Pump mazdoor

Unit Hour Hour Day Total cost of Labour 1118.40 0.14 156.60 1275.00

Quantity 8.00 16.00 2.00

Rate in Rs. 199.70 78.60 250.00 Rs:

Amount in Rs. 1597.60 1257.60 500.00 3355.20

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per Rm NOTE: 3.00 Rm (A+B+C+D)/3.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

4892.24 5523.20 3355.20 13770.64 1927.889556 15698.53 5232.80

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic rate per Rm by 25 percent. 2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic rate per Rm by 40 percent.

IRR-PMW-2-6

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bitvertical / inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water charges,collection of core samples,logging, lebelling, supplying honne wood core boxincluding cement grouting ( excluding cost of cement for grouting )and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Use rate of diamond core bit Use rate of reamer shell Use rate of double tube core barrel Use rate of extension rod set 16.5 m Use rate of honne core box Total cost of Materials B. MACHINERY: Sl No 1 2 3 Unit Rm Rm Rm Rm Rm UNIT : Quantity 3.00 3.00 3.00 3.00 3.00 3.00 Rm Rate in Rs. 666.67 83.33 216.67 22.00 508.75 Rs: Amount in Rs. 2000.00 250.00 650.00 66.00 1526.24 4492.24

Description

Unit Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 8.00 8.00 16.00 16.00 5.00

Core drilling machine Fuel / Energy charges 5 hp pump ( diesel ) 2 Nos. Fuel / Energy charges Sundries

Rate in Rs. 329.30 189.80 11.10 63.30 36.00 Rs:

Amount in Rs. 2634.40 1518.40 177.60 1012.80 180.00 5523.20

C. LABOUR: Sl No 1 2 3

Description Crew for Core drilling machine Crew for Pump mazdoor

Unit Hour Hour Day Total cost of Labour 1118.40 0.14 156.60 1275.00

Quantity 8.00 16.00 2.00

Rate in Rs. 199.70 78.60 250.00 Rs:

Amount in Rs. 1597.60 1257.60 500.00 3355.20

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per Rm NOTE: 3.00 Rm (A+B+C+D)/3.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

4492.24 5523.20 3355.20 13370.64 1871.889556 15242.53 5080.80

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic rate for drilling upto 30 m from surface by 25 percent per Rm. 2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic rate for

307

drilling upto 30 m from surface by 40 percent per Rm.

IRR-PMW

IRR-PMW-2-7

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary / demarcation / chainage / arrow stones including cost of all materials, labour, engraving marks, fixing in position, murum filling etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 18.00 1.00 18 Nos. Rate in Rs. 21.00 110.00 Rs: Rs: Rs: Amount in Rs. 378.00 110.00 0.00 0.00 488.00

Rough stone 20x20x75 cm Each Murrum cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description work inspector Stone chiseller Cl- I mazdoor

Unit Day Day Day Total cost of Labour 75.80 0.14 10.60 86.40

Quantity 1.00 1.00 3.00

Rate in Rs. 300.00 315.00 250.00 Rs:

Amount in Rs. 300.00 315.00 750.00 1365.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 18.00 Nos. (A+B+C+D)/18.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

488.00 0.00 1365.00 1853.00 259.42 2112.42 117.40

IRR-PMW-2-8

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC 1 : 4 : 8 using 40 mm down size graded coarse aggregate including cost of all materials, labour, dressing top surface, engraving BM data etc.,complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 10.00 91.00 0.25 0.15 0.10 0.25 10 Nos. Rate in Rs. 21.00 5.10 1024.00 1076.00 788.00 375.00 Rs: Rs: Rs: Amount in Rs. 210.00 464.10 256.00 161.40 78.80 93.75 0.00 0.00 1264.05

Rough stone 20x20x75 cm Each Cement for CC & top finishing kg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10-4.75 mm cum Sand (Un-Screened ) cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description work inspector Stone chiseller Cl- I mazdoor

Unit Day Day Day Total cost of Labour 224.50 0.14 31.40 255.90

Quantity 1.00 3.00 4.00

Rate in Rs. 300.00 315.00 250.00 Rs:

Amount in Rs. 300.00 945.00 1000.00 2245.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery

Rs: Rs:

1264.05 0.00

308

C. Cost of Labour Total D. Add for contractor's profit and overheads on (A+B+C) 14.00% Rs: Total cost for 10.00 Nos. Rs: Rate per each (A+B+C+D)/10.0 Rs. NOTE: For providing 30 cm thick compacted murum bed in B.C soil area including additional excavation for thickness of murum bedding add per Each

Rs: Rs:

2245.00 3509.05 491.267 4000.32 400.00 Rs: 4.00

IRR-PMW

IRR-PMW-2-9

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC 1 :3 : 6 block of size 90 x 90 x 120 cm using 40 mm down size graded coarse aggregate and providing 35 cm thick 30 cm high UCR masonry in CM 1 : 5 proportion protective wall alround the BM stone, including cost of all materials, labour, dressing top surface of stone, engraving BM data on top surface, excavation, finishing, curing etc., complete with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 particulars Unit UNIT : Quantity 1.00 262.00 0.50 0.30 0.20 0.25 0.04 0.60 1 No. Rate in Rs. 21.00 5.10 1024.00 1076.00 788.00 293.00 337.00 375.00 Rs: Rs: Rs: Amount in Rs. 21.00 1336.20 512.00 322.80 157.60 73.25 13.48 225.00 0.00 0.00 2661.33

4 5 6

Rough stone 20x20x75 cm Each Cement kg Coarse aggregate 40-20 mm cum Coarse aggregate 20-10 mm cum Coarse aggregate 10-4.75 mm cum Rubble stone at quarry cum Stone chips at quarry cum Sand (Un-Screened ) cum Add seignorage charges on stone ( Included in material cost ) Add seignorage charges on murum ( Included in material cost ) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 4

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description work inspector Stone chiseller Cl- I Mason Cl- II mazdoor

Unit Day Day Day Day Total cost of Labour 1992.50 0.14 279.00 2271.50

Quantity 1.00 0.50 1.00 5.00

Rate in Rs. 300.00 315.00 285.00 250.00 Rs:

Amount in Rs. 300.00 157.50 285.00 1250.00 1992.50

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each IRR-PMW-3 IRR-PMW-3-1 DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit MAINTENANCE WORKS : Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetmentincluding stacking all materials separately as directed with initial lead upto 50 m and all lifts. 1.00 No. (A+B+C+D)/1.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

2661.33 0.00 1992.50 4653.83 651.5362 5305.37 5305.40

UNIT : Quantity 0.00 0.00

105 cum Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description Day Day Day

Unit

Quantity 1.00 6.00 48.00

Rate in Rs. 300.00 285.00 250.00

Amount in Rs. 300.00 1710.00 12000.00

309

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total cost of Labour 133.40 0.14 18.70 152.10

Rs:

14010.00

IRR-PMW

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 105.00 cum (A+B+C+D)/105.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 14010.00 14010.00 1961.4 15971.40 152.10

IRR-PMW-3-2

Re-constructing 60 cm thick hand packed rough stone revetment with through stones at 1.5 m c / c over a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick each using sand from approved quarry and stones and filter aggregates obtained from revetment removed for re-construction including cost of all machinery, labour, laying filter and stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 particulars Unit UNIT : Quantity 15.30 15.30 15.30 9.00 57.60 44.00 100 sqm Rate in Rs. 375.00 0.00 0.00 0.00 0.00 0.00 Rs: Rs: Amount in Rs. 5737.50 0.00 0.00 0.00 0.00 0.00 0.00 5737.50

DATA:

Sand (Un-Screened ) ( from quarry) cum Coarse aggregate 10 mm (available) cum Coarse aggr. 40-20 mm ( available) cum Stone chips ( available ) cum Rough stones ( available ) cum Through stones ( available ) Nos Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Day Total cost of Labour 99.80 0.14 14.00 113.80

Quantity 1.00 5.00 33.00

Rate in Rs. 300.00 285.00 250.00 Rs:

Amount in Rs. 300.00 1425.00 8250.00 9975.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

5737.50 0.00 9975.00 15712.50 2199.75 17912.25 179.10

IRR-PMW-3-3

Re-constructing dry rubble rock-toe and filter media for rock-toeconsisting of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick each using sand from approved quarry and stones and filter aggregates obtained from rock-toe removed for re-construction including cost of all machinery, labour, laying filter and stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 particulars Unit UNIT : Quantity 58.20 8.70 19.40 12.10 9.80 100 cum Rate in Rs. 0.00 0.00 0.00 0.00 375.00 Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 3675.00 0.00 3675.00

Rubble ( available ) cum Stone chips ( available ) cum 80-20 mm filter ( available ) cum 20 mm down filter ( available ) cum Sand (Un-Screened) ( fresh from quarry ) cum Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

310

NIL Total hire charges of Machinery

0.00 0.00

0.00 0.00 Rs:

0.00 0.00 0.00

IRR-PMW

C. LABOUR: Sl No 1 2 3 work inspector Mason Cl- II mazdoor

Description

Unit Day Day Day Total cost of Labour 143.00 0.14 20.00 163.00

Quantity 1.00 7.00 48.00

Rate in Rs. 300.00 285.00 250.00 Rs:

Amount in Rs. 300.00 1995.00 12000.00 14295.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 100.00 cum (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

3675.00 0.00 14295.00 17970.00 2515.8 20485.80 204.90

IRR-PMW-3-4

Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with lead upto 50 m and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Unit UNIT : Quantity 101.00 0.21 100 sqm Rate in Rs. 5.10 490.00 Rs: Rs: Amount in Rs. 515.10 102.90 0.00 618.00

Cement 43 Gr kg Sand (Screened ) cum Add seignorage charges on sand @ ( Included in material rate) Total cost of Materials

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 3 4

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description work inspector Mason Class I mazdoor Cartman with Double Bullock cart for water

Unit Day Day Day Day Total cost of Labour 33.90 0.14 4.70 38.60

Quantity 1.00 4.00 6.00 1.00

Rate in Rs. 300.00 315.00 250.00 330.00 Rs:

Amount in Rs. 300.00 1260.00 1500.00 330.00 3390.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

618.00 0.00 3390.00 4008.00 561.12 4569.12 45.70

IRR-PMW-3-5 DATA:

Removing and resetting disturbed dry rubble / khandki stone pitching 25 to 45 cm thick including packing, wedging, finishing etc., complete with all leads and lifts.

RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit

UNIT : Quantity 0.00 0.00

100 sqm Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

311

IRR-PMW

C. LABOUR: Sl No 1 2 3 work inspector Mason Class II mazdoor

Description

Unit Day Day Day Total cost of Labour 35.10 0.14 4.90 40.00

Quantity 1.00 6.00 6.00

Rate in Rs. 300.00 285.00 250.00 Rs:

Amount in Rs. 300.00 1710.00 1500.00 3510.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 3510.00 3510.00 491.4 4001.40 40.00

IRR-PMW-3-6

Removing and refixing disturbed chainage / demarcation / hectometre / guard stones including excavation, back filling etc., complete with all leads and lifts.

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

18 Nos. Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 44.40 0.14 6.20 50.60

Quantity 1.00 2.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 300.00 500.00 800.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each 18.00 Nos. (A+B+C+D)/18.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 800.00 800.00 112 912.00 50.70

IRR-PMW-3-7

Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x 7.5 cm including watering, ramming etc complete with all leads and lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Total cost of Materials B. MACHINERY: Sl No 1 Unit UNIT : Quantity 0.00 0.00 8 Nos. Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

DATA:

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description Day Day Total cost of Labour

Unit

Quantity 1.00 2.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 300.00 500.00 800.00

312

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

100.00 0.14 14.00 114.00

IRR-PMW

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per each IRR-PMW-3-8 8.00 Nos. (A+B+C+D)/18.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 800.00 800.00 112 912.00 114.00

Providing impervious hearting for breached / damaged portion of embankmentwith soil from approved borrow areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts. RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 22.00 Unit UNIT : Quantity 0.00 0.00 480 cum Rate in Rs. 0.00 0.00 Rs: Rs: Amount in Rs. 0.00 0.00 10560.00 10560.00

DATA:

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 5.00 5.00 8.00 8.00 32.00 32.00 2.00 2.00 4.00 4.00 6.00 6.00 2.00

Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Rate in Rs. 1745.70 486.70 1027.10 379.50 454.40 239.10 11.10 63.30 408.80 239.10 1375.40 822.30 36.00 Rs:

Amount in Rs. 8728.50 2433.50 8216.80 3036.00 14540.80 7651.20 22.20 126.60 1635.20 956.40 8252.40 4933.80 72.00 60605.40

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour 19.90 0.14 2.80 22.70

Quantity 4.00 8.00 32.00 3.00 5.00 6.00 2.00 4.00

Rate in Rs. 166.40 166.40 124.80 78.60 117.00 187.20 300.00 250.00 Rs:

Amount in Rs. 665.60 1331.20 3993.60 235.80 585.00 1123.20 600.00 1000.00 9534.40

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 480.00 cum (A+B+C+D)/480.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

10560.00 60605.40 9534.40 80699.80 11297.972 91997.77 191.70

IRR-PMW-3-9

Providing pervious/semi-pervious casing for breached / damaged portion of embankment with soil from approved borrow areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Unit UNIT : Quantity 0.00 325 cum Rate in Rs. 0.00 Amount in Rs. 0.00

313

0.00 Add seignorage charges on soil @ Rs: 22.00 /cum Total cost of Materials

0.00 Rs: Rs:

0.00 7150.00 7150.00

IRR-PMW

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 3.50 3.50 8.00 8.00 24.00 24.00 1.50 1.50 3.00 3.00 4.00 4.00 2.00

Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 3 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Rate in Rs. 1745.70 486.70 1027.10 379.50 454.40 239.10 11.10 63.30 408.80 239.10 1375.40 822.30 36.00 Rs:

Amount in Rs. 6109.95 1703.45 8216.80 3036.00 10905.60 5738.40 16.65 94.95 1226.40 717.30 5501.60 3289.20 72.00 46628.30

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour 23.80 0.14 3.30 27.10

Quantity 3.50 8.00 24.00 1.50 3.00 4.00 2.00 4.00

Rate in Rs. 166.40 166.40 124.80 78.60 117.00 187.20 300.00 250.00 Rs:

Amount in Rs. 582.40 1331.20 2995.20 117.90 351.00 748.80 600.00 1000.00 7726.50

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 325.00 cum (A+B+C+D)/325.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

7150.00 46628.30 7726.50 61504.80 8610.672 70115.47 215.70

IRR-PMW-3-10

Providing impervious hearting for breached / damaged portion of embankmentwith soil from approved dump areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil,sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil @ Rs: 22.00 / cum Total cost of Materials Unit UNIT : Quantity 0.00 0.00 612 cum Rate in Rs. 0.00 0.00 Rs: Rs: Amount in Rs. 0.00 0.00 13464.00 13464.00

B. MACHINERY: Sl No 1 2 3 4 5 6 7

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 4.00 4.00 8.00 8.00 40.00 40.00 4.00 4.00 7.00 7.00 7.50 7.50 2.00

Angle dozer Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 5 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Rate in Rs. 1745.70 486.70 1027.10 379.50 454.40 239.10 11.10 63.30 408.80 239.10 1375.40 822.30 36.00 Rs:

Amount in Rs. 6982.80 1946.80 8216.80 3036.00 18176.00 9564.00 44.40 253.20 2861.60 1673.70 10315.50 6167.25 72.00 69310.05

C. LABOUR: Sl No

Description

Unit

Quantity

Rate in Rs.

Amount in Rs.

314

1 2 3 4 5 6 7 8

Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour 19.00 0.14 2.70 21.70

4.00 8.00 40.00 4.00 7.00 7.50 2.00 6.00

166.40 166.40 124.80 78.60 117.00 187.20 300.00 250.00 Rs:

665.60 1331.20 4992.00 314.40 819.00 1404.00 600.00 1500.00 11626.20

IRR-PMW

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 612.00 cum (A+B+C+D)/612.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

13464.00 69310.05 11626.20 94400.25 13216.035 107616.29 175.80

IRR-PMW-3-11

Providing pervious /semi-pervious casing for breached /damaged portion of embankment with soil from approved dump areas in layers of 10 to 15 cm before compaction including cost of all materials, machinery, labour, all operations such as collection of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each layer to density control of not less than 98 percent or as stipulated by rolling or by using mechanical tampers etc., complete with initiallead upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 particulars NIL Add seignorage charges on soil @ Rs: Total cost of Materials B. MACHINERY: Sl No 1 2 3 4 5 6 7 22.00 Unit UNIT : Quantity 0.00 0.00 440 cum Rate in Rs. 0.00 0.00 Rs: Rs: Amount in Rs. 0.00 0.00 9680.00 9680.00

Description

Unit Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour LS Total hire charges of Machinery

Quantity 3.00 3.00 8.00 8.00 32.00 32.00 3.00 3.00 6.00 6.00 5.50 5.50 2.00

Angle dozer 90 hp Fuel / Energy charges Shovel 0.50 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 4 Nos. Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries

Rate in Rs. 1745.70 486.70 1027.10 379.50 454.40 239.10 11.10 63.30 408.80 239.10 1375.40 822.30 36.00 Rs:

Amount in Rs. 5237.10 1460.10 8216.80 3036.00 14540.80 7651.20 33.30 189.90 2452.80 1434.60 7564.70 4522.65 72.00 56411.95

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description Crew for Dozer Crew for Shovel Crew for Tipper Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor

Unit Hour Hour Hour Hour Hour Hour Day Day Total cost of Labour 22.50 0.14 3.20 25.70

Quantity 3.00 8.00 32.00 3.00 6.00 5.50 2.00 6.00

Rate in Rs. 166.40 166.40 124.80 78.60 117.00 187.20 300.00 250.00 Rs:

Amount in Rs. 499.20 1331.20 3993.60 235.80 702.00 1029.60 600.00 1500.00 9891.40

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seignorage charges B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 440.00 cum (A+B+C+D)/440.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

9680.00 56411.95 9891.40 75983.35 10637.669 86621.02 196.90

IRR-PMW-3-12

Repairing rain cuts / resectioning canal slopes to required lines and gradesas directed using available soil including dressing, clod breaking, packing, tamping etc.,complete with all leads

315

and lifts.

IRR-PMW

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

1000 sqm Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 work inspector mazdoor Total cost of Labour 2.30 0.14 0.30 2.60

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day

Quantity 1.00 8.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 300.00 2000.00 2300.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 1000.00 sqm (A+B+C+D)/1000.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 2300.00 2300.00 322 2622.00 2.60

IRR-PMW-3-13

Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing including chiselling and removing leached lime deposit and disposing off all the waste material out side adits in specified location etc., complete with all leads and lifts.

DATA: A. MATERIALS: Sl No 1 2 3 particulars

RATE ANALYSIS Unit Each Each LS Total cost of Materials

UNIT : Quantity 5.00 10.00 2.00

100 Rm Rate in Rs. 38.00 39.00 36.00 Rs: Amount in Rs. 190.00 390.00 72.00 652.00

Wire brush Coir brush Sundries ( brooms, gloves etc )

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Chiseller Cl II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 20.70 0.14 2.90 23.60

Quantity 2.00 6.00

Rate in Rs. 285.00 250.00 Rs:

Amount in Rs. 570.00 1500.00 2070.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per Rm 100.00 Rm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

652.00 0.00 2070.00 2722.00 381.08 3103.08 31.00

IRR-PMW-3-14

Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing / brushing and washing to remove all surface coatings etc., complete .

DATA: A. MATERIALS: Sl No particulars

RATE ANALYSIS Unit

UNIT : Quantity Rate

100 Rm Amount

316

1 2 3 4

Oxalic acid Wire brush Coir brush Sundries ( brooms, gloves etc )

ltr Each Each LS Total cost of Materials

5.00 5.00 10.00 2.00

in Rs. 66.00 38.00 39.00 36.00 Rs:

in Rs. 330.00 190.00 390.00 72.00 982.00

IRR-PMW

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Total cost of Labour 15.00 0.14 2.10 17.10

Quantity 6.00

Rate in Rs. 250.00 Rs:

Amount in Rs. 1500.00 1500.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per Rm 100.00 Rm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

982.00 0.00 1500.00 2482.00 347.48 2829.48 28.30

IRR-PMW-3-15

Cleaning gates / hoists / embedded parts for re-painting by removing rust, old paint, grease etc., by using wire brush, scrubber, rust remover and applying a coat of rust inhibitive compound etc., complete.

DATA: A. MATERIALS: Sl No 1 2 particulars

RATE ANALYSIS Unit Each LS

UNIT : Quantity 10.00 5.00 TOTAL 10%

100 sqm Rate in Rs. 38.00 36.00 Rs: Rs: Rs: Amount in Rs. 380.00 180.00 560.00 56.00 616.00

Wire brush Sundries (Rust remover/ inhibitor / sand paper etc) Add for scaffolding / ladder etc @

Total cost of Materials B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 40.00 0.14 5.60 45.60

Quantity 5.00 10.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 1500.00 2500.00 4000.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

616.00 0.00 4000.00 4616.00 646.24 5262.24 52.60

IRR-PMW-3-16

Cleaning gates / hoists / embedded parts to expose fresh metal surface for repainting by sand blasting method as per specifications including cost of all materials, labour, machinery, scaffolding, applying a coat of rust inhibitive etc., complete with initiallead for sand upto 1 km and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No particulars Unit UNIT : Quantity Rate in Rs. 100 sqm Amount in Rs.

317

1 2 3 4

Sand (Screened) Use rate of air hose Use rate of sand blast gun nozzle Sundries( Rust inhibitive, seive etc ) Add for scaffolding / ladder etc @

cum Hour Hour LS

30.00 8.00 8.00 5.00 TOTAL 10% .

Total cost of Materials B. MACHINERY: Sl No 1 2

490.00 16.19 3.50 36.00 Rs: Rs: Rs:

14700.00 129.50 28.00 180.00 15037.50 1503.75 16541.25

IRR-PMW

Description

Unit Hour Hour Hour Hour Total hire charges of Machinery

Quantity 8.00 8.00 8.00 8.00

Air compressor 7 cmm diesel Fuel / Energy charges Sand blasting equipment Fuel / Energy charges

Rate in Rs. 248.40 569.30 114.70 0.00 Rs:

Amount in Rs. 1987.20 4554.40 917.60 0.00 7459.20

C. LABOUR: Sl No 1 2 3

Description Crew for Air compressor Crew for Sand blasting equipment mazdoor

Unit Hour Hour Day Total cost of Labour 62.00 0.14 8.70 70.70

Quantity 8.00 8.00 15.00

Rate in Rs. 149.80 156.00 250.00 Rs:

Amount in Rs. 1198.40 1248.00 3750.00 6196.40

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for excise duty (on 75 percent cost excluding cost of materials) E. Add for transportation upto work site @ F. Add for contractor's profit and overheads on (A+B+C+D+E) Total cost for Rate per sqm 0.00% Total 3% 14.00% Rs: 100.00 sqm Rs: (A+B+C+D+E+F)/100.0 Rs.

Rs: Rs: Rs: Rs: Rs: Rs: Rs: Rs:

16541.25 7459.20 6196.40 30196.85 0.00 30196.85 905.91 31102.76 4354.38577 35457.14 354.60

IRR-PMW-3-17

Providing two coats of painting to hoist supporting structures / hoists / moving gantry cranes / railings etc., with zinc chromate alluminium primer paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts.

DATA:

RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Zinc chromate, alluminium primer Sundries Add for scaffolding / ladder etc @ Total cost of Materials B. MACHINERY: Sl No 1 Unit ltr LS

UNIT : Quantity 17.00 2.00 TOTAL 10%

100 sqm Rate in Rs. 156.00 36.00 Rs: Rs: Rs: Amount in Rs. 2652.00 72.00 2724.00 272.40 2996.40

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 42.50 0.14 6.00 48.50

Quantity 10.00 5.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 3000.00 1250.00 4250.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

2996.40 0.00 4250.00 7246.40 1014.496 8260.90 82.60

318

IRR-PMW-3-18

Providing two coats of painting 100 micron dry film thickness each coat to embedded parts / gates with cold applied coal tar epoxy paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete withall leads and all lifts.

IRR-PMW

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Coal tar epoxy paint Sundries ( rust remover / brush etc ) Add for scaffolding / ladder etc @ Total cost of Materials B. MACHINERY: Sl No 1 Unit ltr LS UNIT : Quantity 34.00 4.00 TOTAL 10% 100 sqm Rate in Rs. 187.00 36.00 Rs: Rs: Rs: Amount in Rs. 6358.00 144.00 6502.00 650.20 7152.20

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 54.00 0.14 7.60 61.60

Quantity 13.00 6.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 3900.00 1500.00 5400.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

7152.20 0.00 5400.00 12552.20 1757.308 14309.51 143.10

IRR-PMW-3-19

Providing two coats of painting to hoist supporting structures / hoists / moving gantry cranes / railings etc., with first quality synthetic enemel paint of approved colour including cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts.

DATA: RATE ANALYSIS A. MATERIALS: Sl No 1 2 particulars Synthetic enamel paint ( 1st quality ) Sundries Add for scaffolding / ladder etc @ Total cost of Materials B. MACHINERY: Sl No 1 Unit ltr LS UNIT : Quantity 17.00 2.00 TOTAL 10% 100 sqm Rate in Rs. 216.00 36.00 Rs: Rs: Rs: Amount in Rs. 3672.00 72.00 3744.00 374.40 4118.40

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 2 Painter Class-II mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Day Total cost of Labour 42.50 0.14 6.00 48.50

Quantity 10.00 5.00

Rate in Rs. 300.00 250.00 Rs:

Amount in Rs. 3000.00 1250.00 4250.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per sqm 100.00 sqm (A+B+C+D)/100.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

4118.40 0.00 4250.00 8368.40 1171.576 9539.98 95.40

319

IRR-PMW-3-20

Excavation and removal of silt and silt mixed with sand from canal bed in dry condition including disposing off the same in spoil bank or on the canal embankment in layers as directed etc., complete with initial lead upto 50 m and all lifts.

IRR-PMW

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

10 cum Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Total cost of Labour 100.00 0.14 14.00 114.00

Quantity 4.00

Rate in Rs. 250.00 Rs:

Amount in Rs. 1000.00 1000.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1000.00 1000.00 140 1140.00 114.00

10.00 cum (A+B+C+D)/10.0

IRR-PMW-3-21

Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed including disposing off the same in spoil bank or on the canal embankment in layers as directed etc., complete with initial lead upto 50 m and all lifts.

DATA: A. MATERIALS: Sl No 1 particulars NIL

RATE ANALYSIS Unit

UNIT : Quantity 0.00 0.00 Total cost of Materials

12 cum Rate in Rs. 0.00 0.00 Rs: Amount in Rs. 0.00 0.00 0.00

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Total hire charges of Machinery C. LABOUR: Sl No 1 mazdoor

Rate in Rs. 0.00 0.00 Rs:

Amount in Rs. 0.00 0.00 0.00

Description

Unit Day Total cost of Labour 125.00 0.14 17.50 142.50

Quantity 6.00

Rate in Rs. 250.00 Rs:

Amount in Rs. 1500.00 1500.00

labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour

Total D. Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-3-22 New Item5 - 2010-11 12.00 cum (A+B+C+D)/12.0 14.00% Rs: Rs: Rs.

Rs: Rs: Rs: Rs:

0.00 0.00 1500.00 1500.00 210 1710.00 142.50

Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as excavation, sorting out, transportation, spreading soil in layer of specified thickness, breaking clods, sectioning,etc.,complete with initial lead upto 1 km and all lifts. RATE ANALYSIS Unit:

A. MATERIALS:

807.00 cum

320

Sl No 1

Particulars NIL

Unit

Quantity 0.00 0.00

Add seigniorage charges for soil (As per G.O.Ms.No.198 ,dt:13.08.09) Total cost of Materials B. MACHINERY: Sl No Description Unit 1 2 3 Angle dozer 90 hp Fuel / Energy charges Shovel 0.85 cum capacity Fuel / Energy charges Tippers 5.00 cum capacity 5 Nos. Fuel / Energy charges Total hire charges of Machinery Hour Hour Hour Hour Hour Hour

Rate in Rs. 0.00 0.00 22.00 Rs: Rate in Rs. 1745.70 486.70 1738.10 695.80 454.40 239.10 Rs:

Amount in Rs 0.00 0.00 17754.00 17754.00 Amount in Rs 4713.39 1314.09 13904.80 5566.40 18176.00 9564.00 53238.68

IRR-PMW

Quantity 2.70 2.70 8.00 8.00 40.00 40.00

C. LABOUR: Sl No 1 2 3 4 5

Description Hour Hour Hour Day Day

Unit

Quantity 2.70 8.00 40.00 1.00 2.00 9.40 14% 1.30 10.70

Crew for Dozer Crew for Shovel Crew for Tipper work inspector mazdoor Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-3-23 New Item6 - 2010-11

Rate in Rs. 166.40 166.40 124.80 300.00 250.00 Rs:

Amount in Rs 449.28 1331.20 4992.00 300.00 500.00 7572.48

Rs: Rs: Rs: Rs: 14% 807 cum (A+B+C+D)/807

17754.00 53238.68 7572.48 78565.16

Rs. 10999.12 Rs: 89564.28 Rs: 111.00

Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as watering, compacting to density control of not less than 95 percent or as stipulated using 8T roller etc., complete with initial lead upto 1 km and all lifts. RATE ANALYSIS A. MATERIALS: Sl No Particulars 1 NIL Unit UNIT : Quantity 0.00 0.00 807.00 cum Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Rate in Rs. 1745.70 486.70 3.30 33.60 408.80 239.10 1375.40 822.30 36.00 Rs: Amount in Rs 4713.39 1314.09 13.20 134.40 3270.40 1912.80 8802.56 5262.72 72.00 25495.56

Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No Description 1 2 3 4 5 Angle dozer 90 hp Fuel / Energy charges Pump 5 hp ( ele ) Fuel / Energy charges Water tanker 8000 ltr Fuel / Energy charges Vibratory pad foot roller 8 tonne Fuel / Energy charges Sundries Total hire charges of Machinery Hour Hour Hour Hour Hour Hour Hour Hour LS

Unit

Quantity 2.70 2.70 4.00 4.00 8.00 8.00 6.40 6.40 2.00

C. LABOUR: Sl No 1 4 5 6 7 8

Description Hour Hour Hour Hour Day Day

Unit

Quantity 2.70 4.00 8.00 6.40 1.00 2.00 4.50 14% 0.60 5.10

Crew for Dozer Crew for Pump Crew for Water tanker Crew for Roller work inspector mazdoor Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery

Rate in Rs. 166.40 59.00 117.00 187.20 300.00 250.00 Rs:

Amount in Rs 449.28 236.00 936.00 1198.08 300.00 500.00 3619.36

Rs: 0.00 Rs: 25495.56

321

C. Cost of Labour Total D.Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-3-24 New Item 7 - 2010-11 807.00 cum (A+B+C+D)/807 14%

Rs: 3619.36 Rs: 29114.92 Rs. 4076.09 Rs: 33191.01 Rs: 41.10

IRR-PMW

Providing homogeneous embankment using soil from approved borrow area in layers of 25 to 30 cm before compaction including cost of all materials, machinery, labour, all operations such as compacting to density control of not less than 90 percent or as stipulated using 2T roller etc., complete with initial lead upto 1 km and all lifts. RATE ANALYSIS UNIT : 807.00 cum Unit Quantity Rate Amount in Rs. in Rs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Rs: 0.00 Unit Hour LS Quantity 10.00 2.00 Rate Amount in Rs. in Rs 345.00 3450.00 36.00 72.00 Rs: 3522.00

A. MATERIALS: Sl No Particulars 1 NIL

Add seigniorage charges for soil Total cost of Materials B. MACHINERY: Sl No Description 1 2 Tractor with 2T Roller Sundries Total hire charges of Machinery

C. LABOUR: Sl No 1 2

Description Day Day

Unit

Quantity 0.50 2.00 0.80 14% 0.10 0.90

work inspector mazdoor Total cost of Labour labour component/unit qty Add contractor's profit and overhead charges labour component/unit qty (including contractor's profit) ABSTRACT: A. Cost of Materials including seigniorage charges B. Hire charges of Machinery C. Cost of Labour Total D.Add for contractor's profit and overheads on (A+B+C) Total cost for Rate per cum IRR-PMW-3-25 (New Item 3) 2012-13 IRR-PMW-3-25(a) Weed Removal by Manual Means

Rate Amount in Rs. in Rs 300.00 150.00 250.00 500.00 Rs: 650.00

Rs: Rs: Rs: Rs: 14% 807.00 cum (A+B+C+D)/807

0.00 3522.00 650.00 4172.00

Rs. 584.08 Rs: 4756.08 Rs: 5.90

Removal of Water Hyacinth up to 30 cm thick RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm 14% (A+B+C+D)/2000 Unit Day Day Quantity 3.5 28 Rate in Rs. Amount in Rs. 300.00 1050 250.00 7000 Rs. 8050.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 0.00 2000 Sqm

Rs.

Rs. Rs. Rs.

0.00 0.00 8050.00 8050.00 1127 9177.00 4.6

322

IRR-PMW-3-25(b)

Removal of Water Hyacinth beyond 30 cm thick RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm 14% (A+B+C+D)/2000 Unit Day Day Quantity 5 38 Rate in Rs. Amount in Rs. 300.00 1500 250.00 9500 Rs. 11000.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 2000 Sqm

IRR-PMW

Rs. Rs. Rs.

0.00 0.00 11000.00 11000.00 1540 12540.00 6.3

IRR-PMW-3-25(c)

Clearing Alchi Tilla RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm 14% (A+B+C+D)/2000 Unit Day Day Quantity 3 26 Rate in Rs. Amount in Rs. 300.00 900 250.00 6500 Rs. 7400.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 0.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 2000 Sqm

Rs.

Rs. Rs. Rs.

0.00 0.00 7400.00 7400.00 1036 8436.00 4.2

IRR-PMW-3-25(d)

Removal of Jammu RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour Unit Day Day Quantity 2.5 22 Rate in Rs. Amount in Rs. 300.00 750 250.00 5500 Rs. 6250.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 Unit Quantity 0 Rate in Rs. Amount in Rs. 0 0 Rs. 0.00 2000 Sqm

323

IRR-PMW

ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm IRR-PMW-3-25(e) Removal of Imponea, Cornea RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm IRR-PMW-3-25(f) Removal of Natchu, goobi, thooti, etc. RATE ANALYSIS Unit : A. MATERIALS Sl. No. 1 Particulars NIL Total Cost of Materials B. MACHINERY Sl. No. 1 Description NIL Total hire charges of Machinery C. LABOUR Sl. No. 1 2 Description Work Inspector Mazdoor Total Cost of Labour ABSTRACT: A.COST OF MATERIALS B.COST OF MACHINERY C.COST OF LABOUR Total D. Add for Contractor's Profit and overheads Total Cost for removal weed in the extent of 2000 Sqm Rate per Sqm 14% (A+B+C+D)/2000 Unit Day Day Quantity 1.2 8 Unit Quantity 0 Unit Quantity 0 14% (A+B+C+D)/2000 Unit Day Day Quantity 3 26 Unit Quantity 0 Unit Quantity 0 14% (A+B+C+D)/2000

Rs. Rs. Rs.

0.00 0.00 6250.00 6250.00 875 7125.00 3.6

2000 Sqm

Rate in Rs. Amount in Rs. 0 0 Rs. 0.00

Rate in Rs. Amount in Rs. 0 0 Rs. 0.00

Rate in Rs. Amount in Rs. 300.00 900 250.00 6500 Rs. 7400.00

Rs. Rs. Rs.

0.00 0.00 7400.00 7400.00 1036 8436.00 4.2

2000 Sqm

Rate in Rs. Amount in Rs. 0 0 Rs. 0.00

Rate in Rs. Amount in Rs. 0 0 Rs. 0.00

Rate in Rs. Amount in Rs. 300.00 360 250.00 2000 Rs. 2360.00

Rs. Rs. Rs.

0.00 0.00 2360.00 2360.00 330.4 2690.40 1.3

324

Das könnte Ihnen auch gefallen