Beruflich Dokumente
Kultur Dokumente
voltage distribution grids. Redundancy allows line failures to occur and power is simply rerouted while workmen repair the damaged and deactivated line. A substation receives its power from the transmission network, the power is stepped down with a transformer and sent to a bus from which feeders fan out in all directions across the countryside. These feeders carry three-phase power, and tend to follow the major streets near the substation. As the distance from the substation grows, the fanout continues as smaller laterals spread out to cover areas missed by the feeders. This tree-like structure grows outward from the substation, but for reliability reasons, usually contains at least one unused backup connection to a nearby substation. This connection can be enabled in case of an emergency, so that a portion of a substation's service territory can be alternatively fed by another substation
grid for long-distance transmissions are therefore preferred, but national grid is often still used for the overall structure.
PGCIL plans to interconnect its regional systems to a national power grid, which can facilitate power sharing from neighboring states or countries with surplus power. The entire programme is has been planned out in a phased manner consisting of three phases at an estimated investment of US$ 20 billion. Of this, POWERGRID would invest US$ 11 billion. The rest would be from the private sector.
Phase-I involving interconnection of regional grids through HVDC Back-to-Back links with a cumulative capacity of 5000 MW has already been completed.
Source: PGCIL Phase-II is partially complete and involves a hybrid system comprising of high capacity HVDC and HVAC lines (both 765 kV and 400 kV).
At the end of this phase, cumulative inter-regional capacity would be 23,000 MW. This would help transfer operational surplus and would provide flexibility in inter-regional transfer of power. The Phase-III is scheduled to be completed by 2012. This would consist of a ring of 765 kV transmission lines inter-connecting ER, WR and NR and would be utilised for transfer of short term as well as long term surplus. The cumulative capacity at the end of this phase would be 30,000 MW.
Source: PGCIL
The present cumulative capacity is 16450 MW. On an average, 1500-2000 MW is being transferred and about 35 MU/day is being traded. The major inter regional links of 8000 MW capacity is shown below:
Source: PGCIL To encourage private investment in the transmission business, the Central Government enacted the Electricity Laws (Amendment) Act in August 1998. This Act provides for state transmission utilities and transmission licensees, and thereby facilitates state power reform and private investment in power transmission. An extensive network of Transmission and Distribution lines has been developed over the years for evacuating power produced in the various generating stations and distributing the same to the consumers. Depending upon the quantum of power and the distance involved lines of appropriate voltages are laid. The nominal Extra High Voltage lines in vogue are HVDC, 400 KV, 230/220 KV, 110 KV and 66 KV lines have been introduced so far by the SEBs are Punjab, U.P, W.B, M.P. Maharashtra, Gujarat, Karnataka, Bihar and Orissa as also by BBMB (Punjab) and Central Sector only. The standard voltage of operation on the distribution side are 33 KV, 22 KV,11KV, 400/230 Volts besides 6.6 KV, 3.3 KV and 2.2 KV. The low voltage system has 3 phase 4 wires supply giving 400/420 volts between 2 phases and
220/240 volts between phase and neutral. This has been universally adopted throughout the country. The State of Maharashtra has the largest Transmission and Distribution network of 631972 Ckt. Kms in the country. Apart from Maharashtra the States of Punjab, Haryana, Rajasthan, Uttar Pradesh Gujarat, Madhya Pradesh, Andhra Pradesh,Karnataka, Kerala, Tamil Nadu, Bihar, West Bengal and Orissa have more than 1 lakh Ckt. Kms. of T&D Lines. One of the major reasons of power shortage in the country is high transmission and distribution losses which include power thefts and non-payment by priority sectors. In addition to this is the poor financial conditions of SEBs many of whom have mounting dues aggregating over Rs 100 billion. The restructuring of the power sector, reform of the SEBs rationalization of tariff, improvement in not only generation but also in distribution and transmission, and above all a commercial re-orientation of the entire sector are the core issues to be dealt with for toning up the sector performance.
ahead to isolate the element. To ameliorate this systemic defect, superconducting magnetic energy storage units at critical junctions can store or release power for a few seconds to allow control systems to catch up and actuate isolating procedures.
1.4.1. Causes
Electrical power cannot easily be stored over extended periods of time, and is generally consumed less than a second after being produced. The load on any network must be matched by the supply to it and its ability to transmit that power. Any overload of a power line, or under load/overload of a generator, can cause hard-to-repair and costly damage, so the affected device is disconnected from the network if a serious imbalance is detected. As power lines carry more current, they get hotter. This causes them to lengthen and sag between towers. They may safely reach a specified minimum clearance height above the ground. If the lines sag further, a flashover to nearby objects (such as trees) can occur, causing a transient increase in current. Automatic protective relays detect the high current and quickly act to disconnect the faulted line from service. To maintain the lines' specified operating clearance, the rightof-way must be kept clear of vegetation. Should a fault occur and take a line out of service, the change in current flow is compensated by other transmission lines, which must have enough spare capacity to carry the excess current. If they do not, overload protection in those lines will also trip, causing a cascading failure as the excess current is switched onto neighboring circuits running at or near their capacity. System operators are responsible for ensuring that power supply and loads remain balanced, and for keeping the system within safe operational limits such that no single fault can cause the system to fail. After a failure affecting their system, operators must obtain more power from generators or other regions or "shed load" (meaning cut power to some areas) until they can be sure that the worst remaining possible failure anywhere in the system will not cause a system collapse. In an emergency, they are expected to immediately shed load as required to bring the system into balance. To assist the operators there are computer systems, with backups, which issue alarms when there are faults in the transmission or generation system. Power flow modeling tools let them analyze the current state of their network, predict whether any parts of it may be overloaded, and predict what the worst possible failure left is, so that they can change the distribution of generation or reconfigure the transmission system to prevent a failure should this situation occur. If the computer systems and their backups fail, the operators are required to monitor the grid manually, instead of relying on computer alerts. If they cannot interpret the current state of the power grid in such an event, they follow a contingency plan, contacting other plant and grid operators by telephone if necessary. If there is a failure, they are also required to notify adjacent areas
which may be affected, so those can predict the possible effects on their own systems. Local operators are co-ordinate by regional centers, but the operating principle is the same whether the network is large or small.
1.5. Islanding
Islanding refers to the condition in which a distributed generation (DG) generator continues to power a location even though electrical grid power from the electric utility is no longer present. Islanding can be dangerous to utility workers, who may not realize that a circuit is still powered, and it may prevent automatic re-connection devices. For that reason, distributed generators must detect islanding and immediately stop producing power; this is referred to as anti-islanding. The common example of islanding is a grid supply line that has solar panels attached to it. In the case of a blackout, the solar panels will continue to deliver power as long as the sun is shining. In this case, the supply line becomes an "island" with power surrounded by a "sea" of unpowered lines. For this reason, solar inverters that are designed to supply power to the grid are generally required to have some sort of automatic anti-islanding circuitry in them. In intentional islanding, the generator disconnects from the grid, and forces the distributed generator to power the local circuit. This is often used as a power backup system for buildings that normally sell their power to the grid.
Normally even when the load and production are exactly matched, the so-called "balanced condition", the failure of the grid will result in several additional transient signals being generated. For instance, there will almost always be a brief decrease in line voltage, which will signal a potential fault condition. However, such events can also be caused by normal operation, like the starting of a large electric motor. Methods that detect islanding without a large number of false positives is the subject of considerable research. Each method has some threshold that needs to be crossed before a condition is consider to be a signal of grid interruption, which leads to a "non-detection zone" (NDZ), the range of conditions where a real grid failure will be filtered out.