Sie sind auf Seite 1von 9

INVITATION FOR BIDS

04 MW Thak ChilasHPP Chilas

Bidding Documents

NOTICE FOR INTERNATIONAL COMPETITIVE BIDDING FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) OF 04 MW THAK CHILAS HYDROPOWER PROJECT, CHILAS
Date Loan No. and Title : : <November 18,2012> To be financed from proposed Tranche III under Renewable Energy Development Sector Investment Program. Contract No. and Title : ICB-GB-002

Engineering, Procurement and Construction of 04MW HPP Thack Chilas. Deadline for Bid Submission 1. : January 29, 2013

The Islamic Republic of Pakistan has applied for a loan from Asian Development Bank towards the cost of Renewable Energy Development Sector Investment Program (REDSIP) Tranche 3.A part of this loan will be used for payments under the contract named above. Bidding is open to the qualified bidders from eligible source countries of the ADB.

2.

Water and Power Department Government of Gilgit-Baltistan, Pakistan, (The Employer) invites sealed bids from eligible bidders for the Engineering, Procurement and Construction of 04MW Thak Chilas HPP Chilas (including detailed design, supply, construction, erection, installation, testing and commissioning of the Facilities). The construction period for Thak Chilas HPP is 1320calendar days. The Project is located at Chilas Gilgit-Baltistan, Pakistan. The works mainly comprise of the following:

a.

Civil Structures Access road and bridge, weir, lateral intake including course trashrack,

gates/stoplogs, connecting channel, gravel trap including gates/stoplogs, sand trap including gates/stoplogs, flushing pipes forebay and spill channel, intake gate, flushing gate, steel penstock including expansion joints, bends, aqueduct, penstock manifold, pedestals & anchor blocks for penstock, surface powerhouse, tailrace including connection with headrace of existing Thak Powerhouse, allied structures and protective works, grid station, switchyard, transmission lines, contractor camps and, office. b. Mechanical Equipment Three (3) horizontal shaft Pelton turbines with two or three jets, auxiliary equipment, digital governors (PID type), spherical inlet valves, dewatering, drainage, cooling water, lubrication, HVAC systems,emergency diesel generator set, overhead crane and any other equipment/system necessary for operation of the plant.

Volume I

Invitation for Bids

04 MW Thak ChilasHPP Chilas

Bidding Documents

c.

Electrical Equipment Three(3) horizontal shaft synchronous generators, excitation equipment, control

panels, switchgear panels ,transformers (Step-up/Station auxiliary),33kV outdoor switchyard equipment, SCADA system, AC and DC distribution system, control, alarm, protection, telecommunication, metering, cabling, earthing systems, indoor and outdoor lighting, 18km 33 kV double circuit transmission line from Powerhouse to 33kV Grid Station, 33kV out door Grid station, and any other equipment/system necessary for operation of the plant. International Competitive Bidding (ICB) shall be conducted in accordance with ADBs SingleStage; Two- Envelope Bidding Procedure. The Bidder, either as a single entity or joint venture, shall meet all the qualification criteria set forth. A pass- fail post qualification criteria has been detailed in Bidding Documents and consist of the following basic parameters. Nationality: Conflict of Interest: ADB Eligibility: Govt.owned Entity: The bidders shall have nationality of ADB eligible countries. No conflict of interest in accordance with ADB policy. Not having been declared ineligible by ADB. Entities of Borrower country with financial autonomy, operating under the principal of commercial law and not dependent of the Employer. UN-Eligibility: Not having been excluded by an act of compliance with UN Security Council. Pending litigation: No pending litigation more than 50% of the bidders net worth. Financial Situation: a. b. c. Historical Financial Performance: Average annual turnover: Cash Flow requirement: 3 years US$ 6.04 Million US$ 0.755 Million

Experience: a. b. General Experience: Specific Experience: Completed 7 Years withinthelast(five) 5years atleastone

EPC Hydropower Projectofat least04MWor higher capacity.The Projectmust havebeenin satisfactory operation for at least 3 years. Personnel: Must demonstrate personnel for the key position relevant to the Project. Equipment: Must demonstrate list of key construction equipment relevant to the Project. 3. To obtain further information and inspect the bidding documents, bidders should contact:

Volume I

Invitation for Bids

04 MW Thak ChilasHPP Chilas

Bidding Documents

Project Director Street Address: Office of the Project Director, 04 MW Thak Chilas Hydropower Project, Chilas,Water and Power Department, Chilas Gilgit Baltistan City: Chilas Country: Pakistan Telephone: 0092-5812-450488 Facsimile number: 0092-5812-450486 Electronic mail address: abdul.khaliqpd@gmail.com 4. To purchase the Bidding Documents (in English) from November 26,2012 and onward, eligible Bidder should: Write to the address above, requesting Bidding documents for Engineering, Procurement and Construction of 04MW Thak Chilas Hydropower Project, Chilas Pay a non-refundable Tender Form fee of PAK Rupees Twenty Five Thousand only (Rs.25,000) in the form of a Bank Draft/Pay Order. 5. Deliver your bid: To the address above. On or before the deadline,January 29, 2013 at 12:00 Hours.

Together with a bid security in the amount as specified in the Bidding Document (Data Sheet). in a freely convertible currency in the form of a Bank
Guarantee. Bids will be opened immediately after the deadline in public and in the presence of bidders representatives, who choose to attend. 6. When comparing Bids, ADBs Domestic Preference Scheme will be applied in accordance with the provision stipulated in the Bidding Document. 7. A pre-bid meeting will be held on January 09,2013 at 11.30 AM at the below mentioned address.

ADB(Asian Development Bank) office in Serana Complex Islamabad

Volume I

Invitation for Bids

KASHMIR AFFAIRS & GILGIT BALTISTAN DIVISION


Sl. Name of the Scheme No 1 1 2 Strengthening of Planning & Monitoring Cell, M/o KA & GB, Islamabad Estimated Cost Total Foreign Aid 3 4 29.200 0.000 Expenditure upto June 2012 5 21.962 Throwforward as on 01-07-12 6 7.238 (Million Rupees) Allocation for 2012-13 Foreign Rupee Total Aid 7 8 9 0.000 7.238 7.238

KASHMIR AFFAIRS
2 3 4 Azad Jammu & Kashmir (Block Allocation) 43.5 MW Jagran Hydro Power Project AJK Provision of Water Supply and Sewerage of Mirpur City and Hamlets Construction of Rathua Haryam Bridge across Reservoir Channel on Mirpur Islamgarh Road Multi Sector Rehabilitation & Improvement Project (MSRIP) 4.8 Battar Hydel Power Project (AJK) 1.7 MW Dhannan Hydro Power Project (AJK) 7056.000 5122.972 7056.000 0.000 400.000 3914.664 6656.000 1208.308 0.000 200.000 0.000 9547.036 0.000 785.079 9547.036 200.000 785.079

4232.855

0.000

1695.282

2537.573

0.000

700.000

700.000

3735.345

1100.295

2349.204

1386.141

0.000

500.000

500.000

7 8

760.403 297.254

0.000 0.000

536.338 254.434

224.065 42.820

0.000 0.000

224.065 42.820

224.065 42.820

Capacity Building of HEB (Grant) Total (KA)

44.100 21248.929

44.100 8200.395

0.000 9149.922

44.100 12099.007

10.000 210.000

0.000 11799.000

10.000 12009.000

GILGIT BALTISTAN
10 Gilgit-Baltistan (Block Allocation) 11 26 MW Hydropower Project at Shagarthang Skardu 12 Construction of 14 MW Hydel Power Project Naltar-V 13 Construction of 16 MW Hydel Power Project Naltar-III 14 4 MW Hydropower Project Thak Chilas Total (GB) Total (KA&GB) 4843.726 2688.005 819.055 4024.671 348.164 150.000 6789.090 30.000 7137.254 180.000

1715.170

381.600

974.873

740.297

75.645

274.355

350.000

1372.330

346.379

579.417

792.913

50.480

158.266

208.746

1282.194 9213.420 30491.549

640.605 4056.589 12256.984

383.855 2757.200 11929.084

898.339 6456.220 18562.465

90.000 714.289 924.289

73.000 7324.711 19130.949

163.000 8039.000 20055.238

IEE Report for 04MW Thak Nullah Hydropower Plant

II.
A. 13.

PROJECT DESCRIPTION

BACKGROUND AND JUSTIFICATION According to data provided by GBWPD, there are 3,600 electricity consumers in Chilas

and surrounding areas. Of these 3,200 (89%) are domestic, 300 (8%) are commercial, whereas 100 (3%) are industrial. The total power demand is 2.4 MW however; the total installed capacity of hydel and thermal power plants is 1.7 MW. Thus there is a shortfall of 0.7 MW. Unless new sources of power are added, the situation is likely to aggravate with time as the demand is projected to increase to 4.2 MW by 2015. The proposed 04 MW plant will be an important project to bridging the widening gap between demand and supply. B. 14. LOCATION The proposed Hydel Power Project is located on Thak Nullah which is a left bank tributary

of Indus river having a length of 23 km. Its confluence with the Indus river is at about 5km east of Chilas. The project site is located about 15 Km east of Chilas town. The project area is accessible from Chilas Babusar pass highway running along Thak nullah off-taking from Chilas-Gilgit road (Karakoram Highway).The weir intake is proposed on right side of Thak Nullah in Khun village where as the powerhouse is proposed about 4.5 Km downstream of the weir intake. The location of the project on map of Pakistan is sown in Figure 1 where as its location on regional map of Chilas is given in Figure 2.

Thak Nullah HPP

Figure 1: Project Location in the Map of Pakistan

IEE Report for 04MW Thak Nullah Hydropower Plant

Figure 2: Location of the Project on Regional Map of Chilas D. 15. PROJECT COMPONENTS The layout of the project showing various project components is given in Figure 3.

Figure 3: Layout Plan of Thak Nullah HPP 16. The layout of the project comprises of a diversion weir, intake channel, settling tank, by

pass channel, fore bay, powerhouse, tail race channel, spill channel, penstock pipe and surge tank. Salient features of the layout are listed below.

IEE Report for 04MW Thak Nullah Hydropower Plant

Table 1: Project Components Sr. # i. ii. iii. iv. v. vi. vii. viii. ix x xi xii xiii xiv xv xvi xvii xviii. 17. Item Design Discharge Gross Head Net Head Installed Capacity Mean Annual Energy Plant Factor Penstock Diameter Penstock Length Turbines Type of Turbines Capacity of Each Turbine Forebay capacity Powerhouse Type Powerhouse Size Grid station Generator output Transformer capacity Length of 11kV Transmission Line Units m /s meter meter MW GWh % meters meters Nos. MW m
3 3

Quantity 1 325 300 4 27.33 78 1 4,620 2 750ppm,twin jet Pelton wheel 2 3,900 15m x 6m x7m 15m x15m 2 5 10

Surface m m MW MVA Km

Diversion Weir: The typical weir made of gabions is proposed for diversion of water at the

take of point. The crest of the weir is proposed to be 4m above the nullah bed to provide sufficient head. Two guide walls have been provided to divert water into the intake channel. 18. Intake and By Pass channels: A trapezoidal open channel is proposed for conveyance of

water from the weir to the intake structures. 19. Settling Tank: a settling tank has been proposed for the removal of sand and silt

particles. At the entrance of the settling tank a trash rack is proposed to be provided for the removal of floating objects and bigger particles which may find their way through the intake channel. The tank is also provided with a sluice valve fro periodic flushing. 20. Forebay: A circular tank of 35m dia is proposed for the storage of water for the lean
3

period. The tank can hold 3850m of water to meet the requirements in lean period. 21. Surge Tank: A surge tank of the same size as for the forebay is proposed on the hill slope

near the power house at the height of 315m from the entry point of the penstock at the power house. 22. Penstock: A penstock pipe of about 4.5km long having 1m dia is proposed to bury

underground.

IEE Report for 04MW Thak Nullah Hydropower Plant

23.

Grid Station and Transmission Line: The 33kv grid station has been proposed in Jaldas

in Chilas town thereby developing a stable and flexible distribution network in the area. 24. The 33 kV power transmission line is proposed to transfer the electrical power of Thak

Nullah hydel power plant over a distance of 10 km along the existing transmission line to the proposed 33kV grid station at Jaldas in Chilas Town. 25. Access Road to Weir Site: The project site is accessible through Babusar Pass Highway

off taking from Karakoram Highway near Chilas town. The powerhouse and the weir site are located on this highway at 10km and 14km form Karakoram Highway respectively. No access road construction or rehabilitation would require for project implementation. 26. Manpower: About 200 people will be employed for the implementation of the project

where as 20 persons will get permanent employment for its operation and maintenance. 27. Construction Schedule: The implementation period of the project is 4 years

starting from 2012. 28. Environmental Flow: The weir on Thak Nullah is designed to divert 1.0 m /s of water for
3

the power generation of 4MW. Between October and April the average flow in Thak Nullah is 1.7m /s. Thus in these months, more than half of the water will be diverted for power production and there would be minimal flow in the stream between the weir site and the proposed powerhouse site, a distance of about 4 km. The minimal flow i.e. 0.7m /s is much higher than the 10% of average minimum flow 0.17m /s which is considered as environmental flow for bare survival of biota in the vulnerable reach. During the months of February and March the average monthly flow reduces to 1.17m /s. These months have been declared as lean months and the powerhouse will not be operated at full capacity. Only one turbine will operate using 0.5m /s of flow thus allowing the remaining water as environmental releases.
3 3 3 3 3

Das könnte Ihnen auch gefallen