Sie sind auf Seite 1von 3

My Notes on PMP (Formulas)

Following are the Formulas I consolidated for PMP preparation Earned Value Analysis PV (Planned Value) = BCWS (Budgeted Cost of Work Schedule) EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) CV = EV AC SV = EV PV CPI = EV / AC SPI = EV / PV ETC = BAC EV [Future Variances are Atypical or Not Consistent or Di similar] ETC = (BAC EV) / CPI [Future Variances are Typical or Consistent or similar] EAC = BAC / CPI [simplest formula: typical or no variances] EAC = AC + ETC [Initial Estimates are flawed] EAC = AC + BAC EV [Future variances are Atypical or Not Consistent or Di similar] EAC = AC + BAC EV / CPI [Future Variances are Typical or Consistent or similar] VAC = BAC EAC % COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 CV% = CV / EV x 100 SV% = SV / PV x 100 Float or Slack LS - ES and LF EF MEAN -> Average MODE -> The most found number RANGE -> Largest - Smallest Measure. MEDIUM -> No in the middle or avg. of 2 middle Nos PERT = O + 4ML + P / 6 STD. DEV. OF TASK = P O / 6 TASK VAR. = [(P - O)/6 ] squared = Std. Dev ^ 2 CP STD. DEV. = + + SIGMA 1 = 68.26 2 = 95.46

3 = 99.73 6 = 99.99 Channels of Communication (N x (N 1)) / 2 Project Selection PV = F V / (1+r) (or) FV = PV x (1+r) Cash Flow = Cash Inflow Cash Outflow Discounted Cash Flow = CF x Discount Factor ARR = S Cash Flow / No. of Years ROI = (ARR / Investment) * 100 % Bigger is better BCR = Benefits / Cost Benefit Cost Ratio (BCR) Bigger is better ((BCR or Benefit / Cost) Revenue or Payback VS. cost) Or PV or Revenue / PV of Cost Net Present Value (NPV) = Net Present Value Bigger is better Internal Rate of Return (IRR) Bigger is better Payback Period Less is better Net Investment / Avg. Annual cash flow Exp. Value = Probability % x Consequence $ Class of Estimates Definitive +5% Capital Cost +10-15% Appropriation +15-25% Feasibility +25-35% Order of Magnitude > +35% (-50 - 75%) Contract Incentives Savings = Target Cost Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost Expected Monetary Value Probability * Impact Point of Total Assumption (PTA) ((Ceiling Price - Target Price) / buyer's Share Ratio) + Target Cost To Complete Performance Index [TCPI] Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete

is less than planned. How efficient must the project team be to complete the remaining work with the remaining money? ( BAC - EV ) / ( BAC - AC ) Cost of Quality (CoQ) = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total efforts) x 100 %

Das könnte Ihnen auch gefallen