Sie sind auf Seite 1von 12

SCOPE OF STUDY

Study Ref XXXXX FAO Mr John Doe, Director, Operational Excellence QC Vitamins Bradford BD17 6JY UNITED KINGDOM Date: 30 November 2009 Subject: LEANTrak Study Scope of Work Document
th

Cimlogic Ltd, 11 Baildon Mills, Baildon, West Yorkshire BD17 6JX Phone: 01274 599 955 Fax: 0870 762 5559 Global Internet: http://www.cimlogic.co.uk email : purchasing@cimlogic.co.uk

Dear John,

We are pleased to offer you the attached scope of work document, prior to undertaking a study on your machine number 1. We look forward to agreeing a suitable date and time for the study. If you do have any queries please do not hesitate to contact me. Yours sincerly,

Mike McKenna B.Sc MES and Automation Engineer Cimlogic Ltd 07917 757205 http://www.cimlogic.co.uk mike.mckenna@cimlogic.co.uk

Specialists in Manufacturing Execution Systems & Automation Projects


Cimlogic Limited 11 Baildon Mills Baildon Shipley West Yorkshire BD17 6JY
Registered Office Address: 18 Hallfield Road Bradford BD1 3RQ Company Reg. No. 3477109 VAT Registration No. 745074432

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Project Title: Customer: Cimlogic Reference: Customer Reference:

LEANTrak Study on Machine No 1 Client 1 at Location A Scope.docx XYZ

Prepared By

.... .... Sign / Date Printed Name

.... Title .... Title

Approved By

.... .... Sign / Date Printed Name

Approved as a basis for a non-intrusive trial

Issue

Date

30 November 2009

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 2 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Table of Contents 1 2 DOCUMENTATION RECORD .............................................................. 4 INTRODUCTION ................................................................................... 4


2.1 2.2 2.3 2.4 2.4.1 2.4.2 2.4.3 2.4.4 2.5 Purpose of this document ............................................................................ 4 Objective......................................................................................................... 4 Success Criteria ............................................................................................ 4 Deliverables from Cimlogic .......................................................................... 5 Installation .............................................................................................................. 5 Configuration ......................................................................................................... 5 Operation ............................................................................................................... 5 Report .................................................................................................................... 5 Deliverables from CLIENT ............................................................................ 6

WORK PROCEDURE ........................................................................... 6


3.1 LEANTrak Installation Procedure ............................................................. 6

RISK ASSESSMENT AND REVALIDATION REQUIREMENTS .......... 7


4.1 LEANTrak Installation ................................................................................ 7

5 6

DOCUMENTATION REQUIREMENTS................................................. 7 RE TEST REQUIREMENTS ................................................................. 7

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 3 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

1 DOCUMENTATION RECORD
Revision 1 Date 30 Nov 2009 Prepared By Mike McKenna Details First issue

2 INTRODUCTION
2.1

PURPOSE OF THIS DOCUMENT

The purpose of this document is too: 1 2 3 2.2 Identify the objectives and success criteria of the Study Identify the deliverables from Cimlogic Identify the deliverables from the CLIENT

OBJECTIVE

To establish the productivity of machine XYZ, Cimlogic will fit a LEANTrak Automatic Monitoring and Reporting system to carry out a brief but effective evaluation of the machine. LEANTrak will capture real-time production events, non-intrusively involve operators to contextualize the collected data, analyse the data and provide reports on the key performance indicators (how well production goals were attained, problems that occurred with their frequency, root cause and impact). The study will be conducted over a shift without interfering with ongoing production and without any changes to infrastructure (nothing installed or modified). 2.3

SUCCESS CRITERIA

The report produced by LEANTrak will show: 1. KPI Summary 2. Time loss due to Operational events 3. Time loss due to Manual events An example report is shown in Appendix A.

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 4 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

2.4 2.4.1

DELIVERABLES FROM CIMLOGIC


Installation

Cimlogic will sign a non-disclosure agreement which binds the company to not disclosing any information gathered during the study, without written permission of the CLIENTs nominated legal authority. Cimlogic will then install LEANTrak on a target machine. The schematic of the installation will be similar to that shown below:

2.4.2

Configuration

Cimlogic will configure the LEANTrak system with the following customer supplied information: 2.4.3 Product names, codes that are to be addressed during the shift Standard operating conditions for each products Production target for each product Shift times Downtime categories Starved categories Blocked categories Operation

Once the study has commenced then after every machine event (downtime, starved, etc) the operator will be asked to select one of the categories and offer a comment. Other appropriate users may look at the real-time dashboard display via a web browser display, which will give the status of production rate (actual versus target) availability, performance, quality and OEE. 2.4.4 Report

At the conclusion of the study, Cimlogic will extract the standard reports from the LEANTrak (see Appendix A for an example) and provide these to the CLIENT.

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 5 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A 2.5

DELIVERABLES FROM CLIENT

It is assumed that the client will: 1. 2. 3. 4. Provide its own Non-Disclosure Agreement (NDA) or sign a Cimlogic supplied NDA. Provide suitable supervision and direction to the Cimlogic engineer to ensure he/she complies with the CLIENTS H&S code and Operating Procedures. Provide the necessary information for the LEANTrak system set up as detailed in section 2.4 above. Participate in the review meeting at the end of the study

3 WORK PROCEDURE
3.1

LEANTRAK INSTALLATION PROCEDURE

Installation of the LEANTrak system will comprise of three elements. 1. Installation of the sensors. An example installation is shown as follows

2. Installation of the SENSORTrak Data Collection unit. The sensors shown above will be connected into the SENSORTrak unit. This unit must be powered from a local power supply (95 to 265V ac). 3. Installation of the LEANTrak industrial laptop PC The laptop can be located at a convenient point to the machine. The Laptop is battery operated however a connection to a local power supply is preferred.

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 6 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

4 RISK ASSESSMENT AND REVALIDATION REQUIREMENTS


The risks associated with the procedure are assessed as follows: Seriousness HIGH = 3 MEDIUM = 2 LOW = 1 Likelihood HIGH = 3 MEDIUM = 2 LOW = 1 NOT POSSIBLE = 0 If no checks are carried out on installation If limited checks are carried out to ensure no interference with production If checks are carried out to ensure no interference with production Unaffected by installation Potential for loss of production Potential reduction in production Little risk to production

4.1

LEANTRAK INSTALLATION
Risk Scenario Potential Impact Seriousness Likelihood Overall risk level 1 Revalidation Requirement Confirm the products can be processed without any interference from the installed sensors

Sensors Installation interferes with production

Production fails to start

5 DOCUMENTATION REQUIREMENTS
No changes to existing documentation are required. The output of this study will be a decision support document which, when analysed, will enable qualified corrective action tasks to be identified and executed

6 RE TEST REQUIREMENTS
The CLIENT will need to carry out its standard start up and performance tests after the LEANTrak system is installed and removed.

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 7 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Appendix A EXAMPLE REPORTS

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 8 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 9 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 10 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 11 of 12

LEANTRAK STUDY ON MACHINE 1 CLIENT 1 LOCATION A APPENDIX B Other Information


Cimlogic Ltd is one of the successful companies to join a leading edge scheme, designed to help industry improve its safety record. Cimlogic Ltd has received accreditation from SAFEcontractor, a programme which recognises very high standards of health and safety practice amongst UK contractors.The company's application for SAFEcontractor accreditation was driven by the need for a uniform standard across the business. SAFEcontractor accreditation is expected to enhance the company's ability to attract new contracts and its commitment to safety will be reviewed positively by its insurers. SAFEcontractor is operated by international safety, health and environmental risk management specialists, the National Britannia Group. National Britannia say "Major organisations can no longer run the risk of employing contractors who are not able to prove that they have sound health and safety policies and more companies need to understand the importance of adopting good risk management in the way that Cimlogic Ltd have done. The firm's high standard has set an example, which hopefully will be followed by other companies in the sector." Under the SAFEcontractor system, businesses undergo a vetting process, which examines health and safety procedures and their track record for safe practice.

Cimlogic Ltd are a registered Rockwell Automation Solutions Provider and as such have proven themselves to be a technically competent solutions based Systems Integrator. Whether you need to install a custom built automation solution or upgrade and modify existing Rockwell equipment, Cimlogic have a depth of experience with Rockwell automation technology in all aspects of the automation industry from food and beverage to BMS. Our extensive experience and industrial contacts make us the ideal system integrator for all your automation needs.

As a Wonderware registered Systems Integrator, Cimlogic Ltd. is able to offer vast experience and technical excellence in delivering Wonderware InTouch solutions for major blue chip companies. Through this agreement we are able able to offer you exclusive discounted licensing on many Wonderware products as well as having immediate access to Wonderware support services. Through access to this high quality support network we are able to provide you with the highest possible level of quality.

Cimlogic Ltd are a registered solutions provider for the HMI / SCADA package CIMPLICITY from GE Fanuc. With the latest features of CIMPLICITY 8.0, including a powerful graphics engine, dynamic time handling and digital graphical replay, operators and engineers have the power to precisely monitor and control every aspect of their environment. Having designed and installed numerous Cimplicity based solutions for some of the countries largest Blue chip companies you will not be disappointed when choosing Cimlogic Ltd to implement you GE Fanuc System.

In August 2008, Cimlogic Ltd, went through the process of training in RFID Technology, and as a result has obtained CompTIA RFID+ Certification. CompTIA Radio Frequency Identification (RFID+) certification validates the knowledge and skills of professionals who work with RFID technology. It is an international, vendor-neutral credential that recognizes a technician's ability to install, maintain, repair, and troubleshoot the hardware and software functionality of RFID products. RFID is quickly becoming the standard technology for tracking goods in the supply chain, but it will only be effective if it is executed by properly trained and certified individuals. CompTIA RFID+ provides a baseline for the knowledge and skills required of RFID workers, giving business owners the opportunity to hire qualified professionals, and individuals a credential to prove their ability.

Cimlogic works in close partnership with Microsoft in order to remain fully informed of the latest developments in software and licensing. We have a number of Microsoft qualified staff with more on training paths. We take full advantage of the learning, training, knowledge-sharing and collaborative opportunities available from these memberships to ensure that we continue to improve our abilities, build relationships with complimentary companies and find new ways to get the best deal for our customers.

Filename Scope of Study

Revision 1.0

Version date 30 Nov 2009

Type Doc

Owners CIMLOGIC LTD

Page No Page 12 of 12