Beruflich Dokumente
Kultur Dokumente
Electricity is generated by two Double Extraction-Backpressure Steam Turbines (BP ST), two Condensing Steam Turbines (CT) and one Gas Trbine (GT). Total capacity is 222MW and average load is 150MW. The main idea in this project is to stop one of the two BP ST that are running nearly 40% capacity, and causing a huge amount of loss.
We know that when the turbines are running with low capacity like 40% this will cause energy loss, and stopping one of them and run the other with >80% capacity will improve the overall efficiency. Of course in this complicated electrical system it is hard to give a decition to stop one of the big turbines. It should be well studied in every aspects.
There was a serious problem to stop one of the two BP ST. When it is stopped the safety of 34,5kV main electrical distribution system is disappeared, because of the voltage stability. So this can not applied until this project. This situation is shown in below picture.
Line-2
Line-1
BB-1
154kV
BB-2
34.5kV
Coupling CB
34.5kV
Factories T2
Factories T1
NOT : While working with this configuration TG-2 Steam Turbine can not be stopped because of the safety problem on the 34,5kV main distribution system. Effects of zero impedance faults on the 154kV grid is high, so the sources on 34,5kV main distribution system need to be in service to maintain stability. Also during a fault on the 154kV grid, the GT connected to the same bus-bar with the grid does not help to maintain stability on the 34,5kV main distribution system.
To accomplish this problem we thought to change the bus-bar configuration. By this configuration change we will secure the safety of 34,5kV main electrical distribution system. The stability studies shown that; even though one BP ST is stopped, by this bus-bar configuration change stability issue is improved for the 34,5kV main electrical distribution system.
Line-2
Line-1
154kV
34.5kV
Coupling CB
34.5kV
Factories T2
OPEN
Factories T1
NOT : Whith this configuration TG-2 Steam Turbine can be stopped. Because the safety problem on the 34,5kV main distribution system is solved by serial configuration, instead of parallel configuration. Effects of zero impedance faults on the 154kV grid is low, so this will improve stability on 34,5kV main distribution system and less need TG-2 to be in service. The GT is no longer connected to the same bus-bar with the grid. During a fault on the 154kV grid, GT will act directly to maintain stability on the 34,5kV main distribution system. Diasadvantage of this configuration is; 34,5kV main distribution system is connected to the grid by one transformer instead of two. This will increase the islanding possibility.
By the application of this project in July 2012, the below graph is achieved fort the unit production cost of electricity.
September
January
November
May
March
December
February
October
April
June
July
As can be seen in the graph there is a meaningful decrease in unit electricity cost after July 2012. With this efficiency improvement and energy saving project; we achieved nearly 16% decrease in unit production cost of electricity and 1,25million$ monthly saving. We expect 15million$ saving for each year.
October
August