Project Briefs:
A. Project title : The Rotaryana Branch Office & Cafe Prima

B. Project description

: The Branch Office, Showroom, Caf & Staff Accommodation of Rotaryana Prima : Jl. By Pass Ngurah Rai, Nusa Dua, Bali, Indonesia : 1,124.30 M
2

Private Dinning Wash-up kitchen Display Storage & Work shop Lockers Male & Female Engineering Room 2. Second Floor M2 Mezzarine showroom Open plan office Side Office Virtual Office & Lounge 3. Third Floor 81.00 M2 Pond Skylight Total Building area 1,124.30 M2

: : : 13.50 : 100.00 : :

50.00 8.80 M2 M2 25.00 25.00 :

M2 M2 M2 M2 245.00

C. Location

: 45.00 M2 : 150.00 M2 : 50.00 M2 : 200.00 M2 : : 29.00 M2 : 52.00 M2 :

D. Land area E. Project completion F. Project commencement date G. Construction time required H. Building and facilities: 1. First Floor Entry Foyer Obin House Galerry Caf & Display Show Kitchen, display & cafe

: To be determined : To be determined : - months

: : : : :

16.00 M2 25.00 M2 130.00 M2 150.00 M2 150.00 M2 : 105.00 M2

: 798.30 M2

Design Conceptual
A. Function: PT. Rotaryana Prima branch office complete with kitchen equipment show room, workshop, caf and staff accommodation. B. Architectural conceptual and approach: Unique Balinese Architecture with modern

Prepared by C Design

Page 1 of 3

Rotaryana Pima Project

PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005 standard of technology will shown dominantly to covered the function of building. Combination of natural local sand stone (Paras Silakarang and Paras Krobokan) with simplicity shape appear on over all of building. C. Room Program: Floor : Polished concrete & iron wood Wall : Plaster painted Ceiling : Calciboard 6 mm painted w/ rel aluminium 5. Floor Wall Ceiling 6. Floor Wall Ceiling Caf & Display : Polished terrazzo existing with deco floor : Existing : Calciboard 6 mm painted Show Kitchen : Sulawesi marble 30x30 cm :: Calciboard 6 mm painted

Building Specifications
First Floor 1. Entry Floor : Existing Column : Karang bukit random Ceiling : Existing 2. Foyer Floor : Existing Wall : Existing Ceiling : Existing 3. Floor Wall Ceiling 4. Obin House : Existing : Existing : Existing Gallery

7. Display Floor : Existing Wall : Existing Ceiling : Calciboard 6 mm painted 8. Cafe Floor : Sulawesi marble 30x30 cm Wall :Ceiling : Calciboard 6 mm painted 9. Floor Wall Ceiling Washup Kitchen : Polished concrete : Plaster painted : Calciboard 6 mm painted

10. Locker Male & Female : Floor : Existing Wall : Existing Ceiling : Existing

Prepared by C Design

Page 2 of 3

Rotaryana Pima Project

PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005 11. Floor Wall Ceiling 12. Floor Wall Ceiling 13. Floor Wall Ceiling Engineering Room : Ceramic tile : Plaster painted : Existing Storage & Work shop : Existing : Existing & partisi : Calciboard 6 mm painted Private Dinning : Existing & Deco floor : Plaster painted : Calciboard 6 mm 4. Side Office Floor : Ceramic tile Wall : Plaster painted Ceiling : Calciboard 6 mm 5. Side Office Floor : Existing Wall : Plaster painted & Glass windows existing from Caf existing 1st floor Ceiling : Calciboard 6 mm 6. Open Plan Office Floor : Existing Wall : Existing & partisi Ceiling : Existing Third Floor 1. Pond Floor : Sukabumi stone

Second Floor 1. Mezzanine Showroom Floor : Existing Wall : Panel Ceiling : Existing 2. Virtual Office Floor : Existing Wall : Existing & partisi Ceiling : Calciboard 6 mm 3. Lounge Floor : Existing Wall : Existing & partisi Ceiling : Calciboard 6 mm

2. Skylight Floor : Timber Existing Wall : Paras kerobokan. Architecture fee proposal: 7.5% from the total of project cost estimation with scope of works with following : 1. To provide conceptual design, design development drawing, tender document drawing until contract drawing :

Prepared by C Design

Page 3 of 3

Rotaryana Pima Project

PROJECT SUMMARY
Prepared By:
design

Date: November 3, 2005 Architectural drawing Interior drawing Hard landscape drawing Structure drawing Mechanical, electrical and plumbing drawing (MEP) 2. Provide technical specification 3. Provide tender document and cost plan

Project supervision fee: 4 % from total project cost estimation for supervision during construction.

==== END OF SECTION ====

Prepared by C Design

Page 4 of 3