Beruflich Dokumente
Kultur Dokumente
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
A1 A2 A3 A4 A5 A6 A7 A8 A9
Supply & Install Sanitary Sewers and Structures Supply & Install Storm Sewers & Structures Supply & Install Box Culverts at Tributary Crossings Supply & Install Watermain, Appurtenances & Connections Supply, Place & Compact Road Materials and Appurtenances Construct Highway #26 Left Hand Turn Lane Clearing, Stripping, & Earthworks Supply & Install Utilities, Street Lights & Duct Banks Sediment and Erosion Control Measures
$ $ $ $ $ $ $ $ $
156,600.00 297,000.00 200,000.00 225,000.00 600,000.00 300,000.00 75,000.00 190,000.00 35,000.00 2,078,600.00
300,000.00 $ 75,000.00 $
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 1 of 6
2/21/2013 3:40 PM
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
B1 B2 B3
770 15
m ea
$ $
175.00 $ 5,000.00 $
134,750.00 75,000.00
1 3 46
ea ea ea
$ $ $
B4 B5 B6 B7
790 16 1
m ea LS
$ $ $
3 48
ea ea
$ $
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 2 of 6
2/21/2013 3:40 PM
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
C1
LS
150,000.00 $
150,000.00
C2 C3 C4
800 40
m ea
$ $
200.00 $ 3,700.00 $
160,000.00 148,000.00
1 1 1 20 1
ea ea LS m LS
$ $ $ $ $
C5 C6 C7
15,000.00 $
C8 C9 C10
700 39
m ea
$ $
200.00 $ 3,700.00 $
140,000.00 144,300.00
1 1 1 20 1
ea ea LS m LS
$ $ $ $ $
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 3 of 6
2/21/2013 3:40 PM
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
D2 D3
Supply & Install Water Services c/w Curbstop & Boxes (services may include both fire & domestic service lines) $ a) Block 1 (Clubhouse) 1 ea $ b) Block 4 (2- 30 Unit Lodge & 1- 20 Unit Lodge) 3 ea $ c) Block 5 (1-30 Unit lodge, 6- 6 Unit villa, 2- 8 Unit villa) 46 ea Temporary Watermain Connection, Testing & Disinfection South Development (Blocks 6, 13) Supply & Install 150mm Watermain & Appurtenances 1 LS $
D4
D5 D6
600
225.00 $
135,000.00
Supply & Install Water Services c/w Curbstop & Boxes (services may include both fire & domestic service lines) $ a) Block 6 (3- 30 Unit Lodges) 3 ea $ b) Block 6 (4- 4 unit villas, 2- 6 unit villas, 5- 8 unit villas) 48 ea Temporary Watermain Connection, Testing & Disinfection 1 LS $
D7
E1
LS
20,000.00 $
20,000.00
E2 E3 E4
m m m
$ $ $
E5 E6 E7
m m m
$ $ $
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 4 of 6
2/21/2013 3:40 PM
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
3000 9000
m3 m3
$ $
5.00 $ 10.00 $
15,000.00 90,000.00
F3 F4
30000
m3
6.00 $
180,000.00
m3 m3 m
$ $ $
F5
G2
Hydro services for development blocks inclusive of cabling & transformers up to meter base at each unit or building $ 50,000.00 $ a) Block 1 (Clubhouse) 1 ea $ 50,000.00 $ b) Block 4 (2- 30 Unit Lodge & 1- 20 Unit Lodge) 3 ea $ 4,000.00 $ c) Block 5 (1-30 Unit lodge, 6- 6 Unit villa, 2- 8 Unit villa) 46 ea South Development (Blocks 6, 13)
G3
Street Lighting inclusive of poles, base, luminaries & cabling a) Lighting for roadways (assume 60m spacing between poles) b) Parking areas & internal driveways
5 10
ea ea
$ $
3,500.00 4,500.00
$ $
17,500.00 45,000.00
G4
Hydro services for development blocks inclusive of cabling & transformers up to meter base at each unit or building $ 50,000.00 $ a) Block 6 (3- 30 Unit Lodges) 3 ea $ 4,000.00 $ b) Block 6 (4- 4 unit villas, 2- 6 unit villas, 5- 8 unit villas) 48 ea Sub Total $
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 5 of 6
2/21/2013 3:40 PM
ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL
SUMMARY OF PRELIMINARY OPINION OF PROBABLE COSTS SCHEDULE A - OVERALL COLLECTOR ROADWAYS SCHEDULE B - DEVELOPMENT BLOCKS - SANITARY SEWERS SCHEDULE C - DEVELOPMENT BLOCKS - STORM SEWERS SCHEDULE D - DEVELOPMENT BLOCKS - WATERMAIN SCHEDULE E - DEVELOPMENT BLOCKS - ROADWORKS SCHEDULE F - DEVELOPMENT BLOCKS - EARTHWORKS SCHEDULE G - DEVELOPMENT BLOCKS - UTILITIES Sub-Total Construction Contingency Allowance (20%) $ $ $ $ $ $ $ $ $ 2,078,600.00 585,500.00 1,462,300.00 505,250.00 1,569,100.00 686,000.00 854,500.00 7,741,250.00 1,548,250.00
9,289,500.00
J:\400\446 - Pierre Boiron\3026 - Meaford West Property\Estimates & Schedules\MeafordOverall OPC 02212013\West
Page 6 of 6