Beruflich Dokumente
Kultur Dokumente
Appendix A Cost Estimation Methodology exceed final design estimates. At the preliminary design, design development and final design stage construction cost estimates should be verified to ensure that a project has remained within budget. Value Engineering (VE) is advocated by FTA throughout the design process particularly in the early phase where there is the greatest opportunity to affect the cost of construction with minimal impact to project goals. VE assesses products and systems and provides recommendations for a more economical solution. The process also considers long-term operations and maintenance practices and costs. FTA requires its grantees to escalate construction costs to reflect anticipated inflation and to report this amount as a separate budget line item. This requirement acknowledges that over time, materials and labor costs may rise due to general inflation. Escalation may be calculated by applying an assumed fixed annual percentage to probable construction costs through the mid-point of construction. A more sophisticated approach would be to apply escalation by either individual construction contract or by trade item, e.g. bridge, track, signal, etc., and adjust to the anticipated year of expenditure. Large, complex projects that encompass many construction contracts should add a program contingency over and above design and construction contingencies. A program contingency addresses interfaces between and among construction contracts as well as uncertainty associated with system start-up, testing, and commissioning. FTA participates in reasonable startup costs that directly support activation and pre-revenue operations. These costs should be accounted for in the project estimate.
Recommendations
1
Resolution of Variations in Cost Estimates During project development FTA and the grantee should agree on a method to resolve variances between estimates. Regions 1 and 9 have utilized a Capital Reserve Account (CAPRA) for this purpose. The CAPRA requires the grantee to set aside funds equal to estimating differences. These funds are available for overruns. Cost Management System Grantees should implement a cost management system to operate within the framework of the grant requirements and provide the grantee with reliable cost information. Greater visibility to cost information will permit the timely implementation of alternative solutions. The cost management system will encompass a data warehouse of all project costs organized within the WBS.
Appendix A Cost Estimation Methodology Reporting categories within the cost management system should include: Baseline Budget Authorization Contract Commitments Actual Cost Pending Contract Changes Forecast-to-Complete Estimate-at-Completion Budget Variance Earned Value
Grantees can manage the program/project contingency by evaluating commitments to budget estimates and tracking potential changes as soon as they are identified. Further, the grantee should establish a change order control system that identifies and records the cause of the changes. Increases/changes in scope or scope creep are a common occurrence on large-scale projects. Individual changes should be logged and recorded with the appropriate funding source. Cost Recovery In association with the change order control system, grantees should be encouraged to develop and utilize a cost recovery procedure. Several larger projects have successfully implemented procedures that allow for the potential recovery of costs due to errors and omissions that cause rework of a portion of the project. It is a requirement of all design contracts for the Architect/Engineer to maintain professional and general liability insurance to cover these items. Regardless of how much is recovered through this process, it is an effective negotiation tool.
FTA Project and Construction Management Guidelines Final May 2003 2003 Update Page A-4
1
Preliminary (budget)
15% - 30%
Definitive
15% - 5%
40-scale alignment, facility descriptions, sketches, study reports, cross sections, profiles, elevations, geotechnical data, staging plans, schedule, definition of temporary work Progress Plans and Specifications, working construction schedule
10% - 20%
5% - 15%
5%
PS&E
Complete Plans and Specifications for Bidding, Detailed Construction Schedule, Contract Terms and Conditions
0% - 10%
Probable Accuracy as stated by the Association for the Advancement of Cost Engineering International (AACE)