Date/Time: Doing WorkDay Math in VBA

VBA and Access do not provide any support for working with the typical workdays (Monday through Friday). VBA Developers Handbook (Sybex) contains several functions that provide information about the next and previous workday, and finding the first and last workday in a month. To deal with Holidays, the original SkipHolidays function accepted a reference to a recordset containing all the dates that you would want these functions to skip over. To increase flexibility and ease of use, the original functions have been re-written to accept an array of Holidays, much like Excel's WorkDay function. ' ' ' ' ' ' ' ********* Code Start ************** Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

Public Function dhAddWorkDaysA(lngDays As Long, _ Optional dtmDate As Date = 0, _ Optional adtmDates As Variant) As Date ' Add the specified number of work days to the ' specified date. ' ' ' ' Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' In: ' lngDays: ' Number of work days to add to the start date. ' dtmDate: ' date on which to start looking. ' Use the current date, if none was specified. ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value, if that's what you want. ' Out: ' Return Value: ' The date of the working day lngDays from the start, taking ' into account weekends and holidays. ' Example: ' dhAddWorkDaysA(10, #2/9/2000#, Array(#2/16/2000#, #2/17/2000#)) ' returns #2/25/2000#, which is the date 10 work days ' after 2/9/2000, if you treat 2/16 and 2/17 as holidays ' (just made-up holidays, for example purposes only). ' Did the caller pass in a date? If not, use ' the current date. Dim lngCount As Long Dim dtmTemp As Date

1 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

If dtmDate = 0 Then dtmDate = Date End If dtmTemp = dtmDate For lngCount = 1 To lngDays dtmTemp = dhNextWorkdayA(dtmTemp, adtmDates) Next lngCount dhAddWorkDaysA = dtmTemp End Function Public Function dhNextWorkdayA( _ Optional dtmDate As Date = 0, _ Optional adtmDates As Variant = Empty) As Date ' Return the next working day after the specified date. ' ' ' ' Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Requires: ' SkipHolidays ' IsWeekend ' In: ' dtmDate: ' date on which to start looking. ' Use the current date, if none was specified. ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value. ' Out: ' Return Value: ' The date of the next working day, taking ' into account weekends and holidays. ' Example: ' ' Find the next working date after 5/30/97 ' dtmDate = dhNextWorkdayA(#5/23/1997#, #5/26/97#) ' ' dtmDate should be 5/27/97, because 5/26/97 is Memorial day. ' Did the caller pass in a date? If not, use ' the current date. If dtmDate = 0 Then dtmDate = Date End If dhNextWorkdayA = SkipHolidaysA(adtmDates, dtmDate + 1, 1) End Function Public Function dhPreviousWorkdayA( _ Optional dtmDate As Date = 0, _ Optional adtmDates As Variant = Empty) As Date ' Return the previous working day before the specified date. ' ' ' ' Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

2 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

' Requires: ' SkipHolidays ' IsWeekend ' In: ' dtmDate: ' date on which to start looking. ' Use the current date, if none was specified. ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value. ' Out: ' Return Value: ' The date of the previous working day, taking ' into account weekends and holidays. ' Example: ' ' Find the next working date before 1/1/2000 ' ' dtmDate = dhPreviousWorkdayA(#1/1/2000#, Array(#12/31/1999#, #1/1/2000#)) ' dtmDate should be 12/30/1999, because of the New Year's holidays.

' Did the caller pass in a date? If not, use ' the current date. If dtmDate = 0 Then dtmDate = Date End If dhPreviousWorkdayA = SkipHolidaysA(adtmDates, dtmDate - 1, -1) End Function Public Function dhFirstWorkdayInMonthA( _ Optional dtmDate As Date = 0, _ Optional adtmDates As Variant = Empty) As Date ' Return the first working day in the month specified. ' ' ' ' Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Requires: ' SkipHolidays ' IsWeekend ' In: ' dtmDate: ' date within the month of interest. ' Use the current date, if none was specified. ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value. ' Out: ' Return Value: ' The date of the first working day in the month, taking ' into account weekends and holidays. ' Example: ' ' Find the first working day in 1999 ' dtmDate = dhFirstWorkdayInMonthA(#1/1/1999#, #1/1/1999#)

3 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

Dim dtmTemp As Date ' Did the caller pass in a date? If not, use ' the current date. If dtmDate = 0 Then dtmDate = Date End If dtmTemp = DateSerial(Year(dtmDate), Month(dtmDate), 1) dhFirstWorkdayInMonthA = SkipHolidaysA(adtmDates, dtmTemp, 1) End Function Public Function dhLastWorkdayInMonthA( _ Optional dtmDate As Date = 0, _ Optional adtmDates As Variant = Empty) As Date ' Return the last working day in the month specified. ' ' ' ' Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Requires: ' SkipHolidays ' IsWeekend ' In: ' dtmDate: ' date within the month of interest. ' Use the current date, if none was specified. ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value. ' Out: ' Return Value: ' The date of the last working day in the month, taking ' into account weekends and holidays. ' Example: ' ' Find the last working day in 1999 ' dtmDate = dhLastWorkdayInMonthA(#12/1/1999#, #12/31/1999#) Dim dtmTemp As Date ' Did the caller pass in a date? If not, use ' the current date. If dtmDate = 0 Then dtmDate = Date End If dtmTemp = DateSerial(Year(dtmDate), Month(dtmDate) + 1, 0) dhLastWorkdayInMonthA = SkipHolidaysA(adtmDates, dtmTemp, -1) End Function Public Function dhCountWorkdaysA(ByVal dtmStart As Date, ByVal dtmEnd As Date, _ Optional adtmDates As Variant = Empty) _ As Integer ' Count the business days (not counting weekends/holidays) in ' a given date range.

4 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

' ' ' '

Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Requires: ' SkipHolidays ' CountHolidays ' IsWeekend ' In: ' dtmStart: ' Date specifying the start of the range (inclusive) ' dtmEnd: ' Date specifying the end of the range (inclusive) ' (dates will be swapped if out of order) ' adtmDates (Optional): ' Array containing holiday dates. Can also be a single ' date value. ' Out: ' Return Value: ' Number of working days (not counting weekends and optionally, holidays) ' in the specified range. ' Example: ' Debug.Print dhCountWorkdaysA(#7/2/2000#, #7/5/2000#, _ ' Array(#1/1/2000#, #7/4/2000#)) ' ' returns 2, because 7/2/2000 is Sunday, 7/4/2000 is a holiday, ' leaving 7/3 and 7/5 as workdays. Dim intDays As Integer Dim dtmTemp As Date Dim intSubtract As Integer ' Swap the dates if necessary.> If dtmEnd < dtmStart Then dtmTemp = dtmStart dtmStart = dtmEnd dtmEnd = dtmTemp End If ' Get the start and end dates to be weekdays. dtmStart = SkipHolidaysA(adtmDates, dtmStart, 1) dtmEnd = SkipHolidaysA(adtmDates, dtmEnd, -1) If dtmStart > dtmEnd Then ' Sorry, no Workdays to be had. Just return 0. dhCountWorkdaysA = 0 Else intDays = dtmEnd - dtmStart + 1 ' Subtract off weekend days. Do this by figuring out how ' many calendar weeks there are between the dates, and ' multiplying the difference by two (because there are two ' weekend days for each week). That is, if the difference ' is 0, the two days are in the same week. If the ' difference is 1, then we have two weekend days. intSubtract = (DateDiff("ww", dtmStart, dtmEnd) * 2) ' The answer to our quest is all the weekdays, minus any ' holidays found in the table. intSubtract = intSubtract + _

5 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

CountHolidaysA(adtmDates, dtmStart, dtmEnd) dhCountWorkdaysA = intDays - intSubtract End If End Function Private Function CountHolidaysA( _ adtmDates As Variant, _ dtmStart As Date, dtmEnd As Date) As Long ' ' ' ' ' ' Count holidays between two end dates. Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Required by: ' dhCountWorkdays ' Requires: ' IsWeekend

Dim Dim Dim Dim

lngItem As Long lngCount As Long blnFound As Long dtmTemp As Date

On Error GoTo HandleErr lngCount = 0 Select Case VarType(adtmDates) Case vbArray + vbDate, vbArray + vbVariant ' You got an array of variants, or of dates. ' Loop through, looking for non-weekend values ' between the two endpoints. For lngItem = LBound(adtmDates) To UBound(adtmDates) dtmTemp = adtmDates(lngItem) If dtmTemp >= dtmStart And dtmTemp <= dtmEnd Then If Not IsWeekend(dtmTemp) Then lngCount = lngCount + 1 End If End If Next lngItem Case vbDate ' You got one date. So see if it's a non-weekend ' date between the two endpoints. If adtmDates >= dtmStart And adtmDates <= dtmEnd Then If Not IsWeekend(adtmDates) Then lngCount = 1 End If End If End Select ExitHere: CountHolidaysA = lngCount Exit Function HandleErr: ' No matter what the error, just ' return without complaining.

6 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

' The worst that could happen is that the code ' include a holiday as a real day, even if ' it's in the table. Resume ExitHere End Function Private Function FindItemInArray(varItemToFind As Variant, _ avarItemsToSearch As Variant) As Boolean Dim lngItem As Long On Error GoTo HandleErrors For lngItem = LBound(avarItemsToSearch) To UBound(avarItemsToSearch) If avarItemsToSearch(lngItem) = varItemToFind Then FindItemInArray = True GoTo ExitHere End If Next lngItem ExitHere: Exit Function HandleErrors: ' Do nothing at all. ' Return False. Resume ExitHere End Function Private Function IsWeekend(dtmTemp As Variant) As Boolean ' If your weekends aren't Saturday (day 7) and Sunday (day 1), ' change this routine to return True for whatever days ' you DO treat as weekend days. ' Modified from code in "Visual Basic Language Developer's Handbook" ' by Ken Getz and Mike Gilbert ' Copyright 2000; Sybex, Inc. All rights reserved. ' Required by: ' SkipHolidays ' dhFirstWorkdayInMonth ' dbLastWorkdayInMonth ' dhNextWorkday ' dhPreviousWorkday ' dhCountWorkdays If VarType(dtmTemp) = vbDate Then Select Case Weekday(dtmTemp) Case vbSaturday, vbSunday IsWeekend = True Case Else IsWeekend = False End Select End If End Function Private Function SkipHolidaysA( _ adtmDates As Variant, _ dtmTemp As Date, intIncrement As Integer) As Date ' Skip weekend days, and holidays in the array referred to by adtmDates. ' Return dtmTemp + as many days as it takes to get to a day that's not ' a holiday or weekend.

7 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

' ' ' '

Modified from code in "Visual Basic Language Developer's Handbook" by Ken Getz and Mike Gilbert Copyright 2000; Sybex, Inc. All rights reserved.

' Required by: ' dhFirstWorkdayInMonthA ' dbLastWorkdayInMonthA ' dhNextWorkdayA ' dhPreviousWorkdayA ' dhCountWorkdaysA ' Requires: ' IsWeekend Dim Dim Dim Dim strCriteria As String strFieldName As String lngItem As Long blnFound As Boolean

On Error GoTo HandleErrors ' ' ' ' ' Move up to the first Monday/last Friday, if the first/last of the month was a weekend date. Then skip holidays. Repeat this entire process until you get to a weekday. Unless adtmDates an item for every day in the year (!) this should finally converge on a weekday.

Do Do While IsWeekend(dtmTemp) dtmTemp = dtmTemp + intIncrement Loop Select Case VarType(adtmDates) Case vbArray + vbDate, vbArray + vbVariant Do blnFound = FindItemInArray(dtmTemp, adtmDates) If blnFound Then dtmTemp = dtmTemp + intIncrement End If Loop Until Not blnFound Case vbDate If dtmTemp = adtmDates Then dtmTemp = dtmTemp + intIncrement End If End Select Loop Until Not IsWeekend(dtmTemp) ExitHere: SkipHolidaysA = dtmTemp Exit Function HandleErrors: ' No matter what the error, just ' return without complaining. ' The worst that could happen is that we ' include a holiday as a real day, even if ' it's in the array. Resume ExitHere End Function ' ********* Code End **************

8 of 9

08/01/2013 9:25 AM

Date/Time: Doing WorkDay Math in VBA

http://access.mvps.org/access/datetime/date0012.htm

1998-2010, Dev Ashish & Arvin Meyer, All rights reserved. Optimized for Microsoft Internet Explorer

9 of 9

08/01/2013 9:25 AM

Das könnte Ihnen auch gefallen