Beruflich Dokumente
Kultur Dokumente
How does it fail? How can it fail? What is the likelihood of failure? What does it cost to repair? What are the consequences of failure?
Build AM Plan
Risk
Asset Management
Definition of risk
Risk in AM-speak is the consequence of failure multiplied by the probability of failure Often used as a measure of criticality Preferred term is business risk exposure (BRE)
Probability or likelihood of failure (PoF) Consequence or impact of failure (CoF) Risk mitigation or risk reduction and avoidance
Percent of Failures
Low Decreasing
Time
Increasing
10
Bathtub curvetypically applicable for mechanical and electrical assets Age-based curvetypically applicable for civil passive assets
High
Percent of Failures
Low Decreasing
Time
Increasing
Reliabilitythe probability that a component or system will perform its specified function for the specified period under specified operation conditions Fundamentals of Asset Management 11
Mortality
Efficiency
NPDES is National Pollutant Discharge Elimination System, CSOs are combined sewer overflows, and OSHA is Occupational Safety and Health Administration
12
Failure Mode
Capacity
Range
Yes
Yes
LOS
3 years
Yes
Yes
Mortality
10 years
No
Yes
Yes
Efficiency
5 years
13
Failure analysis
Function
Functional Failure End state or potential end state; Evidence what you see
Failure Cause Contributing & root causes; reasons why failure occurred
14
Effect-Cause
Internal contact Worn bearing
Root Cause
No lubrication
Effect
15
PoF is directly related to the failure mode We cannot absolutely determine PoF Sometimes we have good data, sometimes we do not We can estimate a range of failurehow early (pessimistic) and how late (optimistic)
16
CMMSmean time between failures (MTBF) Vendor and industry information Other failure records (hard copies) Our brilliant memories (staff) Our SCADA system (if we have one and if it keeps records on this asset)
PoF is probability of failure, CMMS is computerized maintenance management system, SCADA is supervisory control and data acquisition
17
Performance
50
100
18
90 Failed
9 10
19
20
Condition
10
Performance
Poor
Minimum
Physical Failure
0 20 40 60 80 100
21
Maintainability
Continuous recurrent breakdown Out of service only for very Out of service for Increasingly difficult to Extensive downtime short periods moderate period; return to service; parts duration; difficult to return moderately difficult to becoming a challenge to service; parts, difficult to return to service acquire, rare skills required Increasing minor Scheduled maintenance Work orders well above Easily maintained; OEM Largely preventive maintenance with some maintenance required; becoming frequent; more average for type of asset; maintenance is corrective maintenance periodic corrective experienced trades people recurrent minor repair; straightforward beginning to show up; maintenance including required for maintenance; close monitoring required; baseline monitoring some repair shortening of frequency of work orders most senior people monitoring intervals increasing substantially required to sustain with short monitoring performance intervals Almost new; up to 10% Up to 30% physical life Up to 50% physical life Up to 70% physical life Up to 90% physical life physical life consumed consumed consumed consumed consumed 1 3 5 7 9
Prob of Failure
0.1
0.3
0.5
0.7
0.9
0.99
22
Maintainability
Continuous recurrent breakdown Out of service only for very Out of service for Increasingly difficult to Extensive downtime short periods moderate period; return to service; parts duration; difficult to return moderately difficult to becoming a challenge to service; parts, difficult to return to service acquire, rare skills required Increasing minor Scheduled maintenance Work orders well above Easily maintained; OEM Largely preventive maintenance with some maintenance required; becoming frequent; more average for type of asset; maintenance is corrective maintenance periodic corrective experienced trades people recurrent minor repair; straightforward beginning to show up; maintenance including required for maintenance; close monitoring required; baseline monitoring some repair shortening of frequency of work orders most senior people monitoring intervals increasing substantially required to sustain with short monitoring performance intervals Almost new; up to 10% Up to 30% physical life Up to 50% physical life Up to 70% physical life Up to 90% physical life physical life consumed consumed consumed consumed consumed 1 3 5 7 9
Prob of Failure
0.1
0.3
0.5
0.7
0.9
0.99
23
Odor
No complaints
A few compliants adjacent to Moderate complaints station adjacent to station Minor violation - reporting only 3 Regulatory sanction possible 5
No consequence 1
Extensive regulatory Regulatory sanction sanction virtually assured; likely; Damage reversible damage reversible in one to less than one year five years 7 9
24
Community Costs
25
26
Assets required to ensure that revenue producing assets are powered or controlled
Assets required for order fulfillment functions such as sales orders, production planning, shipping, and accounting Assets required for other core production or service functions such as material handling or warehousing
Non-revenue producing assets required for protecting revenueproducing assets from inoperable conditions
Non-revenue producing assets required for conducting supporting business functions Non-revenue producing assets that impact quality of life
27
Probability
Low Low
Consequence
High
28
No
Poor
Probability
Fair
Good
Good
High
Low Low
Consequence
29
B
Aggressive monitoring
Immediate work
Risk
Aggressive monitoring
A Sample
monitoring
Aggressive monitoring
Low Low
Consequence
High
30
31
PoF
CoF
BRE
32
Probability of Failure
1
1
Low
2
2
3
3
High
Low
Consequence of Failure
33
Risk mitigation significantly reduces the risk metric BRE = PoF x CoF x R Where
To Aeration Tanks
PoF is probability of failure CoF is consequence of failure R is a risk mitigation factor (1.0)
1
Centrifugal Blower Butterfly Valve Venturi Meter Silencer
25,000 CFM Blower System
2
40,000 CFM Blower System
3
40,000 CFM Blower System
4
40,000 CFM Blower System
5
25,000 CFM Blower System
Air Intake
Louver Damper
34
Does any other system/asset/approach fully fulfill the function if the asset fails? No Does any other system/asset/approach partially fulfill the function if the asset fails? Yes Full Mitigation Yes Partial Mitigation No No Mitigation
35
Set weights considering operating circumstances, where possible True redundancy (peak vs. average) Age and condition of equipment Nature of operating environment Nature of failure modes (evident, hidden, random)
36
5% of Assets
Advanced
BRE 3
20% of Assets
Intermediate
BRE 2
100% of Assets
Basic
BRE 1
1-10 matrix of CoF & PoF, 1-100 Score 1-1,000 CoF, 0-100% PoF, 0-1000 Score
Decreasing
Decreasing
Time
BRE is business risk exposure, CoF is consequence of failure, PoF is probability of failure, MTBF is mean time between failures
37
Level 1simple
BRE rating = probability x consequence
Asset No. 1 2 3 4 5 6 % Probability .60 .70 .40 .66 .95 .10 Consequence 4 2 5 10 7 10 Risk Mitigation Factor 0.50 1.00 1.00 1.00 1.00 0.90 Risk Rating 1.2 1.4 2.0 6.6* 6.7* 0.9
38
Level 2intermediate
Multiple elements, enhanced FMECA analysis techniques
Element Safety Environment Functionality Cost Rating 1-5 1-5 1-5 1-5 Weighting 10 6 5 8 Max. Score 50 30 25 40
145
39
40
As you think of Business Risk Exposure, consider following questions for each asset or asset group:
What is a tolerable Consequence of Failure that can happen repeatedly and why? What is a Consequence of Failure that cannot happen even once and why? What do you want to avoid the most and why? What risk score could be acceptable at times and why?
Categories
Tolerable with reactive/PM focused management strategy (run to failure) Tolerable with proactive/PdM/monitoring management strategy Not tolerable cannot fail
41
3
2 1 0 0 1 2 3 4 5 6 7 Consequence of Failure (CoF) 8 9 10
42
Risk Mapping
Operational Failure
least likely
most likely
Structural Failure
43
Build AMP
44
Build AMP
45
Consequence of Failure
Adjust for Design standard Construction quality Material quality Operational history Maintenance history Operating environ. External stresses Consider Failure mode Condition Operating Performance Reliability Availability Maintainability
Consider Safety, health, and welfare Environmental impact Process criticality Repair costs Revenue and aggravation impact on customers and agency
Heres the point of the analysis to identify and deploy risk mitigation strategies!
46
Reduce Probability
Reduce Consequence
Add Redundancy
Refocus O&M
Insure
Refurbish/Replace
47
Truck hits pole and causes power failure Junes incident report
48
Function
Functional Failure End state or potential end state; Evidence what you see
Failure Cause Contributing & root causes; reasons why failure occurred
49
Effect-Cause
Internal contact Worn bearing
Root Cause
No lubrication
Effect
50
20:25
20:30
20:40
51
05:15
05:30
52
Effect-Cause
Breaker overload Motor overload Bearing dry
Root Cause
Grease cap failed
Effect
Impeller jammed
Defective
Defective
53
Yes
Yes
Capacity
No
Has LOS changed from design?
Yes
Yes
LOS
X
~
54
No
Is physical reliability an issue?
Yes
Yes
Mortality
No
Redoit has to fail somehow
No
Yes
Yes
Efficiency
Inlet Screen
Wet Well
Dry Well
Sump Pump
55
Store key spares on site Modify piping to accommodate bypass pumping Provide proper electrical interface for generator Upgrade alarm system to real time SCADA Bury power line Build berm containment Increase redundancy (full) Other
56
57
7.
8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20.
Terrorist attack on OCSD asset (e.g. treatment plant) Regional power outage (up to 24 hours) Safety incident on OCSD project Internal security breach of IT systems Increase in regulatory requirements Finding places to put our biosolids Potential loss of property tax revenue Internal labor unrest at OCSD Consultants ability to meet stakeholders expectations Level of service change for environmental stewardship (constituents of concern) Loss of public confidence in OCSD ability to perform core services Exceedance of pollutants of concerns in groundwater related to GWRS Internal business fraud (e.g. malfeasance) Non compliance by OCSD that result in fines by regulators and legal activities by NGO's Lack of incentives for early retirement of ageing staff that perform physical activities Poor two way communications across OCSD levels Lack of a leadership model in EMT and management level Changing technology vs. CIP decisions Board not supporting the funding required to support CIP/O&M (Full Cost Pricing) Ability to accurately forecast growth of county
21.
22. 23. 24. 25.
26.
Loss of Board institutional knowledge Not sustaining effective plant operations during construction Disasters that destroy collection system or plant Inability to appropriately fund staff at required technical strength Inability to balance strategic initiatives that support GWRS (Groundwater Replenishment System) with plant operations Emergency (operations level) communication among response teams and management for emergencies Lack of alignment of organizational structure with requirements for strategic initiatives Unable to put into effect funding agreement for SARI (Santa Ana River Interceptor) Unable to negotiate new operating agreement with SAWPA (Santa Ana Watershed Project Authority) Public ceases support for GWRS after investment is in place Inability to meet new air emission standards for generating facility Inability to balance impacts on neighbors with desire by public to reduce cost Cost to meet odor and air emissions standards from facilities Privatization of OCSD Recruiting and retention of staff in face of local cost of living Lack of succession planning at OCSD
58
High Risks:
2 Regional power outage (up to 24 hours) 5 Increase in regulatory requirements 6 Finding places to put our biosolids 8 Internal labor unrest 9 Consultants ability to meet stakeholders expectations 19 Board not supporting the f unding required to support CIP/O&M (Full Cost Pricing) 21 Loss of Board instit utional knowledge 23 Disasters that destroy collection system or plant 28 Unable to put into effectiv e f unding agreement with key customer 30 Public ceases support f or potable water af ter inv estment is in place
Consequence
Major
1
30
6 2
28
Medium Risks:
1 Terrorist attack on assetS (e.g. treatment plant) 3 Saf ety incident on major projects 7 Potential loss of property tax rev enue 10 Lev el of serv ice change f or env ironmental stewardship (constituents of concern) 12 Exceedance of pollutants of concerns in groundwater 13 Internal business f raud (e.g. malf easance) 14 Non compliance that result in f ines by regulators and legal activ ities by NGO's 16 Poor two way communications across department lev els 17 Lack of a leadership model in EMT and management lev el 18 Changing technology vs. CIP decis ions 20 Ability to accurately f orecast growth of county 22 Not sustaining eff ectiv e plant operations during construction 24 Inability to appropriately f und staff at required technical strength 25 Inability to balance strategic initiativ es that support groundwater replenishment with plant operations 26 Emergency (operations lev el) communication among response teams and management f or emergencies 27 Lack of alignment of organizational structure with requirements f or strategic initiativ es 29 Unable to negotiate new operating agreement with key customers 31 Inability to meet new air emission standards 32 Inability to balance impacts on neighbors with desire by public to reduce cost 33 Cost to meet odor and air emissions standards f rom f acilities 34 Priv atization of organisation 35 Recruiting and retention of staff in f ace of local cost of liv ing 36 Lack of succession planning
19 5 8 21
Moderate
13 34
20
26
31 29
36 18
12 11 4
33 2422 17 25 14 35 32 10 16 9
27
Minor
15
Insignificant
Rare
Unlikely
Possible
Probable
Certain
Low Risks: Schematic represents allocation of risk rather than absolute values
Likelihood
4 Internal security breach of IT systems 11 Loss of public conf idence in organisation to perf orm core serv ices 15 Lack of incentiv es f or early retirement of ageing staff that perf orm phy sic al activ ities
59
60
Toms spreadsheet
62