Shaft 1 = 1.0 Shaft 2 = 1.2 (Lower Bound) Shaft 3 = 1.7 (Upper Bound)
Choose "Steel"
Refer STEP 2
From Spreadsheet 2 Pile Make Up, take TOTAL Vertical Length; not True Length From Spreadsheet 4 Skin Damping From SI Report From Spreadsheet XSRD (TOTAL). To key-in the Shaft Resistance value, change "Driveability" to any "Bearing Graph". After key-in then, change back to "Driveability".
Refer STEP 4
STEP 2
GRL Weap will key-in automatically. Follow below instructions: 1. Ensure Cursor at Helmet Weight box. 2. Press F3. 3. Click YES. 4. When "Drive System Help" appear (as shown), click "Check All". 5. Press "OK".
STEP 3
"Click "D""
24 Hr Welding at Seam Connection Manually key-in. Tak kisah nak guna berapa pun intevals (eg 5,10,15). But ade 2 things yg penting: a) Elevation at pile connection/weldment kena correct. Refer Spreadsheet 2 Pile Make Up (Pile Stoppage Below Mudline) b) Depth paling bawah kena BAWAH lagi dari Bottomest Pile Stopage Below Mudline in Spreadsheet 2 Pile Make Up. In this case, 160m is greater than 136m (Spreadsheet 2 Pile Make Up -> Pile Stoppage Below Mudline) Vertical Length from Spreadsheet 2 Pile Make-up
STEP 4
GRL Weap will key-in automatically. Follow below instructions: 1. Ensure Cursor at Section Area box. 2. Press F3. 3. When "Area Calculator" appear (as shown), fill in the blanks. blanks 5. Press "OK".
STEP 5
1. From GRL WEAP main page, click "S1". 2. Click "Edit" 3. Click "Paste Special". 1. Copy from Spreadsheet 6 Preb - Pile. 2. Ensure copy form "to weap" folder. 3. Highlight and copy all Depth (m), Unit Shaft Resist and Toe Resist. 4. Click "Soil Distribution". 5. When "Text Separation" appear, click " Convert to Column". 6. Click "Yes". 7. Click "OK".
Copy from Spreadsheet PrebPile (Predicted Blowcount) and Paste them in GRL WEAP
STEP 6
STEP 7
Set-Up factor. We can request for: a) 1.0
(aka "End" in RNZ Drivability report)
1. After click "O", output will appear insyaAllah. Open .gwd file. 2. For reporting, we require 2 types of infos: a) Blow count at SetUp factor 1.0 (End), 1.2 and 1.7. b) Max Stress (usually Comp Stress) at Set-Up Factor 1.7 only. 3. So, to change setup factor: i) Click "View". ii) Click "Ranges, Selections". iii) When "Graph Properties" (as shown) appear, click desired set-up factor. 4. The Max Stress shall be re-key-in in Spreadsheet 1 Pile Combined Stress at "Driving Stress at GRL WEAP".
b) 1.2 c) 1.7
STEP 8
1. From GRL WEAP Output, generate Blow Count curve for every Hammer with regards to every Setup factor. 2. Manual key-in depth (m) and Blow Count from GRL WEAP output to Spreadsheet 6 PREB-PILE for every set-up factor.