KOILSAGAR LIFT IRRIGATION SCHEME STAGE-I

STATUS OF WORK AS ON 13.11.2007


S.No 1 Name of Component APPROACH CANAL Work Under Further work stopped Progress from due to Land Acquisition Km.2.000 to Problem from Km.0.000 Km.2.500, Km.3.500 to Km.1.500 & Km.5.250 to Km.5.250 to Km.6.150. Unit Length/Nos Status of work Remarks

Km 0.00 to 6.150Km

Km

6.150

TUNNEL KM 6.150 to 13.007 Adit Tunnel 1 @ Km 8.500 Open E/W Tunnel Adit Tunnel 2 @ Km 10.700 Open E/W Tunnel Adit Tunnel-3 @ Km 12.991 Open E/W Tunnel Rmt Rmt Rmt Rmt 200.000 310.000 175.000 435.000 200 mtrs completed, further work under progress Not started Completed 10 Mts. 30 mts. depth completed, balance work under progress 19 mts. depth of excavation completed Not started Not started Balance work will be started after completion of surge pool Designs are not approved Designs are not approved Tunnel face opened Balance work under progress Tunnel face opened Km 6.857 Not started Face Not Opened. Due to Earth work is not completed.

Rmt Rmt

225.000 245.000

Completed 145 mts completed Further work under progress

SURGE POOL@13.007 Size 20x28x67 Depth 67.000

PUMP HOUSE @ 13.077 Size 15x34x71 Depth RMT No 71.000 225.000 1.000

5 6 7

PRESSURE MAIN DELIVERY CISTERN @ 13.287 GRAVITY CANAL

From Km 0.00 to 15.180

Km

15.180

Earth work excavation completed. Km.2.750 to Km.4.500, Km.5.000 to Km.5.250, Km.6.250 to Km.6.750, Km.7.500 to Km.8.250, Balance Land Acquisition work under progress Problem From Km.0.000 from Km.4.500 to to Km.10.500 Km.5.000, Km.5.250 to Km.6.750, Km.7.000 to Km.7.500, Km.10.750 to Km.11.500 & Km.12.000 to Km.12.500.

Page 1 of 10 Koilsagar LIS Stage-I

CM & CD WORKS

No of Structures

Name of the Structure Regulator @ Km. 1.200 SP @ Km. 2.323 SLRB @ Km 2.594 SP @ Km. 3.130

Approved / Not Approved

Remarks Designs are not Submitted Designs are Submitted Not started due Canal E/W not started Designs are Submitted Designs are not Submitted Designs are not Submitted Designs are Submitted Designs are not Submitted Earth work stopped due to land dispute Designs are not Submitted Sub-Structure Under Progress Designs are not Submitted Designs are not Submitted Earth work Under Progress Designs are Submitted Foundation Under Progress Designs are Submitted Earth work completed. SBC not finalized by the 3rd Party Designs are Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted Not started due to Earth work not completed Not started due to Earth work not completed Designs are not Submitted Designs are not Submitted Foundation Under Progress Designs are not Submitted

APPROVED

ON APPROACH CANAL

8 Nos

DLRB @ Km 4.134 SP @ Km. 4.971 SP @ Km. 5.495 DLRB @ Km 5.612 UT @ 1.438 DLRB @ Km 2.585 UT @ 4.109 SYPHON @ Km. 4.558 SP @ Km. 5.238 SLRB @ 5.816 UT @ 6.466 SLRB @ 6.552 UT @ 7.395 SLRB @ 7.604 UT @ 8.358 APPROVED APPROVED APPROVED APPROVED APPROVED

ON GRAVITY CANAL

21 Nos

DLRB @ Km 9.137 ACQUIDUCT @ Km 10.155 SYPHON @ Km. 10.984 DLRB @ 11.736 SLRB @ 11.925 APPROVED

SLRB @ 12.148 SP @ Km. 12.496 SYPHON @ Km. 13.062 SLRB @ 14.704 INFALL REGULATOR @ Km. 15.000

APPROVED

APPROVED

Page 2 of 10 Koilsagar LIS Stage-I

KOILSAGAR LIFT IRRIGATION SCHEME STAGE-I


STATUS OF WORK AS ON 27-09.2007
S.No 1 Name of Component APPROACH CANAL Earth work excavation completed in 1st berm from 4.5 to 5.00 and 5.750 to 6.150 Unit Length/Nos Status of work

Km 0.00 to 6.150Km

Km

6.150

TUNNEL KM 6.150 to 13.007 Adit Tunnel 1 @ Km 8.500 Open E/W Tunnel Adit Tunnel 2 @ Km 10.700 Open E/W Tunnel Adit Tunnel-3 @ Km 12.991 Open E/W Tunnel Rmt Rmt 175.000 533.000 Completed Not started 25 mtrs depth completed, balance work under progress Rmt Rmt 200.000 310.000 200 mtrs completed, further work under progress Not started Rmt Rmt 225.000 245.000 Completed 135 mts completed Km 6.857 Not started

SURGE POOL@13.007 Size 20x28x67 Depth 67.000

PUMP HOUSE @ 13.077 Size 15x34x71 Depth 71.000 16 depth of excavation completed Not started Not started

5 6 7

PRESSURE MAIN DELIVERY CISTERN @ 13.287 GRAVITY CANAL

RMT No

225.000 1.000

From Km 0.00 to 15.180

Km

15.180

Earth work excavation completed from km 13.000 to 15.180, balance work under progress from Km 12.500 to 13.000 , 0.000 to 0.500 and 5.000 to 5.250km

Page 3 of 10 Koilsagar LIS Stage-I

CM & CD WORKS

No of Structures

Name of the Structure Regulator @ Km. 1.200 SP @ Km. 2.323 SLRB @ Km 2.594 SP @ Km. 3.130 DLRB @ Km 4.134 SP @ Km. 4.971 SP @ Km. 5.495 DLRB @ Km 5.612 UT @ 1.438 DLRB @ Km 2.585 UT @ 4.109 SYPHON @ Km. 4.558 SP @ Km. 5.238 SLRB @ 5.816 UT @ 6.466 SLRB @ 6.552 UT @ 7.395 SLRB @ 7.604

Approved / Not Approved

APPROVED

ON APPROACH CANAL

8 Nos

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

ON GRAVITY CANAL

21 Nos

UT @ 8.358 DLRB @ Km 9.137 ACQUIDUCT @ Km 10.155 SYPHON @ Km. 10.984 DLRB @ 11.736 SLRB @ 11.925 SLRB @ 12.148 SP @ Km. 12.496 SYPHON @ Km. 13.062 SLRB @ 14.704 INFALL REGULATOR @ Km. 15.000 APPROVED APPROVED APPROVED

Page 4 of 10 Koilsagar LIS Stage-I

ME STAGE-I
Remarks Further work stopped due to LA problem From km 3.250 to 4.500Km Govt land is available. But sub contractors to be identified

2007

Further work under progress

Tunnel face opened

Tunnel face opened

Balance work will be started after completion of surge pool Designs are not approved Designs are not approved

Further reaches LA is pending

Page 5 of 10 Koilsagar LIS Stage-I

Remarks Designs are not Submitted Designs are Submitted Not started due Canal E/W not started Designs are Submitted Designs are not Submitted Designs are not Submitted Designs are Submitted Designs are not Submitted Earth work stopped due to land dispute Designs are not Submitted Foundation Completed. R.C.C work under progress Designs are not Submitted Designs are not Submitted Designs are Submitted Designs are Submitted Earth work started Designs are Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted

Designs are not Submitted Designs are not Submitted Canal Earth work under Progress Designs are not Submitted

Page 6 of 10 Koilsagar LIS Stage-I

KOILSAGAR LIFT IRRIGATION SCHEME STAGE-I


STATUS OF WORK AS ON 10-09.2007
S.No 1 Name of Component APPROACH CANAL Earth work excavation completed in 1st berm from 4.5 to 5.00 and 5.750 to 6.150 Unit Length/Nos Status of work

Km 0.00 to 6.150Km

Km

6.150

TUNNEL KM 6.150 to 13.007 Adit Tunnel 1 @ Km 8.500 Open E/W Tunnel Adit Tunnel 2 @ Km 10.700 Open E/W Tunnel Adit Tunnel-3 @ Km 12.991 Open E/W Tunnel Rmt Rmt 175.000 533.000 Completed Not started 28 mtrs depth completed, balance work under progress Rmt Rmt 200.000 310.000 190 mtrs completed, further work under progress Not started Rmt Rmt 225.000 245.000 Completed 75 mtr completed Km 6.857 Not started

SURGE POOL@13.007 Size 20x28x67 Depth 67.000

PUMP HOUSE @ 13.077 Size 15x34x71 Depth 71.000 16 depth of excavation completed Not started Not started

5 6 7

PRESSURE MAIN DELIVERY CISTERN @ 13.287 GRAVITY CANAL

RMT No

225.000 1.000

From Km 0.00 to 15.180

Km

15.180

Earth work excavation completed from km 13.500 to 15.180, balance work under progress from Km 13.00 to 13.500 , 0.00 to 0.500 and 5.000 to 5.250km

Page 7 of 10 Koilsagar LIS Stage-I

CM & CD WORKS

No of Structures

Name of the Structure Regulator @ Km. 1.200 SP @ Km. 2.323 SLRB @ Km 2.594 SP @ Km. 3.130 DLRB @ Km 4.134 SP @ Km. 4.971 SP @ Km. 5.495 DLRB @ Km 5.612 UT @ 1.438 DLRB @ Km 2.585 UT @ 4.109 SYPHON @ Km. 4.558 SP @ Km. 5.238 SLRB @ 5.816 UT @ 6.466 SLRB @ 6.552 UT @ 7.395 SLRB @ 7.604

Approved

SLRB @ 2.594

ON APPROACH CANAL

8 Nos

UT @ 1.438

UT @ 4.109

SLRB @ 5.816

SLRB @ 6.552

SLRB @ 7.604

ON GRAVITY CANAL

21 Nos

UT @ 8.358 DLRB @ Km 9.137 ACQUIDUCT @ Km 10.155 SYPHON @ Km. 10.984 DLRB @ 11.736 SLRB @ 11.925 SLRB @ 12.148 SP @ Km. 12.496 SYPHON @ Km. 13.062 SLRB @ 14.704 INFALL REGULATOR @ Km. 15.000 Page 8 of 10 SLRB @ 14.704 SLRB @ 11.925 SLRB @ 12.148

Koilsagar LIS Stage-I

ME STAGE-I
Remarks Further work stopped due to LA problem From km 3.250 to 4.500Km Govt land is available. But sub contractors to be identified

2007

Further work under progress

Tunnel face opened

Balance work will be started after completion of surge pool Designs are not approved Designs are not approved

Further reaches LA is pending

Page 9 of 10 Koilsagar LIS Stage-I

Remarks Designs are not Submitted Designs are Submitted Not started due Canal E/W not started Designs are Submitted Designs are not Submitted Designs are not Submitted Designs are Submitted Designs are not Submitted Earth work Started, stopped by land owners Designs are not Submitted L A problem Designs are not Submitted Designs are not Submitted L A problem Designs are not Submitted Not started due Canal E/W not started Designs are not Submitted Not started due Canal E/W not started Designs are not Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted Designs are not Submitted Not started due Canal E/W not started L A problem Designs are not Submitted Designs are not Submitted Canal Earth work under Progress Designs are not Submitted Page 10 of 10 Koilsagar LIS Stage-I