Beruflich Dokumente
Kultur Dokumente
ITEM
DESCRIPTION
SUBSTRUCTURE (ALL PROVISIONAL) TOPSOIL Excavate oversite to remove vegetable top soil average 150mm thick and remove from site. EXCAVATION
QTY UNIT
RATE
AMOUNT
1250
100.00
B C
Excavate trenches for ground beam starting from reduced level and not exceeding 1.00m depth. Ditto column pit DISPOSAL Remove surplus excavated materials from site BACKFILLING
550 260
m3 m
3
280.00 280.00
240
m3
250.00
581
m3
250.00
Level and Compact bottom of excavated trench to EARTHWORK SUPPORT Earthwork support to both sides of excavated LATERITE FILLING Imported and approved laterite filling in making up levels under floors well compacted and consolidated( 300mm thick) HARDCORE FILLING 150mm thick bed of hardcore filling, deposited, spread, levelled and consilidated to receive CONCRETEWORK Plain in-situ concrete (1:10) in:-
741
m2
100.00
960
m2
60.00
437
m3
950.00
820
m2
1,050.00 =N=
WIS-FAM ASS.
GS/1
MUGPINL
ITEM
DESCRIPTION
CONCRETEWORK Plain in-situ concrete (1:3:6-38mm aggregate) in:-
QTY UNIT
RATE
AMOUNT
A B
Foundation column bases Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately) Stater Columns 150mm thick floor slab Steps Reinforcement (All provisional) High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
97 11
m3
23,500.00 23,500.00
2,279,500.00 258,500.00 -
C D E
14 147 3
m3 m3 m3
F G
10-20mm diameter in starter columns BRC mesh Formwork to:To the vertical sides of starter columns Edge of bed not exceeding 250mm wide Sides of column bases Risers of steps; 175mm high 225mm sandcrete hollow blockwall filled solid with weak concrete
2780 1950
Kg m
2
270.00 600.00
H J K L
88 302 8
m m m
2
520
m2
Carried to Collection COLLECTION PAGE NO. 1 PAGE NO. 2 SUBSTRUCTURE Carried to Summary 2,184,900.00 10,351,600.00 10,351,600.00
12,536,500.00
WIS-FAM ASS.
GS/2
MUGPINL
ITEM
DESCRIPTION
FRAMES CONCRETEWORK Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
QTY UNIT
RATE
AMOUNT
A B C D
Columns Beams Slab Stair case REINFORCEMENT High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
9 27 66 4
m3 m m m
3 3 3
E F G H
10-16mm diameter in columns Ditto beams Ditto in slab Ditto in stair case
Kg Kg Kg Kg
SAWN FORMWORK TO: J K L M Vertical sides of columns Sides and soffit of beams Slab soffit Stair case BLOCKWORK Hollow sandcrete blockwork bedded and jointed in cement and sand (1:6) 225mm wall Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately) 40 210 2535 1010 m2 m2 2 m 2 m 900.00 900.00 900.00 900.00
605
2,150.00
m3
25,500.00
102,000.00 8,908,610.00
WIS-FAM ASS.
GS/3
MUGPINL
ITEM
DESCRIPTION
UPPER FLOOR CONCRETEWORK Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
QTY UNIT
RATE
AMOUNT
A B
Columns Roof Beams REINFORCEMENT High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
4 29
m m3
25,500.00 25,500.00
102,000.00 739,500.00
E F
68 1750
Kg Kg
290.00 290.00
19,720.00 507,500.00
SAWN FORMWORK TO: J K L M Vertical sides of columns Sides and soffit of beams 40 210 m2 m2 900.00 900.00
36,000.00 189,000.00
BLOCKWORK Hollow sandcrete blockwork bedded and jointed in cement and sand (1:6) 225mm wall Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
1,300,750.00
605
2,150.00
m3
25,500.00
229,500.00 3,123,970.00
WIS-FAM ASS.
GS/4
MUGPINL
ITEM
DESCRIPTION
ROOF AND ROOF COVERINGS
QTY UNIT
RATE
AMOUNT
0.55mm guage long span colour coated aluminum roofing sheet laid on steel trusses A in covering 760 m2 2,500.00 1,900,000.00 2,850,000.00 -
B C D E F G H
Steel Trusses Allow for prime cost sum of N2,850,000.00 for construction and fabrication of steel trusses
m m m m m m
2,850,000.00
4,750,000.00
WIS-FAM ASS.
GS/5
MUGPINL
ITEM
DESCRIPTION
WINDOWS Aluminium Windows Factory pre-glazed bronze anodised aluminium windows complete with mosquitoe netting; tinted coloured glass complete with all ironmongery
QTY UNIT
RATE
AMOUNT
A B C D E F
Window size 2400x 1200mm high Window size 1800 x 1200mm high window size 1500 x 1200mm high Window size 1000 x 1200mm high window size 890 x 600mm high window size 4100 x 2100 high (casement window)
15 15 6 10
Nr Nr Nr Nr
=N=
806,700.00
WIS-FAM ASS.
GS/6
MUGPINL
ITEM
DESCRIPTION
DOORS AND IRONMONGERY JOINERY Timber Doors imported doors to Architects specification Size 1200mm x 2100mm high Ditto size 900mm x 2100mm high Ditto size 1970 x 2100mm high Ditto size 750 x 2100mm high Ditto size 1000x 2100mm high Ironmongeries Supply and fix the following "UNION" or equal and approved ironmongeries to positions
QTY UNIT
RATE
AMOUNT
A B C D E
10 8
Nr Nr
100,000.00 75,000.00
1,000,000.00 600,000.00 -
4,500.00 67,500.00 -
E F
Pair 100mm brass butt hinges Mortice lock and set of lever handle furniture
15 Pairs 15 Nr
300.00 4,500.00
WIS-FAM ASS.
GS/7
MUGPINL
ITEM
DESCRIPTION
SERVICES PLUMBING INSTALLATIONS Allow a Provisional Sum of =N=2,500,000.00 (Two Million Five Hundred Thousand Naira Only) for mechanical installations Allow provisional sum for builder"s work
QTY UNIT
RATE
AMOUNT
A B
sum sum
1,800,000.00 65,000.00
ELECTRICAL INSTALLATIONS Allow a Provisional Sum of =N=2,500,000.00 (Three Million Five Hundred Thousand Naira Only) for Electrical Installation Works to be executed by a nominated subcontractor
Sum
2,000,000.00
=N=
3,865,000.00
WIS-FAM ASS.
GS/8
MUGPINL
ITEM
DESCRIPTION
FLOOR, WALL AND CEILING FINISHINGS Internal Works Floor Finishing Tiles, slab and block finishings
QTY UNIT
RATE
AMOUNT
Supply and Vitrifies floor Tiles,slab and other associated works. A B On Floor 450x450x10mm thick vitrified tiles 961 m2 3,150.00 0 3,027,150.00 2,015,000.00 768,450.00 578,550.00 1,450,260.00 229,140.00 1,698,750.00 2,316,600.00
D E
300x300mm unglazed ceramic tiles (Provisional) 100mm high polished wood skirting Beds and Backings 42mm thick cement and sand (1:3) screeded bed to receive ceramic floor finish
775 1635
m2 m m2
2,600.00 470.00
1015
570.00
Wall Finishings In-situ Finishings 15mm thick cement and sand (1:4) smooth rendering on:Blockwall internally & Externally Ditto Externally Isolated columns Reveals not exceeding 300mm Tiles Works 200x200x6mm thick ceramic wall tiles (Provisional) 300x150x10mm thick ditto Ceiling Finishings UPVC ceiling strips Ceiling soffit FLOOR, WALL AND CEILING FINISHINGS Carried to Summary =N= 1404 m
2
G H J
3453
420.00
1206
m2 m2 m
190.00
K L
755
2,250.00
m2
1,650.00
12,083,900.00
WIS-FAM ASS.
GS/9
MUGPINL
ITEM
DESCRIPTION
PAINTING AND DECORATIONS Internal and External Works Prepare and apply two undercoats and one finishing coat of emulsion paint on:-
QTY UNIT
RATE
AMOUNT
A B C E
m m
m2 m2
WIS-FAM ASS.
GS/10
MUGPINL
ITEM
DESCRIPTION
QTY UNIT
RATE
AMOUNT
GENERAL SUMMARY PRELIMINARIES SUBSTRUCTURE FRAMES ROOF AND ROOF COVERINGS WINDOWS DOORS AND IRONMONGERY SERVICES FLOOR, WALL AND CEILING FINISHINGS PAINTING AND DECORATIONS SUB TOTAL ADD CONTIGENCIES
1,000,000.00 12,536,500.00 12,032,580.00 4,750,000.00 806,700.00 2,478,700.00 3,865,000.00 12,083,900.00 2,806,060.00 52,359,440.00
674,000.00
53,033,440.00
ADD 5% VAT
2,651,672.00
=N=
55,685,112.00
WIS-FAM ASS.
GS/11
S/N 1
ELEMENT PRELIMINARIES
BILL OF QUANTITIES FOR PROPOSED MULTIPURPOSE CONFRENCE HALL. ELEMENTALLY BREAKDOWN OF FUND DESCRIPTION THIS INCLUDES SETTING OUT, MOBILISATION TO SITE, SITE OFFICES, TEMPORARY ELECTRICITY, WATER FOR WORKS,OTHER PRELIMINARIES WORKS THIS INCLUDES SITE CLEARANCE, TOPSOIL CLEARANCE, TRENCH EXCAVATION,CONCRETE WORKS IN SUBSTRUCTURE AND FRAME WORKS THIS INCLUDES BLOCKS AND BRICKS WORKS GENERALLY THIS INCLUDES ROOF MEMBERS/CARCAS AND ROOF COVERING THIS INCLUDES DOORS, ALUMINUM SLIDING WINDOW, CASEMENT WINDOWS AND HIGH LEVEL WINDOWS THIS INCLUDES WATER RETICULATIONS, SANITARY FITTINGS, WASTE AND FOUL WATER DISPOSAL, CONSTRUCTION OF SOAK AWAY AND SEPTIC TANKS. THIS INCLUDES CONECTION TO MAINS, DISTRIBUTION BOARDS, LIGHT AND POWER FITTINGS AND EARTHING THIS INCLUDES TILES/ TERRAZZO WORKS, AQOUSTIC CEILING FINISHES AND WALL RENDERING. THIS INCLUDES WALL PAINTING, CEILING PAINTING AND DECORATION. THIS IS FOR ANY UNFORSEEN WORK THAT MIGHT ARISE DURING THE COURSE OF THE PROJECT
AMOUNT
1,000,000.00
3 4 5 6
BLOCKS AND BRICK WORKS ROOF AND ROOF COVERING DOORS AND WINDOW PLUMBING INSTALLATIONS
7 8 9
ELECTRICAL INSTALLATIONS FLOOR, WALL AND CEILING FINISHES PAINTING AND DECORATIONS CONTIGENCIES SUB TOTAL VAT 5% TOTAL
MUGPINL
BILL OF QUANTITIES FOR PROPOSED ADMINISTRATIVE BUILDING.
ITEM
DESCRIPTION
SUBSTRUCTURE (ALL PROVISIONAL) TOPSOIL Excavate oversite to remove vegetable top soil average 150mm thick and remove from site. EXCAVATION
QTY UNIT
RATE
AMOUNT
341
m2
100.00
B C
Excavate trenches for ground beam starting from reduced level and not exceeding 1.00m depth. Ditto column pit DISPOSAL Remove surplus excavated materials from site BACKFILLING
85 3
m3 m3
280.00 280.00
50
m3
250.00
35
m3
250.00
Level and Compact bottom of excavated trench to EARTHWORK SUPPORT Earthwork support to both sides of excavated LATERITE FILLING Imported and approved laterite filling in making up levels under floors well compacted and consolidated( 300mm thick) HARDCORE FILLING 150mm thick bed of hardcore filling, deposited, spread, levelled and consilidated to receive CONCRETEWORK Plain in-situ concrete (1:10) in:-
95
m2
100.00
247
m2
60.00
80
m3
950.00
91
m2
1,050.00 =N=
WIS-FAM ASS.
GS/1
MUGPINL
ITEM
DESCRIPTION
CONCRETEWORK Plain in-situ concrete (1:3:6-38mm aggregate) in:-
QTY UNIT
RATE
AMOUNT
A B
Foundation column bases Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately) Stater Columns 150mm thick floor slab Steps Reinforcement (All provisional) High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
22 3
m3
23,500.00 23,500.00
517,000.00 70,500.00 -
C D E
5 51 1
m3 m3 m3
F G
10-16mm diameter in starter columns BRC mesh Formwork to:To the vertical sides of starter columns Edge of bed not exceeding 250mm wide Sides of column bases Risers of steps; 175mm high 225mm sandcrete hollow blockwall filled solid with weak concrete
421 330
Kg m2
270.00 600.00
H J K L
6 12 1
m2 m m m
2
112
m2
Carried to Collection COLLECTION PAGE NO. 1 PAGE NO. 2 SUBSTRUCTURE Carried to Summary 315,860.00 2,692,970.00 2,692,970.00
3,008,830.00
WIS-FAM ASS.
GS/2
MUGPINL
WIS-FAM ASS.
GS/3
MUGPINL
ITEM
DESCRIPTION
FRAMES CONCRETEWORK Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
QTY UNIT
RATE
AMOUNT
A B C D
Columns Beams Slab Stair case REINFORCEMENT High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
1 18 51 3
m3 m m m
3 3 3
E F G H
10-16mm diameter in columns Ditto beams Ditto in slab Ditto in stair case
Kg Kg Kg Kg
SAWN FORMWORK TO: J K L M Vertical sides of columns Sides and soffit of beams Slab soffit Stair case BLOCKWORK Hollow sandcrete blockwork bedded and jointed in cement and sand (1:6) 225mm wall Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately) 30 162 330 780 m2 m2 m2 m2 900.00 900.00 900.00 900.00
465
2,150.00
m3
25,500.00
76,500.00 5,432,530.00
WIS-FAM ASS.
GS/4
MUGPINL
ITEM
DESCRIPTION
UPPER FLOOR CONCRETEWORK Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
QTY UNIT
RATE
AMOUNT
A B
Columns Roof Beams REINFORCEMENT High tensile steel bar reinforcement to BS 1449 purchased in standard lengths; cut and bent on site including provision for tying wire, distance blocks and ordinary spacers
1 18
m3 m3
25,500.00 25,500.00
25,500.00 459,000.00
E F
45 1270
Kg Kg
290.00 290.00
13,050.00 368,300.00
SAWN FORMWORK TO: J K L M Vertical sides of columns Sides and soffit of beams 30 162 m2 m2 900.00 900.00
27,000.00 145,800.00
BLOCKWORK Hollow sandcrete blockwork bedded and jointed in cement and sand (1:6) 225mm wall Vibrated reinfoced in-situ concrete (1:2:4-19mm aggregate filled into formwork and well packed around reinforcement (both measured separately)
999,750.00
465
2,150.00
m3
25,500.00
76,500.00 2,114,900.00
WIS-FAM ASS.
GS/5
MUGPINL
ITEM
DESCRIPTION
ROOF AND ROOF COVERINGS
QTY UNIT
RATE
AMOUNT
0.55mm guage long span colour coated aluminum roofing sheet laid on steel trusses A in covering 450 m2 2,500.00 1,125,000.00 850,000.00 -
B C D E F G H
Roof Trusses Allow for prime cost sum of N850,000.00 for construction and fabrication of steel trusses
m m m m m m
850,000.00
1,975,000.00
WIS-FAM ASS.
GS/6
MUGPINL
ITEM
DESCRIPTION
WINDOWS Aluminium Windows Factory pre-glazed bronze anodised aluminium windows complete with mosquitoe netting; tinted coloured glass complete with all ironmongery
QTY UNIT
RATE
AMOUNT
A B C D E F
Window size 2400x 1200mm high Window size 1800 x 1200mm high window size 1500 x 1200mm high Window size 1000 x 1200mm high window size 890 x 600mm high window size 4100 x 2100 high (casement window)
7 10 1 7
Nr Nr Nr Nr
=N=
434,700.00
WIS-FAM ASS.
GS/7
MUGPINL
ITEM
DESCRIPTION
DOORS AND IRONMONGERY JOINERY Timber Doors imported doors to Architects specification Size 1200mm x 2100mm high Ditto size 900mm x 2100mm high Ditto size 1970 x 2100mm high Ditto size 750 x 2100mm high Ditto size 1000x 2100mm high Ironmongeries Supply and fix the following "UNION" or equal and approved ironmongeries to positions
QTY UNIT
RATE
AMOUNT
A B C D E
12 4
Nr Nr
100,000.00 75,000.00
1,200,000.00 300,000.00 -
4,800.00 72,000.00 -
E F
Pair 100mm brass butt hinges Mortice lock and set of lever handle furniture
16 Pairs 16 Nr
300.00 4,500.00
WIS-FAM ASS.
GS/8
MUGPINL
ITEM
DESCRIPTION
SERVICES PLUMBING INSTALLATIONS Allow a Provisional Sum of =N=1,500,000.00 (Two Million Five Hundred Thousand Naira Only) for mechanical installations Allow provisional sum for builder"s work
QTY UNIT
RATE
AMOUNT
A B
sum sum
1,500,000.00 35,000.00
ELECTRICAL INSTALLATIONS Allow a Provisional Sum of =N=1,500,000.00 (Three Million Five Hundred Thousand Naira Only) for Electrical Installation Works to be executed by a nominated subcontractor
Sum
1,500,000.00
=N=
3,035,000.00
WIS-FAM ASS.
GS/9
MUGPINL
ITEM
DESCRIPTION
FLOOR, WALL AND CEILING FINISHINGS Internal Works Floor Finishing Tiles, slab and block finishings
QTY UNIT
RATE
AMOUNT
Supply and Vitrifies floor Tiles,slab and other associated works. A B On Floor 450x450x10mm thick vitrified tiles 440 m2 3,150.00 0 1386000 84,130.00 250,800.00 390,600.00 33,250.00 450,000.00 759,000.00
D E
300x300mm unglazed ceramic tiles (Provisional) 100mm high polished wood skirting Beds and Backings 42mm thick cement and sand (1:3) screeded bed to receive ceramic floor finish 179
2,600.00 470.00
m m2
440
570.00
Wall Finishings In-situ Finishings 15mm thick cement and sand (1:4) smooth rendering on:Blockwall internally & Externally Ditto Externally Isolated columns Reveals not exceeding 300mm Tiles Works 200x200x6mm thick ceramic wall tiles (Provisional) 300x150x10mm thick ditto Ceiling Finishings UPVC ceiling strips Ceiling soffit FLOOR, WALL AND CEILING FINISHINGS Carried to Summary =N= 460 m2 1,650.00 175
G H J
930
420.00
m2 m2 m
190.00
K L
200
m2 m2
2,250.00
3,353,780.00
WIS-FAM ASS.
GS/10
MUGPINL
ITEM
DESCRIPTION
PAINTING AND DECORATIONS Internal and External Works Prepare and apply two undercoats and one finishing coat of emulsion paint on:-
QTY UNIT
RATE
AMOUNT
A B C E
Rendered blockwall internally. Ceiling soffit Isolated columns Ditto Texcote paint to rendered blockwall externally.
m2 m2 m2 m2
WIS-FAM ASS.
GS/11
MUGPINL
ITEM
DESCRIPTION
QTY UNIT
RATE
AMOUNT
GENERAL SUMMARY PRELIMINARIES SUBSTRUCTURE FRAMES ROOF AND ROOF COVERINGS WINDOWS DOORS AND IRONMONGERY SERVICES FLOOR, WALL AND CEILING FINISHINGS PAINTING AND DECORATIONS SUB TOTAL ADD CONTIGENCIES ADD 5% VAT
1,030,212.00 3,008,830.00 5,432,530.00 1,975,000.00 434,700.00 1,576,800.00 3,035,000.00 3,353,780.00 723,630.00 20,570,482.00 1,028,524.10 1,305,493.98
=N=
22,904,500.08
WIS-FAM ASS.
GS/12