Beruflich Dokumente
Kultur Dokumente
Mission
Provide resources to reduce serious injury and fatal crashes on Louisianas local roads.
Technical Assistance
a. Data Analysis
b. Problem Identification
c. Countermeasure Selection
d. Project Development and implementation
In the Beginning
a. Blank Slate in 2006
b. Limited Data
2013
a. Data, data, data
b. Established funding process
e. Expanded capacity
LALTAP
Data Presentation Overview for
Jason Taylor, PE
CONFIDENTIAL INFORMATION - This document is exempt from discovery or admission under 23 U.S.C. 409. Contact the Traffic Safety Office at (225)379-1871 before releasing any information.
Difficulties Encountered
Lack of road data
Incomplete crash data
Focus Points
Current method involves visual curve identification System wide identified curves overlaid in GIS
Safety Coalitions
Independently formed as a result of the SHSP
Data Presentations
Who?
Type of Collision Not Reported Non Coll Rear End Head on Rt Angle Left Turn-e Left Turn-f Left Turn-g Right Turn-h Right Turn-i S Swipe(sd) S Swipe(od) Z
What?
Area Crahses State Crashes 498 3434 3579 29680 23935 61373 1420 4447 15281 42111 1857 5207 1997 7584 2163 5253 1728 3707 479 2234 12635 23746 2086 7454 20677 49839 Area % 0.56% 4.05% 27.09% 1.61% 17.30% 2.10% 2.26% 2.45% 1.96% 0.54% 14.30% 2.36% 23.41% State % 1.40% 12.06% 24.94% 1.81% 17.11% 2.12% 3.08% 2.13% 1.51% 0.91% 9.65% 3.03% 20.25% Ratio to State 0.40 0.34 1.09 0.89 1.01 0.99 0.73 1.15 1.30 0.60 1.48 0.78 1.16
When?
Road Assessments
How?
Engineering
Recommendations
Questions?
Rick Holm, PE
Proposed Projects
Must be on locally owned roads
Projects involving state roads are not eligible
Roadway Departure
LRSP analyzes crash data and develops project for each program A staff Traffic Engineer meets with entity representative to explain data/project details Purchase projects DOTD disburse 100% of material costs Entity responsible for 100% installations costs Application completed after Entity agrees to participate
Entity/State Agreement
Important Facts:
Formal contract between DOTD & Entity
Specifies requirements
Engineering
Entity choice If reimbursable - DOTD will select the consultant If not reimbursable entity can select any consultant (unless on DOTD disqualified list or disbarred) Engineering can start before Entity/State Agreement is approved Use CAUTION!
Utility Relocation
Not eligible for reimbursement
100% responsibility of Entity
Disbursement
DOTD will disburse Entity monthly federal share prior to paying consultant share
Lessons Learned
Timely response by DOTD and Entity Entity not promptly paying consultant/contractor Entity not promptly requesting reimbursement Entity not contacting consultant or contractor