Sie sind auf Seite 1von 6

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

Disputes in Construction
Holloway Consulting provides construction consulting, expert witness, advisory and management services to U.S. and international clients. Home Contact Our Team Newsletters/Articles Blog hcgexperts.com

CONSTRUCTION CLAIMS | CONTRACT TERMINATION


HOME PAGE MENU CONSULTING SERVICES EXPERT WITNESS SERVICES ADVISORY SERVICES MANAGEMENT SERVICES Newsletter Articles Index Article 100 Buying Work Below Market Prices Article 101 Delay and Damages Concepts Article 102 Claims Terminology Article 103 Contractor Claim Entitlements Article 104 Delay Analysis Methods Article 105 Residential Dispute Causes Article 106 General Contractor Fiduciary Duty Article 107 Defects in Post Tensioned Decks Article 108 Subcontractor Financial Risks Part I Article 109 Subcontractor Financial Risks Part 2 Article 110 Pitfalls in Cost Plus Contracts Article 111- Labor Productivity Claims Article 112- Supreme Court Signals End to Total Cost Claims Article 113 NECA Labor Productivity Studies Article 114 Schedule Window and Update Analysis Article 115 Owner Maladministration Article 116 As-planned Impacted Schedule Labor Productivity?
1 of 6

3/28/2013 11:09 PM

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

Article 117 The Measured Mile Method Article 118 Cardinal Change Claims Article 119 Constructive Change Article 120 Directed Change Claims Article 121-GMP Contracts Definitions, Terms, & Techniques DISPUTES TERMINOLOGY AND METHODOLOGY CONSTRUCTION CLAIM ENTITLEMENTS CONSTRUCTION SCHEDULE DELAY CONCEPTS CONSTRUCTION DEFECTS V. FAILURES Holloway Consulting Groups Services State-specific Experience Newsletters Prominent Construction Cases HOOVER DAM BYPASS BRIDGE ARBITRATION RESIDENTIAL CONSTRUCTION DISPUTES RESORT AND HOTEL CONSTRUCTION CLAIMS ADVERSE AFFECTS OF HURRICANES ON GULF COAST PROJECT Industry Sector-specific Services INDUSTRY SECTOR DISPUTES INDEX AIRPORT AND RUNWAY DISPUTES CASINO AND HOTEL CONSTRUCTION DISPUTES CIVIL HIGHWAY BRIDGE DISPUTES CORRECTIONAL / DETENTION FACILITY CLAIMS EDUCATION AND SCHOOL CONSTRUCTION CLAIMS HEALTH CARE FACILITY CONSTRUCTION DISPUTES MIDDLE EAST CONSTRUCTION EXPERTS MINING PROJECTS AND DISPUTES OIL & GAS, REFINERY, AND PETRO-CHEMICAL CONSTRUCTION CLAIMS PIPELINE PROJECT DISPUTES POWER PLANT CONSTRUCTION DISPUTES RENOVATION RESTORATION PROJECT DISPUTES RESORT, CONDO AND HOTEL DISPUTES SINGLE-FAMILY | MULTI-FAMILY | ASSISTED LIVING CONSTRUCTION DISPUTES SPORTS STADIUMS AND FACILITIES PROJECTS Construction Consultant Expert Witness Advisory Management Home Posts Directory Construction Disputes Newsletter Subscription State-specific Experience CALIFORNIA EXPERIENCE

2 of 6

3/28/2013 11:09 PM

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

COLORADO EXPERIENCE LOUISIANA EXPERIENCE Search For Data Here Blogroll LinkedIn Recommendations WP Blog WP Documentation WP Planet WP Plugins WP Suggest Ideas WP Support Service Categories Types of Claims in Construction Contracts? Directory of Posts at hcgexperts.com Index of Posts at disputesinconstruction.com Construction Contractor Claims | Standard of Care Construction Means Methods | Experts Litigation Claims Building Construction Disputes Claims Contracts Experts Construction Design Experts Shop Drawing Claims Construction Design Claims, Disputes, Experts Heavy Civil Construction Projects Claims Expert Building Construction Disputes Experts BUILDING CONSTRUCTION DISPUTES Construction Subcontractor Contract Drawing Coordination Analysis Construction Subcontractor Trade Consultants Construction Contract Experts | Guaranteed Maximum Price | Cost Plus Contracts Home Office Overhead Construction Claims Consultants Experts Reducing Financial Risks During Construction Guaranteed Maximum Price (GMP) | Cost-Plus | Contract Disputes OWNER-CAUSED CONSTRUCTION CHANGE CLAIMS Building Dispute? Hire a Building Expert! Searching For a Construction Damages Expert ?

CONSTRUCTION CLAIMS
The Holloway Consulting Group has been retained as a construction consultant or expert witness on numerous projects where a contractor has been terminated or is soon to be terminated, either for cause or for convenience, and where the contractor has abandoned the job, under unit price, fixed-price, GMP and Cost-plus contract forms. Its impractical if not impossible to describe all of our construction claims experiences in terminated contracts cases here. Circumstances vary widely and the termination process is
3 of 6

3/28/2013 11:09 PM

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

different in AIA contracts versus custom agreements, and because the terms of general contractor/subcontractor agreements vary widely. Nevertheless, we have seen at least three formula applied to the quantification of contractor termination damages:

CONTRACT TERMINATION CLAIMS


QUANTIFICATION OF CONTRACTOR TERMINATION DAMAGES
Damages Claims Formula No. 1 The contract price less the amount that it would cost the contractor to complete the work; Damages Claims Formula No. 2 The profit on the entire contract (total contract price less the contractors cost of completion) plus the cost of the work actually performed; and, Damages Claims Formula No. 3 For the work completed, that proportion or ratio of the contract price as the cost of the work performed bears to the total cost at completion, plus, the remaining profit on the uncompleted work. Where adequate proof can be made as to the contractors cost of completing the work and where the entire job can be performed at a profit, the application of formulas two and three may produce similar, if not identical, results. If the contractor is unable to prove with reasonable certainty what it would cost to complete the remaining work, the first formula is not applicable, whereas under formulas two and three, she might recover for the work completed in compliance with the contract.

Termination for Convenience/ Wrongful Termination of Contract by Contractor


Only the owner can terminate, or suspend, the Contract for convenience. The contractor does not have this right. If a contractor wrongfully terminates the contract and abandons the job, he will likely be sued for the difference between the owners cost to complete and the earned value of the contract work completed. He may be required to pay extra costs associated with the delay, the hiring of a completion contractor(s), etc.

Contractors Damages
If it is shown that the contractor terminated the contract for cause, he may be entitled to claim to recover payments for work executed and earned, and for proven compensable loss with respect to materials, equipment, tools, and construction equipment and machinery, including reasonable overhead, profit and damages.

Contractors Termination
4 of 6

3/28/2013 11:09 PM

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

Prior to termination or abandonment, the contractor can elect to suspend the work if a material breach has occurred such as untimely payments by the owner of valid payment applications where proper notice has been given, and where the contractor is not in breach. This is a much safer course of action than termination, and it allows the owner a chance to cure. If the contractor must terminate for cause, he must comply the terms of the contract and provide proper formal written notice to the owner. If both the owner and contractor are in material breach of contract at the time of termination, the above assessments and formula may change and the relative nature and degree of the breaches become relevant. Termination and damages will be examined in greater detail here in the future. The Holloway Consulting Group, LLC Construction Claims Experts Construction Expert Witnesses 12081 W. Alameda Pkwy., #450 Lakewood, CO 80228-2701 Denver Phone: (303) 984-1941 International Toll Free: (888) 545-0666 Fax: (303) 716-0432 Email: steve.holloway@disputesinconstruction.com Blog: disputesinconstruction.com Web: hcgexperts.com
_________________________________________

See Related Selected Pages at our site hcgexperts.com (2-12-12)


Education School Projects Steve Holloway Expert Damages Expert Cost Analysis Home Office Overhead Claims Mediation Arbitration Experts Damages Expert Modified Total Cost Method Cost Segregation Services Contract Cost & Performance Audits Advisory Project Management PMO PMA Advisory Consultants Financial Cost Management International Consulting Services Government Consultants Experts Standard of Care Contractor Manager Design Professional Standard of Care Surety Commercial General Liability Defects Experts Repair Costs Expert Witness Services Dispute Resolution Services
5 of 6

3/28/2013 11:09 PM

CONSTRUCTION CLAIMS | CONTRACT TERMINATION

http://www.disputesinconstruction.com/construction-expert-terminated-f...

Advisory Services | Holloway Consulting Claim Types Holloway Consultings Disputes Newsletter Latest News At The Holloway Consulting Group Consulting Firms Holloway Consulting Consulting Expert Advisory Management Firms Contact Holloway Consulting Group, LLC Consulting Firm Profile
Share this:

construction expertContract Terminationcontractor termination damagesexpert witnessfixed-price contractHolloway Consulting Group We're sorry, but comments are closed. Name (required)

Mail (will not be published) (required)

Website

Leave your comment:

Notify me of follow-up comments by email. Notify me of new posts by email. Denver Wordpress Design by WebStyley.com Copyright 2013 Disputes in Construction. All Rights Reserved.