Beruflich Dokumente
Kultur Dokumente
Contents
1. Introduction .................................................................................................................................... 5 PART A - STORMWATER DRAINAGE CONTROLS FOR DEVELOPMENTS................................... 6 1. Types of Stormwater Drainage Controls......................................................................................... 6 2. On-Site Stormwater Detention Systems......................................................................................... 6 2.1 General .................................................................................................................................... 6 2.2 Site Storage Requirement and Permissible Site Discharge for OSD Design ............................ 6 2.3 Allowable Rainwater Re-use Deductions.................................................................................. 7 2.4 Design Parameters for OSD design used in the Site Specific Method ...................................... 7 2.5 Tailwater Influences ................................................................................................................. 8 2.6 Control Types........................................................................................................................... 8 2.7 Orifice Types............................................................................................................................ 8 2.8 Trash Screens.......................................................................................................................... 9 2.9 What Must Drain to the OSD SYSTEM?................................................................................... 9 2.10 Detention Storage Facilities to be used ................................................................................ 10 2.11 Overland Flows .................................................................................................................... 12 2.12 Freeboard ............................................................................................................................ 12 2.13 Discharge Points .................................................................................................................. 12 2.14 Drainage to a Different Catchment ....................................................................................... 13 2.15 Legal Obligations ................................................................................................................. 13 3. On-Site Stormwater Absorption Systems ..................................................................................... 14 3.1 General .................................................................................................................................. 14 3.2 Design Principles ................................................................................................................... 14 3.3 Minimum Design Criteria ........................................................................................................ 14 4 Charged Systems ......................................................................................................................... 15 4.1 General .................................................................................................................................. 15 4.2 Minimum Design Requirements ............................................................................................. 15 5 Mechanical Pumps-Out Systems .................................................................................................. 16 5.1 General .................................................................................................................................. 16 5.2 Minimum Requirements ......................................................................................................... 16 5.3 Minimum Pump and Sump Specifications .............................................................................. 17 6 Scouring and Erosion Control ....................................................................................................... 18 6.1 General .................................................................................................................................. 18 6.2 Minimum Requirements ......................................................................................................... 18 6.3 Soil and Water Management Plan.......................................................................................... 18 7 Rainwater Re-Use......................................................................................................................... 19 7.1 BASIX Minimum Requirements .............................................................................................. 19 7.2 Rainwater Re-use and OSD................................................................................................... 19 8 Submission Requirements ............................................................................................................ 19
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009 Page 2 of 49
8.1 Development Application Stage ............................................................................................. 19 8.2 When Stormwater Drainage Easements are required............................................................. 20 9 Construction Certificate................................................................................................................. 20 10 Occupation Certificate................................................................................................................. 21 PART B - STORMWATER DRAINAGE SYSTEMS.......................................................................... 22 1. Stormwater Conveyance.............................................................................................................. 22 2 Stormwater Disposals ................................................................................................................... 22 3 Minor and Major System Design ................................................................................................... 22 3.1 Minor System Design ............................................................................................................. 22 3.2 Major System Design ............................................................................................................. 23 4 Hydrology...................................................................................................................................... 24 4.1 Rainfall Data .......................................................................................................................... 24 4.2 Average Recurrence Interval.................................................................................................. 24 4.3 Catchment Area ..................................................................................................................... 25 4.4 Determination of Catchment Runoff ....................................................................................... 25 4.5 Roughness Coefficients for the Calculation of Free Surface Flow .......................................... 25 5. Hydraulics .................................................................................................................................... 26 5.1 Hydraulic Grade Line Analysis ............................................................................................... 26 5.2 Downstream Hydraulic Controls ............................................................................................. 26 6 Pits................................................................................................................................................ 27 6.1 Location of Pits....................................................................................................................... 27 6.2 Pit Types................................................................................................................................ 27 6.3 Inlet Capacity ......................................................................................................................... 28 7. Open Channels............................................................................................................................ 28 8. Building Adjacent to Stormwater Drainage Systems .................................................................... 29 9. Stormwater Connections.............................................................................................................. 29 9.1 Under Buildings...................................................................................................................... 29 9.2 Above-Ground Pipe Work ...................................................................................................... 29 10. Services ..................................................................................................................................... 29 11. Easements................................................................................................................................. 29 12. Inter-Allotment Drainage ............................................................................................................ 30 13. Stormwater Pollution and Erosion Control.................................................................................. 30 13.1 Soil and Water Management Plan ........................................................................................ 30 13.2 Soil Erosion Control.............................................................................................................. 30 13.3 Integrated Developments ..................................................................................................... 31 14. Submission of Design Details..................................................................................................... 31 14.1 Submission Details............................................................................................................... 31 14.2 Information to be submitted .................................................................................................. 31
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009 Page 3 of 49
APPENDIX....................................................................................................................................... 32 A1 Terms of Restriction on the Use of Land and Positive Covenant Existing Allotments.................. 32 Terms of Restriction on the Use of Land ...................................................................................... 32 Terms of Positive Covenant ......................................................................................................... 32 A2 Terms of Restriction on the Use of Land and Positive Covenant New Sub-divisions................... 34 Terms of Restriction on the Use of Land referred to in the above mentioned Plan ....................... 34 Terms of Positive Covenant referred to in the above-mentioned Plan .......................................... 34 A3. Absorption Design Storage Method (Ref Rockdale Council's Stormwater Design Code) ........... 36 A4 ILSAX Rainfall Files for the 5-yr, 20-yr and 100-yr ARI Storm Events ......................................... 37 5-yr ARI stacked rainfall ............................................................................................................... 37 20-yr ARI stacked rainfall ............................................................................................................. 39 100-yr ARI stacked rainfall ........................................................................................................... 41 A5 Standard Drawings ..................................................................................................................... 43
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 4 of 49
1. Introduction
This Specification for the Management of Stormwater compliments the City of Canada Bay Council's Stormwater Policy. It has been prepared to provide guidelines for the management of stormwater runoff from all types of developments within the City of Canada Bay Council Local Government Area (LGA). The objectives of Council's Stormwater Policy are: To provide uniform guidelines and application of systems to achieve consistency in the assessment and conditioning of development applications in relation to stormwater runoff from all developments To minimise any adverse impact on properties caused by stormwater runoff from developments To ensure that the water qualities of receiving waterways are not adversely affected by pollutants such as nutrients, pathogens, and situation, resulting from development sites. To ensure that uniform stormwater controls are applied throughout the whole of the City of Canada Bay Council Local Government Area. These Objectives are achieved by the following controls: The provision of safe overland flowpaths within developments and on public land The definition of floodways for major storms within developments and on public land The provision of controls such as on-site stormwater detention, community basins and the like and on-site retention systems to reduce and control stormwater runoff The application of alternative methods of merit based stormwater control and conveyance devices The removal of flood effected development from known floodways and the prohibition of future developments in such floodways The provision of minimum free-boards for assigning floor levels to reduce the risk of flood damage to property The installation of pipe/channel systems to minimise hazard to pedestrian and vehicular traffic caused by uncontrolled surface stormwater runoff The installation of water quality control devices such as trash screens, gross pollutant traps, water quality ponds and the like to protect the quality of receiving waters. The guidelines to achieve the above controls are provided in this document.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 5 of 49
PART A - STORMWATER DRAINAGE CONTROLS FOR DEVELOPMENTS 1. Types of Stormwater Drainage Controls
Different types of stormwater controls for development sites are permitted. However, their use will depend on the circumstances applicable to the development. For example, any constraint affecting the use of one type or types of stormwater control system may be required as an alternative to be implemented or systems to be used in combination to satisfy Council's Policy objectives. The following controls may be applicable: On-site stormwater detention systems On-site stormwater absorption (retention) systems Charged systems Pump-out systems Direct discharge systems incorporating scour and erosion control devices Rainwater re-use A combination of some or all of the above to achieve Policy objectives
2.2 Site Storage Requirement and Permissible Site Discharge for OSD Design
a) Catchment Based Method - for single residential developments has been adopted. The parameters are as follows: The Site Storage Requirement (SSR) shall be 200cum per ha The Permissible Site Discharge (PSD) shall be 180L/s per ha
Page 6 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
b) Catchment Based Method - for commercial, industrial, mixed, dual occupancy developments and residential flat buildings (RFBs) has been adopted. The minimum parameters are as follows: The Site Storage Requirement (SSR) shall be 300cum per ha. The Permissible Site Discharge (PSD) shall be 200L/s per ha.
c) Site Specific Method - has been adopted for new land subdivisions. New allotments created in excess of 450sqm or more and new roads are covered here. Dual occupancy subdivisions are covered by the Catchment Based Method. The minimum design criteria are explained below. The Site Storage Volume (SSV) shall be sized to cater for the 5-yr ARI (low level), 20-yr ARI (intermediate level) and 100-yr ARI (high level) storm events for all time durations. The general criteria are to ensure that the discharge after the development does not exceed the discharge prior to the development, or better. For alterations and additions, the permissible site discharge is calculated on the existing footprint of the dwelling before the improvements. For new dwellings, the permissible site discharge is based on a pre-developed footprint of not more than 35% of the total site area or the existing footprint of the dwelling, whichever yields the smaller discharge value. If the site drains to the rear, or is a commercial, industrial or multi-residential (including residential flat building) development, the permissible site discharge is to be calculated on a 'state of nature' or 'green fields' site. In all cases, the existing condition or better is to be maintained. If the discharge from the development is to be concentrated at a single point (e.g. to the kerb and gutter) in the road reserve or public land, the maximum concentrated discharge must be limited to no greater than 25L/s per 15 lineal metre of frontage. This will be the maximum allowable discharge from the site should the existing discharge, as calculated above (PSD) exceed this. The site storage volume should be upsized accordingly. In the determination of the SSV and PSD, the ILSAX program for urban stormwater drainage design and analysis, Version 2.13 April 1993 or later, or the DRAINS program for urban stormwater system design and analysis, Version 2001.1 by Geoffrey O'Loughlin and Bob Stack, April 2001 or later, are to be used. Please note that the designer may choose to use this method to calculate the storage volume and site discharge instead of the Catchment Based Methods as outlined above, for greater flexibility when less area (up to 50% of the total site) is to be routed through the detention system.
2.4 Design Parameters for OSD design used in the Site Specific Method
The following design parameters are to be used, where applicable, in the model analysis: Soil type = 2.5 Antecedent moisture content, AMC = 3 Infiltration rates: Initial paved = 1mm Grassed = 5mm Storms, generated in accordance with the Australian Rainfall and Runoff, Volume 1, 1987 or later Editions. Time of concentration, calculated using the kinematic wave equation given in the Australian. Rainfall and Runoff, Volume 1, 1987, page 300, or program generated. For the purpose of determining the time of concentration, the length of flow, L, is the distance from the furthest point of the site to the exit point. The surface roughness, n* is as given in the Australian Rainfall and Runoff, Volume 1, 1987, page 300. The slope is the average gradient of the flowpath.
Page 7 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Type '0' inlets are not to be used. Supplementary areas are not to be used. Graph showing relationship between orifice size and discharge is attached but can be estimated using the following equation:
Q = C.A. (2.g.h) Where: A = area of orifice outlet in sqm h = depth of water above centreline of orifice outlet in metres C = discharge coefficient = 0.6* g = acceleration due to gravity = 9.81m/s2 Q = discharge rate in m3/s or 103 L/s * Note: This value is for a flat plate cut with a square edged circular shaped orifice. 'C' varies between 0.5 to 1.0 depending on the type of outlet control to be used. A pipe stub of approximately 100mm long may be permitted for diameters greater than 90mm. Smaller diameter pipe stubs are not acceptable due to the possibility of frequent choking and blockages. Please note that the accuracy of the controlled outflow may not be achieved when a pipe stub is to be used instead of an orifice plate.
required outflow rate. The plate is to be permanently fixed into the wall of the control pit with four (4) 'dyna' bolts to prevent its unauthorised removal. The advantage of using an orifice plate is it provides the designer greater flexibility and accuracy in controlling the rate of outflow. The orifice equation to be used is: Q = C.A. (2.g.h) For a square-edged orifice, C = 0.6 The above equation can be re-arranged to obtain the required diameter for the maximum discharge. For a circular shaped orifice, the diameter: D= Where A= = area of orifice hole in m2 3.1416 Pit Loss and Pipe Friction - the control is determined by calculating the friction and entry losses in the outlet pipe and pit leading from the OSD facility to the point of connection (or in reverse), to control the discharge rate. This method would require hydraulic grade line calculations for various storm events and duration and best suited to 'drowned outlets'. However, 'drowned outlets' are not recommended. Manual calculations are to be carried out in accordance with current design practices and principals as outlined in the Australian Rainfall and Runoff, volume 1, 1987 or later editions. Pipe Stub - this type of control is not recommended because the diameter of the nominal pipe stub is not as accurate as an orifice plate, which can be machined to the exacting dimension. A short stub of nominal length approximately 100mm long can be used to control the rate of discharge from the OSD facility. The orifice equation given above can be used to determine the outflow rate. For a pipe stub orifice, C = 0.8 The advantage of a pipe stub is that it is a permanent fixture that is not easily tampered with. Pipe stubs are only permitted for diameters greater than 90mm, to minimise the likelihood of chokes.
(4.A/)
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 9 of 49
This method is to be used for all new land subdivisions and when more than 30% of the site is to bypass the OSD system. However, not more than 50% of the site will be permitted to bypass the OSD system. Further reductions in capture would give model instabilities and is therefore unacceptable. Again, try to ensure that the majority of the bypass areas to be mainly pervious surfaces. More than 30% impervious area bypassing the OSD system is not permitted, without Council consent. To minimise bypass, it may be necessary to install more than one OSD facility.
Must have minimum topsoil cover of no less than 600mm over the tank where it is to be located in landscaped areas.
Above Ground Storage Systems in Landscaped Areas o o Shall be designed and located to safely convey all stormwater flows to the Council road gutter or drainage system. Where likely overflow from these facilities is across private property and a suitable overflow path cannot be provided, the overflow shall be contained within an underground piped drainage system with a design capacity equivalent to the peak 100-year ARI storm event. This underground system (both pits and pipes) shall be designed to receive and fully contain controlled flows and overflows from the detention facility. o Must be located external to all building footprints, basements, ground floor parking areas, garages, or patios unless access points and emergency overflow provisions are either provided externally or is easy to get to for the purpose of inspections and maintenance to the system. o A surcharge path shall also be defined even where the 100-year ARI flows can be contained within the system in case of blockages. Easements are to be created in private property over pipe systems and surcharge paths. o o o o o Shall include surface storage in soft and hard landscaped area or above ground structures such as rainwater tanks. Must not be located across the boundary of an allotment. Must not be located such as to restrict pedestrian access from the public road to the building. Must be adequately soundproofed to minimise noise when stormwater is collected or discharged. Are to be located where they can be readily accessible for inspections and routine cleaning. For SEPP5 developments, the OSD facility shall be located in common areas and not in private courtyards. For strata subdivisions, the location is subject to Council assessment but the intent is to ensure that the facility is located in an area, which is easily accessible for routine inspections and maintenance requirements. o o o o o o o o o If a built structure is to be used to retain water, it shall be of masonry type construction or waterproof (prefabricated) material. Control structures must be located where they can be easily accessed for routine inspections and cleaning. Must be graded to drain completely - gradients shall not be less than 1.0%. Where gradients are less than 1.0%, sub soil drains and pits shall be installed. To avoid ground saturation in landscaped areas, subsoil drains shall be installed. Shall be designed in a manner, which minimises inconvenience, unsightliness and hazard. Must not allow water to pond more than 300mm in tennis courts or other surfaced areas. Must not allow water to pond more than 300mm in landscaped areas unless access by persons can be restricted. Must not have batter slopes greater than 1 in 4. Where the depth of ponding exceed 300mm in landscaped areas, it must be fully fenced off with approved pool fencing and childproof, self-closing gates with batter slopes into the basin, around its perimeter, not to exceed 1 in 6. o o The maximum depth of ponding in landscaped areas must not exceed 1200mm. Where above-ground structures such as rainwater tanks are to be used, they must be located in an area least visually obtrusive and in compliance with Councils planning requirements.
Above Ground Storage Systems in Paved Driveways and Carparks o o Shall be designed and located to safely convey all stormwater flows to the Council road gutter or drainage system. Otherwise, the storage facility is to be moved to a more suitable location. Where likely overflow from these facilities is across private property and a suitable overflow path cannot be provided, the overflow shall be contained within an underground piped drainage system with a design
Page 11 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
capacity equivalent to the peak 100-year ARI storm event. This underground system (both pits and pipes) shall be designed to receive and fully contain controlled flows and overflows from the detention facility. o Must be located external to all building footprints. This includes basements, ground floor parking areas, garages, or patios unless all access points and emergency overflow provisions are external to the structure. o A surcharge path shall also be defined even where the 100-year ARI flows can be contained within the system in case of blockages. Easements are to be created in private property over pipe systems and surcharge paths. o o o o o o Must not be located such as to restrict pedestrian access from the public road to the building. Control structures must be located where they can be easily accessed for routine inspections and cleaning. Must be graded to drain completely. Gradients shall not be less than 0.5%. Designed in a manner, which minimises inconvenience, unsightliness and hazard. Must be totally impermeable. Must not allow water to pond more than 200mm in depth.
2.12 Freeboard
Adequate freeboard or clearance between the maximum depth of ponding in the OSD system and the levels of all habitable floor areas, garages, storage facilities, etc., is to be provided so that damage to goods and materials, nuisance flooding, or hazard is avoided. Developments will not be permitted within known floodways unless it can be proven that the development will not be affected by floodwater nor will the development cause flooding both upstream or downstream of the development. Council's Policy is the removal of such flood affected developments from known floodways and the prohibition of future developments in such floodways, where necessary. For OSD facilities and overflow paths, the following freeboard requirements will be required: 150mm - warehouse, factory and carport floor areas. 300mm - office, living rooms, retail space, store rooms, and show rooms. For Flood waters (100-year flood level and PMP). 300mm - to enclosed garages and carparks. 500mm - to all internal building floor levels which includes residential, commercial and retail.
If there are no alternative ways of reducing the outflow including upsizing of the on-site detention facility or insufficient separation of outlet points, the approval of concentrated discharge of more than 25L/s to the kerb will require the submission of supporting calculations to show that the flow width or spread of stormwater along the gutter does not exceed more than 2.5m across the roadway at any point in the gutter. Any contributing runoff from the upstream catchment must be included in the calculations. Discharging stormwater into a watercourse or channel may be permitted subject to joint approval from Council and other relevant authority. Where approval is granted, adequate protection against scouring and erosion at the point of discharge shall be provided. Council should be consulted in regards to appropriate stabilisation treatment to be used. The maximum discharge velocity into an unlined, that is, other than concrete channel shall be in accordance with the Department of Sustainable Natural Resources document Managing Urban Stormwater, Soils and Construction, table 5.1 maximum discharge flow velocities in waterways. Where an existing Council drainage line is available, connection into the system may be permitted subject to Council approval. The connection may require the construction of new inlet pits and the laying of a new pipeline, to Council standards. Refer to Part B for minimum standards required. Council encourages minimising the number of pits, junctions and pipe lengths in the road reserve. However, pits are preferable over bend joins to eliminate blind junctions such that ease of maintenance can be achieved. Any private stormwater pipe leaving the site, must be laid at an angle of no less than 45 degrees to the boundary line. If the pipe needs to be laid at a more acute angle or must run parallel with the kerb line in order to achieve gravity discharge to the kerb, then it must be taken to the kerb at minimum of 45 degrees and then a minimum 375-dia RCP is to be laid parallel to the kerb line to the connection into the nearest downstream underground public drainage system. Standard gully inlet pits with minimum 1.2 metre long kerb lintels will need to be constructed at any bends, junctions and minimum spacing of pits as described in Part B, Section 6. Conduits piped to the kerb must be sized adequately with at least 50mm cover. Where cover is inadequate, the following pipe equivalencies shall be used: 100mm-dia equivalent to one (1) 100mm x 100mm x 6mm thick RHS 150mm-dia equivalent to one (1) 200mm x 100mm x 6mm thick RHS 225mm-dia equivalent to two (2) 200mm x 100mm x 6mm thick RHS
Outlets through existing sandstone kerbing - drilling through sandstone kerbing may be permitted subject to Council approval. The pipe class must also be adequate to withstand traffic loads. All RHS are to be hot-dipped galvanised or stainless steel material.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 13 of 49
The purpose of the Covenant is to ensure that the registered proprietor takes responsibility for the control, care and maintenance of the OSD, OSA and/or charged system. The Restriction ensures that the system is not altered in any manner, shape or form. For newly created parcels of land, these terms shall be created under Section 88B of the Conveyancing Act 1919. For existing titles, the terms of positive covenant and restriction on the use of land shall be created by an application to the Land Titles Office using Forms 13PC and 13RPA. Standard wording for positive covenant and restriction on the use of land are given in the appendix.
The minimum design storm recurrence interval shall be the 100-yr ARI storm event. There is sufficient pervious (open space) area to allow complete percolation of runoff into the ground. Absorption systems are not permitted in shallow soil over bedrock. Suitable soils must have a uniform thickness of at least 3.0 metres. Absorption systems will not be permitted on 'steep' sites with slopes greater than 5%. Absorption trenches must follow the line of contours. Absorption systems will not be permitted where there is the presence of a high water table or that the location of the absorption system would likely to cause the water table to rise. Where a high water table is encountered, the base of any proposed gravel filled trench shall be set at least 500mm above the water table. Where rock is encountered, the base of any proposed gravel filled trench shall be set at least 500mm above the rock. Direct uncleansed stormwater into the absorption system is not permitted. Only roof runoff shall be permitted to directly discharge into the absorption system, but must pass through an approved filter system to remove all debris, silts, sands, etc. prior to absorption. Areas such as courtyards, walkways, driveways, carriageways, car parks, etc., are not to be piped directly into absorption systems. A silt/trash or filtration system to be installed. Runoff must pass across at least 15 metres of grass or through a sand/loam filter at least 200mm thick with grass cover where impervious areas are to run directly to the absorption system. Suitable soils must have hydraulic conductivity values greater than 1 x 10-6 m/s and the minimum absorption rate to be adopted shall be limited to 1.0 L/sqm per second irrespective of the absorption rate achieved by any geotechnical testing.
To ensure likely overflows are not concentrated onto adjoining downstream properties, a dispersion system shall be provided at the overflow outlet. In some cases, a combination of OSD and absorption may be required to control and detain the site runoff. The Storage Method with average rainfall intensity may be used (see appendix for method based on Rockdale City Council's Stormwater Code).
4 Charged Systems
4.1 General
Where a site naturally falls to the rear, and the property is not benefited by any stormwater drainage easement, a 'charged system' may be considered for single residential dwellings, which are not classified as Complying Developments, to convey stormwater to the street frontage. However, charged systems are not to be used if a gravity feed system can be achieved. Other types of developments such as residential flat buildings, dual occupancies, commercial, mixed developments and the like are generally not permitted unless the following constraints apply: Downstream property owners have indicated that they are not prepared to grant easements to permit the drainage of the property to follow the natural fall of the land. Written evidence is to be submitted as proof. Soil absorption characteristics and other physical constraints indicate that on-site absorption is not feasible for the dwelling to be totally catered for by any absorption system. A Geotech Report, indicating that the soil has very poor absorption rate, is to be submitted as proof. Council has assessed that the proposal to discharge to the street's receiving drainage system can adequately cope with the additional runoff. Please note that the approval of charged systems does not negate OSD requirements. However, it may not be possible or practical to be able utilise charged systems if OSD is required. In such circumstances, a mechanical pump-out system used in combination with OSD or OSA may be more practical. Note though that mechanical pump-out systems are not preferred over charged lines due to high installation and ongoing maintenance costs.
Charged lines generally suitable for direct pipe from the roof gutter to the street. Overflows from rainwater re-use systems are to be directed to an OSA system unless details and supporting calculations can be provided showing that sufficient pressure head can be generated to direct flows to the street via a charged system.
Outflows from OSD systems are generally to be by gravity with 'free outlet' control. However, 'drowned outlets' may be permitted if supporting calculations can be provided showing that sufficient pressure head can be generated to direct flows to the street via a charged system and that the permissible discharge from the site can be maintained.
Full hydraulic analysis of the proposed drainage system is to be submitted including design flowrates and a hydraulic grade line. The drainage system including roof gutters pipes and pits and is to be designed for the 1 in 100-year ARI storm event. There is a minimum height difference between the roof gutter level and the discharge pit of 2.0 metres to allow sufficient pressure to drain the system. Alternatively, a hydraulic grade line for the 1 in 100-year ARI storm event shows that the system can drain to the street with a 300mm free board to the gutter line.
The charged line shall discharge to a sump within the property boundary and then gravity fed to the street or receiving drainage system. Typical details of the boundary pit to achieve this can be obtained from Council. Where gravity feed to the street is not achievable, a non-return valve must be installed over the inlet pipe to the sump. However, non-return valves are generally not recommended due to maintenance problems.
The discharge pit is to be located such that any likely overflow is safely directed to the street. Pipes should be minimum 150mm-dia pipes for pressure applications and solvent welded unless hydraulic calculations show that a smaller pipe can be installed but pipes less than 80mm-dia is not recommended. Cleaning eyes must be installed at the lowest point in the system within a sump, which is to be drained into an onsite absorption/dispersal system. Gutter guards are to be installed to minimise debris entering the system. All utility services within the road reserve must be located and shown on the plan in relation to the proposed drainage system. A positive covenant will be required to be placed on the title of the property to inform the owners of their obligation to regularly maintain the system. Full detailed drawings and supporting calculations shall be submitted to Council with the Development Application.
For direct connection into an existing stormwater pipe, a pit must be constructed at the point of connection and a non-return valve must be installed on the upstream (inlet) pipe to prevent water flowing back into the property. Non-return valves shall be installed in a junction pit within the property boundary. Non-return valves are not permitted to be installed in Council maintained (public) systems. When connecting into a Council stormwater system on public land, two (2) pits; a junction pit on the property fitted with a non-return valve and a standard stormwater gully pit at the connection point in the road reserve, may be necessary. Water pressure in the system must be taken into consideration as this could affect the design discharge rate, rendering it unsuitable to achieve the required outflow. Where a charged system is likely, supporting calculations are to be submitted to verify that the system can operate in accordance with this Specification.
The following information shall be submitted with the application: Piping size tabulation sheet - for the rising main. Copy of pump specification and pumping curves. Graph showing the maximum design inflow curves and pump curves for both pumps. A plan of the pump system layout showing pits, pipes and sizes, invert levels and discharge point.
Page 17 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Drawing of the holding tank and pumps including invert level, pump cut in levels, alarm level, etc. Any other calculation and documentation considered necessary in support of the application.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 18 of 49
7 Rainwater Re-Use
Notwithstanding BASIX water conservation targets, the collection of rainwater for non-potable use is encouraged. Nonpotable water usage shall include watering of the garden, irrigation, washing machine and toilet flushing. Rainwater re-use requirements are either in accordance with Council's Policy or BASIX. Reference should be made to Council's Rainwater Re-use Policy for further details and minimum guidelines.
8 Submission Requirements
8.1 Development Application Stage
At the lodgement of the Development Application (DA) a stormwater drainage concept plan (SDCP) shall be submitted. It is advisable that the Applicant submit an SDCP to satisfy that the proposed development is feasible. This SDCP must show
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009 Page 19 of 49
the general layout of the proposed drainage system, with indicative levels, minimum pipe sizes, and location of the OSD and/or OSA facilities including basic volumes and dimensions, overflow routes and points of discharge etc, to demonstrate that the development can be adequately catered for and complies with Council's Drainage Policy. Most importantly, the main issues which need to be shown is the proposed system in relation to any services such as to ensure that there will be no clashes with any services and that the system can operate hydraulically. An SDCP particularly for sites which drain to the rear would be required. This is to demonstrate to Council that the site can be drained without resulting in nuisance flooding or other detrimental factors.
9 Construction Certificate
Prior to the issuing of the Construction Certificate (CC) either by Council or a nominated Principal Certifying Authority (PCA), the final drainage plan should include but not limited to the following: A1, A2 or A3 size drawings clearly showing the layout of the proposed drainage system, including the location of all downpipes, pits and pipes and labelled with their pipe sizes, gradients, existing and finished surface and invert levels, the dimensions of OSD and OSA systems, proposed storage volumes, surcharge/overflow paths, site discharge, etc. All supporting computation information including calculations on computer disc (where applicable) with relevant hydrologic and hydraulic information. Computation information summarised as: Total site area in m2. Total impervious area (roof and paved) in m2. Area draining into the proposed stormwater (OSD or OSA) facility. Dimensions (mm), volume (cum), and discharge rate from the OSD or OSA system. Maximum water depth (mm) from centreline of outlet to top water level. Maximum depth of ponding for above ground OSD systems. Type and size of orifice (mm-dia), outlet pipe (mm-dia) and PSD (L/s). Drawings must be certified by a qualified practising Civil Engineer for residential flat buildings, dual occupancies, commercial, industrial, mixed developments, multi-residential developments, and the like. For single residential developments, residential extensions, and small scale developments, a draftsman, surveyor, or plumber with experience in stormwater design would be acceptable. Where drainage easements are required, evidence in the form of a legal agreement between the affected parties or copies of titles showing the created easements and a longitudinal section of the proposed pipe to the point of connection or to the discharge point for drainage to foreshore areas and where discharge is permitted to waterfronts or bushland. This shall include pipe sizes, gradients, flowrates and a hydraulic grade line which shall include pipe sizes, gradients, flowrates and a hydraulic grade line. Details of the OSD control device(s) used including size and shape, outlet pipe diameter and invert level. For underground systems, at least one (1) detailed section through the OSD or OSA facility sufficient for construction. For above ground systems, at least two (2) detailed sections through the OSD facility, which shall include the maximum water level, gradients and overflow weir, sufficient for construction. Existing and proposed levels and details of adjoining structures and buildings shall be shown on the sections through the OSD or OSA facility. Overland flow path and PSD from the site. Plan showing the location of OSA or OSD facilities including dimensions, pervious (landscape) and paved (existing and proposed roof and paved) areas, and all existing and proposed surface levels.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009 Page 20 of 49
For pump-out systems, relevant information as requested in Section 5. Location of any utility services*, structures, trees, etc., which may affect the proposed drainage system.
*Note: It is the responsibility of the applicant to submit full details of all relevant services, which may conflict with the proposed design. The exact locations of any crossings or connections are to be shown.
10 Occupation Certificate
Prior to the issuing of an Occupation Certificate, the following information must be submitted to Council: Works-as-executed drawings: an engineering survey of the final works is to be submitted on one (1) set of the approved plans. This plan is to include finished levels, dimensions and volume of the built OSA, OSD facility, the location of all drainage pipes, sizes and levels, etc., and signed by a Registered Surveyor. Copies of titles showing the creation of Positive Covenants and Restriction on the use of land. Certification of the constructed drainage system by a suitably qualified and experienced Chartered Professional Engineer, on the National Professional Engineers Register with the Australian Institute of Engineers for residential flat buildings, dual occupancies, commercial, industrial, mixed developments, multi-residential developments, and the like. For single residential developments, residential extensions, and small scale developments, a Certificate from a Surveyor or plumber with experience in stormwater design would be acceptable. Identification Plate: at Council's request, an identification plate of no less than 110mm wide x 80mm high, is to be fixed near or onto the control structure of the OSD system, this is to advise the registered proprietor of their responsibility to maintain the OSD facility and not to tamper with it in any manner without written consent. This plaque shall read 'This is an On-site Stormwater Detention system. It is an offence to reduce the volume of this system or to remove the orifice that controls the outflow. The base of the outlet control pit and debris screen must be cleared of silt and rubbish on a regular basis. This plate must not be removed.'
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 21 of 49
2 Stormwater Disposals
Stormwater runoff shall follow the natural fall of the land and must be disposed by gravity means, whenever possible. Redirecting stormwater runoff from one catchment (or sub-catchment) to another catchment (or sub-catchment) is not permitted. Council will not approve drainage systems which diverts stormwater runoff to another catchment by going against the natural grade of the land for any development. This includes land subdivisions and road drainage design. Redirecting stormwater using pump-out or charged systems is permitted for residential and commercial developments and redevelopments as discussed above. Disposal of stormwater on-site by absorption is also covered in Part A.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 22 of 49
The minimum conduit sizes for the minor system design shall be as follows: Public system - pipes, 375mm-dia Public system - box culverts, 600mm wide x 450mm high Private system - 90mm-dia for roof runoff only Private system - 100mm-dia for surface runoff within the property only Roads - pipes, 375mm-dia
The minimum pipe grade shall be as follows: For pipes less than or equal to 225mm-dia - 3% For pipes greater than 225mm-dia - 1.0% For concrete lined box culverts poured in-situ - 0.5%
Pipes which are to be laid at a slope greater than 20% will require anchor blocks at the top and bottom of the section and at intervals of not more than 3.0 metres in between. Bulkheads shall be provided on steep gradients where soil instability is likely. To retain backfill material, bulkheads shall be installed at intervals of not more than 5.0 metres. Type of pipe material and jointing to be used for the minor system design shall be as follows: Public system - reinforced or fibre reinforced concrete*, rubber ring jointed. Private system - up to 300mm-dia uPVC, solvent welded joints; 300mm-dia and larger reinforced or fibre reinforced concrete*, rubber ring jointed. Subject to Council approval, other types of piping material, for larger conduits, such as plastic pipes may be used, if it can be demonstrated that the substitute material has the same, if not better, structural and durable qualities than reinforced concrete. Depth of cover to the conduit obvert shall be as follows: Public system not subject to vehicle loads - 450mm Pubic system subject to vehicle loads - 600mm Private system not subject to vehicle loads - 300mm Private system subject to vehicle loads - 600mm
Where it is not practical to provide for the above minimum cover requirements, at least 50mm thick granular overlay shall be provided over the obvert of the conduit with a 150mm thick reinforced concrete slab constructed over it or mass concrete surround. The appropriate class of pipe to be used shall depend on the minimum cover provided and the loading onto the pipe in accordance with AS3725 - 1989, loads on buried concrete pipes. Design velocity of flows shall be: Conduits - 0.6 m/s minimum, 6.0m/s maximum Surface flow - 2.0m/s maximum
Where these values cannot be contained, appropriate erosion control measures are to be provided. Maximum permitted depth of surface flow shall be: Road carriageway, driveways, footpaths and carparks - 150mm Landscaped areas - 300mm
The "major system" comprises the drainage route, which conveys the runoff for the major storm events. This may be a series of trunk drainage systems and overland surface routes including open channels, creeks, and river systems. Overland flow routes are to be provided in the following locations: Within the road carriageway excluding footpaths and the footway reserve. Flows across footpaths will only be permitted where this will not cause flooding to property or create danger to pedestrians and is subject to Council approval. Within drainage easements. Where it is not practical to provide an overland flow route over the easement, the piped drainage system shall be sized to accept the runoff for the major storm event i.e. the 100-year ARI. Within a known and designated floodway. Within creeks and river systems.
The minimum freeboard shall be as follows: 150mm for roadways - between the 100-year ARI overland flow route and warehouse, factory, and garage floor levels and entrances to underground carparks. 300mm for roadways - between the 100-year ARI overland flow route and office, living rooms, retail space, storeroom, and show room floor levels. 300mm for surcharge paths e.g. easements - between the 100-year ARI overland flow route and all internal building floor levels, garages and basement carparks. 500mm for channels, creeks and rivers - between the 100-year flood water level and all internal building floor levels, garages, and basement carparks. Design velocities and depths of surface flows shall be in accordance with Figures G1 and G2 of the New South Wales Government Floodplain Management Manual: The management of flood liable land, with hazard category classed as "low hazard".
4 Hydrology
4.1 Rainfall Data
Rainfall data is given in the appendix.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
50* 100*
* Note: The underground drainage system (this includes pipes, conduits and pits) shall be designed for an ARI of 1 in 100years where major system flows (e.g. along a drainage easement) are likely to surcharge across private property or cause localised flooding. A surcharge path must also be provided to safely convey surface stormwater across private property within easements. The minimum design ARI for surcharge paths shall be the 1 in 100-years. Major System Design Classification - public system; overland flowpaths and trunk drainage systems The design ARI shall be the 1 in 100-years. Classification - private system; overland flowpaths and trunk drainage systems The design ARI shall be the 1 in 100-years.
n=
(Pi.ni 3/2) Pi
2/3
where ni = is the Manning's roughness coefficient for section i and Pi = is the wetted perimeter or length of the section with a roughness value ni
5. Hydraulics
5.1 Hydraulic Grade Line Analysis
Hydraulic grade line calculations are to be performed in accordance with the Australian Rainfall and Runoff, and shall be undertaken by a qualified person with experience in hydrology and hydraulic design. Full hydraulic calculations must be submitted for all public and major piped systems (375mm-dia and larger), drainage lines through easements or where Council deems it necessary to determine the feasibility of the proposal. Drainage lines shall be designed with minimal bend losses. Where this is unavoidable, junction pits shall be provided at the location of bends or changes in direction. Pipes will not be permitted to be laid such that a larger pipe joins into a smaller pipe downstream, to avoid potential chokes in the system. However, this may be unavoidable when the new line is connected into an existing system. In this circumstance, the starting hydraulic control shall be adopted at the ground level at the point of connection. For surface drainage systems e.g. channels, open drains and the like, hydraulic calculations must include the determination of the water surface profiles and backwater effects using suitable computer models such as DRAINS and HEC-RAS. Frictional losses in closed conduits of circular cross-section e.g. pipes, shall be determined using the Darcy-Weisbach Formula. This Formula may be applied to rectangular sections e.g. box culverts, by converting the product of the area and hydraulic radius to the power of two-thirds (A.R2/3) to an equivalent circular section. The following Colebrook-White roughness parameters shall be used: uPVC , k=0.03mm Reinforced concrete, k=0.60mm Fibre reinforced concrete, k=0.60mm
Pit energy losses and pressure changes at junctions, bends, transition structures, slope junctions, inlet pits, junction pits, drops and outlets must be considered. Pressure head coefficients for determining these "head losses" are to be obtained from the following sources: Missouri Charts Hare Equations U S Corp of Engineers mitre bend charts AR&R 1987 or later editions
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 26 of 49
Where the outlet is to an open channel, and downstream flood levels are known, the water surface level to be adopted shall be the 1% AEP flood level. Where the outlet is affected by tidal or wave action, the resulting tide water level shall be adopted. Where the outlet is to an existing pipe or conduit, the hydraulic grade line of the conduit shall be determined downstream to a pit where its water level is known e.g. at a grate in the gutter where the maximum free surface ponding is at the top of kerb.
Where the outlet is at the invert of the kerb, the water surface level shall be adopted at the top of the kerb.
6 Pits
6.1 Location of Pits
Stormwater drainage inlet pits shall be: Spaced such that the gutter flow width is limited to 2.5 metres maximum width for the minor system design. Located at the upstream side of allotments to minimise runoff flowing across the road. Located at sag points and at road depressions. Located where access for inspections and maintenance is readily available. Provided at changes in direction, grade, conduit level, size, or class of conduit. Provided at junctions. Spaced at a distance of no greater than 50 metres apart.
7. Open Channels
Piped systems are preferred over open channel systems. Open channels will only be permitted if they form part of the major drainage system and where permitted, shall be designed to have smooth transitions, with adequate access provisions available for inspections, general maintenance and adequate safety measures installed to protect persons and vehicles. These include perimeter fences, bollards, and grills over outlet pipes. Step irons shall be installed; flow velocities and depths reduced at nominated access points. Open channels shall be designed in accordance with the Australian Rainfall and Runoff and the NSW Government Floodplain Management Manual and should be able to contain the major system runoff. Mannings roughness coefficients for open channel sections applicable to specific channel types shall be obtained from the Australian Rainfall and Runoff. Typical values are given below: Mannings Roughness Coefficients Surface Concrete pipes or box sections Concrete trowel finish Concrete formed without finishing Sprayed concrete, granite Bitumen, smooth finish Bricks or pavers Pitchers or dressed stone in mortar Rubble masonry or random stone in mortar Rock lining or rip-rap Earth, clean Corrugated metal Earth, weed and gravel Rock cut Short grass Long grass Medium to dense brush n 0.012 0.015 0.016 0.018 0.016 0.016 0.016 0.028 0.028 0.027 0.027 0.022 0.028 0.033 0.035 0.150
Open channels shall be designed to avoid hydraulic jumps or generate supercritical flow conditions. Side slopes shall not exceed 1 in 4, unless fully fenced off. Where-ever possible, low flows shall be contained within a piped system or contained within a concrete lined channel at the invert of the channel.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 28 of 49
9. Stormwater Connections
9.1 Under Buildings
Shall be carried out in accordance with AS/NZS3500.3, Section 3.
10. Services
Care shall be taken to ensure that the proposed stormwater drainage system will not conflict with utility services. In this regard, all services shall be located prior to final drainage system design. Stormwater drainage conduits crossing over or under sewer lines must be laid in accordance with Sydney Water's requirements. This may require support trenching and concrete encasement of sections that traverse the utility. Where drainage lines are to be laid in the road reserve, they shall be located under the kerb line or within the road carriageway, to avoid conflict with the utility services in the footway. If drainage lines must cross the footway reserve, they shall be laid across the footway perpendicular to or at a maximum angle of 45 degrees to the kerb face to minimise conflict with services.
11. Easements
Easements for stormwater drainage shall be required over constructed drainage systems within private properties, to ensure that Council has full rights of access to such drainage systems for the purpose of inspection, maintenance or upgrade. Stormwater drainage easements shall be required for all inter-allotment drainage lines. Drainage easements will not be required within or over natural drainage systems and watercourses. Council does not favour or encourages the piping, construction within or over, or interference with natural drainage systems and watercourses. Any proposal to carry out such works will be subject to an assessment pursuant to other relevant Council policies and joint approval from other relevant authorities. Council will take the opportunity to acquire drainage easements over existing constructed public drainage systems within the private property whenever a development occurs by Condition of Consent. When a developer or property owner proposes to relocate or reconstruct a public drainage system within the site, a drainage easement in Council's favour must be created to suit the relocated or reconstructed drainage system at the cost to the developer. Any construction of buildings or other permanent structures over a public drainage easement is not permitted, unless the encroachment still permits reasonable access for Council to construct and maintain the system, that it does not impede or re-direct flows within the easement, that it does not load bear onto the underlying drainage structure, and that the site cannot be reasonably developed without the encroachment over the easement (refer to Council's Policy on Drainage Easements). Alternatively the conduit and easement may be relocated subject to Council approval. Any structural support such as footings and piers will only be permitted to be located adjacent to an easement if they do not load bear onto the underlying drainage structure, and that the built structure will not be undermined by any future maintenance work necessary within the easement. Planting of trees or large shrubs, particularly those with extensive root systems will not be permitted in drainage easements. Construction over a public drainage easement is prohibited unless Council does not require future access to the drainage structure for the life of the underlying structure. Public drainage easements must be free of encroachments with a minimum vertical clearance from the surface ground level over the drainage structure to a height of 5.0 metres above. Paved surfaces over the public drainage easement are permitted provided that construction joints along each longitudinal edge of the easement are installed to facilitate access to the drainage structure.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009 Page 29 of 49
These above figures are not to be used for pre-development calculations for the purpose of on-site detention sizing. Inter-allotment drainage pits and pipes shall be of reinforced concrete, fibre reinforced concrete or uPVC material. Pipes are to be rubber ring jointed or solvent welded as specified by the manufacturer and in accordance with AS4058, AS4139, and AS1254 respectively.
Scour protection devices shall include embankment stabilisation e.g. rock walls, concrete aprons, gabions, turfing, jute mesh, energy dissipating units, or other more appropriate erosion control devices approved by Council. Please note that some types of scour protection devices may be inappropriate along certain creek locations. In this regard, the Department of Lands may be contacted for advice about suitable erosion control measures. Control devices may be required as part of a development to remove pollutants during the "first flush". These devices shall be installed on line or within the site and may include proprietary items such as Humeceptors or CDS units, silt and grease arrestors approved by Council. Installation of these devices shall be in accordance with the manufacturer's specification. Other sediment control devices such as stilling basins, constructed wetlands shall be required for large-scale developments. These shall include land and community title subdivisions. Design of these devices shall be in accordance with the Managing Urban Stormwater, Soils and Construction Manual, NSW Department of Housing, August 1998.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 30 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 31 of 49
APPENDIX A1 Terms of Restriction on the Use of Land and Positive Covenant Existing Allotments
The generic wording for the terms of restriction on the use of land and positive covenant are given below. For existing allotments where there is no land subdivision, that is, there is no Section 88B instrument required, the following wording for the "Terms of Restriction on the Use of Land" and "Terms of Positive Covenant" shall be attached to the NSW Department of Lands standard forms 13RPA and 13PC respectively:
ii.
The Council may recover from the registered proprietor in a Court of competent jurisdiction: (a) Any expense reasonably incurred by it in exercising its powers under subparagraph (i) hereof. Such expense shall include reasonable wages for the Council's own employees engaged in effecting the said work, supervising the said work and administering the said work together with costs, reasonably estimated by the Council, for the use of machinery, tools and equipment in conjunction with the said work (b) Legal costs on an indemnity basis for issue of the said notices and recovery of the said costs and expenses together with the costs and expenses of registration of a covenant charge pursuant to section 88F of the Act or providing any certificate required pursuant to section 88G of the Act or obtaining any injunction pursuant to section 88H of the Act.
VI)
This covenant shall bind all persons who claim under the registered proprietors as stipulated in section 88E(5) of the Act.
For the purposes of this covenant: Structure and Works shall mean the on-site stormwater detention system constructed on the land as set out in the plan annexed hereto and marked with the letter 'A' (or alternatively as detailed on the plans approved by Council or Private Certifier No. {INSERT DA NUMBER/DRAWING NUMBER(S)/DESIGNER DETAILS/DATE/REVISION NUMBER}), including all gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers, basins and surfaces designed to temporarily detain stormwater on the land. The Act means the Conveyancing Act 1919.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 33 of 49
A2 Terms of Restriction on the Use of Land and Positive Covenant New Subdivisions
The generic wording for the terms of restriction on the use of land and positive covenant are given below. Where a subdivision has been lodged and a Section 88B instrument created, then the following wording for the "Terms of Restriction on the Use of Land" and "Terms of Positive Covenant" is to be included:
Terms of Restriction on the Use of Land referred to in the above mentioned Plan
The registered proprietor covenant with the City of Canada Bay Council (The Council) in respect to the structure erected on the land described as 'on-site stormwater detention system' (which expression includes all ancillary gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers, basins and surfaces designed to temporarily detain stormwater) shown on the plans approved by Council or Private Certifier No. {INSERT DA NUMBER/DRAWING NUMBER(S)/DESIGNER DETAILS/DATE/REVISION NUMBER} (herein called "the system"). The registered proprietors covenant with Canada Bay Council (The Council) that they will not: I) II) Do any act, matter or thing which would prevent the structure and works from operating in an efficient manner. Make any alterations or additions to the structure and works or allow any development within the meaning of the Environmental Planning and Assessment Act 1979 to encroach upon the structure and works without the express written consent of the authority. III) This covenant shall bind all persons who claim under the registered proprietors as stipulated in section 88E(5) of the Act. For the purposes of this covenant: Structure and Works shall mean the on-site stormwater detention system constructed on the land as set out in the plan annexed hereto and marked with the letter 'A' (or alternatively as detailed on the plans approved by Council or Private Certifier No.{ INSERT DA NUMBER/DRAWING NUMBER(S)/DESIGNER DETAILS/DATE/REVISION NUMBER}) including all gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers, basins and surfaces designed to temporarily detain stormwater on the land. The Act shall mean the Conveyancing Act 1919.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 34 of 49
i.
In the event that the registered proprietor fails to comply with the terms of any written notice issued by the Council as set out above the Council or its authorised agents may enter the land with all necessary equipment and carry out any work which the Council in its discretion considers reasonable to comply with the said notice referred to in (I) hereof.
ii. a.
The Council may recover from the registered proprietor in a Court of competent jurisdiction: Any expense reasonably incurred by it in exercising its powers under sub-paragraph (i) hereof. Such expense shall include reasonable wages for the Council's own employees engaged in effecting the said work, supervising the said work and administering the said work together with costs, reasonably estimated by the Council, for the use of machinery, tools and equipment in conjunction with the said work.
b.
Legal costs on an indemnity basis for issue of the said notices and recovery of the said costs and expenses together with the costs and expenses of registration of a covenant charge pursuant to section 88F of the Act or providing any certificate required pursuant to section 88G of the Act or obtaining any injunction pursuant to section 88H of the Act.
VI)
This covenant shall bind all persons who claim under the registered proprietors as stipulated in section 88E(5) of the Act.
For the purposes of this covenant: Structure and Works shall mean the on-site stormwater detention system constructed on the land as set out in the plan annexed hereto and marked with the letter 'A' (or alternatively as detailed on the plans approved by Council or Private Certifier No. {INSERT DA NUMBER/DRAWING NUMBER(S)/DESIGNER DETAILS/DATE/REVISION NUMBER}), including all gutters, pipes, drains, walls, kerbs, pits, grates, tanks, chambers, basins and surfaces designed to temporarily detain stormwater on the land. The Act means the Conveyancing Act 1919.
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 35 of 49
A3. Absorption Design Storage Method (Ref Rockdale Council's Stormwater Design Code)
Project: A= C= ARI = Absorption rate = Adjusted rate = No 10 Blogg Street, Drummoyne 409 1 100 0.00007 0.0000595 sqm* coefficient* years m/s* m/s minimum allowable clogging factor = 15% (* variables to be entered) length, L = width, B = depth, h = area = Available storage = 5 2.5 1 12.5 12.5 12500 m* m* m* sqm cum litres total impervious area collected
Checking storms duration (min) 5 6 7 8 9 10 12 15 20 25 30 40 45 50 55 60 65 70 75 80 85 90 100 120 180 270 intensity 241 227 211 202 194 189 174 164 144 132 120 102 97 90.6 85.8 84 77.9 74.6 71.5 68.7 66.2 66 59.8 55.3 42.7 32.3 inflow rate (l/s) 27 26 24 23 22 21 20 19 16 15 14 12 11 10 10 10 9 8 8 8 8 7 7 6 5 4 vi (l) 8214 9284 10068 11016 11902 12884 14233 16769 19632 22495 24540 27812 29755 30880 32168 34356 34516 35597 36554 37464 38357 40491 40764 45235 52393 59448 vo (l) 2231 2678 3124 3570 4016 4463 5355 6694 8925 11156 13388 17850 20081 22313 24544 26775 29006 31238 33469 35700 37931 40163 44625 53550 80325 120488 vi - vo (l) 5983 6607 6944 7446 7886 8421 8878 10075 10707 11339 11153 9962 9674 8567 7624 7581 5510 4359 3086 1764 426 329 -3861 -8315 -27932 -61039
Note: This method does not allow emptying time. It is assumed the trench fills and quickly empties instantaneously. Since available storage is greater than the maximum storage required - ok
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 36 of 49
A4 ILSAX Rainfall Files for the 5-yr, 20-yr and 100-yr ARI Storm Events
5-yr ARI stacked rainfall
3 2 11 5 YR. 10 MIN. ARI CCBC 1 2 -1 0 -0.300 0 1 5 10.00 5.00 1.00 1 0 5 YR. 15 MIN. ARI -1 0 1 5 15.00 5.00 1.00 1 0 5 YR. 20 MIN. ARI -1 0 1 5 20.00 5.00 1.00 1 0 5 YR. 25 MIN. ARI -1 0 1 5 25.00 5.00 1.00 1 0 5 YR 30 MIN. ARI -1 0 1 5 30.00 5.00 1.00 1 0 5 YR. 45 MIN. ARI -1 0 1 5 45.00 5.00 1.00 1 0 5 YR. 1 HOUR ARI -1 0 1 5 60.00 5.00 1.00 1.000
Page 37 of 49
-375
0.300
5 122
3.00 1.000
5 103
3.00 1.000
90.1
3.00 1.000
80.9
3.00 1.000
73.9
3.00 1.000
60.3
3.00
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
1 0
51.2
5 YR. 1.5 HOUR ARI -1 0 1 5 90.00 5.00 2.00 1 0 5 YR 2 HOUR ARI -1 0 1 5 120.00 5.00 2.00 1 0 5 YR 3 HOUR ARI -1 0 1 5 180.00 15.00 2.00 1 0 5 YR. 4.5 HOUR ARI -1 0 1 5 270.00 15.00 5.00 1 0 5. 19.8 1.000 3.00 5 25.7 1.000 3.00 5 33.3 1.000 3.00 5 39.9 1.000 3.00
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 38 of 49
-375
0.300
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
67.7
-1 0 1
3.00 1.000
5 90.00 5.00 2.00 1 20 0 20 YR. 2 HOUR ARI -1 0 1 5 120.00 5.00 2.00 1 20 0 20 YR. 3 HOUR ARI -1 0 1 5 180.00 15.00 2.00 1 20 0 34.1 3.00 44.1 3.00 52.8
1.000
1.000
20 YEAR, 4.5 HOUR ARI -1 0 3.00 1 5 270 15.00 2.00 1.000 1 20 26.4 0
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 40 of 49
-375
0.300
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
3.00 1.000
89.4
-1 0 1
3.00 1.000
5 90.00 5.00 2.00 1 100 0 100 YR. 2 HOUR ARI -1 0 1 5 120.00 5.00 2.00 1 100 0 100 YR. 3 HOUR ARI -1 0 1 5 180.00 15.00 2.00 1 100 0 100 YR.4.5 HOUR ARI -1 0 1 5 270.00 15.00 5.00 1 100 0 35 3.00 45.2 3.00 58.4 3.00 69.8
1.000
1.000
1.000
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 42 of 49
A5 Standard Drawings
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 43 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 44 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 45 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 46 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 47 of 49
Owner: Technical Services and Operations - City Assets Last Revised: 11/03/2009
Page 48 of 49
Owner: Technical Services and Operations City Assets 1a Marlborough Street, Drummoyne NSW 2047 Last Revised: 11/03/2009 Tel 9911 6555 Fax 9911 6550 www.canadabay.nsw.gov.au
Page 49 of 49