Beruflich Dokumente
Kultur Dokumente
Calculate the net present value of the following project for discount rates of 0, 50, and 100%: Cash flows ($) C(1) C(2) 4500 18000
Present values 0% 50% -6750 -6750 4500 3000 18000 8000 15750 4250
b. What is the IRR of the project? Answer: the IRR is the rate such that the NPV=0. Therefore, based on part a, the IRR equals 100%.
Time: CF:
0 -100
1 200
2 -75
a. Which of the following numbers is the project IRR: (i) -50%; (ii) -12%; (iii) +5%; (iv) +50%
b. The opportunity cost of capital is 20%. Is this an attractive project? Briefly explain.
Rate 20%
NPV 14.58
Cash flows Project Alpha Beta 0 -400000 -200000 1 241000 131000 2 293000 172000 IRR 21% 31%
a. What are the incremental cash flows from investing in Alpha relative to Beta? Answer: 0 -200000 1 110000 2 IRR 121000
Increment
10%
Answer: see IRR above. c. The opportunity cost of capital is 8%. Suppose you can undertake Apha or Beta, but not both. Which project should you take? Answer: The IRR on project Beta is greater than 8% and the incremental IRR on Alpha is greater than 8%. Therefore you should take Alpha over Beta.
Problem 4 Calculate the IRR (or IRRs) for the following project:
Time: CF:
0 -3000
1 3500
2 4000
3 -4000
For what range of discount rates does the project have a positive NPV?
Answer: Year 0 1 2 3 PV= CF -3000 3500 4000 -4000 Present value at different rates -17.44% 0% 10% -3000 -3000 -3000 4239 3500 3182 5868 4000 3306 -7108 -4000 -3005 0 500 482 15% -3000 3043 3025 -2630 438 20% -3000 2917 2778 -2315 380 25% -3000 2800 2560 -2048 312
The two IRRs for this project are approximately : -17.44% and 45.27%. Between these two discount rates the NPV
Problem 5
The Titanic Shipbuilding Company has a noncancelable contract to build a small cargo vessel. Construction involv $250,000 at the end of each of the next two years. The company can speed up construction by working an extra there will be a cash outlay of $550,000 at the end of the first year followed by a cash payment of $650,000 at the year. Use the IRR rule to show the (approximate) range of opportunity costs of capital at which the company sho shift.
Answer using incremental analysis: Time: 1 Current arrangement -250000 Extra shift 550000 Incremental flows -300000
3 650000 0 -650000
NPV of incremental flows for different rates: Rate NPV -50.00% -1100000 -25.00% -255556 0.00% -50000 15.00% -8885 20.00% -1389 21.13% -3 25.00% 4000 50.00% 11111 75.00% 2041 78.87% -1 80.00% -617 The IRRs for the incremental cash flows are (approximately): 21.13% and 78.87%. If the cost of capital is between these rates, Titanic should work the extra shift.
essel. Construction involves a cash outlay of ction by working an extra shift. In this case ayment of $650,000 at the end of the second at which the company should work the extra