Sie sind auf Seite 1von 36

CHAPTER 3

DISCUSSION QUESTIONS

Q3-1.

Q3-2.

Q3-3.

Q3-4.

The total dollar amount of a fixed cost is constant at different levels of activity within the
relevant range, but fixed cost per unit of activity varies. In contrast, the total amount of a
variable cost varies at different levels of activity, but the variable cost per unit remains constant within the relevant range. A semivariable
cost contains both fixed and variable elements. Consequently, both total semivariable
cost and semivariable cost per unit vary with
changes in activity.
The relevant range is the range of activity
over which a fixed cost remains constant in
total or a variable cost remains constant per
unit of activity. The underlying assumptions
about the relationship of the activity and the
incurrence of cost change outside the relevant range of activity. Consequently, the
amount of fixed cost or the variable cost rate
must be recomputed for activity above or
below the relevant range.
The fixed and variable components of a semivariable cost should be segregated in order to
plan, analyze, control, measure, and evaluate
costs at different levels of activity. Separation
of the fixed and variable components of semivariable cost is necessary to:
(a) compute predetermined factory overhead
rates and analyze variances;
(b) prepare flexible budgets and analyze variances;
(c) analyze direct cost and the contribution
margin;
(d) determine the break-even point and analyze the effect of volume on cost and
profit;
(e) compute differential cost and make comparative cost analyses;
(f) maximize short-run profits and minimize
short-run costs;
(g) budget capital expenditures;
(h) analyze marketing profitability by territories, products, and customers.
The obvious advantage to using managerial
judgement to separate fixed and variable

3-1

Q3-5.

Q3-6.

Q3-7.

costs is expediency, i.e., it requires less time


and is, therefore, less costly than the use of
any of the three computational methods. The
disadvantage is that the use of managerial
judgment to separate fixed and variable costs
often results in unreliable estimates of cost.
Cost behavior is not always readily apparent
from casual observation. As a consequence,
managers often err in determining whether a
cost is fixed or variable and frequently ignore
the possibility that some costs are semivariable.
The three computational methods available
for separating the fixed and variable components of semivariable costs are: (1) the high
and low points method; (2) the statistical scattergraph method; and (3) the method of least
squares.
The high and low points method has the
advantage of being simple to compute, but it
has the disadvantage of using only two data
points in the computation, thereby resulting in
a significant potential for bias and inaccuracy
in cost estimates. The scattergraph has the
advantage of using all of the available data,
but it has the disadvantage of determining the
fixed and variable components on the basis of
a line drawn by visual inspection through a
plot of the data, thereby resulting in bias and
inaccuracy in cost estimates. The method of
least squares has the advantage of accurately describing a line through all the available data, thereby resulting in unbiased
estimates of the fixed and variable elements
of cost, but it has the increased disadvantage
of computational complexity.
The $200 in the equation, referred to as the
y intercept, is an estimate of the fixed portion
of indirect supplies cost. The $4 in the equation, referred to as the slope of the regression equation, is an estimate of the variable
cost associated with a unit change in
machine hours. These estimates may not be
perfectly accurate because they were derived
from a sample of data that may not be entirely

3-2

Q3-8.

Q3-9.

Chapter 3

representative of the universe population,


and because activities not included in the
regression equation may have some influence on the cost being predicted.
The coefficient of correlation, denoted r, is a
measure of the extent to which two variables
are related linearly. It is a measure of the
covariation of the dependent and independent variables, and its sign indicates whether
the independent variable has a positive or
negative relationship to the dependent variable. The coefficient of determination is the
square of the coefficient of correlation and is
denoted r 2. The coefficient of determination is
a more easily interpreted measure of the
covariation than is the coefficient of correlation, because it represents the percentage of
variation in the dependent variable explained
by the independent variable.
The standard error of the estimate is defined
as the standard deviation about the regression line. It is essentially a measure of the
variability of the actual observations of the
dependent variable from the points predicted
on the regression line. A small value for the
standard error of the estimate indicates a

good fit. A standard error of zero would indicate a perfect fit, i.e., all actual observations
would be on the regression fine.
Q3-10. Heteroscedasticity means that the distribution
of observations around the regression line is
not uniform for all values of the independent
variable. If heteroscedasticity is present, the
standard error of the estimate and confidence
interval estimates, based on the standard
error, are unreliable measures.
Q3-11. Serial correlation means that rather than
being random, the observations around the
regression line are correlated with one
another. If serial correlation is present, the
standard error of the estimate and confidence
interval estimates, based on the standard
error, are unreliable measures.
Q3-12. Multicollinearity means that two or more of
the independent variables in a multiple
regression analysis are correlated with one
another. When the degree of multicollinearity
is high, the relationship between one or more
of the correlated independent variables and
the dependent variable may be obscured.
However, this circumstance would normally
not affect the estimate of cost.

Chapter 3

3-3

EXERCISES
E3-1
Activity Level
High............................................ 2,600 hours
Low............................................. 2,100
Difference ..................................
500 hours

Cost
$1,300
1,100
$ 200

Variable rate: $200 500 machine hours = $.40 per machine hour
High
$1,300

Low
$1,100

Total cost ...................................


Variable cost:
$.40 2,600 hours........
1,040
$.40 2,100 hours........
Fixed cost.................................. $ 260

840
$ 260

E3-2
$1,000
$900

SUPPLIES COST

$800
$700
$600
$500
$400
$300
$200
$100
$0
0

200

400

600

DIRECT LABOR HOURS

Average cost ($7,575 total 10 months)....................


Fixed cost per month ...................................................

$757.50
350.00

Average total variable cost ..........................................

$407.50

$407.50 average total variable cost


5,875 total direct labor hours 10 months

$.6936 variable cost


per direct labor hour

800

3-4

Chapter 3

E3-3
( x i x )(y i y ) 87, 000
=
= $60
( x i x )2
1, 450
a = y bx = $10,000 ($60 125) = $2,500
Travel and entertainment expense for 200 sales calls would be:
yi = a + bxi = $2,500 + ($60 200 calls) = $14,500
b=

E3-4
(1)
y
Electricity
Cost
Month
January...... $1,600
February .... 1,510
March ......... 1,500
April ........... 1,450
May............. 1,460
June ........... 1,520
July ............ 1,570
August ....... 1,530
September . 1,480
October...... 1,470
November .. 1,450
December .. 1,460
Total
$18,000

(2)
)
(y y
Cost
Deviation
100
10
0
(50)
(40)
20
70
30
(20)
(30)
(50)
(40)
0

(3)
x
Machine
Hours
2,790
2,680
2,600
2,500
2,510
2,610
2,750
2,700
2,530
2,520
2,490
2,520
31,200

(4)
(x x)
Activity
Deviation
190
80
0
(100)
(90)
10
150
100
(70)
(80)
(110)
(80)
0

(5)
(x x)2

(6)

)
(x x )(y y

(4) Squared
36,100
6,400
0
10,000
8,100
100
22,500
10,000
4,900
6,400
12,100
6,400
123,000

(4) (2)
19,000
800
0
5,000
3,600
200
10,500
3,000
1,400
2,400
5,500
3,200
54,600

y = y = n = $18,000 12 = $1,500
x = x = n = 31,200 12 = 2,600
54, 600
( x x )(y y ) Column 6 total
=
= $.44
=
2
( x x )
Column 5 total 123, 000
bx
Fixed cost (a) = y
= $1,500 ($.44)(2,600)
= $356
Variable rate (b ) =

Chapter 3

3-5

E3-5
r=

( x i x )(y i y )
( x i x )2 (y i y )2

1, 564
(850) (3, 400)

= .92

r 2 = (.92)2 .8464
E3-6
(1)
y
Shipping
Month
Expense
January ..... $ 560
February....
600
March ........
600
April...........
580
May ............
570
June...........
550
July ............
590
August.......
610
September
650
October .....
620
November .
630
December..
640
Total....... $7,200

(2)
)
(y y
Expense
Deviations
(40)
0
0
(20)
(30)
(50)
(10)
10
50
20
30
40
0

(3)
x
Sales
Revenue
$26,500
30,000
29,000
28,000
27,000
25,500
30,000
33,000
35,000
32,000
30,500
33,500
$360,000

(4)
(x x)
Activity
Deviations
(3,500)
0
(1,000)
(2,000)
(3,000)
(4,500)
0
3,000
5,000
2,000
500
3,500
0

(5)
(x x)2

(6)
)
(x x)(y y

(7)
)2
(y y

(4) Squared
12,250,000
0
1,000,000
4,000,000
9,000,000
20,250,000
0
9,000,000
25,000,000
4,000,000
250,000
12,250,000

(4) (2)
140,000
0
0
40,000
90,000
225,000
0
30,000
250,000
40,000
15,000
140,000

(2) Squared
1,600
0
0
400
900
2,500
100
100
2,500
400
900
1,600

97,000,000

970,000

y = y n = $7, 200 12 = $600


x = x n = $360, 000 12 = $30, 000
( x x )(y y )
970, 000
r=
=
= .939
2
2
(97, 000, 000) (11, 000)
( x i x ) (y i y )
39)2 = .882
r 2 = (.93

11,000

3-6

Chapter 3

E3-7
(1)

r=

( x i x )(y i y )

( x i x )2 (y i y )2

2, 400
= .96
(6, 250) (1, 000)

r 2 = (.96)2 = .9216

(2)

(3)

b=

( x i x )(y i y ) 2, 400
variable maintenance
=
= $.384
2
cost
per machine ho
our
( x i x )
6, 250

y = y i n = $50, 000 10 = $5, 000


x = x i n = 40, 000 10 = 4, 000 hours
Since y = a + bx , then :
a = y bx
a = $5, 000 ($.384 )(4, 000)
a = $5, 000 $1, 536
a = $3, 464

E3-8
(1)

For electricity cost and direct labor hours:


r=

( x i x )(y i y )
( x i x ) (y i y )
2

5, 700
5, 700
= .9497
=
(28, 500) (1, 264 ) 6, 002

r 2 = (.9497 )2 = .9019
(2)

For electricity cost and machine hours:


r=

( x i x )(y i y )
( x i x )2 (y i y )2

7, 000
7, 000
= .8805
=
(50, 000) (1, 264 ) 7, 950

r 2 = (.8805)2 = .7753
(3)

In this case, direct labor hours should be chosen as the appropriate activity
measure to be used in predicting electricity cost because the coefficient of
determination (r2 = .9019) is higher than that for machine hours (r2 = .7753).

Chapter 3

3-7

E3-8 (Concluded)
(4)

b=

( x i x )(y i y )
5, 700
variable ellectricity
=
= $.20
2
cost rate
( x i x )
28, 500

Since y = a + bx and y = y i n and x = x i n, then :


a = ( y i n ) b ( x i n )
42, 000 20) (.20)(180, 000 20)
a = (4
a = 2, 100 (.20)(9, 000)
a = 2, 100 1, 800 = $300 fixed electricity cost
E3-9
(1)
xi
Month
January ..................
February ................
March .....................
April........................
May .........................
June........................
July.........................
August....................
September .............
October ..................
November ..............
December ..............
Total....................

s=

Labor
Hours
2,650
3,000
2,900
2,800
2,700
2,550
3,000
3,300
3,500
3,200
3,050
3,350
36,000

(2)
yi
Actual
Utility
Cost
$ 3,600
4,000
4,000
3,800
3,700
3,500
3,900
4,100
4,500
4,200
4,300
4,400
$48,000

(3)
(4)
(5)
(yi = a + bxi) (yi yi)
(yi yi)2
Predicted Prediction
Utility
Error
(4)
Cost
(2) (3)
Squared
$ 3,650
(50)
$2,500
4,000
0
0
3,900
100
10,000
3,800
0
0
3,700
0
0
3,550
(50)
2,500
4,000
(100)
10,000
4,300
(200)
40,000
4,500
0
0
4,200
0
0
4,050
250
62,500
4,350
50
2,500
$48,000
0
$130,000

(y i y i )2
Column 5 total
$130, 000
=
=
= $114.018
12 2
10
n 2

3-8

Chapter 3

E3-10
s=

(y i y i )2
$49, 972
=
= 3, 844 = $62
15 2
n 2

The 90 percent confidence interval estimate at the 1,500-hour level of activity


would be:
y i t 90% s 1+

( x i x )2
1
+
n ( x i x )2

$500 (1.771)($62) 1+

1 (1, 500 1, 300)2


+
150, 000
15

$500 (1.771)($62) 1.3333


$500 (1.771)($62) (1
1.1547 )
$500 $126.79

Chapter 3

3-9

PROBLEMS
P3-1
(1)

Coefficient of correlation and coefficient of determination between:


(a) Travel expenses and the number of calls made:
(1)
y
Travel
Expense

Month
January............
February ..........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........
Total

r=
r=
r=

(2)
)
(y y
Expense
Deviations

(3)
x
Calls
Made

$ 3,000
3,200
2,800
3,400
3,100
3,200
2,900
3,300
3,500
3,400
3,200
3,400

(200)
0
(400)
200
(100)
0
(300)
100
300
200
0
200

410
420
380
460
430
450
390
470
480
490
440
460

$38,400

5,280

( x i x )(y i y )
( x i x )2 (y i y )2

(4)
(x x)
Activity
Deviations
(30)
(20)
(60)
20
(10)
10
(50)
30
40
50
0
20

r 2 = .8957

(6)

)
(x x )(y y

(7)
)2
(y y

(4) Squared

(4) (2)

(2) Squared

900
400
3,600
400
100
100
2,500
900
1,600
2,500
0
400

6,000
0
24,000
4,000
1,000
0
15,000
3,000
12,000
10,000
0
4,000

40,000
0
160,000
40,000
10,000
0
90,000
10,000
90,000
40,000
0
40,000

13,400

79,000

520,000

Column 6 total
(Column 5 total) (Column 7 total)

79, 000
79, 000
=
00
(13, 400)(520, 000)
6, 968, 000, 00
79, 000
= .9464
83, 475

(5)
(x x)2

3-10

Chapter 3

P3-1 (Concluded)
(b)

Travel expenses and orders received:

Month
January............
February .........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........

(1)
y
Travel
Expense
$ 3,000
3,200
2,800
3,400
3,100
3,200
2,900
3,300
3,500
3,400
3,200
3,400

Total ............

$38,400

r=
=
=

(2)
(3)
(4)

(y y )
x
(x x)
Expense
Orders
Activity
Deviations Received Deviations
(200)
$53,000 (13,000)
0
65,000
(1,000)
(400)
48,000 (18,000)
200
73,000
7,000
(100)
62,000
(4,000)
0
67,000
1,000
(300)
60,000
(6,000)
100
76,000
10,000
300
82,000
16,000
200
62,000
(4,000)
0
64,000
(2,000)
200
80,000
14,000
0

$792,000

( x i x )(y i y )
( x i x ) (y i y )
2

(5)
(x x)2
(4) Squared
169,000,000
1,000,000
324,000,000
49,000,000
16,000,000
1,000,000
36,000,000
100,000,000
256,000,000
16,000,000
4,000,000
196,000,000
1,168,000,000

(6)
(7)

)2
(x x )(y y ) (y y
(4) (2) (2) Squared
2,600,000
40,000
0
0
7,200,000 160,000
1,400,000
40,000
400,000
10,000
0
0
1,800,000
90,000
1,000,000
10,000
4,800,000
90,000
(800,000) 40,000
0
0
2,800,000
40,000
21,200,000

520,000

Column 6 total
(Column 5 total) (Column 7 total)

21, 200, 000


21, 200, 000
=
607, 360, 000, 000, 000
(1, 168, 000, 000)(520, 000)
21, 000, 000
= .8602
24, 644, 675

r 2 = .7399
(2)

Perfect direct correlation would be evidenced by a correlation coefficient of one.


The coefficient of .9464 revealed in (1)(a) is closer to one than the coefficient of
.8602 in (1)(b). This means that the variable portion of travel expense varies more
directly with movements in the number of calls made than with the value of orders
received. To explain this further, the relative coefficients of determination are
obtained by squaring the coefficients of correlation and expressing the answer
as a percentage in each case. The coefficients of determination are 89.57% for
calls made and only 73.99% for orders received. This means that approximately
90% of the movements in the variable portion of travel expense are related to fluctuations in the number of calls made, and the remaining 10% of the movements
are related to other factors.

Chapter 3

3-11

P3-2
(1)

Month
January............
February ..........
March ...............
April ................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........

(1)
y
Supplies
Cost
$ 1,505
1,395
1,565
1,515
1,445
1,415
1,465
1,505
1,575
1,535
1,500
1,580

(2)
)
(y y
Cost
Deviations
5
(105)
65
15
(55)
(85)
(35)
5
75
35
0
80

Total ............. $18,000

(3)
x
Labor
Hours
5,000
4,600
5,160
5,100
4,830
4,750
4,900
5,080
5,200
5,130
4,950
5,300
60,000

(4)
(x x)
Activity
Deviations
0
(400)
160
100
(170)
(250)
(100)
80
200
130
(50)
300
0

(5)
(x x)2
(4) Squared
0
160,000
25,600
10,000
28,900
62,500
10,000
6,400
40,000
16,900
2,500
90,000
452,800

y = y n = $18, 000 12 = $1, 500


x = x n = $60, 000 12 = $5, 000
r=

( x x )(y y )
( x x )2 (y y )2

r 2 = (.977 )2 = .955

131, 950
= .977
(452, 800) (40, 250)

(6)
(7)

)2
(x x )(y y ) (y y
(4) (2)
0
42,000
10,400
1,500
9,350
21,250
3,500
400
15,000
4,550
0
24,000
131,950

(2) Squared
25
11,025
4,225
225
3,025
7,225
1,225
25
5,625
1,225
0
6,400
40,250

3-12

Chapter 3

P3-2 (Concluded)

Month
January............
February ..........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........

(1)
y
Supplies
Cost
$ 1,505
1,395
1,565
1,515
1,445
1,415
1,465
1,505
1,575
1,535
1,500
1,580

(2)
)
(y y
Cost
Deviations
5
(105)
65
15
(55)
(85)
(35)
5
75
35
0
80

Total ............ $18,000

(3)
(4)
x
(x x)
Machine Activity
Hours Deviations
2,000
(50)
1,990
(60)
2,140
90
2,080
30
1,960
(90)
1,940
(110)
2,020
(30)
1,990
(60)
2,140
90
2,050
0
2,030
(20)
2,260
210
24,600

(5)
(x x)2
(4) Squared
2,500
3,600
8,100
900
8,100
12,100
900
3,600
8,100
0
400
44,100
92,400

(6)
(7)
) (y y)2
(x x)(y y
(4) (2)
(250)
6,300
5,850
450
4,950
9,350
1,050
(300)
6,750
0
0
16,800

(2) Squared
25
11,025
4,225
225
3,025
7,225
1,225
25
5,625
1,225
0
6,400

50,950

40,250

y = y n = $18, 000 12 = $1, 500


x = x n = $24, 600 12 = 2, 050
( x x )(y y )
50, 950
r=
=
= .835
(92, 400) (40, 250)
( x x )2 (y y )2
r 2 = (.835)2 = .69
97

(2)

Since the coefficient of determination for supplies cost and labor hours (r 2 = .955)
is greater than the coefficient of determination for supplies cost and machine
hours (r 2 = .697), labor hours should be used as the basis for estimating supplies
cost. Labor hours explain more of the variance in supplies cost than do machine
hours.

(3)

With labor hours as the basis for predicting supplies cost, the fixed cost and the
variable cost rate can be determined by the method of least squares as follows:
( x x )(y y ) Column 6 total 131, 950
=
= $.29141
=
( x x )2
Column 5 total 452, 800
= y bx

Variable rate (b ) =
Fixed cost (a )

= $1, 500 ($.29141)(5, 000)


= $42.95

Chapter 3

3-13

P3-3

Month
January............
February ..........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........

(1)
y
Electricity
Cost
$1,600
1,570
1,610
1,550
1,530
1,540
1,520
1,530
1,580
1,650
1,660
1,620

(2)
)
(y y
Cost
Deviations
20
(10)
30
(30)
(50)
(40)
(60)
(50)
0
70
80
40

Total ............. $18,960

(3)
x
Labor
Hours
4,200
4,000
4,360
4,000
4,050
4,100
4,150
4,250
4,150
4,500
4,600
4,400
50,760

(4)
(x x)
Activity
Deviations
(30)
(230)
130
(230)
(180)
(130)
(80)
20
(80)
270
370
170
0

(5)
(x x)2
(4) Squared
900
52,900
16,900
52,900
32,400
16,900
6,400
400
6,400
72,900
136,900
28,900

(4) (2)
(600)
2,300
3,900
6,900
9,000
5,200
4,800
(1,000)
0
18,900
29,600
6,800

(2) Squared
400
100
900
900
2,500
1,600
3,600
2,500
0
4,900
6,400
1,600

424,800

85,800

25,400

y = y n = $18, 960 12 = $1, 580


x = x n = $50, 760 12 = 4, 230
r=

( x x )(y y )
( x x ) (y y )
2

r 2 = (.826)2 = .682

(6)
(7)
) (y y)2
(x x)(y y

85, 800
= .826
(424, 800) (25, 400)

3-14

Chapter 3

P3-3 (Concluded)

Month
January............
February ..........
March ..............
April .................
May ..................
June .................
July ..................
August ............
September.......
October............
November ........
December ........

(1)
y
Electricity
Cost
$1,600
1,570
1,610
1,550
1,530
1,540
1,520
1,530
1,580
1,650
1,660
1,620

(2)
)
(y y
Cost
Deviations
20
(10)
30
(30)
(50)
(40)
(60)
(50)
0
70
80
40

Total ........... $18,960

(3)
(4)
x
(x x)
Machine Activity
Hours Deviations
2,300
0
2,150
(150)
2,400
100
2,250
(50)
2,160
(140)
2,240
(60)
2,180
(120)
2,170
(130)
2,260
(40)
2,500
200
2,540
240
2,450
150
27,600

(5)
(x x)2

(6)
(7)
) (y y)2
(x x)(y y

(4) Squared
0
22,500
10,000
2,500
19,600
3,600
14,400
16,900
1,600
40,000
57,600
22,500

(4) (2)
0
1,500
3,000
1,500
7,000
2,400
7,200
6,500
0
14,000
19,200
6,000

(2) Squared
400
100
900
900
2,500
1,600
3,600
2,500
0
4,900
6,400
1,600

211,200

68,300

25,400

y = y n = $18, 960 12 = $1, 580


x = x n = $27, 600 12 = 2, 300
r=

( x x )(y y )
( x x )2 (y y )2

68, 300
= .933
(211, 200) (25, 400)

r 2 = (.933)2 = .870
(2)

Since the coefficient of determination for electricity cost and machine hours
(r2 = .870) is greater than the coefficient of determination for electricity cost
and labor hours (r2 = .682), machine hours should be used as the basis for
estimating electricity cost. Machine hours explain more of the variance in
electricity cost than do labor hours.

(3)

With machine hours as the basis for predicting electricity cost, the fixed cost
and the variable cost rate can be determined by the method of least squares as
follows:
( x x )(y y ) Column 6 total 68, 300
=
= $.32339
=
( x x )2
Column 5 total 211, 200
= y bx

Variable rate (b ) =
Fixed cost (a )

= $1, 580 ($.32339)(2, 300)


= $836.20

Chapter 3

3-15

P3-4
(1)

High .................................................................
Low ..................................................................
Difference........................................................

Maintenance
Cost
$2,290
2,000
$ 290

Machine
Hours
2,700
2,000
700

Variable rate = $290 700 hours = $.4142857 per machine hour


Total cost ........................................................
Total variable cost ..........................................
Average fixed cost .........................................
(2)

(1)
(2)
)
yi
(yi y
Maintenance
Cost
Month
Cost
Deviations
January............ $2,200
40
February ..........
2,130
(30)
March ...............
2,000
(160)
April .................
2,170
10
May ..................
2,050
(110)
June .................
2,220
60
July ..................
2,150
(10)
August .............
2,250
90
September.......
2,290
130
October............
2,150
(10)
November ........
2,210
50
December ........
2,100
(60)
Total ........... $25,920

(3)
(4)
xi
(xi x)
Machine Activity
Hours Deviations
2,500
100
2,350
(50)
2,000
(400)
2,400
0
2,100
(300)
2,600
200
2,450
50
2,550
150
2,700
300
2,450
50
2,400
0
2,300
(100)
28,800

High
$2,290.00
1,118.57
$1,171.43
(5)
(xi x)2
(4) Squared
10,000
2,500
160,000
0
90,000
40,000
2,500
22,500
90,000
2,500
0
10,000
430,000

Low
$2,000.00
828.57
$1,171.43
(6)
(7)

)2
(xi x )(yi y ) (yi y
(4) (2)
4,000
1,500
64,000
0
33,000
12,000
(500)
13,500
39,000
(500)
0
6,000

(2) Squared
1,600
900
25,600
100
12,100
3,600
100
8,100
16,900
100
2,500
3,600

172,000

y = y i n = $25, 920 12 = $2, 160


x = x i n = $28, 800 12 = 2, 400
( x x )(y y ) Column 6 total 172, 000
ariable cost rate
=
=
= $.40 va
( x x )2
Column 5 total 430, 000
Since y = a + bx , then :
a = y bx
b=

a = $2, 160 ($.40)(2, 40


00 )
a = $2, 160 $960
a = $1, 200

75,200

3-16

Chapter 3

P3-4 (Concluded)
(3)
r=
r=

( x x )(y y )
( x i x )2 (y i y )2

Column 6 total
olumn 7 total)
(Column 5 total) (Co

172, 000
172, 000
172, 000
=
=
= .9565
(430, 000)(75, 200)
32, 336, 000,0
000 179, 822

r 2 = (.9565)2 = .91489
(4)

(1)

xi
Month
January ..................
February ................
March .....................
April........................
May .........................
June........................
July.........................
August....................
September .............
October ..................
November ..............
December ..............
Total....................

s=
(5)

Machine
Hours
2,500
2,350
2,000
2,400
2,100
2,600
2,450
2,550
2,700
2,450
2,400
2,300
28,800

(2)

(3)

(4)

yi
(yi = a + bxi) (yi yi)
Actual
Predicted Prediction
Maintenance Maintenance
Error
Cost
Cost
(2) (3)
$2,200
$2,200
$0
2,130
2,140
(10)
2,000
2,000
0
2,170
2,160
10
2,050
2,040
10
2,220
2,240
(20)
2,150
2,180
(30)
2,250
2,220
30
2,290
2,280
10
2,150
2,180
(30)
2,210
2,160
50
2,100
2,120
(20)
$25,920
$25,920
$0

(5)

(yi yi)2
(4)
Squared
$0
100
0
100
100
400
900
900
100
900
2,500
400
$6,400

(y i y i )2
Column 5 total
$6, 400
=
=
= $25.29822
12 2
10
n 2

The 95% confidence interval for maintenance cost at the 2,500 machine hour
level of activity is
y t 95%

( x i x )2
1
s 1+ +
n ( x i x )2

1 (2, 500 2, 400)2


$1, 200 + ($.40)(2, 500) (2.228)(25.29822) 1+
+
12
430, 000
$2, 200 $59.29

Chapter 3

3-17

P3-5
(1)

(a)

The method of least squares:

(1)
yi

Month
January............
February ..........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........
Total ...........

b=

Electricity
Cost
$ 400
500
500
700
600
800
1,000
900
900
700
600
800
$8,400

(2)
)
(yi y
Difference
from
Average of
$700
Electricity
Cost
$(300)
(200)
(200)
0
(100)
100
300
200
200
0
(100)
100
0

(3)
xi

Guest
Days
1,000
1,500
2,500
3,000
2,500
4,500
6,500
6,000
5,500
3,000
2,500
3,500

(4)
(xi x)
Difference
from
Average of
3,500
Guest
Days
(2,500)
(2,000)
(1,000)
(500)
(1,000)
1,000
3,000
2,500
2,000
(500)
(1,000)
0

42,000

(5)
(xi x)2

(4) Squared
(000s
omitted)
6,250
4,000
1,000
250
1,000
1,000
9,000
6,250
4,000
250
1,000
0
34,000

(6)
(7)
) (y y)2
(xi x)(yi y
i

(4) (2)
(000s
omitted)
$ 750
400
200
0
100
100
900
500
400
0
100
0
$3,450

( x i x )(y i y ) Column 6 total $3, 450


= $.1015 variable rate
=
=
( x i x )2
Column 5 total 34, 000

Since y = a + bx , then:
$700 = a + ($.1015 3, 500)
a = $700 $355
a = $345 fixed cost per month

(2)
Squared
(000s
omitted)
$ 90
40
40
0
10
10
90
40
40
0
10
10
$380

3-18

Chapter 3

P3-5 (Continued)
(b)

The high and low points method:


Electricity
Cost
$1,000
400
$ 600

High ............................................................
Low.............................................................
Difference ..................................................

Guest
Days
6,500
1,000
5,500

$600
= $.1091 per guest day
5, 500
= $1, 000 (6, 500 $.1091)

Variable rate =
Fixed cost

= $1, 000 $709


= $291
OR
Fixed cost

= $400 (1, 000 $.1091)


= $400 $109
= $291

(c)

A scattergraph with trend line fitted by inspection:


$1,100
$1,000

ELECTRICITY COST PER MONTH

July
$900
Dec.

Sept.

Aug.

$800
June

Apr. & Oct.

$700
$600

May & Nov.

$500
Feb.
$400

Mar.

Jan.
Approx. $350

$300
$200
$100
$0
0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

GUEST DAYS PER MONTH

Fixed cost per month


determined
by inspection....... $350
Average cost ...........
Less fixed cost........
Variable cost ...........

$700
350
$350

$350
3,500 average guest days

$.10 variable cost


per guest day

Chapter 3

3-19

P3-5 (Continued)
(2)

The coefficient of correlation (r) and the coefficient of determination (r2), using
data from the requirement (1)(a) answer:
r =
r =
=

( x i x )(y i y )
( x i x )2 (y i y )2

Column 6 total
(Column 5 total) (Column 7 total)

3, 450, 000
3, 450, 000
=
(34, 000, 000)(380, 000)
12, 920, 000, 000, 000
3, 450, 000
= .9598
3, 594, 440

r 2 = .9212
(3)

The standard error of the estimate:

Month
January ..................
February ................
March .....................
April........................
May .........................
June........................
July ........................
August....................
September .............
October ..................
November ..............
December ..............
Total....................

(1)
xi

(2)
yi

(3)
(yi = a + bxi )

Guest
Days
1,000
1,500
2,500
3,000
2,500
4,500
6,500
6,000
5,500
3,000
2,500
3,500
42,000

Actual
Electricity
Cost
$ 400
500
500
700
600
800
1,000
900
900
700
600
800
$8,400

Predicted
Electricity
Cost
$ 447
497
599
650
599
802
1,005
954
903
650
599
700
$8,405*

(4)
(yi yi)

(5)
(yi yi)2
Prediction
Error
Prediction
Squared
Error
(4)
(2) (3)
Squared
$(47)
$ 2,209
3
9
(99)
9,801
50
2,500
1
1
(2)
4
(5)
25
(54)
2,916
(3)
9
50
2,500
1
1
100
10,000
$ (5)*
$29,975

*rounding error
(y i y i )2
Column 5 total
$29, 975
5
s=
=
=
= $2, 997.5 = $54.75
12 2
10
n 2

3-20

Chapter 3

P3-5 (Concluded)
(4)

The 90% confidence interval for electricity cost at 2,000 guest days would be:

y i t 90%

( x i x )2
1
s 1+ +
n ( x i x )2

1 (2, 000 3, 500)2


($345 + ($.1015)(2, 000)) (1.812)($54.75) 1+
+
12
34, 000, 000
$548 (1.812)($54.75)(1.072)
$548

$106.35

P3-6
(1)

(a)

The high and low points method:

High ................................................................
Low .................................................................
Difference .......................................................
Variable rate = $100 1,000 Billets = $.10
Fixed cost = $500 ($.10 2,400 Billets) = $260
or
Fixed cost = $400 ($.10 1,400 Billets) = $260

Cost
$500
400
$100

Activity
2,400
1,400
1,000

Chapter 3

3-21

P3-6 (Continued)
(b)

A scattergraph with a trend line fitted by inspection:


$500

ELECTRICITY

$400

$300

$200

$100

$0
0

500

1,000

1,500

2,000

BILLETS

Fixed cost determined by inspection = $260


Average cost = $5,520 total cost 12 months = $460
Average activity = 24,000 total Billets 12 months = 2,000
Variable cost = ($460 average cost $260 fixed cost) 2,000 average
activity = $.10 per Billet

2,500

3-22

Chapter 3

P3-6 (Continued)
(c)

Month
January............
February ..........
March ...............
April .................
May ..................
June .................
July ..................
August .............
September.......
October............
November ........
December ........
Total ...........

(1)
y
Electricity
Cost
$ 455
450
435
485
470
475
400
450
435
500
495
470

(2)
(3)
(4)

(y y )
x
(x x)
Cost
Number Activity
Deviations of Billets Deviations
(5)
2,000
0
(10)
1,800
(200)
(25)
1,900
(100)
25
2,200
200
10
2,100
100
15
2,000
0
(60)
1,400
(600)
(10)
1,900
(100)
(25)
1,800
(200)
40
2,400
400
35
2,300
300
10
2,200
200

$5,520

24,000

(5)
(x x)2
(4)
Squared
0
40,000
10,000
40,000
10,000
0
360,000
10,000
40,000
160,000
90,000
40,000
800,000

(6)
(7)

)2
(x x )(y y ) (y y
(2)
(4) (2)
Squared
0
25
2,000
100
2,500
625
5,000
625
1,000
100
0
225
36,000
3,600
1,000
100
5,000
625
16,000
1,600
10,500
1,225
2,000
100
81,000

8,950

= y n = $5,520 12 = $460
y
x = x n = 24,000 12 = 2,000
81, 000
( x x )(y y ) Column 6 total
=
= $.10125
=
2
( x x )
Column 5 total 800, 000
= y bx

Variable rate (b ) =
Fixed cost (a )

= $460 ($.10125)(2, 000)


= $257.50
(2)

The coefficient of correlation (r) and the coefficient of determination (r2), using
data from the answer in requirement (1)(c) follow:
r=

( x i x )(y i y )
( x i x )2 (y i y )2

r 2 = (.957 )2 = .916

81, 000
= .957
7
(800, 000) (8, 950)

Chapter 3

3-23

P3-6 (Concluded)
(3)

Month
January ..................
February ................
March .....................
April........................
May .........................
June........................
July.........................
August....................
September .............
October ..................
November ..............
December ..............
Total....................

(1)
y
Actual
Electricity
Cost
$ 455
450
435
485
470
475
400
450
435
500
495
470
$5,520

(2)
x
Number
of
Billets
2,000
1,800
1,900
2,200
2,100
2,000
1,400
1,900
1,800
2,400
2,300
2,200
24,000

(3)
(y= a + bx)
Estimated
Electricity
Cost
$ 460
440
450
480
470
460
399
450
440
501
490
480
$5,520

(4)
(y y )

(5)
(y y )2

(1) (3)
(5)
10
(15)
5
0
15
1
0
(5)
(1)
5
(10)
0

(4)
Squared
25
100
225
25
0
225
1
0
25
1
25
100
752

(y y )2
Column 5 total
$752
s=
=
=
= $8.672
12 2
10
n 2
The 95% confidence interval for electricity costs at the 2,200 Billets level of
activity would be determined as follows:
a + bx t 95% s 1+

1 ( x x )2
+
n ( x x ) 2

28)($8.672) 1+
$257.50 + ($.10125)(2,200) (2.22

1 (2,200 2,000)2
+
12
800,000

$480.25 (2.228)($8.672)(1.065)
$480.25 $20.58
or between a low of $459.67 and a high of $500.83.

3-24

Chapter 3

P3-7
(1)
(1)
yi
Factory
Overhead
Cost

(2)
)
(yi y
Difference
from
Average
of $7,900

Direct
Labor
Hours

$8,500
9,900
8,950
9,000
8,150
7,550
7,050
6,450
6,900
7,500
7,150
7,800

600
2,000
1,050
1,100
250
(350)
(850)
(1,450)
(1,000)
(400)
(750)
(100)

2,000
2,400
2,200
2,300
2,000
1,900
1,400
1,000
1,200
1,700
1,600
1,900

200
600
400
500
200
100
(400)
(800)
(600)
(100)
(200)
100

8,700
9,300
9,300
8,700
8,000
7,650
6,750
7,100
7,350
7,250
7,100
7,500

800
1,400
1,400
800
100
(250)
(1,150)
(800)
(550)
(650)
(800)
(400)

2,100
2,300
2,200
2,200
2,000
1,800
1,200
1,300
1,500
1,700
1,500
1,800

Jan ...................
8,600
Feb ...................
9,300
Mar ...................
9,400
Apr. ..................
8,700
May ..................
8,100
June .................
7,600
July ..................
7,000
Aug...................
6,900
Sep...................
7,100
Oct ...................
7,500
Nov...................
7,000
Dec...................
7,600
Total ................. $284,400

700
1,400
1,500
800
200
(300)
(900)
(1,000)
(800)
(400)
(900)
(300)
0

2,000
2,300
2,300
2,200
2,000
1,800
1,300
1,200
1,300
1,800
1,500
1,900
64,800

Month
20A
Jan ...................
Feb ...................
Mar ...................
Apr ...................
May ..................
June .................
July ..................
Aug...................
Sep...................
Oct ...................
Nov...................
Dec...................

(3)
xi

(4)
(5)
(xi x)
(xi x)2
Difference
from Average
of 1,800
(4)
Hours
Squared

(6)
(7)
) (y y)2
(xi x)(yi y
i

(4) (2)

(2)
Squared

40,000
360,000
160,000
250,000
40,000
10,000
160,000
640,000
360,000
10,000
40,000
10,000

120,000
1,200,000
420,000
550,000
50,000
(35,000)
340,000
1,160,000
600,000
40,000
150,000
(10,000)

360,000
4,000,000
1,102,500
1,210,000
62,500
122,500
722,500
2,102,500
1,000,000
160,000
562,500
10,000

300
500
400
400
200
0
(600)
(500)
(300)
(100)
(300)
0

90,000
250,000
160,000
160,000
40,000
0
360,000
250,000
90,000
10,000
90,000
0

240,000
700,000
560,000
320,000
20,000
0
690,000
400,000
165,000
65,000
240,000
0

640,000
1,960,000
1,960,000
640,000
10,000
62,500
1,322,500
640,000
302,500
422,500
640,000
160,000

200
500
500
400
200
0
(500)
(600)
(500)
0
(300)
100
0

40,000
250,000
250,000
160,000
40,000
0
250,000
360,000
250,000
0
90,000
10,000
5,280,000

20B
Jan ...................
Feb ...................
Mar ...................
Apr ...................
May ..................
June .................
July ..................
Aug...................
Sep...................
Oct ...................
Nov...................
Dec...................
20C
140,000
490,000
700,000 1,960,000
750,000 2,250,000
320,000
640,000
40,000
40,000
0
90,000
450,000
810,000
600,000 1,000,000
400,000
640,000
0
160,000
270,000
810,000
(30,000)
90,000
11,625,000 29,155,000

Chapter 3

3-25

P3-7 (Continued)
b=

( x i x )(y i y ) Column 6 total 11, 625, 000


=
=
= $2.20 variable cost rate
( x i x )2
Column 5 total 5, 280, 000

Since y = a + bx and y = y i n and x = x i n, then :


($284, 400 36) = a + ($2.20)(64, 800 36)
$7, 900 = a + $3,, 960
a = $3, 940 fixed overhead cost
(2)

The coefficient of correlation and the coefficient of determination, using data


from the requirement (1) answer:
r

( x i x )(y i y )
( x i x )2 (y i y )2

Column 6 total
(Column 5 total) (Column 7 total)

11, 625, 000


11, 625, 000
11, 625, 000
=
=
= .9370
153, 938, 400, 000, 000 12, 407, 191
(5, 280, 000)(29, 155, 000)

r 2 = (.9370)2 = .8780

3-26

Chapter 3

P3-7 (Continued)
(3)
The standard error of the estimate:
(1)
xi

Month
20A
January ..................
February ................
March .....................
April .......................
May.........................
June .......................
July.........................
August ...................
September .............
October ..................
November ..............
December ..............
20B
January ..................
February ................
March .....................
April .......................
May.........................
June .......................
July.........................
August ...................
September .............
October ..................
November ..............
December ..............
20C
January ..................
February ................
March .....................
April .......................
May.........................
June .......................
July.........................
August ...................
September .............
October ..................
November ..............
December ..............
Total....................

Direct
Labor
Hours

(2)
yi
Actual
Factory
Overhead
Cost

(3)
(4)
(5)
(yi = a + bxi) (yi yi)
(yi yi)2
Predicted
Prediction
Factory
Prediction
Error
Overhead
Error
Squared
Cost
(2) (3)
(4) Squared

2,000
2,400
2,200
2,300
2,000
1,900
1,400
1,000
1,200
1,700
1,600
1,900

$ 8,500
9,900
8,950
9,000
8,150
7,550
7,050
6,450
6,900
7,500
7,150
7,800

$ 8,340
9,220
8,780
9,000
8,340
8,120
7,020
6,140
6,580
7,680
7,460
8,120

$160
680
170
0
(190)
(570)
30
310
320
(180)
(310)
(320)

$ 25,600
462,400
28,900
0
36,100
324,900
900
96,100
102,400
32,400
96,100
102,400

2,100
2,300
2,200
2,200
2,000
1,800
1,200
1,300
1,500
1,700
1,500
1,800

8,700
9,300
9,300
8,700
8,000
7,650
6,750
7,100
7,350
7,250
7,100
7,500

8,560
9,000
8,780
8,780
8,340
7,900
6,580
6,800
7,240
7,680
7,240
7,900

140
300
520
(80)
(340)
(250)
170
300
110
(430)
(140)
(400)

19,600
90,000
270,400
6,400
115,600
62,500
28,900
90,000
12,100
184,900
19,600
160,000

2,000
2,300
2,300
2,200
2,000
1,800
1,300
1,200
1,300
1,800
1,500
1,900
64,800

8,600
9,300
9,400
8,700
8,100
7,600
7,000
6,900
7,100
7,500
7,000
7,600
$284,400

8,340
9,000
9,000
8,780
8,340
7,900
6,800
6,580
6,800
7,900
7,240
8,120
$284,400

260
300
400
(80)
(240)
(300)
200
320
300
(400)
(240)
(520)
0

67,600
90,000
160,000
6,400
57,600
90,000
40,000
102,400
90,000
160,000
57,600
270,400
$3,560,200

Chapter 3

3-27

P3-7 (Concluded)
s=

(4)

(y i y i )2
Column 5 total
$3, 560, 200
=
=
= $104, 712 = $324
36 2
34
n 2

Since a large sample is used in this problem, t95% = z95% and the confidence
interval is:
y i

z 95% s

($3, 940 + ($2.20)(2, 200)) (1.960)($324 )


$8, 780 $635

3-28

Chapter 3

P3-8
(1)
(1)
yi
Maintenance
Months
Cost
Jan., 20A.......... $ 1,195
Feb., 20A .........
1,116
Mar., 20A..........
1,390
Apr., 20A ..........
1,449
May, 20A ..........
1,618
June, 20A ........
1,525
July, 20A ..........
1,687
Aug., 20A .........
1,650
Sep., 20A .........
1,595
Oct., 20A..........
1,675
Nov., 20A .........
1,405
Dec., 20A .........
1,251
Jan., 20B..........
950
Feb., 20B .........
1,175
Mar., 20B..........
1,425
Apr., 20B ..........
1,506
May, 20B ..........
1,608
June, 20B ........
1,653
July, 20B ..........
1,675
Aug., 20B .........
1,724
Sep., 20B .........
1,626
Oct., 20B..........
1,575
Nov., 20B .........
1,653
Dec., 20B .........
1,418
Total ............ $35,544

(2)
)
(yi y
Cost
Deviation
(286)
(365)
(91)
(32)
137
44
206
169
114
194
(76)
(230)
(531)
(306)
(56)
25
127
172
194
243
145
94
172
(63)
0

(3)
xi
Labor
Hours
950
1,024
1,109
1,148
1,313
1,261
1,552
1,372
1,366
1,455
1,221
1,150
999
1,022
1,220
1,283
1,339
1,250
1,440
1,290
1,335
1,164
1,373
1,124

(4)
(xi x)
Activity
Deviation
(290)
(216)
(131)
(92)
73
21
312
132
126
215
(19)
(90)
(241)
(218)
(20)
43
99
10
200
50
95
(76)
133
(116)

29,760

(5)
(xi x)2
(4)
Squared
84,100
46,656
17,161
8,464
5,329
441
97,344
17,424
15,876
46,225
361
8,100
58,081
47,524
400
1,849
9,801
100
40,000
2,500
9,025
5,776
17,689
13,456
553,682

(6)
(7)

)2
(xi x )(yi y ) (yi y
(2)
(4) (2)
Squared
82,940
81,796
78,840
133,225
11,921
8,281
2,944
1,024
10,001
18,769
924
1,936
64,272
42,436
22,308
28,561
14,364
12,996
41,710
37,636
1,444
5,776
20,700
52,900
127,971
281,961
66,708
93,636
1,120
3,136
1,075
625
12,573
16,129
1,720
29,584
38,800
37,636
12,150
59,049
13,775
21,025
(7,144)
8,836
22,876
29,584
7,308
3,969
651,300

1,010,506

y = yi n = $35,544 24 = $1,481
x = xi n = 29,760 24 = 1,240
r

=
=

( x i x )(y i y )
( x i x )2 (y i y )2

Column 6 total
(Column 5 total) (Column 7 total)

651, 300
651, 300
651, 300
=
= .870725
=
(553, 682)(1, 010, 506)
559, 498,, 983, 092 747, 997

r 2 = (.870725)2 = .758162

Chapter 3

3-29

P3-8 (Continued)
(1)
yi
Maintenance
Months
Cost
Jan., 20A.......... $1,195
Feb., 20A .........
1,116
Mar., 20A..........
1,390
Apr., 20A ..........
1,449
May, 20A ..........
1,618
June, 20A ........
1,525
July, 20A ..........
1,687
Aug., 20A .........
1,650
Sep., 20A .........
1,595
Oct., 20A..........
1,675
Nov., 20A .........
1,405
Dec., 20A .........
1,251
Jan., 20B..........
950
Feb., 20B .........
1,175
Mar., 20B..........
1,425
Apr., 20B ..........
1,506
May, 20B ..........
1,608
June, 20B ........
1,653
July, 20B ..........
1,675
Aug., 20B .........
1,724
Sep., 20B .........
1,626
Oct., 20B..........
1,575
Nov., 20B .........
1,653
Dec., 20B .........
1,418
Total ............. $35,544

(2)
)
(yi y
Cost
Deviation
(286)
(365)
(91)
(32)
137
44
206
169
114
194
(76)
(230)
(531)
(306)
(56)
25
127
172
194
243
145
94
172
(63)
0

(3)
(4)
xi
(xi x)
Machine Activity
Hours Deviation
809
(266)
744
(331)
987
(88)
987
(88)
1,186
111
1,154
79
1,291
216
1,238
163
1,186
111
1,246
171
997
(78)
841
(234)
502
(573)
733
(342)
1,090
15
1,135
60
1,174
99
1,246
171
1,264
189
1,323
248
1,230
155
1,165
90
1,237
162
1,035
(40)
25,800

(5)
(xi x)2
(4)
Squared
70,756
109,561
7,744
7,744
12,321
6,241
46,656
26,569
12,321
29,241
6,084
54,756
328,329
116,964
225
3,600
9,801
29,241
35,721
61,504
24,025
8,100
26,244
1,600
1,035,348

(6)
(7)
) (y y)2
(x x)(y y
i
(2)
(4) (2)
Squared
76,076
81,796
120,815
133,225
8,008
8,281
2,816
1,024
15,207
18,769
3,476
1,936
44,496
42,436
27,547
28,561
12,654
12,996
33,174
37,636
5,928
5,776
53,820
52,900
304,263
281,961
104,652
93,636
(840)
3,136
1,500
625
12,573
16,129
29,412
29,584
36,666
37,636
60,264
59,049
22,475
21,025
8,460
8,836
27,864
29,584
2,520
3,969
1,013,826

1,010,506

y = yi n = $35,544 24 = $1,481
x = xi n = 25,800 24 = 1,075
r

=
=

( x i x )(y i y )
( x i x )2 (y i y )2

Column 6 total
(Column 5 total) (Column 7 total)

1, 013, 826
1, 013, 826
1, 013, 826
=
=
= .991176
1,, 046, 225, 366, 088 1, 022, 852
(1, 035, 348)(1, 010, 506)

r 2 = (.991176)2 = .982430

3-30

Chapter 3

P3-8 (Continued)
(2)
The activity measure used to predict maintenance expense should be machine
hours, which will result in the following cost estimates:
( x x )(y y ) Column 6 total 1, 013, 826
= $.979213 variable rate
=
=
( x x )2
Column 5 total 1, 035, 348
Since y = a + bx , then the estimated fixed cost is determined as follows:
a = y bx

b=

a = $1, 481 ($.979213)(1, 075)


a = $1, 481 $1, 052.65
a = $428.35
(3)

(1)
xi

Months
Jan., 20A ................
Feb., 20A ................
Mar., 20A ................
Apr., 20A ................
May, 20A.................
June, 20A ...............
July, 20A.................
Aug., 20A ...............
Sep., 20A................
Oct., 20A ................
Nov., 20A ................
Dec., 20A................
Jan., 20B ................
Feb., 20B ................
Mar., 20B ................
Apr., 20B ................
May, 20B.................
June, 20B ...............
July, 20B.................
Aug., 20B ...............
Sep., 20B................
Oct., 20B ................
Nov., 20B ................
Dec., 20B................
Total....................
*rounding error

Machine
Hours
809
744
987
987
1,186
1,154
1,291
1,238
1,186
1,246
997
841
502
733
1,090
1,135
1,174
1,246
1,264
1,323
1,230
1,165
1,237
1,035
25,800

(2)
(3)
(4)
yi
(yi = a + bxi) (yi yi)
Actual
Predicted Prediction
Maintenance Maintenance
Error
Cost
Cost
(2) (3)
$ 1,195
$ 1,221
$(26)
1,116
1,157
(41)
1,390
1,395
(5)
1,449
1,395
54
1,618
1,590
28
1,525
1,558
(33)
1,687
1,693
(6)
1,650
1,641
9
1,595
1,590
5
1,675
1,648
27
1,405
1,405
0
1,251
1,252
(1)
950
920
30
1,175
1,146
29
1,425
1,496
(71)
1,506
1,540
(34)
1,608
1,578
30
1,653
1,648
5
1,675
1,666
9
1,724
1,724
0
1,626
1,633
(7)
1,575
1,569
6
1,653
1,640
13
1,418
1,442
(24)
$35,544
$35,547*
$ (3)*

(y i y )2
Column 5 total
$17, 817
=
=
= $28.458103
s=
24 2
22
n 2

(5)
(yi yi)2
(4)
Squared
$ 676
1,681
25
2,916
784
1,089
36
81
25
729
0
1
900
841
5,041
1,156
900
25
81
0
49
36
169
576
$17,817

Chapter 3

3-31

P3-8 (Concluded)
(4)

The 95% confidence interval for maintenance cost at the 1,100 machine hour
level of activity is:
y i t 95% s 1+

( x i x )2
1
+
n ( x i x )2

$428.35 + ($.979213)(1, 100) (2.074 )(28.458103) 1+


$1, 505.48 $60.26

(1, 100 1, 075)2


1
+
24
1, 035, 348

3-32

Chapter 3

CASES
C3-1
(1)

=
=
=
=

a + bS
5.062 + (.023) (1,200)
5.062 + 27.6
32.662 or about 33 total workers

Total workers needed ..........................................................


Less permanent workers ....................................................

33
10

Number of temporary workers needed..............................

23

(2)

Regression 2 appears to be better than Regression 1 because:


(a) Data outside the relevant range have been excluded, thereby removing
any bias.
(b) The standard error of the estimate (s) for Regression 2 is smaller than
the standard error of the estimate for Regression 1 (.432 compared to
2.012).
(c) The coefficient of determination (r 2) is higher for Regression 2 than the
coefficient of determination for Regression 1 (.998 compared to .962).

(3)

Jim Locter can use the regression in his planning for temporary workers if the
following conditions exist:
(a) The forecasted daily shipments are greater than 300 and do not deviate
too much from the actual shipments.
(b) The amount of work to be done is dependent only on the number of
shipments to be made and does not change from shipment to shipment.
(c) Worker productivity is expected to remain approximately the same as
that experienced during the period used to develop the regression.
(d) A strong cause and effect relationship exists between the dependent
variable and the independent variable.
(e) The time frame for a forecast is short-term.

(4)

The regression could be improved by the following:


(a) Redeveloping the regression using the number of hours worked as the
dependent variable.
(b) Performing another analysis if rush orders or deviations of actual orders
from forecasts occur with any degree of regularity.
(c) Investigating the historical data used as a basis for the regression to
determine if there are any further unusual circumstances that should be
removed from the data set.
(d) Redoing the regression after a period of time, such as four to six
months, to discover if there have been any changes in the relationship
between the dependent and the independent variables.

Chapter 3

3-33

C3-2
(1)

(2)

The increase in y associated with a unit increase in x is 1.2. Therefore, a 500unit increase in x will result in a 600-unit increase (1.2 500) in y (direct labor
hours).
(a) The equation may be unreliable if the correlation is spurious. The
assumption is that there is a logical relationship between output and the
use of electric power and direct labor.
(b) The equation may be reliable under the conditions at the time of the
study, but if conditions change, the results may be unreliable.
(c) Data used were limited to a range of 5002,000 units.
(d) It is assumed that a straight-line assumption is valid.
(e) The coefficient of correlation is a measure of the extent to which two
variables are related linearly. It is a relative measure of goodness of fit.
More of the variation in y is explained by the regression equation for
direct labor hours than for electric power, that is, the equation for direct
labor hours is a better fit than the equation for electric power.
(f)
The standard error of the estimate is a measure of variation from the
regression line. If the observations are normally distributed about the
regression equation, the standard error can be interpreted in the same
way as the standard deviation. The standard error is greater in the case
of direct labor hours than in the case of electric power.
CGA-Canada (adapted). Reprint with permission.

C3-3
(1)

An advantage of Alternative A is that using time as an independent variable is


a convenient way to take into consideration all possible factors that may be
influencing the dependent variable during each period of time. A disadvantage
of Alternative A is that there is no logical relationship between years and rental
expense.
An advantage of Alternative B is that this method is logical because as revenues increase, the stores increase, and, thus, rental expense increases. A disadvantage of Alternative B is that an estimate of revenues is required.
An advantage of Alternative C is that the mathematical calculations are relatively easy and the method is easy to understand. A disadvantage of
Alternative C is that the arithmetic average is an oversimplification that does
not recognize any relationship between variables.

3-34

Chapter 3

C3-3 (Concluded)
(2)

(3)

Motorco Corporation should select Alternative B because the relationship


between revenue and the rental expense is logical, the coefficient of correlation
is high, and the standard error of the estimate is low.
A statistical technique is an appropriate method for estimating rental expense
before Motorco actually contacts Alpha Auto Parts. A statistical technique
attempts to measure the covariation between the variables that are presumed
to have a cause and effect relationship, and such a relationship appears to exist
in this situation. Of course, Motorco is assuming that any relationships that
exist in the historical data will continue in the future without change.
Management may want to adjust the variables for changes that it expects will
occur, and Motorco may wish to introduce other quantitative variables.

C3-4
(1)

(2)

(3)

The phrase regression provides a relational statement rather than a causal


statement means that regression analysis is used to determine a relationship,
but not necessarily a cause-and-effect relationship. A specific value for a
regression coefficient does not imply that the independent variable(s) causes a
change in the dependent variable.
The meaning of each of the symbols in the basic formula for a regression equation follows:
yi = estimated value of the i th observation of the dependent variable.
a = the y-axis intercept or constant term (e.g., the fixed portion of a
semivariable expense).
b = the regression coefficient corresponding to the independent variable x
(e.g., the variable cost element associated with a one unit change in
activity x).
xi = the i th observation of the first independent variable.
c = the regression coefficient corresponding to the independent variable z
(e.g., the variable cost element associated with a one unit change in
activity z).
zi = the i th observation of the second independent variable.
ei = the error term associated with the i th observation.
Statistical factors used to test a regression equation for goodness of fit include:
(a) The coefficient of determination, r 2, which indicates the portion of the
variance in the dependent variable explained by the independent
variables. A coefficient of determination approaching 1 indicates a
good fit.

Chapter 3

3-35

C3-4 (Concluded)
(b)

(4)

(a)

(b)

(c)

(d)

(e)

The standard error of the estimate which measures the dispersion of the
observed points about the regression line. A standard error of the
estimate approaching zero indicates a good fit.
The term linearity within a relevant range means that in a specific
situation, a straight-line relationship between the dependent variable and
the independent variables can be assumed only within the range of
historically observed values.
The term constant variance (homoscedasticlty) means that the
distribution of the observations about the regression line is uniform for
all values of the independent variables within the observed range of
values.
The term serial correlation refers to the lack of independence in a
series of successive observations over time. The deviation of a value
from the regression line should be unrelated to the deviation of any
other point from this line.
The term normality means that the joint probability distribution of the
variables is normally distributed (multivariate normal). The frequency of
the observations should approximate a normal curve.
The term multicollinearity refers to the correlation of independent
variables. When independent variables are highly correlated with each
other, the relationship(s) between the independent variables may
obscure the relationship between the independent variables(s) and the
dependent variable.

C3-5
(1)

(2)

(a)

D = (2.455 + (.188)(1,500,000 100,000)) 10,000 units


= (2.455 + 2.82) 10,000 units
= 5.275 10,000 units
= 52,750 units
(b) D = (2.491 + (.44)(12,000,000 1,000,000)) 10,000 units
= (2.491 + 5.28) 10,000 units
= 7.771 10,000 units
= 77,710 units
The 50% confidence interval for demand is calculated as follows:
D = 104,160 units (.69)(.922 10,000 units)
= 104,160 units 6,361.8 units
or between 97,798 units and 110,522 units.

3-36

Chapter 3

C3-5 (Concluded)
(3)

(4)

Equation 4 is the best. The coefficient of correlation and the coefficient of determination are the highest of the four equations. The coefficient of determination
indicates that 70.3% of the sample variance of automobile sales is explained by
the regression. For predictive purposes, the standard error of the estimate at
.922 is also the lowest of the four models, giving the tightest (smallest) physical confidence interval of any of the equations.
Equation 3 assumes that factory rebates (R) are dependent on advertising
funds (A). The results of the analysis show that factory rebates and advertising
funds are almost totally independent and, therefore, cannot be used to predict
each other. The results of Equation 3 lend credibility to the use of A and R in
Equation 4. The independence of A and R reduces the possible negative
aspects of collinearity.

Das könnte Ihnen auch gefallen