C & V ENGINEERING PTE LTD

Project Consultant Engineers GST. Reg. No. 198202518K Maxwell House, # 09-04/05. 20, Maxwell Road, Singapore 069113 Tel: 62260828 Fax: 62225645 Email : vkengr9@singnet.com.sg Website : www.cvconslt.com
SS ISO 9001:2008 Certificate No : FS 500171

Our ref: ER420-130328-5003-CV-ULT - Method Statement of Box Culvert Construction Your ref: 12605-LTA/1301/s/C028/L

28 March 2013 Officer-in-Charge Land Transport Authority 1 Hampshire Road Singapore 219428 Attn: Ms Tan Ai Ping Dear Sirs, CONTRACT NO. : ER420QP PROJECT TITLE: QUALIFIED PERSON (SUPERVISION) SERVICES FOR CONTRACT ER420 NEW ROAD LINK BETWEEN UPPER CHANGI ROAD AND UPPER CHANGI ROAD EAST

Re: - Method Statement for Works. 1. We refer to the Contractors' submission (Ref: 12605-LTA/1301/s/C028/L Dated 31st January 2013. 2. The Above submission is accepted with comments as attached in Annex A. 3. Contractor to incorporate responses to comments in the next submission.

Thank you Yours faithfully,

Cheng Kim Hua QP(Supervision), ER420QP

Cc:

Mr. Ho Tuck Kai ( S.O. Rep) Mr. Pat Sio Poh (Project Officer) Mr. Wong Keng wah (Project Supervisor)

Annex A Comment Codes Review Form 1 = Minor Importance 2 = Moderate Importance 3 = Major Importance

DOCUMENT REVIEW Document No. Subject: Review Department Date: QP(Supervision) Comments Code 28 March 2013

Method Statement for Box Culvert Construction.

NO. Document/Drawing No.

Hierarchy Chart for this Operation

Please include Safety officer/ Safety Supervisor in the Organization Chart and ensure that they involve in this operation

Relevant certificates for Equipment and Manpower

No certificates attached with this method Statement for personnel involved in this operation. Please provide relevant certificates for excavator operator. Please specify how the updated certificates would be submitted before commencement of work Please state that an excavator with rubber tracks will be used to protect the road surface when working on Upper Changi Road East and Upper Changi Road. Please include Traffic Control Plan at Upper Changi Road and Upper Changi Road East

Resources Plant and Manpower

Temporary Traffic Control Plan

Overall Acceptance Status Please cross (x) one box 1. Accepted 2. Accepted with comments 3. Noted with comments 3. Rejected

The above comments do not relieve the contractor of his contractual obligations. The submission is a) Accepted with comments; b) Please resubmit, incorporating response to the above comments.

__________________ Cheng Kim Hua QP (Supervision) for ER420QP