BIM.

02 integrated cost budgeting and cost estimating model for building projects

sarmad al-mashta dr. sabah alkass

Author Biography
Degree: University: Years of Experience: Professional Field: Tools Developed: M.A.Sc. Building Engineering B.Sc. Architectural Engineering Concordia University University of Baghdad 16 Architectural design Interior Design Fenestration Management System Automated Cost Estimation CPI 3D Visualization Risk Registrar

agenda
introduction methodology proposed model conclusion case study research contribution research limitation literature review problem statement assembly costing mapping different WBS

introduction

research
scope
building projects assets cost

objectives
streamline cost estimate process integrated model cost estimates class 1/2 AACE multiple WBS simultaneously multiple cost sources

AACE classification

literature review

deliverable-oriented hierarchy of decomposed project components that organizes and defines the total scope of the project(PMI)

work breakdown structure (WBS)

WBS types (CSI and CSC)


functional elements of building owner, designer, or general contractor Uniformat materials & methods or work results specifier or subcontractor MasterFormat products product representative
8

Estimating Process
WBS

project design cost data

quantity take-off calculate cost data lookup


process

cost estimate group & classify


output

input

automated quantity take-off


CAD based 2D, requires user input of 3D dimension 3D geometric data, generic solids require user input to identify object type BIM based full object oriented 3D geometric data Parametric environment, data replication

10

types of quantities
product/procurement quantities (PPQ) physical material quantities part of final building product determined by the design length and weight of rebar, volume of concrete beams, areas of metal decking

11

types of quantities
Process of Construction Quantities (PCQ) depend on construction process/methods, specific conditions of job based on more detailed breakdown of associated PPQs productivity factors, ex. locations, geometric characteristics, construction methods shoring/scaffolding, areas of formwork, labour hours for hanging drywall, and excavation quantities for earthwork
12

Traditional vs. Automated


Estimating Software
2D paper drawings from design/ engineering team Manual takeoff and manual check for conditions Manually associate take-off info. with assembly items Manual link, changes must be updated by estimator Digital link, changes updated automatically Cost database

Traditional paper-based estimating process Automated estimating process


Extract quantities within BIM tool

Associate digitized take-off info. with component

Associate with assembly items

Calculation of additional quantities item properties

Estimate

3D/BIM models from project

Manually extract quantities with specialized take-off / estimating tool

Auto-extract and associate with assembly items

Supplier / subcontractor pricing

13

problem statement
cost estimate is time consuming task performed at distant points leaving gaps lack of framework and methodology for automated detailed cost estimating automated quantity take-off for PCQ use of TWBS.
14

methodology

components that are commonly encountered in the construction are viewed as estimating group (Halpin)

assembly costing

assembly costing
component 1 component 2 component 3 component 4 component n
m at er ia ls eq ui pm en t la bo ur

assembly cost

17

mapping EWBS to TWBS


materials

component 1
assembly cost

equipment labour materials equipment labour materials

component 2

component n

equipment labour
18

mapping EWBS to TWBS


UniFormat: System B1010 219 3000: BM. & Slab One way 15x15 Bay, 40 PSF S. Load, 12 Min. Col.

Forms In Place, Flat Plate to 15 High, 4 uses Reinforcing in place, elevated slabs #4 to #7 Concrete Ready mix, regular Weight 3000 psi Place and vibrate concrete, elevated slab less than 6, pump 19

proposed model

proposed model components

Database Solution

CAD/BIM With quantity take-off module

21

proposed model design (simplified)


CAD/BIM

EWBS (UniFormat) Assemblies Components

Cost Data (In-house) Cost Data (3rdParty) Cost Estimates (Assemblies) Cost Estimates (Trades) TWBS (MasterFormat)

22

proposed model design


EWBS components
Cost Estimates (Assemblies) B.O.Q

TWBS components

Cost Estimates (Trades)

CAD/BIM System Core Functions (Set-1) Assemblies Components System Core Functions (Set-2) SCML

GAC

EWBS (UniFormat)

EWBS (Other) Cost Data (In-house) Cost Data (3rdParty)

Generic TWBS

(MasterFormat)

TWBS (Other)

23

How it Works

24

proposed model topology

25

step I: cost data processing


EWBS cost data
(RS Means)

Standardize
(assemblies)

cost data
(In-House)

Standardize
(assemblies)

Map GAC SCML Map

Standardize Standardize TWBS


input

(Sys. Components) (Sys. Components)

process

output

26

step II: quantity take-off


user
(CAD/BIM GUI)

geometrical data

link

(assembly code)

elemental B.O.Q.

GAC

data export
(ODBC)

input

process

output

27

step III: cost calculation


GAC cost data lookup calculate elemental cost trade cost

elemental B.O.Q. mapping SCML


input
(EWBS to TWBS)

calculate

cost data lookup


process output

28

step IV: cost estimate reporting


user
(RDBMS GUI)

elemental cost reports group & classify trades cost reports


process output

elemental cost trades cost

input

29

cost estimate reports


EWBS cost estimate level 5 EWBS cost estimate level 4 assemblies with no cost data TWBS cost estimate level 5 TWBS cost estimate level 4 TWBS cost estimate level 5 by EWBS TWBS cost estimate level 4 by EWBS

30

research contributions
Integrated model streamline cost estimate process cost monitoring for design phases framework multiple simultaneous WBS multiple cost data sources addressing particular limitations of current 3D modelling technologies detailed quantity take-off from generic model

31

research limitation
assembly unit cost hides the productivity factor no optimization no consideration for the schedule effects

32

case study

quick demo
?
33

quick demo

case study project

34

linking BIM object to GAC entry

35

EWBS cost estimate report snapshot


(level 4)

36

EWBS cost estimate chart


(level III)

37

TWBS cost estimate report snapshot


(level 4)

38

Questions ?

thank you