Beruflich Dokumente
Kultur Dokumente
654
3. SETTING TO WORK.
3.1 Select Burner output control switch on position (2). 1 = Automatic, 2 = Small Load, 3 = Stop, 4 = Full Load 3.2 Close air relief valve when a steam pressure of 0.5 Bar is reached. If you have opened it during filling of the boiler time. 3.3 After reaching the working pressure, open main steam valve on boiler slowly. Then open valves of the steam using section. 3.4 Turn Burner switch to position automatic.
4. BOILER OPERATION
4.1 Keep Feed water temperature at 80C. 4.2 Open blow down valve approx. every 8 hours for a few seconds. 4.3 Test feed water, Softener water and blow down water. Then regenerate softener as per water report. 4.4 Add 200 gm scale and corrosion inhibitor into feed tank every 8 hours. 4.5 Run softener and feed pump alternatively. 4.6 Record steam pressure, gas pressure and water level of feed tank & boiler. 4.7 Record boiler running hours and Flow meter reading.
5 BOILER SHUT-DOWN
5.1 Turn the burner control switch at (2) small load position. 5.2 Switch off the Burner 5.3 Should do following works if the boiler remains out of service for a long time; (a) Release pressure unto 0 by blow down. (b) Close main stop valve of steam and gas and header. Close feed water valve. (d) Switch off main circuit breaker.
Sr.Engineer. (Utility)
SOP FOR FIRE TUBE FLUE GAS BOILER 1. FILLING OF THE BOILER
1.1 Be sure water level of Feed tank and Boiler is in workable level. If need, Fill the Feed tank & Boiler only with the treated water; 1.2 Be sure that the blow down valve and main steam valve is closed. If need, close. 1.3 Open air relief valve (Air cock valve). (Need for after longtime and No need when pressure is exist). 1.4 Switch on main circuit breaker and softener pump to fill feed tank with treaded water. Then select the Feed Pump position at Auto (2) to automatically fill boiler. Before switch on the pump be sure that valve is opened. Feed Pump Position: 0 = OFF, 1 = Manual, 2 = Auto.
3. SETTING TO WORK.
3.1 Close air relief valve when a pressure of 0.5 Bar is reached. If you have opened it during filling of the boiler. 3.2 After reaching the working pressure, open main steam valve on boiler slowly. Then open valves of the steam using section. 3.3 Turn Feed pump switch to position automatic.
4. BOILER OPERATION
4.1 Keep Feed water temperature at 80C by continuous running circulation pump. 4.2 Open blow down valve approx. every 8 hours for a few seconds. 4.3 Test feed water, Softener water and blow down water. Then regenerate softener as per water report. 4.4 Add 100 gm scale and corrosion inhibitor into feed tank every 8 hours. 4.5 Run softener and feed pump alternatively. 4.6 Record steam pressure, gas pressure and water level of feed tank & boiler. 4.7 Record boiler running hours and Flow meter reading, pressure, temperature.
5 BOILER SHUT-DOWN
5.1 Switch OFF the damper switches and to ensure is closed. 5.2 Switch off Feed pump. 5.3 Should do following works if the boiler remains out of service for a long time; (a) Release pressure unto 0 by blow down. (b) Close main stop valve of steam and gas and header. Close feed water valve. (d) Switch off main circuit breaker.
Sr.Engineer. (Utility)
Sr.Engineer. (Utility)
Sr.Engineer. (Utility)
Sr.Engineer. (Utility)
Sr.Engineer. (Utility)
Sr.Engineer. (Utility)
SOP FOR HYDROSTATIC TEST OF FIRE TUBE BOILER The following is a recommended procedure for hydrostatic testing; 1. Open the air purge brass ball valve which is on the steam drum. 2. Gagging the safety valve if impossible, remove the safety valves and replace with test plugs or blind flanges. 3.Close steam outlet valve (Main steam valve on boiler). 4. Close glove valve that is before the blow down valve. 5. Isolate pressure switches or other control components that are not intended to be subjected to a hydrostatic test. 6. Close gauge glass valve, pressure gauge valves. 7. Fill the boiler with treated water (water temperature 21 C to 48 deg C) and fill until water overflows the vent. 8. Apply pressure slowly. The recommended rate of pressure increase is less than 50 psi per minute. Raise pressure up to desired/test pressure ( 1.5 times of design pressure). 9. When the proper test pressure is reached, Inspection in accordance with the test objective can begin. Examine the system for any leaks. If no leaks are visible, Hold the system in a pressurized static condition for a period. 10. Upon completion of the test, release pressures slowly thoroughly a blow down valve.
Sr.Engineer. (Utility)