Beruflich Dokumente
Kultur Dokumente
PowerFactory
Submission Date:
Objectives The objective of this experiment is to study the performance of a small power system under various fault events. PowerFactory is used to carry out the simulation studies. The Power System
3.5
G1
b1
G2
b4
Slack Bus
1
b2
2
b5
1.0pu
T1
b3 b6
T2
3
b7 b8
4
b9 b10
L3 L1 L2
b11
b12
5
P = 25MW Q = 9 MVAr
Figure 1
ENG455 Experiment 02 : Short-Circuit Analysis Element Data G1 G2 T1 T2 L1 L2 L3 10MVA 20MVA 10MVA 20MVA 6kV 6kV 6kV/33kV 6kV/33kV xd'' = 0.15 xd'' = 0.18 X2 = 0.12 X2 = 0.20 X0 = 0.10 X0 = 0.10
Enter the system shown in figure 1, using the element values given in the diagram. NOTE: In the interests of reducing complexity, it is recommended that terminals are used instead of busbars as the connecting points, as this avoids having to attached elements to specific bays.
Tasks
1. 2. 3. Enter the circuit shown in Figure 1 into Power Factory. Perform a load flow analysis of the system. Note that Bus 2 is the Slack Bus, Bus 1 acts as a PQ bus that supplies power to the network, and Bus 5 is the load bus. Perform the following bus faults at each of the buses in turn, and record the fault current at the faulted bus and the current that flows through Breaker bk: balanced three-phase to ground; single phase to ground; two phase short-circuit; and two phase to ground. Calculate the fault current that flows through Breaker bk due to a balanced threephase at Bus m. Assume E2 = 1.0pu and E1 = 1.0pu.
4.
Submission Requirements
Your submission should be in the form of a brief report with (a) (b) An Introduction that includes the purpose of the project, a description of the network, and the key tasks that will be carried out. A results section that briefly introduces each task and presents the results of each task in a suitable format. The required outcomes are: (i) (ii) (iii) (iv) from Task 1 - a PowerFactory listing of the input data for generators, transmission lines, transformers, and load. from Task 2 - a table of bus voltages taken from the initial load flow analysis. from Task 3 - a tabulation of the results from PowerFactory from Task 4 the calculated values for the required fault currents, along with a brief comparison of calculated results with the relevant simulated results. Explain the source of any discrepancies.
(c) (d)
NOTE: the impedance values are given as short-circuit voltage, in per unit. The short circuit voltage is the voltage that needs to be applied across the primary terminals in order to generate the nominal current in the secondary when the secondary terminals are short-circuited. If the nominal current is 1 pu, then shortcircuit voltage in per unit will be the same as the equivalent transformer impedance in per unit. Per unit is often specified as a percentage rather than as a fraction, so 0.1 pu is the same as 10%.
2. Create new generator types for each generator. Set the Nominal Apparent Power and Nominal Voltage to the rated values given in Figure 1. Use the default Power Factor setting of 0.8, and select either the Y or YN Connection, as required. The subtransient reactance is entered by clicking the Complete Short-Circuit tab and then entering the required value as the value for xd. Also enter Negative-Sequence and Zero Sequence values.
3.
Create a new line type the same type can be used for both transmission lines. Set the Rated Voltage to 33 kV, the Rated Current to 1 kA and the Nominal Frequency to 50 Hz. Set Cable/OHL to Overhead Line. Enter the required reactance values.
4.
ENG455 Experiment 02 : Short-Circuit Analysis Performing Short-Circuit Calculations Single Faults Left Click to select the Busbar that will be faulted, then right-click to open the contextsensitive menu. Select Calculate Short-Circuit. This last step opens the Short Circuit Calculations dialogue box. Use the following settings:
Item
Method
Selection
Complete
Alternatives
According to IEC60909 According to IEC61363 According to VDE0102 According to ANSI
Fault Type
3-Phase Short-Circuit
Notes:
1. 2. 3. The Complete Method first evaluates the pre-fault load flow to obtain bus voltages. It is possible to check or modify load flow options using the Load Flow button. The Fault Impedance can be used to model arc impedance or some other impedance of the shortened path. For Show Output, ticking the box will mean that the text report is automatically sent to the output window at the bottom of the screen.
Finally, click the Execute button. The fault analysis will be carried out, with the output results for fault current at the faulted Bus are given in the Output Window. Notice that the messages printed out ahead of the output fault data confirm that a load flow analysis was carried out prior to the short-circuit calculations. Also notice that a red lightning icon appears next to the faulted bus. Note: The fault currents are listed as Ik''. Change the fault type to one of the other possibilities, such as Single phase to ground, and repeat the analysis. Note that because these faults are unbalanced, separate results are given for each of the three phases.
ENG455 Experiment 02 : Short-Circuit Analysis Alternative Methods for Executing a Single Fault
A short-circuit fault analysis can also be initiated by clicking the Calculate Short-Circuit button on the main menu bar (this is the button with a red lighting strike icon). The Short-Circuit Calculation dialogue window will appear. The user can then select the required fault location by selecting the location at User Selection, and then clicking the Down Arrow button next to User Selection. The desired fault location can be selected from the Please Select Object browser window. Then click Execute. A short-circuit analysis can be made at all buses and terminals by selecting the Fault