DETAIL OF CONSTRUCTION SCHEDULE

COAL FIRED STEAM POWER PLANT PROJECT


2X 110 MW- TENAYAN RIAU
UPDATE DECEMBER 2011

ID

Task Name

Detail Construction Schedule

Duration

Start

Finish

Baseline1 Start

Baseline1 Finish

Quantity

Unit

Productivity

Unit
W2 W2 W2 W2 W2 W2 W2 W2 W2 W3 W3 W3 W3 W3 W3 W3 W3 W3 W3 W4 W4 W4 W4 W4 W4 W4 W4 W4 W4 W5 W5 W5 W5 W5 W5 W5 W5 W5 W5 W6 W6 W6 W6 W6 W6 W6 W6

240 days

Thu 9/1/11

Thu 7/5/12

Thu 9/1/11

Mon 7/16/12

Backfill Platform

162 days

Thu 9/1/11

Mon 3/19/12

Thu 9/1/11

Thu 1/19/12

Chimney

20 days

Thu 9/1/11

Wed 9/28/11

Thu 9/1/11

Wed 9/28/11

25,932.8

m3

3,000

m3/day

Boiler

20 days

Thu 9/15/11

Sat 10/8/11

Thu 9/15/11

Sat 10/8/11

13,575.55

m3

3,000

m3/day

Turbine Generator

20 days

Thu 9/15/11

Sat 10/8/11

Thu 9/15/11

Sat 10/8/11

11,106,45

m3

3,000

m3/day

150 KV Building

20 days

Thu 9/29/11

Tue 10/18/11

Thu 9/29/11

Tue 10/18/11

21,962.3

m3

3,000

m3/day

Admin Building

20 days

Wed 10/19/11

Mon 1/16/12

Wed 10/19/11

Mon 11/7/11

21,840.9

m3

3,000

m3/day

Cooling tower

20 days

Tue 11/8/11

Mon 1/30/12

Tue 11/8/11

Sun 11/27/11

21,785.5

m3

3,000

m3/day

Waste water treatment plant

20 days

Mon 11/28/11

Mon 2/13/12

Mon 11/28/11

Thu 12/22/11

13,988.5

m3

3,000

m3/day

10

Coal yard

25 days

Tue 2/14/12

Mon 3/19/12

Fri 12/23/11

Thu 1/26/12

68,246.9

m3

3,000

m3/day

171 days

Thu 11/17/11

Thu 7/5/12

Thu 11/17/11

Wed 6/13/12

11

Vertical drain & Horizontal drain

12

Chimney

22 days

Thu 11/17/11

Sat 12/10/11

Thu 11/17/11

Sat 12/10/11

175,718

m3

8,000

m/day

13

Boiler

12 days

Mon 1/30/12

Wed 2/15/12

Sat 11/26/11

Sat 12/10/11

91,984

m3

8,000

m/day

14

Turbine Generator

10 days

Wed 2/15/12

Tue 2/28/12

Sat 12/10/11

Thu 12/22/11

75,259

m3

8,000

m/day

15

150 KV Building

19 days

Tue 1/3/12

Fri 1/27/12

Mon 12/12/11

Thu 1/5/12

148,816

m3

8,000

m/day

16

Admin Building

20 days

Mon 1/30/12

Fri 2/24/12

Fri 1/6/12

Thu 2/2/12

161,452

m3

8,000

m/day

17

Cooling tower

20 days

Mon 2/27/12

Fri 3/23/12

Fri 2/3/12

Thu 3/1/12

161,035

m3

8,000

m/day

18

Waste water treatment plant

13 days

Mon 3/26/12

Wed 4/11/12

Fri 3/2/12

Tue 3/20/12

103,406

m3

8,000

m/day

19

Coal yard

61 days

Thu 4/12/12

Thu 7/5/12

Wed 3/21/12

Wed 6/13/12

486,930

m3

8,000

m/day

20

Surcharge fill

111 days

Tue 1/3/12

Tue 6/5/12

Sat 12/10/11

Mon 7/16/12

21

Boiler

20 days

Wed 2/15/12

Tue 3/13/12

Wed 2/15/12

Tue 3/13/12

49,362.6

m3

2500

m3

22

Turbine Generator

30 days

Wed 2/15/12

Tue 3/27/12

Wed 2/15/12

Tue 3/27/12

74,043.9

m3

2500

m3

23

Chimney

31 days

Tue 1/3/12

Tue 2/14/12

Tue 1/3/12

Tue 2/14/12

77,798.4

m3

2500

m3

24

150 KV Building

21 days

Tue 2/14/12

Tue 3/13/12

Tue 2/14/12

Tue 3/13/12

109,811.5

m3

5000

m3

25

Admin Building

21 days

Wed 3/14/12

Wed 4/11/12

Wed 3/14/12

Wed 4/11/12

109,204.5

m3

5000

m3

26

Cooling tower

21 days

Tue 2/14/12

Tue 3/13/12

Tue 2/14/12

Tue 3/13/12

108,927.5

m3

5000

m3

27

Waste water treatment plant

14 days

Wed 3/14/12

Mon 4/2/12

Wed 3/14/12

Mon 4/2/12

69,942.5

m3

5000

m3

28

Coal yard

60 days

Wed 3/14/12

Tue 6/5/12

Wed 3/14/12

Tue 6/5/12

307,111.05

m3

5000

m3

78.5 days

Tue 12/20/11

Fri 4/6/12

Thu 12/8/11

Thu 3/15/12

29
30

Test Pile

18 days

Tue 1/3/12

Thu 1/26/12

Thu 12/8/11

Fri 12/30/11

31

Preparation test Compression

7 days

Tue 1/3/12

Wed 1/11/12

Thu 12/8/11

Thu 12/15/11

32

Compression test

2 days

Thu 1/12/12

Fri 1/13/12

Fri 12/16/11

Mon 12/19/11

33

preparation test lateral

7 days

Mon 1/16/12

Tue 1/24/12

Tue 12/20/11

Wed 12/28/11

34
35

Boiler House

Lateral test
Main Power Building

2 days

Wed 1/25/12

Thu 1/26/12

Thu 12/29/11

Fri 12/30/11

37 days

Tue 12/20/11

Wed 2/8/12

Tue 12/20/11

Thu 1/12/12

36

Preparation test compression

7 days

Tue 12/20/11

Thu 1/19/12

Tue 12/20/11

Wed 12/28/11

37

Compression test

2 days

Thu 1/19/12

Mon 1/23/12

Thu 12/29/11

Fri 12/30/11

38

Preparation test lateral

7 days

Fri 1/27/12

Mon 2/6/12

Mon 1/2/12

Tue 1/10/12

39

Lateral test

2 days

Tue 2/7/12

Wed 2/8/12

Wed 1/11/12

Thu 1/12/12

27 days

Mon 1/23/12

Wed 2/29/12

Mon 1/2/12

Tue 2/7/12

Mon 1/23/12

Wed 2/1/12

Mon 1/2/12

Tue 1/10/12
Thu 1/12/12

40

Chimney

41

Preparation test compression

7 days

42

Compression test

2 days

Wed 2/1/12

Fri 2/3/12

Wed 1/11/12

43

Preparation test lateral

7 days

Thu 2/16/12

Mon 2/27/12

Thu 1/26/12

Fri 2/3/12

44

Lateral test

2 days

Mon 2/27/12

Wed 2/29/12

Mon 2/6/12

Tue 2/7/12

45

Preparation test tension

7 days

Fri 2/3/12

Tue 2/14/12

Fri 1/13/12

Mon 1/23/12

46

Tension test

2 days

Tue 2/14/12

Thu 2/16/12

Tue 1/24/12

Wed 1/25/12

47

150 KV Building

Mon 2/20/12

42.5 days

Fri 1/13/12

Tue 3/13/12

Fri 1/13/12

48

Preparation test compression

7 days

Fri 1/13/12

Mon 1/23/12

Fri 1/13/12

Mon 1/23/12

49

Compression test

2 days

Tue 1/24/12

Wed 1/25/12

Tue 1/24/12

Wed 1/25/12

50

Preparation test lateral

7 days

Wed 2/29/12

Fri 3/9/12

Wed 2/8/12

Thu 2/16/12

51

Lateral test

2 days

Fri 3/9/12

Tue 3/13/12

Fri 2/17/12

Mon 2/20/12

52

Preparation test tension

7 days

Thu 2/16/12

Mon 2/27/12

Thu 1/26/12

Fri 2/3/12

53

Tension test

2 days

Mon 2/27/12

Wed 2/29/12

Mon 2/6/12

Tue 2/7/12

54

Admin Building

Fri 3/2/12

42.5 days

Thu 1/26/12

Mon 3/26/12

Thu 1/26/12

55

Preparation test compression

7 days

Thu 1/26/12

Fri 2/3/12

Thu 1/26/12

Fri 2/3/12

56

Compression test

2 days

Mon 2/6/12

Tue 2/7/12

Mon 2/6/12

Tue 2/7/12

57

Preparation test lateral

7 days

Tue 3/13/12

Thu 3/22/12

Tue 2/21/12

Wed 2/29/12

58

Lateral test

2 days

Thu 3/22/12

Mon 3/26/12

Thu 3/1/12

Fri 3/2/12

59

Preparation test tension

7 days

Wed 2/29/12

Fri 3/9/12

Wed 2/8/12

Thu 2/16/12

60
61

Tension test
Jetty

2 days

Fri 3/9/12

Tue 3/13/12

Fri 2/17/12

Mon 2/20/12

42.5 days

Wed 2/8/12

Fri 4/6/12

Wed 2/8/12

Thu 3/15/12

62

Preparation test compression

7 days

Wed 2/8/12

Thu 2/16/12

Wed 2/8/12

Thu 2/16/12

63

Compression test

2 days

Fri 2/17/12

Mon 2/20/12

Fri 2/17/12

Mon 2/20/12

64

Preparation test lateral

7 days

Mon 3/26/12

Wed 4/4/12

Mon 3/5/12

Tue 3/13/12

65

Lateral test

2 days

Wed 4/4/12

Fri 4/6/12

Wed 3/14/12

Thu 3/15/12

90 days

Fri 11/11/11

Tue 3/6/12

Fri 11/11/11

Wed 2/15/12

59 days

Fri 11/11/11

Mon 1/23/12

Fri 11/11/11

Thu 12/15/11

66
67

Project: detail const2


Date: Tue 12/27/11

Temporary Jetty
Preparation and Mobilization

Task

Progress

Summary

External Tasks

Split

Split

Milestone

Project Summary

External MileTask

critical
Page 1

milestone

DETAIL OF CONSTRUCTION SCHEDULE


COAL FIRED STEAM POWER PLANT PROJECT
2X 110 MW- TENAYAN RIAU
UPDATE DECEMBER 2011

ID

Task Name

Duration

Start

Finish

Baseline1 Start

Baseline1 Finish

Quantity

Unit

Productivity

Unit
W2 W2 W2 W2 W2 W2 W2 W2 W2 W3 W3 W3 W3 W3 W3 W3 W3 W3 W3 W4 W4 W4 W4 W4 W4 W4 W4 W4 W4 W5 W5 W5 W5 W5 W5 W5 W5 W5 W5 W6 W6 W6 W6 W6 W6 W6 W6

68
69
70

Equipment mobilization
Land clearing
Dead man/ Counter weight

2 days

Fri 11/11/11

Wed 12/14/11

Fri 11/11/11

Sat 11/12/11
Thu 12/15/11

30 days

Sun 11/13/11

Mon 1/23/12

Sun 11/13/11

34 days

Tue 12/13/11

Fri 1/27/12

Tue 12/13/11

Thu 1/12/12

Wed 1/4/12

Fri 12/16/11

Tue 12/20/11

71

Excavation and Install Plastic Sheet

3 days

Fri 12/16/11

72

Rebar

7 days

Tue 12/13/11

Thu 1/26/12

Tue 12/13/11

Wed 12/21/11

73

Formwork + Accessories

7 days

Tue 1/3/12

Wed 1/11/12

Mon 12/19/11

Tue 12/27/11

74

Concreting

12 days

Thu 1/12/12

Fri 1/27/12

Wed 12/28/11

Thu 1/12/12

7 days

Thu 1/19/12

Fri 1/27/12

Tue 12/13/11

Wed 12/21/11
Wed 12/14/11

75

Platform Crane preparation

76

Geotextile

2 days

Thu 1/19/12

Fri 1/20/12

Tue 12/13/11

77

Sandy backfill

3 days

Mon 1/23/12

Wed 1/25/12

Thu 12/15/11

Mon 12/19/11

78

Compaction

2 days

Thu 1/26/12

Fri 1/27/12

Tue 12/20/11

Wed 12/21/11

79

Sheet piling

30.56 days

Wed 1/11/12

Wed 2/22/12

Thu 12/22/11

Tue 1/17/12

80

East

8 days

Wed 1/11/12

Tue 2/7/12

Thu 12/22/11

Mon 1/2/12

38

EA

81

South

5 days

Tue 2/7/12

Tue 2/14/12

Tue 1/3/12

Mon 1/9/12

22

EA

82

West

6 days

Tue 2/14/12

Wed 2/22/12

Tue 1/10/12

Tue 1/17/12

30

EA

Mon 2/13/12

Wed 12/28/11

Tue 1/24/12

83

Anchoring

20 days

Tue 1/17/12

84

Install

17 days

Tue 1/17/12

Wed 2/8/12

Wed 12/28/11

Thu 1/19/12

85

Stressing

17 days

Fri 1/20/12

Mon 2/13/12

Mon 1/2/12

Tue 1/24/12

86

Fender

2 days

Fri 2/10/12

Mon 2/13/12

Mon 1/23/12

Tue 1/24/12

21 days

Tue 1/24/12

Tue 2/21/12

Wed 1/4/12

Wed 2/1/12

7 days

Tue 1/24/12

Wed 2/1/12

Wed 1/4/12

Thu 1/12/12

14 days

Thu 2/2/12

Tue 2/21/12

Fri 1/13/12

Wed 2/1/12

7 days

Mon 2/13/12

Tue 2/21/12

Tue 1/24/12

Wed 2/1/12

87

Dredging

88

Standard Excavation

89

Long Arm

90

Ponton

91

Backfill and Levelling

17 days

Tue 1/24/12

Wed 2/15/12

Wed 1/4/12

Thu 1/26/12

92

PC Pile Driving

14 days

Thu 2/16/12

Tue 3/6/12

Fri 1/27/12

Wed 2/15/12

14 days

Thu 2/16/12

Tue 3/6/12

Fri 1/27/12

Wed 2/15/12

11 days

Tue 2/21/12

Tue 3/6/12

Wed 2/1/12

Wed 2/15/12

3 days

Fri 3/2/12

Tue 3/6/12

Mon 2/13/12

Wed 2/15/12

157 days

Thu 10/13/11

Fri 4/27/12

Thu 10/13/11

Wed 3/28/12

7 days

Thu 10/13/11

Wed 10/19/11

Thu 10/13/11

Wed 10/19/11

93

PC Pile Work

94

Platform

95

Bollard

96

Batching Plant

97

Owner estimate

98

TBE & CBE

15 days

Sat 11/19/11

Mon 12/5/11

Sat 11/19/11

Mon 12/5/11

99

Mix design

45 days

Thu 11/17/11

Wed 1/11/12

Thu 11/17/11

Wed 1/11/12

100

Trial mix internal

27 days

Sat 11/19/11

Fri 1/20/12

Sat 11/19/11

Tue 12/20/11

101

Trial mix design

54 days

Tue 1/3/12

Fri 3/16/12

Mon 12/5/11

Wed 2/15/12

102

Bid process

30 days

Thu 10/20/11

Fri 11/18/11

Thu 10/20/11

Fri 11/18/11

103

Contract

3 days

Tue 12/6/11

Tue 1/3/12

Tue 12/6/11

Thu 12/8/11

104

Mobilization

20 days

Tue 1/3/12

Tue 1/31/12

Fri 12/9/11

Wed 1/4/12

105

Fence material deliveries

20 days

Tue 1/3/12

Tue 1/31/12

Fri 12/9/11

Wed 1/4/12

106

Soil development

60 days

Sun 11/20/11

Thu 3/8/12

Sun 11/20/11

Mon 2/6/12

107

Piling work

30 days

Wed 11/30/11

Fri 1/27/12

Wed 11/30/11

Mon 1/9/12

108

Concreting foundation batching plant

15 days

Tue 1/3/12

Mon 1/23/12

Tue 12/20/11

Mon 1/9/12

109

Install batching plant

14 days

Tue 1/31/12

Mon 2/20/12

Tue 1/10/12

Fri 1/27/12

110

Bore well

7 days

Tue 1/24/12

Wed 2/1/12

Tue 1/10/12

Wed 1/18/12

111

Trial Batching plant

30 days

Mon 3/19/12

Fri 4/27/12

Thu 2/16/12

Wed 3/28/12

112

Install Fence

14 days

Tue 1/31/12

Mon 2/20/12

Thu 1/5/12

Tue 1/24/12

113

Loader Ramp

21 days

Tue 1/3/12

Tue 1/31/12

Tue 12/27/11

Tue 1/24/12

114

Laboratory

14 days

Tue 2/7/12

Mon 2/27/12

Tue 1/17/12

Fri 2/3/12

115

Site office

14 days

Tue 2/7/12

Mon 2/27/12

Tue 1/17/12

Fri 2/3/12

116

Warehouse

14 days

Tue 2/7/12

Mon 2/27/12

Tue 1/17/12

Fri 2/3/12

117

Water pond

14 days

Tue 1/24/12

Fri 2/10/12

Tue 1/10/12

Fri 1/27/12

118
119

Solar Tank
Piling Work

14 days

Tue 1/31/12

Mon 2/20/12

Tue 1/10/12

Fri 1/27/12

47 days

Mon 2/6/12

Wed 4/11/12

Tue 1/24/12

Tue 5/22/12

120

Piling work at Boiler

0 days

Tue 2/28/12

Tue 2/28/12

Tue 2/28/12

Tue 2/28/12

121

Piling work at Turbine generator

0 days

Tue 2/28/12

Tue 2/28/12

Tue 2/28/12

Tue 2/28/12

122

Piling Work at Chimney

0 days

Mon 2/6/12

Mon 2/6/12

Mon 2/6/12

Mon 2/6/12

123

Piling Work at 150 KV building

0 days

Tue 3/13/12

Tue 3/13/12

Tue 3/13/12

Tue 3/13/12

124

Piling work at Admin building

0 days

Wed 4/11/12

Wed 4/11/12

Wed 4/11/12

Wed 4/11/12

125

Piling work at Cooling Tower

0 days

Tue 3/13/12

Tue 3/13/12

Tue 3/13/12

Tue 3/13/12

126

Piling work at Waste water treatment plant

0 days

Mon 4/2/12

Mon 4/2/12

Mon 4/2/12

Mon 4/2/12

Project: detail const2


Date: Tue 12/27/11

2/28
2/28
2/6
3/13
4/11
3/13
4/2

Task

Progress

Summary

External Tasks

Split

Split

Milestone

Project Summary

External MileTask

critical
Page 2