Beruflich Dokumente
Kultur Dokumente
ID
Task Name
Duration
Start
Finish
Baseline1 Start
Baseline1 Finish
Quantity
Unit
Productivity
Unit
W2 W2 W2 W2 W2 W2 W2 W2 W2 W3 W3 W3 W3 W3 W3 W3 W3 W3 W3 W4 W4 W4 W4 W4 W4 W4 W4 W4 W4 W5 W5 W5 W5 W5 W5 W5 W5 W5 W5 W6 W6 W6 W6 W6 W6 W6 W6
240 days
Thu 9/1/11
Thu 7/5/12
Thu 9/1/11
Mon 7/16/12
Backfill Platform
162 days
Thu 9/1/11
Mon 3/19/12
Thu 9/1/11
Thu 1/19/12
Chimney
20 days
Thu 9/1/11
Wed 9/28/11
Thu 9/1/11
Wed 9/28/11
25,932.8
m3
3,000
m3/day
Boiler
20 days
Thu 9/15/11
Sat 10/8/11
Thu 9/15/11
Sat 10/8/11
13,575.55
m3
3,000
m3/day
Turbine Generator
20 days
Thu 9/15/11
Sat 10/8/11
Thu 9/15/11
Sat 10/8/11
11,106,45
m3
3,000
m3/day
150 KV Building
20 days
Thu 9/29/11
Tue 10/18/11
Thu 9/29/11
Tue 10/18/11
21,962.3
m3
3,000
m3/day
Admin Building
20 days
Wed 10/19/11
Mon 1/16/12
Wed 10/19/11
Mon 11/7/11
21,840.9
m3
3,000
m3/day
Cooling tower
20 days
Tue 11/8/11
Mon 1/30/12
Tue 11/8/11
Sun 11/27/11
21,785.5
m3
3,000
m3/day
20 days
Mon 11/28/11
Mon 2/13/12
Mon 11/28/11
Thu 12/22/11
13,988.5
m3
3,000
m3/day
10
Coal yard
25 days
Tue 2/14/12
Mon 3/19/12
Fri 12/23/11
Thu 1/26/12
68,246.9
m3
3,000
m3/day
171 days
Thu 11/17/11
Thu 7/5/12
Thu 11/17/11
Wed 6/13/12
11
12
Chimney
22 days
Thu 11/17/11
Sat 12/10/11
Thu 11/17/11
Sat 12/10/11
175,718
m3
8,000
m/day
13
Boiler
12 days
Mon 1/30/12
Wed 2/15/12
Sat 11/26/11
Sat 12/10/11
91,984
m3
8,000
m/day
14
Turbine Generator
10 days
Wed 2/15/12
Tue 2/28/12
Sat 12/10/11
Thu 12/22/11
75,259
m3
8,000
m/day
15
150 KV Building
19 days
Tue 1/3/12
Fri 1/27/12
Mon 12/12/11
Thu 1/5/12
148,816
m3
8,000
m/day
16
Admin Building
20 days
Mon 1/30/12
Fri 2/24/12
Fri 1/6/12
Thu 2/2/12
161,452
m3
8,000
m/day
17
Cooling tower
20 days
Mon 2/27/12
Fri 3/23/12
Fri 2/3/12
Thu 3/1/12
161,035
m3
8,000
m/day
18
13 days
Mon 3/26/12
Wed 4/11/12
Fri 3/2/12
Tue 3/20/12
103,406
m3
8,000
m/day
19
Coal yard
61 days
Thu 4/12/12
Thu 7/5/12
Wed 3/21/12
Wed 6/13/12
486,930
m3
8,000
m/day
20
Surcharge fill
111 days
Tue 1/3/12
Tue 6/5/12
Sat 12/10/11
Mon 7/16/12
21
Boiler
20 days
Wed 2/15/12
Tue 3/13/12
Wed 2/15/12
Tue 3/13/12
49,362.6
m3
2500
m3
22
Turbine Generator
30 days
Wed 2/15/12
Tue 3/27/12
Wed 2/15/12
Tue 3/27/12
74,043.9
m3
2500
m3
23
Chimney
31 days
Tue 1/3/12
Tue 2/14/12
Tue 1/3/12
Tue 2/14/12
77,798.4
m3
2500
m3
24
150 KV Building
21 days
Tue 2/14/12
Tue 3/13/12
Tue 2/14/12
Tue 3/13/12
109,811.5
m3
5000
m3
25
Admin Building
21 days
Wed 3/14/12
Wed 4/11/12
Wed 3/14/12
Wed 4/11/12
109,204.5
m3
5000
m3
26
Cooling tower
21 days
Tue 2/14/12
Tue 3/13/12
Tue 2/14/12
Tue 3/13/12
108,927.5
m3
5000
m3
27
14 days
Wed 3/14/12
Mon 4/2/12
Wed 3/14/12
Mon 4/2/12
69,942.5
m3
5000
m3
28
Coal yard
60 days
Wed 3/14/12
Tue 6/5/12
Wed 3/14/12
Tue 6/5/12
307,111.05
m3
5000
m3
78.5 days
Tue 12/20/11
Fri 4/6/12
Thu 12/8/11
Thu 3/15/12
29
30
Test Pile
18 days
Tue 1/3/12
Thu 1/26/12
Thu 12/8/11
Fri 12/30/11
31
7 days
Tue 1/3/12
Wed 1/11/12
Thu 12/8/11
Thu 12/15/11
32
Compression test
2 days
Thu 1/12/12
Fri 1/13/12
Fri 12/16/11
Mon 12/19/11
33
7 days
Mon 1/16/12
Tue 1/24/12
Tue 12/20/11
Wed 12/28/11
34
35
Boiler House
Lateral test
Main Power Building
2 days
Wed 1/25/12
Thu 1/26/12
Thu 12/29/11
Fri 12/30/11
37 days
Tue 12/20/11
Wed 2/8/12
Tue 12/20/11
Thu 1/12/12
36
7 days
Tue 12/20/11
Thu 1/19/12
Tue 12/20/11
Wed 12/28/11
37
Compression test
2 days
Thu 1/19/12
Mon 1/23/12
Thu 12/29/11
Fri 12/30/11
38
7 days
Fri 1/27/12
Mon 2/6/12
Mon 1/2/12
Tue 1/10/12
39
Lateral test
2 days
Tue 2/7/12
Wed 2/8/12
Wed 1/11/12
Thu 1/12/12
27 days
Mon 1/23/12
Wed 2/29/12
Mon 1/2/12
Tue 2/7/12
Mon 1/23/12
Wed 2/1/12
Mon 1/2/12
Tue 1/10/12
Thu 1/12/12
40
Chimney
41
7 days
42
Compression test
2 days
Wed 2/1/12
Fri 2/3/12
Wed 1/11/12
43
7 days
Thu 2/16/12
Mon 2/27/12
Thu 1/26/12
Fri 2/3/12
44
Lateral test
2 days
Mon 2/27/12
Wed 2/29/12
Mon 2/6/12
Tue 2/7/12
45
7 days
Fri 2/3/12
Tue 2/14/12
Fri 1/13/12
Mon 1/23/12
46
Tension test
2 days
Tue 2/14/12
Thu 2/16/12
Tue 1/24/12
Wed 1/25/12
47
150 KV Building
Mon 2/20/12
42.5 days
Fri 1/13/12
Tue 3/13/12
Fri 1/13/12
48
7 days
Fri 1/13/12
Mon 1/23/12
Fri 1/13/12
Mon 1/23/12
49
Compression test
2 days
Tue 1/24/12
Wed 1/25/12
Tue 1/24/12
Wed 1/25/12
50
7 days
Wed 2/29/12
Fri 3/9/12
Wed 2/8/12
Thu 2/16/12
51
Lateral test
2 days
Fri 3/9/12
Tue 3/13/12
Fri 2/17/12
Mon 2/20/12
52
7 days
Thu 2/16/12
Mon 2/27/12
Thu 1/26/12
Fri 2/3/12
53
Tension test
2 days
Mon 2/27/12
Wed 2/29/12
Mon 2/6/12
Tue 2/7/12
54
Admin Building
Fri 3/2/12
42.5 days
Thu 1/26/12
Mon 3/26/12
Thu 1/26/12
55
7 days
Thu 1/26/12
Fri 2/3/12
Thu 1/26/12
Fri 2/3/12
56
Compression test
2 days
Mon 2/6/12
Tue 2/7/12
Mon 2/6/12
Tue 2/7/12
57
7 days
Tue 3/13/12
Thu 3/22/12
Tue 2/21/12
Wed 2/29/12
58
Lateral test
2 days
Thu 3/22/12
Mon 3/26/12
Thu 3/1/12
Fri 3/2/12
59
7 days
Wed 2/29/12
Fri 3/9/12
Wed 2/8/12
Thu 2/16/12
60
61
Tension test
Jetty
2 days
Fri 3/9/12
Tue 3/13/12
Fri 2/17/12
Mon 2/20/12
42.5 days
Wed 2/8/12
Fri 4/6/12
Wed 2/8/12
Thu 3/15/12
62
7 days
Wed 2/8/12
Thu 2/16/12
Wed 2/8/12
Thu 2/16/12
63
Compression test
2 days
Fri 2/17/12
Mon 2/20/12
Fri 2/17/12
Mon 2/20/12
64
7 days
Mon 3/26/12
Wed 4/4/12
Mon 3/5/12
Tue 3/13/12
65
Lateral test
2 days
Wed 4/4/12
Fri 4/6/12
Wed 3/14/12
Thu 3/15/12
90 days
Fri 11/11/11
Tue 3/6/12
Fri 11/11/11
Wed 2/15/12
59 days
Fri 11/11/11
Mon 1/23/12
Fri 11/11/11
Thu 12/15/11
66
67
Temporary Jetty
Preparation and Mobilization
Task
Progress
Summary
External Tasks
Split
Split
Milestone
Project Summary
External MileTask
critical
Page 1
milestone
ID
Task Name
Duration
Start
Finish
Baseline1 Start
Baseline1 Finish
Quantity
Unit
Productivity
Unit
W2 W2 W2 W2 W2 W2 W2 W2 W2 W3 W3 W3 W3 W3 W3 W3 W3 W3 W3 W4 W4 W4 W4 W4 W4 W4 W4 W4 W4 W5 W5 W5 W5 W5 W5 W5 W5 W5 W5 W6 W6 W6 W6 W6 W6 W6 W6
68
69
70
Equipment mobilization
Land clearing
Dead man/ Counter weight
2 days
Fri 11/11/11
Wed 12/14/11
Fri 11/11/11
Sat 11/12/11
Thu 12/15/11
30 days
Sun 11/13/11
Mon 1/23/12
Sun 11/13/11
34 days
Tue 12/13/11
Fri 1/27/12
Tue 12/13/11
Thu 1/12/12
Wed 1/4/12
Fri 12/16/11
Tue 12/20/11
71
3 days
Fri 12/16/11
72
Rebar
7 days
Tue 12/13/11
Thu 1/26/12
Tue 12/13/11
Wed 12/21/11
73
Formwork + Accessories
7 days
Tue 1/3/12
Wed 1/11/12
Mon 12/19/11
Tue 12/27/11
74
Concreting
12 days
Thu 1/12/12
Fri 1/27/12
Wed 12/28/11
Thu 1/12/12
7 days
Thu 1/19/12
Fri 1/27/12
Tue 12/13/11
Wed 12/21/11
Wed 12/14/11
75
76
Geotextile
2 days
Thu 1/19/12
Fri 1/20/12
Tue 12/13/11
77
Sandy backfill
3 days
Mon 1/23/12
Wed 1/25/12
Thu 12/15/11
Mon 12/19/11
78
Compaction
2 days
Thu 1/26/12
Fri 1/27/12
Tue 12/20/11
Wed 12/21/11
79
Sheet piling
30.56 days
Wed 1/11/12
Wed 2/22/12
Thu 12/22/11
Tue 1/17/12
80
East
8 days
Wed 1/11/12
Tue 2/7/12
Thu 12/22/11
Mon 1/2/12
38
EA
81
South
5 days
Tue 2/7/12
Tue 2/14/12
Tue 1/3/12
Mon 1/9/12
22
EA
82
West
6 days
Tue 2/14/12
Wed 2/22/12
Tue 1/10/12
Tue 1/17/12
30
EA
Mon 2/13/12
Wed 12/28/11
Tue 1/24/12
83
Anchoring
20 days
Tue 1/17/12
84
Install
17 days
Tue 1/17/12
Wed 2/8/12
Wed 12/28/11
Thu 1/19/12
85
Stressing
17 days
Fri 1/20/12
Mon 2/13/12
Mon 1/2/12
Tue 1/24/12
86
Fender
2 days
Fri 2/10/12
Mon 2/13/12
Mon 1/23/12
Tue 1/24/12
21 days
Tue 1/24/12
Tue 2/21/12
Wed 1/4/12
Wed 2/1/12
7 days
Tue 1/24/12
Wed 2/1/12
Wed 1/4/12
Thu 1/12/12
14 days
Thu 2/2/12
Tue 2/21/12
Fri 1/13/12
Wed 2/1/12
7 days
Mon 2/13/12
Tue 2/21/12
Tue 1/24/12
Wed 2/1/12
87
Dredging
88
Standard Excavation
89
Long Arm
90
Ponton
91
17 days
Tue 1/24/12
Wed 2/15/12
Wed 1/4/12
Thu 1/26/12
92
PC Pile Driving
14 days
Thu 2/16/12
Tue 3/6/12
Fri 1/27/12
Wed 2/15/12
14 days
Thu 2/16/12
Tue 3/6/12
Fri 1/27/12
Wed 2/15/12
11 days
Tue 2/21/12
Tue 3/6/12
Wed 2/1/12
Wed 2/15/12
3 days
Fri 3/2/12
Tue 3/6/12
Mon 2/13/12
Wed 2/15/12
157 days
Thu 10/13/11
Fri 4/27/12
Thu 10/13/11
Wed 3/28/12
7 days
Thu 10/13/11
Wed 10/19/11
Thu 10/13/11
Wed 10/19/11
93
PC Pile Work
94
Platform
95
Bollard
96
Batching Plant
97
Owner estimate
98
15 days
Sat 11/19/11
Mon 12/5/11
Sat 11/19/11
Mon 12/5/11
99
Mix design
45 days
Thu 11/17/11
Wed 1/11/12
Thu 11/17/11
Wed 1/11/12
100
27 days
Sat 11/19/11
Fri 1/20/12
Sat 11/19/11
Tue 12/20/11
101
54 days
Tue 1/3/12
Fri 3/16/12
Mon 12/5/11
Wed 2/15/12
102
Bid process
30 days
Thu 10/20/11
Fri 11/18/11
Thu 10/20/11
Fri 11/18/11
103
Contract
3 days
Tue 12/6/11
Tue 1/3/12
Tue 12/6/11
Thu 12/8/11
104
Mobilization
20 days
Tue 1/3/12
Tue 1/31/12
Fri 12/9/11
Wed 1/4/12
105
20 days
Tue 1/3/12
Tue 1/31/12
Fri 12/9/11
Wed 1/4/12
106
Soil development
60 days
Sun 11/20/11
Thu 3/8/12
Sun 11/20/11
Mon 2/6/12
107
Piling work
30 days
Wed 11/30/11
Fri 1/27/12
Wed 11/30/11
Mon 1/9/12
108
15 days
Tue 1/3/12
Mon 1/23/12
Tue 12/20/11
Mon 1/9/12
109
14 days
Tue 1/31/12
Mon 2/20/12
Tue 1/10/12
Fri 1/27/12
110
Bore well
7 days
Tue 1/24/12
Wed 2/1/12
Tue 1/10/12
Wed 1/18/12
111
30 days
Mon 3/19/12
Fri 4/27/12
Thu 2/16/12
Wed 3/28/12
112
Install Fence
14 days
Tue 1/31/12
Mon 2/20/12
Thu 1/5/12
Tue 1/24/12
113
Loader Ramp
21 days
Tue 1/3/12
Tue 1/31/12
Tue 12/27/11
Tue 1/24/12
114
Laboratory
14 days
Tue 2/7/12
Mon 2/27/12
Tue 1/17/12
Fri 2/3/12
115
Site office
14 days
Tue 2/7/12
Mon 2/27/12
Tue 1/17/12
Fri 2/3/12
116
Warehouse
14 days
Tue 2/7/12
Mon 2/27/12
Tue 1/17/12
Fri 2/3/12
117
Water pond
14 days
Tue 1/24/12
Fri 2/10/12
Tue 1/10/12
Fri 1/27/12
118
119
Solar Tank
Piling Work
14 days
Tue 1/31/12
Mon 2/20/12
Tue 1/10/12
Fri 1/27/12
47 days
Mon 2/6/12
Wed 4/11/12
Tue 1/24/12
Tue 5/22/12
120
0 days
Tue 2/28/12
Tue 2/28/12
Tue 2/28/12
Tue 2/28/12
121
0 days
Tue 2/28/12
Tue 2/28/12
Tue 2/28/12
Tue 2/28/12
122
0 days
Mon 2/6/12
Mon 2/6/12
Mon 2/6/12
Mon 2/6/12
123
0 days
Tue 3/13/12
Tue 3/13/12
Tue 3/13/12
Tue 3/13/12
124
0 days
Wed 4/11/12
Wed 4/11/12
Wed 4/11/12
Wed 4/11/12
125
0 days
Tue 3/13/12
Tue 3/13/12
Tue 3/13/12
Tue 3/13/12
126
0 days
Mon 4/2/12
Mon 4/2/12
Mon 4/2/12
Mon 4/2/12
2/28
2/28
2/6
3/13
4/11
3/13
4/2
Task
Progress
Summary
External Tasks
Split
Split
Milestone
Project Summary
External MileTask
critical
Page 2
milestone