Beruflich Dokumente
Kultur Dokumente
P4
Supply Records of Oil Filled Power Cable
P4
Characteristics
P5
System Design
P6
P9
Tests
P13
Construction
P14
Accessories
P18
Installation
P22
P4
1978
Started Supply and Installation of 154kV OF Cable to KEPCO, Korea. Contracted with TNB for Turnkey Project of 132kV OF Cable Underground Network in Kuala Lumpur, Malaysia. Contracted with Dubai Electricity Company for Turnkey Project of 132kV OF Cable Underground Network in United Arab Emirates. Contracted with TNB for Turnkey Project of 132kV OF Cable Underground Network in kuala Lumpur, Malaysia. Contracted with PLN for 150kV OF Cable Underground Network Project in Surabaya, Indonesia. Contracted with Dubai Electricity Comapnay for Turnkey Project of 132kV OF Cable Underground Network in United Arab Emirates. Started Supply and Installation of 345kV OF Cable to KEPCO, Korea. Contracted with PLN for 150kV OF Cable Underground Network Project in Semarang, Indonesia. Contracted with TNB for Turnkey Project of 132kV OF Cable Underground Network in Malaysia. Contracted with Meta-Epsi for Turnkey Project of 150kV OF Cable Underground Network in Jakarta, Malaysia.
1983
1985
1986
1988
1991
1992
1994
1995
1996
Contracted with TNB for Turnkey Project of 132kV OF Cable Underground Network in Kuala Lumpur City Center, Malaysia. Contracted with SCECO-C for Turnkey Project of 132kV OF Cable Underground Network in Riyadh, Saudi Arabia. Contracted with TNB for Turnkey Project of 275kV OF Cable Underground Network in Malaysia. Contracted with TPC for Turnkey Project of 161kV OF Cable Underground Network in Taiwan. Contracted with TPC for Turnkey Project of 161kV OF Cable Underground Network in Taiwan.
1998
1999
2000
2002
Characteristics
Through incessant research and development, the excellent functions of oil filled cable has been improved since 1924. Among the many excellent characteristics, some typical ones can be listed as follows.
There is absolutely no void within insulation and is stable electrically. The insulation oil, whose air bubbles and humidity are sufficiently removed by performing degassing treatment, is impregnated in insulating paper layer which is fully dried under high vacuum beforehand and kept under high degree of vacuum, and the cable is made accordingly. Since a definite positive pressure is always kept inside of the finished cable, there is absolutely no void in the cable insulation.
Operating potential gradient can be large. Since no deterioration takes place in voids in the insulation by ionizations as in the case with the solid-type cable, the operating potential gradient can be large. Therefore, the insulation thickness can be selected as thin.
Expansion and contraction of insulation oil due to temperature change can be compensated by the oil tanks. Expansion and contraction of insulating oil, due to change of load under use or due to change of the external temperature, can be fully compensated by the oil tank installed in a suitable position on the cable route. Therefore, there can be no void in the insulation.
Possibility of cable self-monitoring The inside of the cable is always kept at positive oil pressure so that no humidity intrudes from the outside in case damage occurs in the cable sheath, or in the joint box. Further, in case the insulating oil leaks, the trouble is detected earlier as the alarm device actuates and it is possible to repair before occurrance of full-scale trouble in the cable system.
P5
P6
System Design
OF cable system can be derived from economical decision and maker s engineering capability about super high tension engineering. The reason is that many sites, around the world, have their own characteristics, for instances, swamp or desert, field or mountain, and inland or seaside. So pracrical route survey can only give precise answer just suitable to its own geographical characteristics. We, Taihan based upon the accumulated technical know-how, have the capability to design any kind of cable system requried and install at any site under any circumstances. By the calculation through computer, cable and accessories can be fixed to make a turn-key system for OF cable.
Cable Design
Taihan manufactures oil filled cables according to the following specification and accomplishes design and manufacture of oil filled cables which are suitable for using conditions to meet the following requirements. 1) Standard specification IEC : International Electrotechnical Commission BS : British Standard(U.K) AEIC : Association of Edition Illuminating Company(U.S.A) Taihan Standard : Taihan Electric Wire Co., Ltd. Others a. Maximum permissible Oil Pressure
Oil Pressure Type Low-Pressure Medium-Pressure Maximum Permissible Oil Pressure ( / ) Normal Operation 3 6~8 Transient Operation 6 11 ~ 14
2) Cable design parameters a. Maximum Permissible Oil Pressure b. Nominal Voltage and Conductor Sectional Area c. Protective Cover
c. Protective Cover
Metalic Sheath Lead Corrugated Aluminum Reinforcement Stainless Steel Armor Steel Tape Anti-corrosion Layer Compound Jute PVC or Polyethylene PVC or Polyethylene
Single Core OF Cable Outdoor Sealing End Sealing End for SF6 Switchgear Insulation Joint Stop Insulation Joint Straight Through Joint Oil Pressure Tank Gauge Panel Link Box for Cross Bonding with Surge Diverter Alarm Receiver Oil Feeding Pipe Control Cable
P7
P8
Route Survey
Route Profile
Off-set Calculation
Selection of Stop Joint Position Selection of Oil Feeding Tank Position Determination of Oil Feeding Method
Transportation Condition
Humidity control
Paper lapping machines are installed in an special control room in order to keep the humidity in the room. The room is kept at slightly higher than atmospheric pressure so that the entry of dust, litter and fine particles of metal which are detrimental to the insulation of cable can be prevented.
P9
P10
Cabler
Besides singe core, all kind of cables should be passed this machine for cabling. Smooth and clean pass lines for paper core are essential to manufacture high quality cable.
Drying Tank
Dielectric power loss, one of the important characteristics of OF cable can be achieved by complete drying method.
Vacuum degree
The vacuum degree of a drying tank is measured at two points, recorded continuously, and checked. Vacuum pumps are in automatic operation and when something goes wrong, they activate and alarm on the central control panel.
Degasifying
Before degasifying, the oil is stored in a low vacuum tank, the vacuum degree being monitored, as the pretreatment. During degasification, the vacuum degree is continuously recorded, and the rate of oil flow is automatically controlled to the vacuum degree so as to obtain a uniform degasification degree. After degasifying, the resistivity, power factor, water content for all oil are measured. In order to reduce moisture infiltration, the oil is held under the pressure of nitrogen during storage.
Completion of oil-impregnation
The judgement that oil-impregnation is completed is made when the oil pressure ceases to drop.
P11
P12
Vacuum Sheathing Equipment
To withstand inner oil pressure and prevent outer mechanical shock, OF cable should be made with metallic layer. To maintain the low moisture contents of dried insulation paper while sheathing metal layer, OF cable should be made under the vacuum continuously. The manufacturing condition for Aluminum Press and Lead Extruder is almost same. For instance, working condition of aluminum press is as follows.
Vacuum sheathing
After the completion of drying, the cable is covered with an aluminum sheath while still being held in high vacuum degree. Throughout this process, the vacuum degree in the cable is monitored and recorded continuously, and any abnormality in vacuum degree triggers and alarm.
Temperature control
The temperatures of the die-block, the ingot heating furnace, and ingots are continuously recorded for consistent operation.
Surface inspection
As the metallic sheath is one of the vital parts of oil filled cables, its surface is inspected continuously in order to confirm that surface damage, pinhole, and other defects do not exist.
Automatic operation
The aluminum press has fully automatic operation to avoid human error and to obtain stablized quality.
PE/PVC Extruder
As an anti-corrosion protection, in many cases underground cable is used with plastic outer sheathes.
Tests
Before the cables leave factory for their destinations all over the world, a thorough program of extensive testing is carried out.
Routine Test
The tests are carried out on all supplied lengths and the results are recorded. The scope of the test is mainly based on IEC 141-1.
Type Tests
Each new type of cable is submitted to a type approval test that is executed in our high voltage research laboratory. A type tests on short cable lenghs may be agreed. If proof is provided that type tests have previously been carried out on cables of similar construction, no further test needs to be carried out. The scope of the test is mainly based on IEC 141-1.
Site Tests
The scope of the tests after installation is mainly based on IEC 141-1.
P13
P14
Construction
Single Core
Conductor Rated Voltage Oil Passage Nominal Area
mm2
I. D
mm
Material
Thickness
of Sheath
kV
mm
mm
600 800 1200 1400 1600 345 BIL = 1,300kV 1800 2000 600 800 1200 1400 1600 1800 2000 600 800 1200 1400 1600 275 BIL = 1,050kV 1800 2000 600 800 1200 1400 1600 1800 2000
18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0
0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
37.9 42.0 47.2 50.3 53.3 56.1 58.8 37.9 42.0 47.2 50.3 53.3 56.1 58.8 35.6 40.6 45.7 48.9 51.9 54.8 57.5 35.6 40.6 45.7 48.9 51.9 54.8 57.5 PPLP Kraft Paper PPLP Kraft Paper
23.4 23.4 23.4 23.4 23.4 23.4 23.4 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 19.5 17.5 17.5 17.5 17.5 17.5 17.5 17.5
2.3 2.4 2.5 2.6 2.6 2.7 2.8 2.2 2.3 2.4 2.4 2.5 2.5 2.6 2.1 2.2 2.4 2.4 2.5 2.5 2.6 2.0 2.1 2.3 2.3 2.4 2.4 2.5
6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
118 122 129 133 136 140 143 107 114 120 124 127 130 134 106 112 118 122 126 129 132 99 105 114 117 121 124 128
Thickness of Sheath
mm
Thickness of Jacket
mm
19,500 22,000 26,900 29,500 31,900 34,500 37,200 17,200 20,000 24,600 27,000 29,600 32,000 34,500 16,700 19,800 24,200 26,800 29,300 31,700 34,300 15,400 18,400 23,100 25,600 28,100 30,400 32,900
3,900 4,250 4,640 4,920 5,160 5,420 5,680 2,580 2,990 3,270 3,450 3,070 3,850 4,070 2,940 3,320 3,630 3,880 4,110 4,320 4,560 2,070 2,500 2,770 2,940 3,140 3,310 3,500
3.7 3.8 3.9 4.0 4.1 4.1 4.2 3.5 3.6 3.7 3.8 3.9 3.9 4.0 3.4 3.5 3.7 3.8 3.8 3.9 4.0 3.3 3.4 3.6 3.7 3.7 3.8 3.9
6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0
111 115 121 125 128 131 134 103 107 113 116 119 123 125 100 105 111 115 118 121 124 96 101 107 110 114 117 120
29,500 32,900 38,600 41,800 45,100 47,900 51,100 26,100 29,300 34,800 38,000 41,000 43,800 47,000 24,800 28,700 34,400 37,500 40,300 43,300 46,600 23,100 26,900 32,500 35,600 38,400 41,400 44,500
3,100 3,360 3,660 3,870 4,080 4,280 4,470 1,750 2,210 2,400 2,560 2,720 2,870 3,020 2,290 2,600 2,830 3,020 3,190 3,370 3,550 1,600 1,840 2,000 2,150 2,290 2,440 2,570
0.0299 0.0227 0.0151 0.0131 0.0114 0.0102 0.00915 0.0299 0.0277 0.0151 0.0131 0.0114 0.0102 0.00915 0.0299 0.0227 0.0151 0.0131 0.0122 0.0102 0.00915 0.0299 0.0277 0.0151 0.0131 0.0122 0.0102 0.00915
0.37 0.25 0.27 0.30 0.31 0.33 0.34 0.35 0.28 0.31 0.35 0.37 0.39 0.40 0.42 0.26 0.29 0.32 0.33 0.35 0.36 0.38
P15
P16
Construction
Conductor Rated Voltage Oil Passage Nominal Area
mm2
I. D
mm
Material
Thickness
of Sheath
kV
mm
mm
200 400 600 220 BIL = 900kV 800 1000 1200 1400 1500 2000 200 400 154 BIL = 750kV 600 800 1000 1200 1500 2000
14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0 14.0
0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
24.4 30.6 35.6 40.6 42.2 45.7 48.9 50.4 57.5 24.4 30.6 35.6 40.6 42.2 45.7 50.4 57.5 Kraft Paper Kraft Paper
18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 18.0 14.0 13.0 12.5 12.5 13.5 13.5 13.5 13.5
1.9 2.0 2.1 2.2 2.2 2.3 2.4 2.4 2.5 1.7 1.8 1.8 2.0 2.1 2.2 2.2 2.4
6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5
97 104 110 115 119 123 126 127 136 83 87 93 96 102 106 111 119
Three Core
Conductor Rated Voltage Nominal Area
mm2
Approx. O.D
mm
kV
Thickness of Sheath
mm
Thickness of Jacket
mm
10,400 13,400 16,100 19,000 19,400 23,400 26,200 27,900 34,100 7,600 9,900 12,100 14,800 17,300 19,800 23,000 29,100
2,230 2,610 2,890 3,250 3,310 3,470 3,680 3,800 4,270 1,480 1,640 1,820 2,050 2,220 2,380 2,630 3,140
3.0 3.2 3.3 3.4 3.5 3.6 3.7 3.7 3.9 2.8 2.9 3.0 3.1 3.3 3.3 3.5 3.6
6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 6.0 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5
15,000 19,200 22,200 26,100 27,900 30,800 33,700 37,100 43,200 12,700 15,800 18,900 22,300 26,100 28,900 33,700 40,700
1,440 1,680 1,890 2,120 2,200 2,310 2,410 2,490 2,750 1,150 1,270 1,390 1,600 1,720 1,850 1,980 2,240
0.0889 0.0441 0.0299 0.0227 0.0181 0.0151 0.0131 0.0122 0.00915 0.0131 0.0122 0.0102 0.00915 0.0181 0.0151 0.0122 0.00915
0.39 0.43 0.27 0.34 0.39 0.43 0.43 0.45 0.51 0.57
Thickness of Sheath
mm
Thickness of Jacket
mm
P17
P18
Accessories
As oil filled cable accessories, there are sealing ends(EB-A, EB-G, EB-O), joint boxes(IJ, NJ, SJ, SIJ), oil feeding and alarm equipments. Sealing Ends
Indoor and outdoor sealing end (EB-A) Sealing end is sends and takes electric power into and out of cable. Porcelain bushings are needed to be insulated between the earth potential parts and the high voltage parts, and this sealing end has stress relief cone formed of wide paper or a condenser cone formed of insulating paper layers and metal foil for inside reinforcement according to the voltage uesd. Connector is fastened to the cable conductor by compression method and a flexible terminal lug is placed between the conductor and the lead wire to avoid applying unnecessary external force against the sealing end.
Dimension(mm) A 1,480 1,830 2,940 3,350 3,975 B 1,725 2,075 3,290 3,700 4,250 C 435 435 500 500 600 D 360 360 480 480 550 E 315 315 470 470 510
Dimension(mm) A 80 110 110 B 112 202 252 C 220 480 540 D 298 559 617 E 320 582 640 F 757 960 1,400
Joint Box
Straight through joint (NJ)
This joint is used for jointing cables, and electrical jointing and oil passage are part of its function or structure. And this joint has same quality as, or better than cable itself, and is free from any electrical and mechanical defects due to the trouble developed by the power transmission system.
Rated Voltage (kV) 110 ~ 161 220 ~ 300 330 ~ 420 Nominal Area of Conductor (mm2) less than 1,000 1,200 ~ 2,000 less than 2,000 less than 2,000 Dimension(mm) L 1,300 1,530 2,000 2,400 D 130 180 200 240
P19
P20
Insulation joint (IJ)
The structure of this joint is almost same as straight through joint box, and the difference between them is to put an insulator flange at the center of copper casing. This box is used for jointing cables and at the same time for insulating on metal sheath from the other metal sheath to get a sheath voltage reducing under safety level.
Rated Voltage (kV) 110 ~ 161 220 ~ 300 330 ~ 420 Nominal Area of Conductor (mm2) less than 1,000 1,200 ~ 2,000 less than 2,000 less than 2,000 Dimension(mm) L 1,300 1,530 2,000 2,400 D 130 180 200 240
Valve panel
The valve panel(guage panel) shall be installed at the intermediate of pressure tank and sealing end or oil stop joint and have such a function as to sense and indicate the oil pressure. If necessary, the pressure guage shall be provided with the electrical contacts which shall make the electric cirucit for the oil pressure alarm.
Other Accessories
Cross bond link box
The cross bonding link box shall be used for connecting the bonding wire properly and be provided with surge diverters to discharge at the suitable for installation in joint handholes and manholes and be fully watertight.
Alarm device
It is advisable to have an alarm device to notify the guard when the cables are out of order or damaged. Usually a transmitter is located at the oil tank and a receiver is placed in the control room. We manufacture three kinds of alarm devices; one alarm device operates when the minimum pressure or volume is reached. Another continuously indicates the pressure or volume, and the third has an indicator and a recorder. The proper one should be chosen after duly considering the functional importance of the cable and the maintenance system adopted for the line.
P21
P22
Installation
Taihan has many achievements and excellent techniques, relative to cable installation work and is making performance doubly sure in regard to safety of operations, besides vigorously promoting development, rationalization and speedy installation. And also Taihan is performing its work consistently, from planning to testing after installation, including laying of oil filled cables, sealing ends assembly, construction of joints, and oil feeding equipment. There are the following methods in laying of oil filled cables and special features are as follows.
Direct Burial
Where the road is narrow, the construction of conduit under the road is usually not permitted. Where the number of cables is few and no future increase is expected. Where the road digging is easy.
Underground Duct
In case of a main underground transmission line where the number of cables are many or expected to be increased in near future. In case of hard pavement or where hard pavement will be constructed in future. Where digging is difficult due to heavy traffic.
Special Laying
In case cables are installed in special places where there are bridges or railways, special laying methods are employed as follows ; When a cable crosses a river or canal, cables are attached to the bridge. If there is no suitable bridge in the neighborhood, an exclusive bridge should be buit or a method of submarine laying should be adopted. As long as the strengh and space of the bridge permits, it is best to attach the cables to the bridge. Whether it is better to build an exclusive bridge or to lay submarine cable depends on the cost and difficulty of construction. In case of crossing a railway, there are two methods; one is digging through the railway bed, and the other is piercing from the side of the railway by using an excavator. When the cable crosses many tracks like a surface from railroad or suburban railway, digging the railway bed is usually adopted. Except for the above case, piercing by using an excavator is adopted.
P23
Head Office
Insong Building, 194-15, 1-ga, Hoehyeon-dong, Jung-gu, Seoul, Korea Tel. 82-2-316-9114 Fax. 82-2-757-2942
R & D Center
996, Siheung-dong, Geumcheon-gu, Seoul, Korea Tel. 82-2-890-9504 Fax. 82-2-806-0186
Anyang Plant
785, Gwanyang-dong, Dongan-gu, Anyang, Gyeonggi-do, Korea Tel. 82-31-420-9114 Fax. 82-31-423-2685
Siheung Plant
113-119, Siheung-dong, Geumcheon-gu, Seoul, Korea Tel. 82-2-890-9114 Fax. 82-2-808-6320
Ansan Plant
603, Seonggok-dong, Ansan, Gyeonggi-do, Korea Tel. 82-31-490-5114 Fax. 82-31-491-3721
Singapore Office
629 Aljunied Road #05-19, Cititech Industrial Building, Singapore 389838, Singapore Tel. 65-842-5069 Fax. 65-842-5076
Riyadh Office
Al Akariyah Shopping Center 2, Room No. 726, Olaya Road, P.O.Box 201, Riyadh, Saudi Arabia Tel. 966-1-419-0227 Fax. 966-1-419-0262
Malesela Taihan Telecom & Energy Electric Cable (Pty) Ltd. Cables Corp.
Vereeniging 1930, Steel Road, Peacehaven Vereeniging 1939, Gauteng, South Africa Tel. 27-16-450-8333 Fax. 27-16-450-8266 85, Denton Avenue, New Hyde Park, NY 11040, U.S.A Tel. 1-718-347-6030 Fax. 1-718-347-6045