Sie sind auf Seite 1von 44

Schedule Oriented Project Planning

The SkillsThe KnowledgeThe Experience www.projectmanagementexperts.com

Joseph (Joe) D. Launi, PMP President & CEO


2009 Project Management Experts, LLC 1

Agenda
Introduction Project/Product Analysis Develop Project Management Plan: 1. Project Scope Management/Scope Baseline 2. Project Schedule Management/Schedule Baseline 3. Project Human Resource Plan 4. Cost Management Plan/Cost Baseline 5. Quality Management Plan 6. Procurement Management Plan 7. Communications Management Plan 8. Risk Management Plan
2009 Project Management Experts, LLC 2

Agenda cont.

Perform Project Integration and Finalize Project Management Plan Closing

INTRODUCTION

2009 Project Management Experts, LLC

Planning Goal is to Baseline the Project Management Plan


Communications
S e p co
Tim e

Procurement
HR

Quality

Risk
e g n a Ch gt. M

Cost

2009 Project Management Experts, LLC

Project Management Process Groups


Monitoring & Controlling Process Planning Processes

Initiating Processes

Closing Processes

Executing Processes

2009 Project Management Experts, LLC

Mapping the Process Areas and the Knowledge Groups


Knowledge Areas 4. Project Integration Mgt.

Initiating
4.1 Develop Project Charter

Project Management Process Groups Monitoring & Executing Planning Controlling


4.2 Develop Project Management Plan 4.3 Direct & Manage Project Execution 4.4 Monitor & Control Project Work 4.5 Perform Integrated Change Control 5.4 Verify Scope 5.5 Control Scope 6.6 Control Schedule

Closing
4.6 Cost Project or Phase

5. Project Scope Mgt.

5.1 Collect Req. 5.2 Define Scope 5.3 Create WBS 6.1 Define Activities 6.2 Sequence Act. 6.3 Est. Activ. Res. 6.4 Est. Activ. Dur. 6.5 Develop Sched 7.1 Estimate Costs 7.2 Determine Budget 8.1 Plan Quality 8.2 Perform Quality Assurance

6. Project Time Mgt.

7. Project Cost Mgt. 8. Project Quality Mgt.

7.3 Control Costs

8.3 Perform Quality Control

Guide to the Project Management Body of Knowledge Fourth Edition 2009 Project Management Experts, LLC 7

Mapping the Process Areas and the Knowledge Groups (cont.)


Knowledge Areas 9. Project HR Mgt.

Project Management Process Groups Initiating Planning


9.1 Develop HR Plan

Executing
9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.3 Distribute Information 10.4 Manage Stakeholder Expectations

Monitoring & Controlling

Closing

10. Project Comm.. Mgt.

10.1 Identify Stakeholders

10.2 Plan Communications

10.5 Report Performance

11. Project Risk Mgt.

11.1 Plan Risk Mgt. 11.2 Identify Risks 11.3 Perform Qualitative Risk Anal. 11.4 Perform Quantitative Risk Anal. 11.5 Plan Risk Resp. 12.1 Plan Procurements 12.2 Conduct Procurements

11.6 Monitor and Control Risks

12. Project Procurement Mgt.

12.3 Administer Procurements

12.4 Close Procurements

Guide to the Project Management Body of Knowledge Fourth Edition 2009 Project Management Experts, LLC

Develop Project Management Plan


Risk
Pr oc ure m
m Ti e

en t

Quality

Scope

. m m o C
2009 Project Management Experts, LLC

Co

st
9

HR

Develop WBS and Project Schedule via PMBOK


5.1 Collect Req. 5.2 Define Scope 6.1 Define Activities 6.2 Sequence Activities 6.3 Est. Act. Res.

5.3 Create WBS 12.2 Conduct Procure, 12.1 Plan Procure.

6.5 Develop Sched.

6.4 Est. Act. Duration

11.2 Identify Risks

9.2 Acquire Proj. Team

8.1 Plan Quality

7.2 Determine Budget

7.1 Estimate Costs

2009 Project Management Experts, LLC

10

Develop Project Schedule and WBS via Schedule Oriented Project Planning (SOPP)
2.1 Define Activities 2.3 Est. Act. Res 2.2 Seq. Activities 2.5 Dev. Sched.

1.2 Define Scope

1.3 Create WBS

WBS Complete

2.4 Est. Act. Durations

1.1 Collect Requre.

3.1 Dev. HR Plan

Draft/ Final Schedule

Start

Schedule Oriented Project Planning (SOPP)


1.3 Create WBS 2.1 Define Act. 2.3 Estimate Act. Res. 2.2 Seq. Act. 2.5 Dev. Sch. 4.1 Est. Costs 4.2 Determine Budget 5.1 Plan Quality 6.1 Plan Procure. 7.1 Plan Comm.

1.2 Define Scope 1.1 Collect Require. Start

2.4 Estimate Act. Dur.

Draft/ Final Sch. 8.1 Plan Risk Mgt. 8.2 Id. Risks

WBS Complete

3.1 Dev.HR Plan 8.3 Perform Qual. Risk Analysis

Develop PM Plan

8.4 Perform Quan. Risk Analysis

The SkillsThe KnowledgeThe Experience www.projectmanagementexperts.com

8.5 Plan Risk Response

Project Analysis Checklist and Survey (PACS)

Documenting what you know and dont know about the project and/or product. (Please give me a business card and I will email PACS to you)

2009 Project Management Experts, LLC

13

1. Project Scope Management

1.2 Define Scope

1.3 Create WBS

WBS Complete

1.1 Collect Requirements

Start

2009 Project Management Experts, LLC

14

1. Project Scope Management


1.3 Create Work Breakdown Structure
Basement Project 1.0 Planning 1.1 Scope 1.1.1 Schedule 1.1.2 Cost 1.1.3
2009 Project Management Experts, LLC 15

Design 1.2

Construction 1.3

Furnishing 1.4

Closure 1.5

WBS WBS Dictionary Scope Baseline Project Document Updates

2. Project Time Management


2.1 Define Activities 2.2 Sequence Activities 2.5 Develop Schedule

WBS Complete

2.3 Estimate Activity Res.

2.4 Estimate Activity Durations

Draft/ Final Schedule

3.1 Develop HR Plan

2009 Project Management Experts, LLC

16

2. Project Time Management


2.1 Define Activities
Planning Work Package(s) Activity 1: Activity 2: Activity 3: Furnishing Work Package(s)
Define Milestones as well

Design Work Package(s) Activity 1: Activity 2: Activity 3:

Construction Work Package(s) Activity 1: Activity 2: Activity 3: Closure Work Package(s) Activity 1: Activity 2: Activity 3:
17

Activity 1: Activity 2: Activity 3:


2009 Project Management Experts, LLC

2.

Project Time Management


Network Diagram
Development 2 3 A B 4 C

1 Start D

Testing

4 E 5

9 End 8

3 F

5 G Critical Path Analysis

2009 Project Management Experts, LLC

18

2. Project Time Management


2.5 Develop Schedule

Develop schedule/time management approach Schedule baseline will be created after the PM Plan is approved. Changes to the schedule baseline must be approved via change control. Approved schedule changes will be re-baselined along with cost and scope changes after the change has been approved via change control. How actual time will be captured and entered into the PMIS.
2009 Project Management Experts, LLC 19

2. Project Time Management


2.5 Develop Schedule

Information Captured in a Project Schedule Level of Effort Duration Resources Start and Finish Dates by Activity and Task Dependencies Milestones Deliverables Comments WBS numbers Etc.
2009 Project Management Experts, LLC

20

3. Project Human Resource Management


2.1 Define Activities 2.2 Sequence Activities

2.5 Develop Schedule

2.3 Estimate Activity Res.

2.4 Estimate Activity Durations

WBS Complete

3.1 Develop HR Plan

2009 Project Management Experts, LLC

21

3. Project Human Resource Management


3.1 Develop HR Plan Identify Potential Project Team and Create Project Organization Chart
Bill Jones Project Mgr

Shirley Long Development

Harry Testor Testing

Hugo Berardi QA

What are the advantages of developing an organization chart?

Joe Technical Programmer Karen Smith Programmer

2009 Project Management Experts, LLC

22

3. Project Human Resource Management


3.1 Develop HR Plan Create Responsibility Assignment Matrix
ACTIVITY Mary Analysis Design Develop Test M M M M Flo L,A L,A --Lou --L,A L,A PERSON Jim TM TM --George TM TM --Karen --TM TM Bill --TM TM

M Manager; L Technical Lead, A - Accountable; TM Team Member

2009 Project Management Experts, LLC

23

4. Project Cost Management

2.5 Develop Schedule

4.1 Estimate Costs

Draft/ Final Schedule

4.2 Determine Budget

2009 Project Management Experts, LLC

24

4. Project Cost Management


4.1 Estimate Costs Approximating monetary resources (1) Attach labor rates (2) Estimate non-labor costs (3) Finalize cost estimate
TASKS NON-LABOR COSTS LABOR COSTS TOTAL PLANNED COST

1. 2. 3. 4. 5.

Planning Design Construction Furnishings Closure TOTAL:


2009 Project Management Experts, LLC 25

4. Project Cost Management


Cost Based Metrics Terminology Planned Value (PV): Budgeted cost of the work scheduled Earned Value (EV): Budgeted amount in the work actually completed Actual Cost (AC): Total cost incurred in accomplishing work Estimate to Complete (ETC): Estimated remaining amount to complete the project Estimate at Completion (EAC): Estimated cost of the entire project including work performed and work to be performed. Budget at Completion (BAC): Total budgeted cost of the project.
2009 Project Management Experts, LLC 26

4. Project Cost Management

BAC AC

What Happened?

PV EV

To Implement an Earned Value System You Must: - Baseline - Capture Accurate Physical % Complete

Time
2009 Project Management Experts, LLC 27

4. Project Cost Management


Cost Based Metrics Formulas

Cost Variance (CV): EV AC Cost Performance Index (CPI): EV/AC Schedule Variance (SV): EV PV Schedule Performance Index (SPI): EV/PV EAC based on new estimate: New ETC + AC EAC based upon atypical variances: AC + BAC-EV EAC based in current spending patterns: BAC/CPI
2009 Project Management Experts, LLC 28

5. Project Quality Management


2.5 Develop Schedule

Draft/ Final Schedule 5.1 Plan Quality

8.1 Plan Risk Management 8.2 Identify Risks

2009 Project Management Experts, LLC

29

5. Project Quality Management


5.1 Plan Quality

Develop Quality Management Approach


Quality baseline will be created after the PM Plan is approved. Changes to the quality baseline must be approved via change control. Approved quality changes will be re-baselined along with schedule and scope changes after the change has been approved via change control. Actual quality will be captured and entered into the PMIS by The following quality related metrics will be captured: The following are not included in the quality of this project: . The following checklists will be used to assure the quality of this project:

2009 Project Management Experts, LLC

30

6. Project Procurement Management


2.5 Develop Schedule

Draft/ Final Schedule

8.1 Plan Risk Management 8.2 Identify Risks 6.1 Plan Procurements
31

2009 Project Management Experts, LLC

6. Project Procurement Management


6.1 Plan Procurements Determine Contract Type
Buyer Risk FP FPI CPAF T&M CPIF CPFF

Seller Risk
FP: FPI: Fixed price Fixed price plus incentive

CPAF: Cost plus award fee T&M: Time and materials CPIF: Cost plus incentive fee CPFF: Cost plus fixed price

2009 Project Management Experts, LLC

32

7. Project Communications Management


2.5 Develop Schedule

Draft/ Final Schedule

8.1 Plan Risk Management 8.2 Identify Risks 7.1 Plan Comm.

2009 Project Management Experts, LLC

33

7. Project Communications Management


7.2 Plan Communications Document Communication Requirements
? ho W
W ha t?

W hy ?

n he W

2009 Project Management Experts, LLC

34

7. Project Communications Management


7.2 Plan Communications Document Deliverable Distribution Requirements
Deliverable Detailed Design Doc. Change Requests Recipient Bill, Henry, Julie CCB, Bill

2009 Project Management Experts, LLC

35

8. Project Risk Management


2.5 Develop Schedule

Draft/ Final Schedule 8.1 Plan Risk Management 8.2 Identify Risks 8.3 Perform Qualitative Risk Analysis 8.4 Perform Quantitative Risk Analysis
2009 Project Management Experts, LLC

8.5 Plan Risk Responses


36

8. Project Risk Management


8.1 Plan Risk Management

Document risk management approach New risks will be added to the register throughout the project. All risks will be monitored throughout the project. Risk owners are responsible for executing the response plan. Risks will be discussed at all status meetings.
2009 Project Management Experts, LLC 37

8. Project Risk Management


8.2-8.5 Perform Risk Assessment & Create Risk Register Identify risks, perform qualitative and quantitative risk analysis, and develop response plan
Risk Register
Project Name: Project Manager:

Assessment ID 1 Risk Prob Impact Score Trigger Response Plan Contingency Owner

2009 Project Management Experts, LLC

38

Project Integration and Finalization of PM Plan


1. Update WBS with risk response activities 2. Document the project management life cycle 3. Document the integrated change control process 4. Document how the Project Management Information System (PMIS) will be used 5. Develop the final project schedule and highlight the critical path 6. Finalize the project management plan
2009 Project Management Experts, LLC 39

INVICTUS
William Ernest Henley (18491903)

Out of the night that covers me Black as the Pit from pole to pole, I thank whatever gods may be For my unconquerable soul In the fell clutch of circumstance I have not winced nor cried aloud Under the bludgeonings of chance My head is bloody, but unbowed Beyond this place of wrath and tears Looms but the Horror of the shade, And yet the menace of the years Finds, and shall find me unafraid It matters not how strait the gait, How charged with punishments the scroll, I am the master of my fate: I am the captain of my soul.

INVICTUS
William Ernest Henley (18491903)

Out of the night that covers me Black as the Pit from pole to pole, I thank whatever gods may be For my unconquerable soul In the fell clutch of circumstance I have not winced nor cried aloud Under the bludgeonings of chance My head is bloody, but unbowed Beyond this place of wrath and tears Looms but the Horror of the shade, And yet the menace of the years Finds, and shall find me unafraid It matters not how strait the gait, How charged with punishments the scroll, I am the master of my fate: I am the captain of my soul.

..and I will stop using duct tape

Reference Material

The Project Management Institutes (PMIs) A Guide to the Project Management Body of Knowledge (PMBOK) Version 4 was used as the primary reference for the material in this course.

2009 Project Management Experts, LLC

42

Questions

2009 Project Management Experts, LLC

43

Thank You

The SkillsThe KnowledgeThe Experience www.projectmanagementexperts.com

Joseph (Joe) D. Launi, PMP President & CEO jdlauni@projectmanagementexperts.com 305 Rangers Way SE Leesburg, VA 20175 Office: 703-777-1689 Mobile: 703-362-5774
2009 Project Management Experts, LLC 44

Das könnte Ihnen auch gefallen