Beruflich Dokumente
Kultur Dokumente
Agenda
Introduction Project/Product Analysis Develop Project Management Plan: 1. Project Scope Management/Scope Baseline 2. Project Schedule Management/Schedule Baseline 3. Project Human Resource Plan 4. Cost Management Plan/Cost Baseline 5. Quality Management Plan 6. Procurement Management Plan 7. Communications Management Plan 8. Risk Management Plan
2009 Project Management Experts, LLC 2
Agenda cont.
INTRODUCTION
Procurement
HR
Quality
Risk
e g n a Ch gt. M
Cost
Initiating Processes
Closing Processes
Executing Processes
Initiating
4.1 Develop Project Charter
Closing
4.6 Cost Project or Phase
5.1 Collect Req. 5.2 Define Scope 5.3 Create WBS 6.1 Define Activities 6.2 Sequence Act. 6.3 Est. Activ. Res. 6.4 Est. Activ. Dur. 6.5 Develop Sched 7.1 Estimate Costs 7.2 Determine Budget 8.1 Plan Quality 8.2 Perform Quality Assurance
Guide to the Project Management Body of Knowledge Fourth Edition 2009 Project Management Experts, LLC 7
Executing
9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.3 Distribute Information 10.4 Manage Stakeholder Expectations
Closing
11.1 Plan Risk Mgt. 11.2 Identify Risks 11.3 Perform Qualitative Risk Anal. 11.4 Perform Quantitative Risk Anal. 11.5 Plan Risk Resp. 12.1 Plan Procurements 12.2 Conduct Procurements
Guide to the Project Management Body of Knowledge Fourth Edition 2009 Project Management Experts, LLC
en t
Quality
Scope
. m m o C
2009 Project Management Experts, LLC
Co
st
9
HR
10
Develop Project Schedule and WBS via Schedule Oriented Project Planning (SOPP)
2.1 Define Activities 2.3 Est. Act. Res 2.2 Seq. Activities 2.5 Dev. Sched.
WBS Complete
Start
Draft/ Final Sch. 8.1 Plan Risk Mgt. 8.2 Id. Risks
WBS Complete
Develop PM Plan
Documenting what you know and dont know about the project and/or product. (Please give me a business card and I will email PACS to you)
13
WBS Complete
Start
14
Design 1.2
Construction 1.3
Furnishing 1.4
Closure 1.5
WBS Complete
16
Construction Work Package(s) Activity 1: Activity 2: Activity 3: Closure Work Package(s) Activity 1: Activity 2: Activity 3:
17
2.
1 Start D
Testing
4 E 5
9 End 8
3 F
18
Develop schedule/time management approach Schedule baseline will be created after the PM Plan is approved. Changes to the schedule baseline must be approved via change control. Approved schedule changes will be re-baselined along with cost and scope changes after the change has been approved via change control. How actual time will be captured and entered into the PMIS.
2009 Project Management Experts, LLC 19
Information Captured in a Project Schedule Level of Effort Duration Resources Start and Finish Dates by Activity and Task Dependencies Milestones Deliverables Comments WBS numbers Etc.
2009 Project Management Experts, LLC
20
WBS Complete
21
Hugo Berardi QA
22
23
24
1. 2. 3. 4. 5.
BAC AC
What Happened?
PV EV
To Implement an Earned Value System You Must: - Baseline - Capture Accurate Physical % Complete
Time
2009 Project Management Experts, LLC 27
Cost Variance (CV): EV AC Cost Performance Index (CPI): EV/AC Schedule Variance (SV): EV PV Schedule Performance Index (SPI): EV/PV EAC based on new estimate: New ETC + AC EAC based upon atypical variances: AC + BAC-EV EAC based in current spending patterns: BAC/CPI
2009 Project Management Experts, LLC 28
29
30
8.1 Plan Risk Management 8.2 Identify Risks 6.1 Plan Procurements
31
Seller Risk
FP: FPI: Fixed price Fixed price plus incentive
CPAF: Cost plus award fee T&M: Time and materials CPIF: Cost plus incentive fee CPFF: Cost plus fixed price
32
8.1 Plan Risk Management 8.2 Identify Risks 7.1 Plan Comm.
33
W hy ?
n he W
34
35
Draft/ Final Schedule 8.1 Plan Risk Management 8.2 Identify Risks 8.3 Perform Qualitative Risk Analysis 8.4 Perform Quantitative Risk Analysis
2009 Project Management Experts, LLC
Document risk management approach New risks will be added to the register throughout the project. All risks will be monitored throughout the project. Risk owners are responsible for executing the response plan. Risks will be discussed at all status meetings.
2009 Project Management Experts, LLC 37
Assessment ID 1 Risk Prob Impact Score Trigger Response Plan Contingency Owner
38
INVICTUS
William Ernest Henley (18491903)
Out of the night that covers me Black as the Pit from pole to pole, I thank whatever gods may be For my unconquerable soul In the fell clutch of circumstance I have not winced nor cried aloud Under the bludgeonings of chance My head is bloody, but unbowed Beyond this place of wrath and tears Looms but the Horror of the shade, And yet the menace of the years Finds, and shall find me unafraid It matters not how strait the gait, How charged with punishments the scroll, I am the master of my fate: I am the captain of my soul.
INVICTUS
William Ernest Henley (18491903)
Out of the night that covers me Black as the Pit from pole to pole, I thank whatever gods may be For my unconquerable soul In the fell clutch of circumstance I have not winced nor cried aloud Under the bludgeonings of chance My head is bloody, but unbowed Beyond this place of wrath and tears Looms but the Horror of the shade, And yet the menace of the years Finds, and shall find me unafraid It matters not how strait the gait, How charged with punishments the scroll, I am the master of my fate: I am the captain of my soul.
Reference Material
The Project Management Institutes (PMIs) A Guide to the Project Management Body of Knowledge (PMBOK) Version 4 was used as the primary reference for the material in this course.
42
Questions
43
Thank You
Joseph (Joe) D. Launi, PMP President & CEO jdlauni@projectmanagementexperts.com 305 Rangers Way SE Leesburg, VA 20175 Office: 703-777-1689 Mobile: 703-362-5774
2009 Project Management Experts, LLC 44