Beruflich Dokumente
Kultur Dokumente
1. Background
2. Introduction
5. Bottlenecks
6. Recommendation
7. Conclusion
Background:
ABT has been under discussion since 1994 when M/s ECC, an ADB consultant, first
supported it. GOI constituted a National Task Force in February 1995. It had ten
meetings till end 1998 where all the related issues were discussed. A draft notification
was prepared for issue by government. With effect from May 15, 1999 the jurisdiction
was vested in the CERC. Papers were sent to the Commission in June 1999 by the
MOP. The proceedings were held in the Commission from July 26 to 28, 1999. The ABT
order dated January 4, 2000 of the Commission departs significantly from the draft
notification as also from the prevailing tariff design.
Why ABT?
1. India plans to have an integrated National Grid. This will assist in meeting demand
with the least cost supply. Five Regional grids already exist. Some linkages between
Regions are also in place.
The five Regional grids work at vastly varying operational parameters today.
Frequency level is one such operational parameter. The target frequency
prescribed by the Indian Electricity Rules is 50 Hz.
Integrated grid operations require the normalization of frequency across all five
Regions. The alternative is to insulate each Regional Grid by Back to Back
HVDC links. This is an expensive option. Normalization of frequency requires
proactive load management by beneficiaries and dispatch discipline by
generators.
There is currently no formal system of financial incentives to promote grid
discipline.
The ABT provides this mechanism.
2. Chronic surpluses in the East and shortages in the South, have resulted in sustained
functioning of these grids at frequencies which are far beyond even the normal band,
liberally defined by the IEGC as frequency variation within 49.5 to 50.3 Hz
Continued functioning at non-standard frequency results in long-term damages to
both generation and end use equipment .This is a “hidden cost” which is borne
by the customer in the long term.
The ABT will induce corrections in the prevailing frequency to bring it within the
permissible band.
3. Frequent fluctuations in frequency caused by short-term variations in the demand
supply gap due to the tripping of load or outage of a generator or a transmission line
impose substantial costs on generators and consumers.
The ABT will address this problem by inducing grid discipline.
4. Economic efficiency dictates that least cost power should be dispatched in preference
to more costly power (merit order dispatch). This becomes difficult without a two part
tariff for all stations. States tend to compare the total cost of central generators with the
variable cost of their own stations, since for them the fixed costs of state level stations
are sunk costs. This results in making central generation appear artificially more
expensive than state level stations even though on variable cost basis the former may
be cheaper.
The two-part tariff of the ABT by making the payment of fixed cost a fixed liability
of the states converts it into a sunk cost thereby leveling the playing field
between central generators and state level plants.
5. Currently beneficiaries are not liable for payment of the fixed cost associated with the
share of capacity allocated to them. If a beneficiary decides not to draw any energy he
can escape payment of the fixed charge, which then gets paid by the person drawing
energy. This is unfair since it increases the cost of energy even for those beneficiaries
who may be drawing energy within their entitlements.
The two-part tariff of the ABT assures that each beneficiary will be liable for
payment of the fixed cost associated with its share of allocated generation
capacity.
6. Currently generators have a perverse financial incentive to go on generating even
when there may be no demand. This results in high frequency in the grid as is endemic
in the East
The ABT will discourage such behavior by pricing generation outside the
schedule in relation to the prevailing frequency.
What Is ABT?
• It is a performance-based tariff for the supply of electricity by generators owned
and controlled by the central government
• It is also a new system of scheduling and dispatch, which requires both
generators and beneficiaries to commit to day-ahead schedules.
• It is a system of rewards and penalties seeking to enforce day ahead pre-
committed schedules, though variations are permitted if notified One and one half
hours in advance.
• The order emphasises prompt payment of dues. Non-payment of prescribed
charges will be liable for appropriate action under sections 44 and 45 of the ERC
Act.
It has three parts:
- A fixed charge (FC) payable every month by each beneficiary to the generator for
making capacity available for use. The FC is not the same for each beneficiary. It varies
with the share of a beneficiary in a generators capacity. The FC, payable by each
beneficiary, will also vary with the level of availability achieved by a generator.
- In the case of thermal stations like those of NLC, where the fixed charge has not
already been defined separately by GOI notification, it will comprise interest on loan,
depreciation, O&M expenses, ROE, Income Tax and Interest on working capital.
- In the case of hydro stations it will be the residual cost after deducting the variable cost
calculated as being 90% of the lowest variable cost of thermal stations in a region.
- An energy charge (defined as per the prevailing operational cost norms) per kwh of
energy supplied as per a pre-committed schedule of supply drawn upon a daily basis.
- A charge for Unscheduled Interchange (UI charge) for the supply and consumption of
energy in variation from the pre-committed daily schedule. This charge varies inversely
with the system frequency prevailing at the time of supply/consumption. Hence it
reflects the marginal value of energy at the time of supply.
How is ABT different from normal proceedings to determine generation tariff?
1. The ABT proceeding has not attempted to consider most of the cost drivers like ROE,
Operational Costs, depreciation rate, composition of the Rate Base, capital structure
etc. Proceedings to redefine these norms are being held separately. Hence the ABT
proceedings have been concerned more with tariff design rather than definition of tariff
norms or determination of tariff levels.
2. It's incidence is a function not only of the behavior of a generator but also of the
behavior of a beneficiary. Disciplined beneficiaries and generators stand to gain.
Undisciplined beneficiaries and generators stand to lose.
Broad features of ABT design.
1. It implements the long held view that electricity tariffs should be two-part
comprising of a fixed charge and a separate energy charge.
2. It increases the target availability level at which generators will be able to recover
their fixed costs and ROE from 62.79% deemed PLF at present to 80% (85%
after one year) for all thermal stations, 85% for Hydro in the first year and 77%
(82% after one year) for NLC.
3. Misdeclaration of availability entails severe penalties.
4. It rationalizes the relationship between availability level and recovery of fixed
cost.
The draft notification provided for recovery of (annual fixed costs minus ROE) at
30% availability and recovery of ROE on pro-rata basis between 30% and 70%
availability. This order provides for payment of capacity charges between 0% and
target availability (as indicated in item 2 above) on pro-rata basis.
5. The draft notification had provided for payment of capacity charges for prolonged
outages. This order disallows such payments.
6. It delinks the earning of incentive from availability and links it instead to the actual
achievement of generation. Hence incentives will be earned by generators only
where there is a genuine demand for additional energy generation unlike the
prevailing situation, or the proposed draft received from the GOI, under which it is
earned purely because the generator is available.
7. Draft notification linked incentives to equity. This order preserves the status quo
of one paise per KWh per each 1% increase in PLF above target availability.
8. It increases the minimum performance criterion for the earning of an incentive
from 68.5% deemed PLF at present to 80% (85% after one year) for all thermal
stations, 85% for Hydro and 77% (82% after one year) for NLC.
9. It introduces severe financial penalties for grid indiscipline along with significant
rewards for behavior, which enforces grid discipline for both generators as well
as beneficiaries.
10. The order permits market pricing for the trading of surplus energy by
beneficiaries and generators.
11. The order urges the GOI to allocate the unallocated capacity a month in advance
so that beneficiaries know their exact share in capacity in advance and can take
steps to trade surplus power.
12. It will be implemented in stages from April 1,2000 starting from the South. The
new norm for incentive will however be applicable from this date for all central
stations. In the case of NPC, GOI to decide applicability of the order.
ABT concerns itself with the tariff structure for bulk power and is aimed at bringing about
more responsibility and accountability in power generation and consumption through a
scheme of incentives and disincentives. As per the notification, ABT is applicable to only
central generating stations having more than one SEB/State/Union Territory as its
beneficiary. Through this scheme, the CERC (Central Electricity Regulatory
Commission) looks forward to improve the quality of power and curtail the following
disruptive trends in power sector:
Capacity charges: Fixed charges are payable to the generating station, by the
intended beneficiaries of the generation facility (state governments of the region in most
cases). In the present tariff regime, capacity charges are payable against the (deemed)
PLF (Plant Load Factor) of the station. Full fixed charges are payable at achieving a
PLF of 68.49%, and incentive is payable for each unit of electricity generated above this
PLF. Under the ABT regime, fixed charges are payable against the availability(declared
capacity) of the generating facility. Fixed charges excluding ROE is payable on a
prorated basis for 0-30% availability. Prorated ROE is payable from 30-70% availability.
Incentive is payable to the generating station for availability beyond 70%. The incentive
is pegged at 0.4% of equity for each percent increase in availability in the 70-85%
range. Thereafter, the incentive falls to 0.3%. This decrease in incentive after 85% is
aimed at discouraging the generating facility from overloading the units at the cost of
maintenance and equipment life. ABT also contains provision for penalizing the
generating utility for over/under declaration of the availability. Fixed charges are payable
by the beneficiaries in proportion to the allocated capacity and does not depend on the
actual consumption.
Variable charges: Under the present tariff regime, there is no bifurcation between fixed
and variable charges. Both are bundled together and payable in proportion to the actual
energy drawn by the consumer. As we have seen already, under ABT fixed charges vary
with the allocated capacity and has nothing to do with actual energy consumed. In
contrast, variable charges are to be paid against the actual energy consumed. This
splitting is expected to promote power trading.
UI charges: In the present regime, there is no penalty for deviation from the
generating/drawl schedule by an entity. The ABT regime stipulates that UI (Unscheduled
Interchange) charges are payable under the following conditions:
The penalty imposed varies with the grid condition at the time of the indiscipline and the
magnitude increases with the severity of the frequency deviation caused.Apart from this
tariff structure, ABT provides for -
a) Implementation in a phased manner.
By ushering in the Availability Based Tariff, the CERC looks to bring forth the following
positive changes in the Indian power sector:
1. Enhanced grid discipline that will pave the way for higher quality power with
more reliability and availability. Grid disturbances and frequency fluctuations as
occur in our power system today are serious problems and would be considered
unacceptable in any advanced economy. The system of incentives and
disincentives allow for penalization of the party responsible for any disruption.
This will serve all participating bodies in a power grid to be self-disciplined
ensuring quality power supply for all consumers.
4. Introduce and encourage MOD (Merit Order Dispatch) in the Indian power
scene. In the current scenario, the generators tend to produce as much as they
can irrespective of the demand side of the power equation. Under ABT,
generators will need to ramp up and ramp down generation based on the
declared generation schedule given by the RLDC (Regional Load Dispatch
Center). Thus when the plant (or a cluster of generating stations owned by a
single entity) will need to use the power generation combination that will incur the
least cost for all loads below the maximum load. This exactly is the formulation of
the MOD, which is an optimization problem. MOD is used by modern power
plants to save millions of dollars in generating cost every year. Thus introduction
of MOD is expected to benefit the power industry greatly.
Concerns on ABT:
f) Another interesting concern is the CERC diktat that any revision in schedule
by the RLDC will deemed to be effective irrespective of the successful
communication of the same to concerned parties. As has already been pointed
out, most of the concerned parties being PSUs lagging on the technology front
are yet to have fool-proof or redundant communication infrastructure in place.
Thus rescheduling may fail to reach concerned parties in a timely manner and if
somebody is caught unawares on the wrong side of the UI charges, they are not
going to be pleased about ABT.
Capital cost of the generating facility being redeemable only against declared availability
and successful demonstration of the same will require the generators to really have a
tight rein on their complete infrastructure. All the generators will now need to set a target
of 85% availability to ensure that complete capital costs, ROE and incentives are
available to them. And the provision for surprise audit to demonstrate the availability will
need to them to monitor all the equipments and ensure adequate and timely
maintenance of their overall infrastructure. This will usher a modern outlook and calls for
the latest and best technology in performance calculations, efficiency and IT.
Variable costs and UI charges will require the generators to closely match their output
with the demand curve and the ability to take corrective actions in the shortest possible
time. ABT also calls for elaborate computation of the payable tariffs and close
monitoring of the cost of production. Ushering in of MOD is going to be a positive
development for all generators enabling them to make huge savings on cost. All these
factors will involve a good amount of technology investment but will set the right
background for an efficient power structure and the right launching pad for a market
oriented approach. This will naturally result in higher reliability and increased customer
confidence giving the right impetus for more industrialization and enhancing our
development process.
At the consumption end also there is going to be the need to forecast demands as
accurately as is possible and to follow the strictest possible grid discipline. This again
will prove vastly beneficial to the power industry as a whole.
Impact of ABT on different Players
Impact on generation utilities:
Of the three, power generation utilities will need to adapt most to the ABT regime. This
because most of the changes specified in the ABT, such as computation of capacity
charges, assessment of plant availability, revised tariff structure, UI (unscheduled
interchange) charges etc. will be of direct significance to power generation companies.
Initially only those power stations that cater to more than one SEB (state electricity
boards) are expected to abide by ABT. However, since the objective of ABT is to usher
in more responsibility and accountability and thereby improving the quality power, it is
quite likely that all generation companies would soon need to abide by ABT or similar
acts. Such abidance and discipline will only increase as ABT slowly paves the way for a
completely deregulated and market driven energy economy.
Under ABT, there is a paradigm shift for generating stations from maximum power to
maximum reliability. Pre-ABT generating stations used to generate to their capacity
irrespective of load demand in the network. Under ABT regime, the loads requirements
are given in 15-minute blocks and the generating station needs to closely follow this
demand curve so that frequency deviation on either side of 50 Hz is a minimum. Some
of the technology requirements thrown up by this paradigm shift are:
c) Production following demand will mean that the plant will not be operating
at peak capacity at all times. This will require for an optimization problem
between different units of a power plant since the cost of generation,
ramping, start up and shut down associated with each unit will vary. This is
called the merit order dispatch (MOD) problem. MOD solutions can
potentially provide huge savings for a power plant and ABT will require
most plants to accommodate MOD to ensure economic operation.
f) The economy of power generation is vastly altered under the ABT regime.
Earlier capacity charges were paid against PLF (plant load factor) and
power charges against the power sent out. Under ABT capacity charges
are payable against declared (deemed) availability and a UI (unscheduled
interchange) component is payable as part of the power charges for any
grid indiscipline. UI charges are a system of incentives and disincentives
and depend on the declared demand, declared availability, deviation from
forecasts, grid conditions etc. As a result of this new structure, the
parameters influencing the monetary returns from power generation are
much more complex. Power generation stations would do well to have a
full-fledged tariff calculation system that can do a detailed computation
and optimization of power generation from the revenue angle. This kind of
digitized linking between power generation and revenue will prove greatly
beneficial during the journey to a full-fledged market system.
Grid operator typically manages the power transmission infra-structure. This will
correspond to the role of the ISO (independent system operator) in more evolved power
markets. ISO’s are typically no-profit organizations formed by a consortium of all
interested parties in a specific geographic area for a power market. Their goal is to
ensure smooth operation of the grid and to ensure adequate load-supply balance in the
grid. In India this role of power transmission and coordination is handled by PGCL
(Power Grid Corporation of India Limited) which incidentally is the single largest power
transmission utility in the world. PGCL is responsible for operating the national and
regional power grids as well as managing the RLDCs (Regional Load Dispatch
Centres). Under ABT regime, the role of balancing the demand and generation side of
power is vested with the RLDCs. As such some of the system requirements at the grid
operator for the successful implementation of ABT will be:
b) Better forecasting systems: Presently the RLDCs are vested with the role
of coordination between consumers and generators regarding the demand
and generation schedule for each day split into 15-minute intervals. Since
UI charges are payable by the generator or consumer, it may seem that
the onus of forecasting more lies with these parties (especially
consumers). However to ensure that the spirit and objective of ABT is not
thwarted, it would indeed be important for the PGCL to predict as
accurately as is possible the demand in different consuming regions.
Variations as a result of climate, festivals and other events also need to be
taken into consideration. Only then can they ensure that enough
bandwidth is available across different routes to carry adequate power to
each region.
c) Better communication and information systems: It is the responsibility of
the RLDC to communicate the 15 minute generation and consumption
schedule to each party. It is also the role of the RLDC to convey any
unforeseen change in such a schedule. ABT envisages that the UI
charges will get suspended for specific periods in the event of an
unforeseen disruption in the grid for which responsibility cannot be pinned
down on any particular generator or consumer. It is very important that the
disruption and revised schedule is communicated in a timely fashion to all
the concerned partied failing which the credibility of the whole system may
soon get pulled into the question. This aspect requires the grid operator to
have excellent communication and information infrastructure in place.
Impact on consumers:
As already mentioned, the major thrust of ABT is to improve the reliability and quality of
the power grid. Primary beneficiary of such an enhanced system would be the
consumers. Consumers in the ABT regime consist of SEBs (State Electricity Boards)
and other major distribution companies. Most important benefit they can realize from an
improved power grid is to pass on these benefits of quality and reliability to their
consumers in turn, who are typically the end user links in the T&D (transmission and
distribution) chain. While providing these benefits, ABT also confers some responsibility
on the consumers which will require them to fine-tune their process. Some of the
requirements ABT will make on consumers are:
a) Enhanced load forecasting system: Under ABT regime, each SEB will
need to provide their load requirements in ninety six 15-minute intervals
for each day. The consumer is expected to stick to this schedule in the
absence of external grid disturbances and corresponding revisions by the
RLDC. Failure to comply with the schedule will attract penalty in the form
of UI charges. Thus it becomes very critical for the SEBs to have accurate
short-term load forecasting systems in place. Once the ABT regime moves
to further deregulation, long term forecasting will also become critical
since only on that basis can the SEBs enter into commercial agreements
with the generating utilities.
The primary objectives which have to be fulfilled by the new system have to be looked
at. The most important objectives are:
To bring in more generation in the system and improve the grid frequency.
Currently, Maharashtra is facing acute power shortage with peak demand
growing at a very high rate. During peak summer months, even Mumbai licensee
faced acute power shortage necessitating initiation of load regulation measures.
While the future position of demand-supply will depend on load growth and
capacity additions, tapping of surplus power available today, if any, would assist
in improvement of grid frequency and quality of supply.
Cost of power in the Maharashtra system as a whole should not increase. Any
increase in the cost has to be borne by the end consumer and hence, any new
mechanism that is implemented should not increase the cost of the system as a
whole. Thus, while introducing intra-state ABT with the objective of tapping more
generation, we should bear in mind that the extra generation does not come at a
very high cost. At the same time, while extending ABT to the state participants,
there should not be any significant financial loss to the Distribution Licensees. In
the recent past, MSEDCL has incurred significant cost on account of UI. While
designing the new system, the intra- state UI mechanism should be such that the
utilities do not incur significant UI costs on account of inter-state UI mechanism.
Quality of supply and the efficiency of various entities should improve .One of the
most important objectives behind reforms in the electricity sector in the State will
have to be improvement in efficiency of the various entities and improvement in
the quality of supply. The generating stations should dispatched in most efficient
manner taking into account economy of operations and merit order dispatch
principles for the power system as a whole irrespective of the ownership. Any
new system should promote/incentivize the improvement in efficiency and quality
of supply and exchange of power amongst market participants. Tapping of
excess generation will improve the frequency profile of the system and thus will
lead to improvement in quality of supply.
The new system should promote the development of market, i.e., encourage
participation by many buyers and sellers. Another objective behind the reform
process has been the development of a market in the long term. Therefore, any
new system should be in line with the overall objective of market development.
The new system should offer opportunities to many buyers and sellers to take
part in the market and maximize economic gains.
Fair and equitable sharing of risks amongst various State participants The
proposed arrangement should not result in in-equitable allocation of risks and
costs amongst the State participants. The proposed mechanism should take into
consideration existing contractual arrangements and agreed risk sharing
arrangements amongst the State participants. The risk and returns should be
commensurate with each other.
System Operations and Stability SLDC has the responsibility to maintain system
security and stability and for that purpose SLDC can exercise control on the
system participants. Before implementing any new mechanism in the State, it is
extremely important to examine the impact and implications of the new
mechanism on critical system parameters and to ensure that the stability and
security of the system is not jeopardized in the new mechanism. The system
parameters which are of critical importance are frequency of the grid, line
loading, voltage profile, transformer loading etc.
GOVERNANCE STRUCTURE
Specific areas covered under this are (a) Objective of Governance under state level
ABT mechanism (b) Constitution of Maharashtra State Power Committee (c) Functions
of Maharashtra State Power Committee (d) Powers of Maharashtra State Power
Committee
Intra-state ABT shall be applicable on suppliers and drawers involved in the State Grid,
who are required to give daily schedules to State Load Dispatch Center (SLDC), and
have agreed to pay as per ABT for any deviations from schedule.
All generating station except the following shall be covered by intra-state ABT, if:-
(i) Covered by inter-state ABT,
(ii) Nuclear, Wind and Solar Power Stations,
(iii) Hydro Stations,
(iv) Power Plants of capacity below 10 MW and
(v) CPPs & Co-Generating Stations.
On account of generation from hydro, wind & solar power stations being dependent on
nature and their generation cannot be predicted with certainty, these power stations
have to be excluded from Intra-State ABT. Similarly Nuclear Power Stations because of
their nature of operating in base load, cannot adjust their generation to load demand
and hence they have also been excluded. Renewable sources such as biomass, solid
waste, etc. are controllable and a schedule can be generated day-ahead. However,
given the many benefits for the generation from renewables, and also in view of the
relatively very small capacity of units, biomass and other renewables have also to be
exempted from ABT. As UI rate applies on deviation of actual generation from the
scheduled generation, generating station of capacity up to 10 MW shall not give daily
schedule and as such they cannot be covered by ABT.
(b) Licensee:
(i) it effects drawl from generating stations & licensees governed by interstate and/or
intra-state ABT and
(ii) Its total drawl during any time block exceeds its drawal from Non-ABT sources i.e.
generating, trading licensee & distribution licensees not governed by interstate or intra-
state ABT .Provided that the intra-state ABT shall be applicable on bilateral exchanges
only, if for such exchanges, scheduling & payment as per ABT for deviations from
schedule has been agreed.
Basic infra structure and other requirements for intra state ABT
a) Metering:
The Forum of Indian Regulators (FOR) sub-committee has rightly pointed out that for
implementation of Intra-State ABT, the activity of installation of special energy meters on
the periphery of all entities would be the critical part. The meters should be capable of
recording the following parameters in a 15 minute block.
• Cumulative active energy
• Cumulative apparent energy (KVAhr)
• Cumulative reactive energy under high voltage (> 103 %)
• Cumulative reactive energy under low voltage (< 97 %)
• Active energy
• Average frequency
• Date & Time
• Average power factor
The interface points such as interface of IPP’s with the grid, CPP’s / Co generators with
the grid, open access consumers with the grid, CGS ( NLC1) with the grid etc., will have
to be metered. by the SEB within a certain time frame .
b) Communication facility:
In ABT mechanism, the metering data should be transferred from Special Energy
Meters to ALDC/SLDC on a real time basis. Hence adequate & reliable communication
facilities should be established by TNEB/STU. In order to provide load forecast to the
SLDC on a daily basis, communication facility from the ABT compliant meters at the
interface points to the ALDC of the distribution licensee should also be established
along with SLDC.
c) Tariff:
The basic requirement for implementation of ABT is a three-part tariff comprising of fixed
charges, variable charges and UI charges. As discussed earlier, the fixed charge would
be linked to availability and variable charges to the scheduled energy. The UI charges
shall be applicable for the deviations from the schedules. A three-part tariff for the
central generating stations is already in force under the inter-state ABT.
Regarding the third part of the tariff i.e. UI charges, the UI rate determined by the CERC
is already in force for inter-state ABT and it has been recommended by various experts
including the Forum of Indian Regulators (FOIR) sub-committee to adopt the same UI
rate for intra-state ABT also. Hence it is appropriate to adopt the same UI rate as
determined by the CERC for intra-state transactions also.
d) Setting up of Area Load Dispatch Center (ALDC):
Each Distribution Licensee should have an Area Load Dispatch Centre to monitor and
control the drawl of power within their jurisdiction. Even though some SEB still remains
as a vertically integrated utility and a deemed Licensee for the present, they have to
design the system for intrastate ABT to suit the future scenario with multiple Licensees.
This involves additional investments and may have to be agreed as a pass through in
the future tariff.
e) Up-gradation of SLDC:
In order to handle the increased volume of data under Intra-state ABT and also to
perform the functions of monitoring and energy accounting, the state load dispatch
centre needs to be up-graded suitably by providing necessary software, hardware,
human resources and other infrastructure. This again involves additional investments
and also have to be agreed as a pass through in the future tariff
TNEB have reported that presently in the SLDC scheme 34 numbers of generating
stations and 49 numbers of grid stations have been covered with state-of-art
communication and SCADA system. These are used for ABT based grid operation in the
integrated operation of the southern grid. TNEB has also reported that additionally 8
numbers generating stations and 5 numbers grid stations are proposed to be linked with
SLDC/SSLDC during the current year. All the new substations to be commissioned are
also being provided with SCADA and proposed to be linked with SLDC. It has initiated
action to provide ABT compliance meters in its generating stations and in grid feeders
during the current year. It has also been reported that TNEB have already provided the
state of art DCC-SCADA system for Chennai metro area covering 95 Substations and
upgrade the existing DCC to accommodate additional 200 substations along with
distribution management system (DMS) facility during the current year. TNEB is
understood to have proposed to provide SCADA and communication facility to all
substations, connecting them with circle level area control centre (ACC), which in turn,
will facilitate open access, energy accounting and auditing. TNEB at present is a
vertically integrated utility. With the present unbundled structure, the scope of
implementing the ABT mechanism in Tamil Nadu may appear not to yield any major
benefits to TNEB / consumers. In fact, it has also been pointed out during the
discussions in a FOR Meeting on 10.11.2006 that unbundling is a necessary precedent
condition for introduction of intra State ABT. However, even under an integrated set up,
TNEB have to necessarily move towards establishment of profit centre concepts and
under such a scenario, self discipline, proper accounting and optimum use of its energy
resources will be automatic with intrastate ABT. In fact, this cannot be postponed
indefinitely and we should not be lagging behind when the situation warrants such
arrangements to be in place at the appropriate time. The intention of the Commission is
that the TNEB should immediately start establishing the left over infra structure and
other facilities with a time frame and to the extent possible.
Taking into consideration, the necessity for introducing intra state ABT, the
advantageous, the present status of required infra structure, emerging scenarios , along
with the additional expenditure TNEB have to spend to establish the requirements,
which, in turn will have to be allowed as a pass through in the future tariff, Commission
have decided to invite the public opinion through this consultative paper, conduct a
public hearing and issue a suo motu proceedings to TNEB to initiate a time bound
program for establishing the infra structure and other requirements for introducing intra
State ABT at an appropriate period on a later date after these works are completed.
ABT to deregulated Power Market
Self-regulating power market
Going by the commonly accepted definition of market, a power market would indicate
an entity (or arrangement) where power generators will offer their distribution capacity
or actual energy and interested consumers (such as distribution companies) would
purchase them. The energy charges payable to the generators will depend on the
demand-supply characteristics of the market. By the term “self-regulating” we imply that
no external influence (such as directives from a regulating agency) shall be responsible
for the power tariffs in the market and it will be determined purely on the demand-supply
ratio. This is in contrast to the current scene in Indian (and most other) power sectors
where government regulatory agencies are responsible for setting the rules of the game
and the applicable tariffs. In fact, presently most of the generating companies and
distribution companies are public sector units controlled by the government thereby
curtailing the notion of a market system considerably.
However, the economics of a general market cannot be directly imported to the power
sector due to the peculiarities of the commodity involved viz. electricity. For one,
electricity cannot be stored for consumption and need to be generated synchronously
with consumption and then transferred over conducting medium. This means that the
production system needs to be ramped up and down closely in pursuit of the market
demand. The implication is that your generation capacity needs to exceed the
instantaneous maximum demand and your transmission bandwidth also needs to
support the same. This “real time” nature makes demand forecasting a messy job as far
electricity is concerned. For example, you may be able to predict that X tons of wheat is
required for the next month based on past consumption data and other relevant
information. This prediction will be more or less accurate if you have got your statistics
right. But it is not possible to predict exactly how many tons of wheat will be consumed
on a particular day at a particular time. And in the case of wheat, it is not necessary to
do so. But in a typical power market, you are required to predict the demand for each
five minute interval (at least).
Another differentiating fact for electricity is that it is not a stand alone commodity. Along
with electric power other resources also need to be supplied such as reactive power,
stand-by (spinning and non-spinning reserves) etc. which are commonly termed as
ancillary services. In general practice terms for ancillary services are negotiated
separately and in many instances actual power and ancillary services may be provided
by different entities. This further complicates the process of modeling the electricity
market.
Due to the points enumerated above a completely free power market is yet to take
shape (or even successfully conceived). What has been implemented in several
advanced economies is a restricted power market. The restriction is implemented by
means of a central coordinating agency (called an Independent System Operator – ISO)
who regulates the market and ensures that the social objectives are met within the
parameters of the system. Thus ensuring adequate and reliable supply of electricity to
all consumers, preventing undue manipulation of the market by participating entities for
profiteering etc. are the objectives of this entity. To facilitate the meeting of these
objectives, in many cases all the transmission facilities are managed by this
coordinating entity while it owns no generation or distribution mechanism. Selling and
buying of power happens through bilateral agreements (between a generator-consumer
pair) as well as in a power market. In may instances, the power market is run by the ISO
while it may also be run by a separate independent agency. The ISO typically operates
as a no-profit organization and is run by representatives from a regulating agency. All
the stakeholders (such as generators and consumers) are also allowed representation
in the ISO though mostly without decision making authority and only as recommending
participants.
Thus it is quite easy to see that power markets are typically “engineered” markets and
not “free” markets. Why then is it necessary to have such a market? Unfortunately, there
is no unambiguous answer. Given the physics of power, perhaps the ideal system is a
single generation-transmission-distribution-billing-collection agency. This unification of
roles enables a lot of convenience in terms of managing unit commitment, merit order
dispatch, congestion management, ancillary services etc. The problem is similar to one
of the most debated issues faced by society viz. what is the best form of government?
At a purely conceptual level it is quite tempting to accept a benevolent dictatorship or a
Platonic educated-oligarchy as the best form. Why then is democracy preferred? For
the simple reason that the conceptual level seldom translates into practice. A centralized
system consisting chiefly of large generating capacities is posing environmental as well
as reliability issues. And a monopoly nature inherent in such a
mechanism does not turn out to be fair to all participants and stakeholders. The
availability and economics of such a vital commodity as power tend to be dictated by
political or other nefarious considerations. And at a much more fundamental level, it is
sometimes quite impossible for a central agency (especially a PSU with its inherent
handicaps) to run a vast and complicated power system efficiently and transparently.
Decentralization, thus, needs to be ushered in and thence the market approach.
Most power markets operate along three lines: long term (year ahead, month ahead,
week ahead), mid term (day ahead, hour ahead) and short term (intra hour market).
Participants in the market such as generators and distributors typically take part in all
three markets to ensure purchase/ selling of their power in the most economical fashion.
There is a non-profit ISO which coordinates the power system and ensures reliability by
responsibly managing the transmission system. The power market may or may not be
run by this ISO. Of the three, short term power market is the most significant. This
because long and mid term power purchase quite often happens through bilateral
agreements. In such cases the price and other terms are part of a private contract and
may not be made public. Long term contracts may also be made available by the ISO in
a transparent manner paving way for market dynamics. The short term arrangements
are typically handled in a pure market fashion. Ancillary services are typically bought
and arranged by the ISO which then charges all the participants in an equitable fashion
for the same.
Power price is typically set in the market through supply side bids. This means that each
power supplier (generator) will submit bids into the market indicating their prices and
ramp rates. (For example, a generator may quote Rs.1300/- per MWh at an output rate
less than 200MW, Rs.1600/- per MWh when the output is between 200MW and 420MW
and Rs.2500/- when the generation capacity required is between 420MW and 500MW).
Such bids will reflect the operating costs for the generator associated with different
units. Demand side is typically not considered in determining the price of power in most
markets. Market price of power is typically considered as the price paid against the
highest successful bid. How each of the suppliers are paid for power supplied varies
from market to market: in some, all will be paid the same price (which would be the
market clearing price denoted above). In other markets, there may exist a pay-as-bid
mechanism where different suppliers may get paid differently. Sometimes the long term
and mid term power prices are set against the short term (or real time power price).
Ancillary services (especially spinning and non-spinning reserves) may be priced
against the real time prices.
Irrespective of the pricing model, it follows that price is normally set depending on
applicable regulations of the market. And such regulations invariable allow the players
to exploit loopholes gain undue benefit from the market. For example, a supplier of
ancillary services has a lot of incentive to “fix” the real time price since he is going to get
paid on the basis of that. Again where the real-time prices are fixed based on MCP
(Market Clearing Price), suppliers can manipulate availability or demand to unethically
bloat the MCP (this has actually happened in several markets). Where bilateral contract
prices are also dependent on the real-time price, this incentive goes up much more. In
pay-as-bid systems also such manipulations are possible by participants to gain undue
advantage. In fact, in any of the four common auction methods (ascending bid auction,
descending bid auction, highest price sealed price auction, Vickrey auction), given the
restricted nature of power market, it is possible to manipulate the auction for participants
to gain undue advantage. It is the crucial responsibility of the market coordinator to fine
tune the market structure to discourage users from such manipulations. How successful
such an attempt is what determines how efficient and beneficial the market is. And in
most cases where power markets have failed, it was caused due to some unfair conduct
by the participants exploiting vagueness or loopholes in the market regulations.
There are other implications to a power market as well. Along with power, trade will be
encouraged in other commodities as well. One of the important components here can
be emission rights. Environmental norms are becoming more stringent every day and
power generation (especially in fossil-fired power plants) is a pollution-intensive
exercise. Under such international contracts as the Kyoto protocol, capacity for different
emissions can be traded. For example an entity (an organization, body or even a nation)
that has the rights to emit 1000 tons of NOx per year can trade part or whole of this
capacity to another entity for monetary or other considerations. Such trades are already
underway in European markets. Another important result of a power market is that end
customer expectation regarding quality and availability will go up than when it is
managed by public sector organizations. This customer expectation will also prove
beneficial to the industry by compelling participants to set higher benchmarks for
themselves.
Successive milestones
Next step is to provide adequate economic incentives for different players to participate
in power trading. Again such measures are already allowed for in the ABT and
Electricity act. This includes incentives captive generators as well as removing a lot of
regulatory hurdles for private and cooperative bodies in setting up power generation
facilities. Once these steps are covered, we can have an atmosphere conducive for a
self-regulating power market.
From here, the crucial step is setting up the market itself. As our earlier discussion
indicates, there is no perfect model available to import even when we do not take into
account factors unique to India. A completely successful and satisfactory power market
is yet to emerge anywhere across the world. So it will more be a question of learning
from other’s mistakes. We will also need to adapt their good practices. The role of a
central coordinating agency will be crucial in ensuring smooth operation of the market
without failing any of the social and national objectives. One possibility is for the
government to disinvest the generation capacity of PSUs and then for the PTC (Power
Trading Corporation of India) with its Load Dispatch Centers to act as the central
coordinating agency. This is however likely to raise a lot of opposition, not all of which
will be invalid.
Bottlenecks
Thus after providing the conducive ambience for a power market, setting up of the
actual market is going to be a major challenge. This challenge will first involve how to
set the rules of the game and how to define the roles and responsibilities for the nodal
coordinating agency. The onus is then on this agency to ensure the smooth operation of
the market balancing the interests of different stakeholders. This agency will then also
need to appropriately tone down its influence so that the market becomes more and
more self-regulatory. The government (of India) will however need to divest all its
generation facilities before setting up such a body to ensure that there is no conflict of
interest in operating the market. If this is not done conclusively and transparently, it will
act as a major deterrent for many players in entering the market. As already mentioned
such a disinvestment itself is going to be a major concern with opposition to be
anticipated from multiple quarters. Compared to others, divesting nuclear power plants
may cause additional worries taking into account environmental as well proliferation
problems.
Another problem that needs to be solved is the disparity between different types of
generators that take part in the market. ABT (as the first step in this direction) itself is
faced with this problem and is not able to address it completely satisfactory. For a
market scenario, in the absence of external regulations such disparities can seriously
hamper the success of the market since different generation facilities (like hydro,
thermal, nuclear, non-polluting) will be bound by vastly different physical constraints in
participating in the market. Many of the other issues enumerated by ABT (such as
adequate metering infrastructure) will also manifest themselves as serious hurdles in
the progress to a self-regulating market.
Conclusion
Thus we conclude that the path from ABT to a self-regulating power market is an
arduous one. What is called for is a lot of perseverance and professionalism. It is quite
easy to run into a crisis situation in this journey, as has quite often happened in other
markets. So it is very critical for the regulatory authorities to have a clear vision of the
goal and the will to see the path to its logical conclusion. If technology (say, studies on
super conductivity making it possible to bring down transmission losses to negligible
levels in real life situations) emerges to seriously alter the physics of power generation-
transmission-distribution, such a journey will be fraught with interesting consequences.
Bottlenecks
Issues 1: Applicability of ABT to Nuclear Stations:
A. A question has arisen regarding the applicability of ABT to nuclear stations
though owned by the Central Government. The basis for the query is the
provision contained in section 49 of the ERC Act which makes the
provisions of this Act ineffective in so far as they are inconsistent with the
Atomic Energy Act, 1962. Thus though the commission has jurisdiction to
regulate the tariff of centrally owned generating companies, since the
Atomic Energy Act 1962 in section 22(b) states that the Central
government shall have the authority of fix rates for and regulate supply of
electricity from atomic power stations the Commission faces a constraint.
This constraint did not exist when it was the central government that was
seized of the matter.
B. During the NTF proceeding the general consensus was to include the
nuclear stations under the regime of ABT. However, in view of the special
constraints involved in operation of nuclear stations, it was considered
necessary to discuss the with NPC before taking a final division.
Subsequently after discussion with NPC it was decided to include nuclear
stations under the regime of availability based tariff.
C. In the proceedings before us, both on the grid code and on the ABT, NPC
took an active part and filed replies to the proposals. The jurisdiction of
the commission has not been challenged in these proceedings. We have
also made special provisions for nuclear stations in our order on the grid
code. Under the ABT regime, NPC has expressed willingness to submit
its stations to the regime subject to certain special considerations in view
of the peculiar nature of their operations. We are also of the view that in
the interest of better grid discipline and merit order dispatch nuclear
stations should also be included in the system. In fact, even other entities
like DVC and BBMB which do not fall within our jurisdiction though they
are engaged in inter state transmission, would like to be covered by the
ABT system. The practical solution for this problem lies in making use of
the alternative under section 22(b) of the Atomic Energy Act, 1962 which
contemplates of the central government authorizing any authority
established by the Government to do rate fixation and regulation of supply
of supply of atomic stations. As such, it is only required of the Central
government through the department of Atomic Energy to authorize the
commission in this regard. We have already suggested to the Nuclear
Power Corporation to initiate appropriate steps for the Government to
authorize the Commission.
D. We have also pointed out this inadequacy in the present legislation to
GOI, under Section 60 of the ERC Act of 1998 vide letter No. L-7/7(1)/99-
CERC dated September 21, 1999 which is pending with the Government.
In view of the above, the provisions of this order shall apply to atomic
stations subject to the government’s response to these references.
We have considered these objections. As regards capacity charges for hydro stations,
we consider that the present arrangement should be continued in the interest of
simplicity of the system of charging. Regarding free hydro power to the home state the
existing arrangements based on agreement can not be wished away and the free
element becomes part of the cost to be taken into account for tariff. Regarding
unallocated power, the arrangement proposed in the draft notification is satisfactory. As
regards surrendering of shares we are in agreement with the suggestion of NTPC.
However, this matter relates to the government for its decision for reallocation of shares.
We have already covered these issues, regarding unallocated shares in this order.
C. The third element viz. the UI charge, is proposed to be settled through
a regional pool account to be operated by the member secretary of REB.
Detailed procedure in this regard was proposed to be laid down by the
central electricity authority from time to time. From the correspondence on
files, it is found that CEA has proposed a broad outline of procedure for
operation of the regional pool account by which:
a) The billing for UI payable shall be done by REB to
various parties;
b) The parties shall pay the UI charges within 15 days of
billing;
c) Can delay in payment shall attract interest @ 2% per
month;
d) Any money received on account of UI to be distributed to
the claimants pro-rata to their claim; and
e) Any undue delay in payment will attract the extreme step
of regulating the supply.
D. The above proposed system of operation of pool account does not appear
to be satisfactory. The UI charge is not in the nature of penalty but is part
of the tariff as contemplated in the notification. As tariff, it constitutes the
income/expenditure of the utilities concerned. As such it will have to be
included in the revenue accounts of the utilities in pursuance of the
accrual system of accounting which is a statutory requirement and can not
be kept unaccounted outside its books. With the possibility of all the
utilities ultimately becoming corporate bodies, this is a necessary
accounting requirement. Any outstanding UI charges at the end of each
year has to be reflected in the balance sheet of the utilities concerned as
asset or liability as the case may be.
The pool mechanism was contemplated perhaps on account of the
difficulty in relating the receipt and payment on one to one basis, between
the receiver and the giver of the UI. Though the solution suggested
appears to be simplistic it goes against the principles of accrual
accounting particularly when it is recognized as part of the tariff to be
received or paid. Further a one-to-one identification cannot be totally
avoided. As more and more utilities join the pool, the accounting task
would be stupendous. ON a sample basis the UI calculated for Eastern
Region for a typical day in March, 1999 worked out to Rs. 99.44 lakhs.
Thus the amount 8involved is substantial, unlike a penalty element, alone
which may be small.
Any party, who is to receive a tariff has to raise a bill for the tariff. If the bill
for UI is raised by the REB the question is whether it would constitute the
income of REB? Similarly do any outstanding charges have to be shown
as the assets of REB? This however, is not the correct position. REB is
only carrying out the function of a clearing house. In that case it would not
appear as asset or liability of anyone REB should not take up the financial
responsibility for managing the funds of the utilities unless it is specifically
agreed to by all parties concerned. In this connection, NTPC has
suggested that since it would be the net receiver of UI it may be adjusted
in the energy bills of NTPC instead of merging he same in the pool
account. Thus the proposed arrangement does not have the concurrence
of NTPC.
By resorting to the system of pool account, the task of identifying the UI
charges on a one-to-one basis is only postponed but not finally resolved.
Under the proposed arrangement any portion of UI as and when received
is to be distributed pro rata to the outstanding of all parties. Alternatively
from the records, it should be possible to link up over drawals and under
drawals on a regular basis. This can be adjusted on every 48 hour basis
from control room readings. In this way composite scheme can be
evolved by which at the end of the month the balance portion for
distribution of the UI could be finalized by the REB. The arrangement has
to be organized by the RLD in consultation with REB. The net UI charges
after these regular adjustments should be distributed, billed and paid at
the end of each month. This accounting system should be worked out by
CTU in consultation with all the beneficiaries and could be put in position
in the next three months time so that when the ABT is implemented the
method of distribution is also finalized. Based on the distribution of UI at
the end of each month as advised by REB bills can be raised by the
utilities including the generators against each party so that any
outstanding can be pursued by the respective parties as a commercial
debt rather than left to the REB to sort out. The utility concerned can also
initiate steps for recovering the dues as considered appropriate. This
would also enable reflection of a true and fair view of the
income/expenditure and assets and liabilities of the various utilities. This
will also enable the generators to justify their sales based on bills duty
raised. This system may also obviate any difficulty on account of sales tax
or other levies which may be payable on tariffs of generating companies.
The setting out of a fool proof system was assigned by us to the CTU in
the grid code order accordingly the CTU should in consultation with all
concerned down the procedure for distributing the UI charges.
Issue 10: Metering Arrangements and Programme of Implementation
.A. A number of parties who deposed before us have stated that the ABT
should be enforced only after proper metering, telemeter and associated
hardware and software is commissioned. It is stated by MPEB that, in the
western region, the ABT cannot be implemented unless the special energy
meters are installed. It is also suggested that after the installation of the
meters there should be some time allowed to conduct mock exercises. It
is also felt in some quarters that the joint meter reading would be a
mammoth exercise which goes against the practicability of implementing
ABT with 15 minute interval for UI charges. We however understand that
the metering system does not involved elaborate manual reading.
B. We understand that the metering arrangements are primarily confined to
the special energy meters which measure both energy flows and
frequency over 15 minute time block to enable working of the UI charge. It
is understood from Powergrid that these meters have been procured and
installed in consultation with all concerned. According to the Union of
India, meters are already in place in the southern region, Eastern Region
and North-Eastern Region. Meters in Northern and Western Regions are
yet to be installed. According to the Union of India in its region, Eastern
Region and exercises may not serve much purpose. However, it would be
necessary to ensure that all the meters are in place and the procedure for
collection, reading, decoding of data and software for accuracy are made
operational. Trial run for these should take place to trouble-shoot these
procedures before actual implementation.
During the hearing NLC has expressed certain apprehensions about the
metering arrangements. However, it will not be possible for the
commission to check the adequacy and reliability of the metering
arrangements. This will be the responsibility of the CTU.
C. On a consideration of the above facts and submissions we find that the
Southern and Eastern Region are in readiness for implementation of the
ABT. PGCIL has clarified that the meters for Northern Region are already
ordered and the specifications for the meters for the Western Region are
in the process of finalization. As regards North-Eastern Region, though
the meters are stated to be in position, according to the ASEB, it is not
possible to implanted ABT due to the presence of certain agreement for
single part tariff. Keeping all the above we consider that the
CTU/Powergrid should take on hand the complete responsibility of
installation, testing and trial run of the metering arrangements. As regards
North-Eastern Region it may not be possible in view of the special
situation to implement ABT in the present from. However, it is not clear as
to how exactly the region would like to proceed in this matter. Therefore,
it is appropriate that NEPCO should come forward the a petition, with all
concerned parties as respondents, on the programme for implementation
of ABT. This shall be done within a month from the date of receipt of a
copy of this Order.
1. In View of the special request of Powergrid/CTU to stagger the
Implementation of ABT so that they will be able to make satisfactory
arrangements before implementation the following schedule for
implantation of ABT shall be followed:-
Southern Region - 1-4-2000
Eastern Region - 1-6-2000
Northern Region - 1-8-2000
Western Region - 1-10-200
We understand from Powergrid/CTU that this schedule is practicable.
As already, stated as an interim arrangement after 1st April, 2000 till the
introduction of ABT the PLF excluding deemed generation for calculation
of incentives shall be 80% instead of the present including deemed
generation in East, North and Western Regions for Thermal stations, 77%
for lignite and 85% for hydro stations.
Issue 11: Applicability of ABT to Hydro Stations
A. None of the utilities represented before us have contested the applicability of
the ABT to the Hydro sector. However, questions have been raised regarding
the manner of application to Hydro stations taking into account the special
features of hydro operations as compared to other systems of generation.
For instance, ASEB has stated that there is duplication of elements
considered for energy charge and capacity charges. DVC has stated that
hydro units should also pay UI charges if actual generation is less than
schedule generation in case of frequency below 49.5 Hz, though the draft
notification exempts them from UI charges. ASEB has objected to the
payments for deemed scheduled generation on account of spillage of water.
RSEB has suggested a review of the formula for determining availability by
eschewing any capacity not available for peaking.
B. A number of suggestions have been received with regard to the valuation of
secondary energy. NHPC has questioned the valuation of secondary energy.
RESEB has suggested that the secondary energy relates for hydro stations
should be les than the lowest variable cost on thermal power stations and
proposed a rate of 15 to 20 paise per kWh. DVC has suggested that the
energy charges for hydro stations should be limited to 30 paise per kWh
which is equal to the UI rate at 50.2 Hz as per the UI scheme suggested by it.
NHPC has also suggested modifications in the reckoning of sent out capacity
for hydro stations for working out the availability. According to it though total
actual generation may be limited to Design Energy, any loss of generation
due to reason not attributable to the generator should also be included for
determining availability.
We have gathered from the minutes of the National Task Force that
till their last meeting they could not come to any definite
conclusions on the treatment to be given to hydro stations in the
ABT system. At the instance of NTF, CEA constituted a committee
on Time of day metering and peak load Pricing, which was later
reconstituted as committee on hydro tariff. The committee finalized
its report but the same could not be taken up by the NTF. This
committee had considered the recommendations of ECC in regard
to tariff for hydro stations, apart from the proposals of BHPC. The
following are the major recommendations this committee, which we
consider as relevant for our purposes:
1. The hybrid tariff structure comprising of capacity charges and energy charges should
be continued, however, the method of bifurcating energy charges shall be on notional
variable cost of thermal station.
2. The following two alternative computations for bifurcating energy charges were
recommended:
a) Rate for primary energy for all hydro stations except for pumped
storage stations to be take n as 90% of the lowest variable charges of the
thermal power station of the concerned region. Total energy charges may
be computed on the basis of the rate and saleable energy of the project.
This is intended to facilitate merit order dispatch; or
b) The rate for primary energy during peak and off-peak to be taken as
90% of the highest variable charges and 90% of the lowest variable
charges of thermal stations of the region respectively. After determining
the quantum of peak energy, balance saleable energy should be taken as
off-peak energy. Total energy charges shall be computed on the aforesaid
rates and corresponding saleable energy figures.
3. In case the energy charges exceed the total annual charges, 50% of the annual
charges may be recovered as energy charges and in case of second alternative the rate
for peak and off-peak energy may be reduced proportionately.
4. The rate for primary energy may be computed for each project on the above lines
and may be reviewed every year.
5. The balance amount after deducting energy charges as referred to above may be
recovered as capacity charges. In case the actual availability happens to be lower than
the target availability the capacity charges may get reduced on pro-rata basis. The
capacity charges may be recovered from the beneficiaries in proportion to their
entitlement.
6. In case of actual availability being higher than the target availability incentive will
be payable.
7. The parameters for target availability and rate of incentive for higher availability to
be finalized separately.
• We have considered the special treatment granted in the draft notification under
para 3(b) and 6(b) with regard to hydro stations. We have also considered the
replies from various utilities as well as the recommendations as summarized
already of the committee on hydro tariff constituted by the CEA. We consider the
committee’s recommendation to bifurcate the energy charges into peak and off-
peak based on the highest and lowest variable cost of thermal power station of
the concerned region respectively as sensible keeping in view the need for
promotion of hydel generation as well as avoidance of backing down of hydro
station when they are really required. However, this has to wait till our detailed
consideration of peak and off peak pricing of power. A study on this subject is in
progress. We do not advocate the arbitrary splitting of the total cost into capacity
charges and energy charges. However, since a two part tariff is essential for ABT
the procedure for bifurcation as suggested by the committee under alternative a
as already referred to in para 5.12 (ii) should be implemented. This would
facilitate merit order dispatch for hydro stations. The balance of total charges in
any case would be recovered as capacity charges.
• As regards determination of sent out capacity and availability which are covered
in para 5(b) and 6(b), the following are our findings:
1. Since the hydro stations are willing to submit to the discipline of UI there is no
need for a special treatment at extreme low or high frequencies. Hence hydro station
should also be subject to UI mechanism at all levels of frequency. However in order to
prevent undue earning of UI charges, the hydro stations shall be obliged to revise their
scheduled generation in case of higher inflow of water. In other words, in monsoon
season on any sudden increase in flow of water the scheduled generation shall be
deemed to have been revised and the hydro stations shall inform RLDC accordingly.
2. it shall be ensured that by declaring capacity above designed energy and
actually generating above designed energy a situation of more than 100% availability is
not brought above which of course is presently covered by the notification. It shall also
ensured that the Declared Capacity does not exceed the Installed Capacity of the Plant.
3. Regarding the pricing of secondary energy we are in agreement with the
contentions NHPC that the same should be priced as primary energy.
4. We are convinced that the proposal as contained in the draft notification read
with this order shall ensure (a) full recovery of all costs and (b) provide scope for
incentive on better performance as well as on secondary energy.
5. The method or reckoning the incentive shall be based on the actual PLF and
not on availability i.e. the same procedure as for thermal stations shall be adopted.
6. Apart from the above which are specific deviations from the draft notification,
the rest of the features of the notification with regard to hydro stations stand approved.
i. There is no separate provision necessary fro tariff of pumped
storage stations because the underlying idea tariff proposals is
that the full cost would get recovered either in the form of
energy charges or fixed charges. With the bifurcation of
variable charges by adopting the lowest available cost of
thermal station in the region, it is only necessary to add thereto
the cost of pumping as part f the variable charges. Hence a
separate Tariff treatment is consider unnecessary.
ii. The objection of ASEV with regard to the bifurcation of cost into
fixed and variable has been already taken into account. Regard
in the other objection of ASEB on compensation for water
spillage, it has been adequately dealt with in notification as the
underlying principle is that compensation has to be made upto
the design energy. However, the reason for this spillage have
been restricted to low system demand or constraints in
transmission system or any other reason not attributable to the
generator which means the spillage is virtually a capacity
charge. As regards the objection of DVC on exemption of hydro
units from UI charges, the same has been taken note of by us
and hydro stations shall also be liable to pay UI charges. We
understand that it should be possible to schedule the generation
even by run of the river station with the facility to revise the
schedule within six time blocks. Regarding the objection of
capping the secondary energy, the same has been already
taken care of in this order.
Recommendation
1. Following improvements have been brought about in operation of regional grids
by ABT:
(i) Grid frequency has dramatically improved from 48-52 Hz range to 49.0-50.5Hz range
for most of the time.
(ii) A higher consumer demand is being met, due to built-in incentives to maximise
generation in peak-load hours.
(iii) Generating stations are being operated according to real meritorder, on region-wide
basis, through decentralized scheduling.
(iv) Hydro-electric generation is being harnessed more optimally than done previously.
(v) States’ share in Central generating stations have acquired a new meaning and grid
discipline is encouraged.
(vi) Open access, wheeling of captive generation and power tradinghave been enabled
by placing in position the mechanism (UI) forhandling deviations/mismatches.
(vii) States meet their occasional excess demand by over-drawing from the regional grid
and paying applicable UI charges to the under-drawing States.
2. The intra-State generating stations are not yet on ABT, due to which opportunities for
further optimisation are being lost. For example, the intra-State stations (other than
those owned by the still-bundled SEB) have no incentive presently to maximise their
generation in peak-load hours and to back down during off-peak hours. They are also
not induced to respond to grid contingencies. Scheduling disputes between generating
stations and State LDCs could arise, particularly in case of IPPs. With the present focus
on commercial aspects, it is very desirable that ABT is applied to all intra-State stations
(except those embedded in vertically bundled licensees’ systems) as well, whether
SEB-owned or otherwise, for optimised utilisation of intra-State resources.
4. The foregoing has been duly appreciated by the Central Government and the
following has been stipulated in the National Electricity Policy notified on 12.2.2005:
“
5. The ABT regime introduced by CERC at the national level has had a positive impact.
It has also enabled a credible settlement mechanism for intra-day power transfers from
licensees with surpluses to licensees experiencing deficits. SERCs are advised to
introduce the ABT regime at the State level within one year.”
6. As and when an SEB is unbundled and the State’s distribution system is divided into
zones, it would be essential that each zone has a schedule for power that it is to receive
through the State grid. The intra- State system would then look very much like the
present regional system : a number of generating stations supplying power through a
transmission grid to a number of beneficiaries, with scheduling, metering and energy
accounting carried out by a load dispatch centre. It would only be logical to replicate the
regional system (of shares/allocations, scheduling, metering, UI, etc), which is already
tried and proven.
7. The UI liability of a State, after unbundling, would depend on judicious scheduling for
the intra-State entities and their dynamic response. This can all be centralised at the
State LDC adopting a disciplinarian approach, but it has the risk of being resisted and
flouted. Highly reliable communication, SCADA, AGC etc would also be required, with
associated cost and complications. A more pragmatic approach, therefore, would be to
delegate the responsibilities to the intra-State entities for decentralised action, with UI
mechanism providing the required frame work for keeping all entities on track. In other
words, it would be desirable to apply UI on all intra-State entities which are
supposed to have a schedule.
8. While for a total compatibility with the system presently operating at the inter-State
(regional) level, it would be desirable to adopt the same system in-toto for intra-State
entities, it is recognized that there could be valid reasons, State-specific, to deviate from
the regional mechanism. It is recommended that the concerned SERCs examine the
following issues in detail, in association with the respective SEB/STU and pragmatically
decide their approach.
11. Treatment of secondary oil consumption It has been a practice so far in India to treat
secondary oil consumption as a component of energy charge. However, secondary oil is
consumed only when a coal/lignite-fired unit has to back down below about 60% or has
to be started up/shut down. During normal operation, secondary oil should not have to
be fired at all. In other words, during normal operation (above 70% load), the variable
cost of a generating unit would comprise of only the coal cost. In order to get the energy
charge to reflect the unit’s correct variable cost (and thereby to give the unit a better
merit-order position), it would be desirable to treat secondary oil consumption as a
component of plant’s fixed cost, and recover it through capacity charge instead of
energy charge. This is particularly important for load-centre stations which would be
required to back-down during off-peak hours due to their comparatively higher variable
cost, and may be considered by SERCs at an appropriate stage.
12. Relationship between capacity charge and plant availability is should be such that
the incentive may be linked to plant availability. Once this is done, incentive can as well
be merged with capacity charge. The relationship between capacity charge payment for
the year and average plant availability can then have three possible shapes, that can be
easily derived.
13. Time block for UI In the inter-State ABT, UI is determined for each 15-minute time
block. This inherently requires 15-minute wise energy metering on all interchange points
of each regional constituent. Similar special energy meters shall be required for all intra-
State constituents if the same 15- minute time block is to be applied intra-State. As
some States already have meters for 30-minute time-block, a question has been raised
as to whether the intra-State time block can be of 30 minutes. The primary idea of UI is
to price the deviations from schedules according to prevailing (i.e., real time) system
conditions. The time block should, therefore, be as small as practicable, and a 5-minute
time block would be still better, theoretically. 15-minute has been a satisfactory
compromise, as regional grid operation over the last 2-3 years has shown. As such, we
recommend that all States adopt a time block of 15 minutes only, which would also
enable direct back-to-back accounting with regional UI. However, implementation of
intra-State UI should not get delayed on this account alone. It is, therefore, suggested
that following procedure may be adopted as an interim arrangement for determination of
UI charges for those intra-State entities who are having 30 - minute meters on their
periphery.
Energy actually drawn in a 30 - minute block = A
UI rate corresponding to C = E
UI rate corresponding to D = F
UI charge for the intra-State entity, for the 30 - minutes block =(A-B)x (E+F)/2.
17. Entities to be covered in ABT In the first instance, intra-State ABT should be
implemented for
19. For implementation of ABT and UI mechanism within a State, the activity on the
critical path would be installation of special energy meters on the periphery of all entities
which are to be covered by ABT and UI. It is recommended that the meters already
field-proven, and fully conforming to the specification used in case of Gujarat be ordered
by the respective SEB/STU on priority. Other preparatory action can follow.
20. In conformity with section 166(4) of the Electricity Act, 2003, the SERCs may
request the respective State Governments to constitute a Coordination Forum at the
State level, which may also oversee the implementation of intra-State A.B.T., if so
decided.
Some States are contemplating balancing mechanisms differing from the concept of
frequency-linked U.I. rate. The implications are explained below through an example.
Suppose two States A and B have a thermal station each, both having a variable cost of
150 paise/kWh. Suppose both have been scheduled to generate at 90% of their
available capability during off-peak hours on a certain day. Also suppose that State-A
has adopted UI mechanism totally identical to the regional UI mechanism, but State-B
has adopted a different balancing mechanism concept in which the price of balancing
power, instead of being a function of frequency, is calculated by the SLDC from time to
time. Suppose it is 210 paise/kWh at a certain time, while frequency is 49.9 Hz and
corresponding regional UI rate is 180 p/kWh. In State-A, the thermal station would see
the frequency and ramp up its generation from 90% to 100% of available capability (say
500 MW), at an incremental expenditure of 150 paise/kWh. The 50 MW over-generation
would result in 50 MW of underdrawal by State-A, for which it would receive UI charges
@ 180 paise/kWh from regional UI pool account, which would get passed on to the
thermal station. There would thus be a saving of 30 paise/kWh on 50 MW for the
thermal station of State-A, which would work out to Rs.15000 per hour. Other utilities in
State-A would not have any financial impact on the above account. The situation in
State-B would be more complex. The thermal station may want to increase its
generation, since it would get 210 paise/kWh against an incremental fuel expenditure of
150 paise/kWh. But this would result in a loss for State-B DISCOMs; they would pay
210paise/kWh to the thermal station for its extra generation, but would receive only 180
paise/kWh from regional UI pool account for the resulting underdrawal. Due to this
anomaly, the SLDC of State-B may not permit the thermal station to increase its
generation beyond the given schedule (90%), and the State as a whole would miss an
opportunity for some financial gain. In other words, generally speaking, State-B may not
gain anything by adopting a balancing mechanism differing from regional UI.
A.B.T. is basically meant for large power plants whose capacity is assigned to one or
more beneficiaries on a 24 - hour, long-term basis. It presumes that the plant operator is
able to declare the plant availability on day-ahead basis, and is then able to supply
power as per the schedule advised by his beneficiaries. As such, A.B.T. is not an
appropriate/practicable mechanism for captive/co-generation, or for non-conventional
sources of energy (wind, solar, biomass, mini-hydel, etc.), which are mostly
unpredictable regarding their power supply capability. For example, payment of capacity
charge in A.B.T. is dependent on MW availability declaration. If a figure cannot be
committed for the whole of the next day, capacity charge itself cannot be determined.
Further, the actual generation could vary widely, from the given schedule (e.g. due to
changes in wind speed), and a plant could run up huge UI liability. A.B.T. should
therefore not be applied for such plants. They may continue on the single-part tariffs as
presently specified by SERCs, or the entire power supplied by them into the grid may be
treated as UI (and paid for by the concerned DISCOM at the frequency-linked UI rate).
The logic for the latter is fairly simple. If a DISCOM receives one MW from a captive
plant or wind farm, its drawal from the State grid would reduce by one MW. If it goes in
underdrawal mode, it would receive UI payment for one MW, which it can pass on to the
captive plant/wind farm, and remain financially immune.
Open access, as contemplated in the Electricity Act, 2003, means supply of power by
entity-A to entity-B through the electricity grid. Power injection by A may not be constant,
and may differ from contracted amount, by a varying degree from time to time. Similarly,
power drawal by B may also vary and differ from the contracted amount. For example,
the contract between the two parties may stipulate that A has to inject 10 MW, and B
has to draw 9.5 MW (after accounting for transmission loss in the electricity grid). The
actual injection and drawal may however be 9.0 and 10.0 MW respectively. Commercial
treatment of such a situation, which is dynamic, could be very complex. The matter,
however, becomes fairly simple if it is stipulated that B has still to pay to A for 10 MW at
contracted rate, A has to pay at the UI rate to UI pool account for one MW of
undersupply, and B has to pay at the UI rate for 0.5 MW of over-drawal to the UI pool
account. This has already been specified by CERC for inter- State open access, and the
same approach should be stipulated by the SERCs for intra-State open access. This
necessarily requires installation of special energy meters for all open access customers,
for recording energy 15-minutes block wise.
As and when they are allowed open access, they would have to pay charges for
contracted energy as per tariff bilaterally agreed with their supplier, and the UI charges
for deviations from contracted schedule. This has to be duly taken care of while
extending open access to end consumers.
Conclusion
All the apprehensions regarding the new system not withstanding, ABT is still a
welcome and necessary development. Next step is for the concerned authorities to
ensure the necessary infrastructure to remove all the bottlenecks on the transmission
side. Once this id done, the path should be clear to a completely market driven scenario
with much better systems and infrastructure in place. The culminating point shall be an
elaborate and efficient system with much more reliance on distributed power systems as
well. This will iron out any monopoly tendencies in the system delivering maximum
benefits to the consumers. This will also prove beneficial to the environment since
“green power” norms are much more effectively implemented in a distributed and
deregulated power scenario.
ABT notification defines availability for any specific time-period as the ratio of the
average sendout capability (SOC) for all time blocks of the time-period to the rated
SOC. Thus availability canbe expressed using the formula:
n
Avaliability = ∑ {SOC/(1- AUX/100)+ CL}*100/(h*IC)
i=1
where
IC =Installed capacity of station in MW
SOCi = Send out capability in ith time block
N = number of time blocks in the durations
AUX =Normative auxiliary consumption for the plant as a percentage of gross
consumption
H =Number of hours in the duration
CL =Gross MWH of capacity units kept closed on account of the generation
scheduling order