) -PREPARED BY MANIRUL ISLAM Quantity Surveyor (Civil), Teejan, Oman 1. UNITS OF MEASUREMENTS UNIT FOR LABOUR WORK UNIT FOR COMPLETED ITEM (MATERIAL+LABOUR)
SL.NO
ITEMS
01 02 03 04 05
Excavation Back filling / soling Footing (Concreting) P.C.C Column / Beam / Lintel Concreting
cum / cft cum / cft cum / cft cum / cft cum / cft
06 07
08 09
10 11 12 13 14 15 16 17 18 19 20
Brick masonry 23cm thick Brick masonry 35cm thick U.C.R. masonry Plastering Pointing Flooring / /
sqm / sft cum / cft cum / cft sqm / sft sqm / sft rm / rft rm / rft No. or rm / rft sqm / sft
cum / cft cum / cft cum / cft sqm / sft sqm / sft rm / rft rm / rft rm / rft sqm / sft sqm / sft rm / rft
Tiling Skirting / Steps Sill Patti Kitchen otta Painting Doors Windows Plumbing /
pipes 21 Plumbing fitting sanitary ware 22 23 24 25 Water tanks Septic tanks Road Electrical cabling Wiring 26 27 28 29 30 Electrical points Water-proofing to terrace Water-proofing of W.C Gardening (lawn) Gardening (trees bushes) / No. No. sqm / sft sqm / sft No. sqm / sft sqm / sft sqm / sft No. No. / work ltr. ltr. sqm / sft rm / rft ltr. No. of users sqm / sft rm / rft / No. No.
(asphalting)
01 02 04 05 07 08 09 10 11 13 14 15 16 17 18 19 20 21
1 meter 1 meter 1 centimeter 1 foot 1 inch 1 tone 1 kg 1 kg 1 gram 1 sq meter 1 brass 1 brass 1 cu meter 1 cu meter 1 cu feet 1 brass 1 cu feet 1 liter
100 centimeter 3.28 feet 0.393 inch 0.305 meter 2.54 centimeter/ 25.4 mm 1000 kg 1000 grams 0.001 tone 0.001 kg 10.76 sq feet 100 sq feet 9.29 sq meter 35.28 cu feet 1000 liters 28.315 liters 100 cu feet 0.0283 cu meter 0.001 cu meter
22 23 24
3. WEIGHTS OF BUILDING MATERIAL SR.NO 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 Cement Steel Dry sand River sand Stone Water P.C.C R.C.C. (2% steel) Bricks Brick masonry Soil Cement concrete block (solid) Cement mortar Lime mortar Lime Glass Teak wood Sal wood Marble stone Granite stone Cuddappa Bitumen MATERIAL 1440 7850 1600 1840 2850 to 2960 1000 2240 2420 1600 to 1920 1920 1760 1800 2080 1760 640 2530 670 to 830 990 2620 2460 to2800 2720 1040 THEORETICAL WEIGHT IN Kg/cum
RATE ANALYSIS
Volume of dry concrete = 15.2 cum. (Adding 50 to 52% for compaction, wastages etc)
MATERIAL
QTY
RATE
PER
AMOUNT
CEMENT
44
265 Rs.
Bag
11660.00
SAND
4.56
1270 Rs.
Cum
5791.20
METAL
9.12
900 Rs.
Cum
8208.00
NO. 02 04 16 07
TOTAL TOOLS & PLANTS L.S. 1% TOTAL=31709.2+317.092 WATER & ELECTRIC CHARGES 2% = TOTAL=32026.292+640.52 CONTRACTORS PROFIT 25%
= = =
= =
= 40833.505 Rs.
2. BRICK WORK
= 0.00154cu.m.
= 0.002 cu.m.
= 5 0.002
= 2500
=2500 x 0.00154
= 1.323cu.m
Vol. of dry mortar = 1.323 + 33% in wet mortars for interlocking =1.759cu.m
=10.057bags.
10.00bags
= 1.408cu.m.
ITEM DESCRIPTION
QUANTITY
RATE RS.
AMOUNT RS.
a. Material
Cement
10 bags
250/bag
2500.00
Sand
1.408 cu.m
1270/cu.m
1788.16
Bricks
2500 Nos.
4/no.
10000.00
Mason
250/day
1000.00
Head Mason
400/day
400.00
Male coolie
10
200/day
2000.00
Total
17688.16
1%
0f total
176.88
Total
17865.04
d. Water charges
2%
Of total
357.30
Total
18222.34
25%
Of the total
4555.58
Total
22777.92
22777.92 Rs.
3. R.C.C. COLUMN
Consider 10 cum volume. Grade of concrete M 40 Proportion (1: 1.808: 1.616) 1+1.808+1.616= 4.424 {as per mix design}
Volume of dry concrete = 15.2 cum. (52% for compaction & wastages)
Cement bags
MATERIAL
QTY
RATE
PER
AMOUNT
CEMENT
99
265 Rs.
Bag
26235.00
SAND
6.21
1270 Rs.
Cum
7886.70
METAL
5.55
900 Rs.
Cum
4995.00
NO. 1
PER Day
AMOUNT 400.00
3 16 7 4 8
250 Rs. 200 Rs. 150 Rs. 200 Rs. 125 Rs.
TOTAL
46316.7
463.167
TOTAL=46316.7+463.167
46779.86
= 935.59 = 47715.45
= 11928.8
TOTAL = 47715.45+11928.8
= 59644.31
4. INTERNAL PLASTER
Quantity of one cement bag = 0.035cum Quantity of wet mortar = 0.012 x 100 = 1.2cum Adding 15% wastage = 1.2 + (1.2 x 0.15) =1.38cum Volume of dry mix = 1.38 + (1.38 x 1/3) =1.84cum Volume of cement = (dry volume / 5) x 1 = (1.84 /5) x 1 = 0.368cum = 0.368 / 0.035 =10.5 bags Volume of sand = (dry volume / 5) x 4 = (1.84 /5) x 4 = 1.472 cum
RATE (RS) 1300 /cum 250 / bag 550 RATE (RS) 200 90 Total
AMOUNT (RS) 1913 2625 550 AMOUNT (RS) 1600 1080 7768
1%
0f total
77.68
Total
7845.68
Water charges
2%
Of total
156.91
Total
8002.59
25%
Of the total
2000.65
Total
10003.23
Considering 100sqm area. Proportion for mix C:M = 1:4. Summation of proportion = 5. Quantity of one cement bag = 0.035cum. Quantity of wet mortar = 0.02 x 100 = 2cum. Adding 20% wastage = 2 +( 2 x 0.2 ) = 2.4cum. Volume of dry mix = 2.4 + (2.4 x 1/3) = 3.2cum. Volume of cement = (dry volume / 5) x 1 = (3.2 /5) x 1 = 0.64cum = 0.64 / 0.035 = 18.3 bags = 19 bags Volume of sand = (dry mix / 5) x 4 = (3.2 /5) x 4 = 2.56cum.
PARTICULAR Materials
QUANTITY
RATE(RS)
AMOUNT(RS)
8nos 12nos
200 90 Total
1%
0f total
117.08
Total
11825.60
Water charges
2%
Of total
236.512
Total
12062.112
25%
Of the total
3015.53
Grand Total
15077.64
USEFULL DATA FOR ESTIMATION Mixer Machine Capacity: Sr. No: Capacity 1 2 3 6' / '4' 7' / '5' 10' / '7' Dry volume in cum 0.170 0.198 0.283 Wet volume in cum 0.113 0.142 0.198 Output per hour 2.266 2.832 3.965 Petrol consumption per hour Remarks in litre 1.000 1.400 1.700 Each batch of concrete requires about 3 minutes of mixing
Cement Mortar:
Cement in Kg
Cement in bag
Sand in 'cum'.
Remarks
1 2 3 1 5 6
0.73 0.96 1.02 1.05 1.05 1.06 50 kg. cement bag size is (400mm x Water may be generally 350mm x 250mm internally. Volume taken as 140 litres per 'cum'. per is = 0.035 'cum'.
Cement Concrete:
Cement in Kg
Cement in bag
Sand in 'cum'.
Aggregate in 'cum'.
Remarks
1 2 3 4 5
1 : 4 : 8' Nominal 161 Mix 1 : 3 : 6' Nominal 212 Mix 1 : 2 : 4' M15 317
Remarks Considering dry density of concrete is 1.54 'cum'. Aggregate may be used 60% : 40% ratio of 20mm and 10mm down respectively. Water required for concrete varies from 28 to 35 litres per bag of (50kg) cement depending on the mix and proportion.
Reinforcement (Steel) works: Reinforcement usually required in various situation is as follows: Culvert and foundaion = 0.5% to 1% Slab and landing = 0.5% to 1.5% Arch, wal, floor and flate roof = 1% to 2% Column and brace = 2 % to 3% Column and brace = 2 % to 3% Pile = 2% to 5% Remarks
Binding or tying wire for reinforcement may be taken as 0.9 to 1.3 kg per quintal of reinforcement.
One 50 kg. bag of cement will make approximately following volume of concrete: The equivalent size of a box for 50 kg. cement bag is 400mmx350mmx250mm internally. 0.133 'cum' of 1 : 1.5 : 3 concrete. 0.166 'cum' of 1 : 2 : 4 concrete. 0.140 'cum' of 1: 1 : 2 concrete. 0.250 'cum' of 1: 3 : 6 concrete. 0.333 'cum' of 1: 4 : 8 concrete. 0.400 'cum' of 1: 5 : 10 concrete. 0.500 'cum' of 1: 6 : 12 concrete.