CODE REVISION REVIEW SHEET (CRRS)

CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA

DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & NECESSITY FOR REVISION NO PAGE: 1 of 6

CONTENTS Submittal of Technical Inquiries to the Boiler and Pressure Vessel Committee Mandatory Introduction of the New ASME Certification Mark and Certification Designators References to Appendix W were added to NCA-1130(a) Endnote 3 and NCA-3252(a) (3) Endnote 9. Revised NCA-1140 to state that a Certificate Holders Quality Program shall meet and be updated to the latest Subsection NCA in effect. Updates are to be made within six months of the date of issuance NCA-3250 and NCA-8162 were revised to add provisions for Owners who receive notification from the regulatory authority that a Combined Operating License Application(COLA) for a specific plant has been docketed to obtain an Owners Certificate(C of A) from ASME. Corrected NCA-3556 by changing or to for. (1) Revised NCA-3561 (2) Moved test allowing N or NV Certificate Holder to supply replacement material without material supply being shown in the scope of their certificates from NCA3561(a) to new subparagraph NCA-3561(d)

Foreword

NCA

Numerous Paragraphs

QAM-01 Section 8 EXHIBIT : 8-11

YES

NCA

1130 & 3252

NO

NCA

1140

QCM-01 Section 2 Para. 2.2.3

NO

NCA

3250 & 8162(a)

NO

NCA

3556

NO

NCA

3561

NO

PREPARED BY :

REVIEWED BY :

REMARKS

___________________ _________ QA TEAM LEADER DATE

POSCO E & C

___________________ _________ QUAILTY MANAGEMENT DATE GROUP LEADER FORM No.: N-00122(0) DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & QAM-01 Section 15 Para. 15.2.2.2 NECESSITY FOR REVISION NO PAGE: 2 of 6

CODE REVISION REVIEW SHEET (CRRS)


CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA CONTENTS

NCA

3851.3(a)

NCA NCA

3859.1

10

3900 Table NCA7100-2 & 7100-3 Table NCA7100-3

11

NCA

12

NCA

13

NCA

Table NCA7100-3

14

NCA

Table NCA8100-1, Fig. NCA-8212-1

The word Assurance was changed to System in NCA-3851.3(a) Revised NCA-3859.1(d) to clarify the requirement for Internal Audit to be at least once annually. Revised NCA-3900 requiring the Nonmetallic Material Constituent Supplier to also have a Quality System Program. Updated Reference Edition from 1992 to 2006 for ASNT SNT-TC-1A. Revised Table NCA-7100-3 to delete the reference & Supplements in the SNTTC-1A in its entirety. Added National Ready Mixed Concrete Association(NRMCA) QC Manual Section 3 Plant Certification Check List(Tenth Revision -2007 as a reference. ASME has replaced the Code symbols previously used in Section III with a single ASME Certification Mark.

NO

NO

NO

NO

NO

QAM-01 Section 8 EXHIBIT : 8-11

YES

15

NCA

9200

16

Attachment page 9 to 46 except foreword and Numerous Paragraphs

17

Foreword I Numerous Paragraphs

Editorial changes to replace the word accredited with certified were made to 8 definitions in NCA-9200 as well as in NCA-3820(a) and NCA-5121(a). See Attachment page 9 to 46 (Attachment : 2011 Addenda ASME Boiler & Pressure Vessel Code Synopsis Section III & IX Nuclear) Submittal of Technical Inquiries to the Boiler and Pressure Vessel Committee Introduction of the New ASME Certification Mark and Certification Designators

NO

NO

QCM-01 Section 6 EXHIBIT : 6-9

NO

18

YES

CODE REVISION REVIEW SHEET (CRRS)


CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA CONTENTS

DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & NECESSITY FOR REVISION PAGE: 3 of 6

19

Fig-PG-33.2

20

Figures PG58.3.1(a), (b) and (c) Fig. PG58.3.3 PG-5.1

21

22

23

PG-8.4.1.2

This action corrects sketches (h) and (i) of Fig. PG-33.2 that show doublesided welded joints with unshaded squares at the mid-wall root giving a false appearance of failure to achieve full penetration. The Figures contain references to other paragraphs that are not mentioned in PG-58 The Figure is revised by adding a control valve for the recirculation pump (if used). Lower case m in the word manufacturer was capitalized This action corrected the reference of PG-67.7 (Which was deleted in the 2009 Addenda) in PG-8.4.1.2 from PG-67.7 to PG-73.3.4

NO

NO

NO

NO

NO

24

PG-16.6

25

PG-22.1

26

PG-27.4.4

Further to the clarification made by ASME that Forewords are not part of the Code, a proposal was developed to clean up the Forewords of all Code books by moving those portions of previous Forewords, that are often presumed to be mandatory and enforceable, into the main body of the Code books. The term average stress is deleted from PG-22.1 as it is not defined anywhere in the Code. It is important to note that Weld Strength referred in PW-15 and Strength Weld referred in paragraphs PG27.4.4 Note 4 & A-317.3(d) Note 4 are not synonymous terms.

NO

NO

NO

CODE REVISION REVIEW SHEET (CRRS)


CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA CONTENTS

DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & NECESSITY FOR REVISION PAGE: 4 of 6

27

PG-28

28

PG-31.2

This action basically brings the external pressure design rules of PFT-51 to a general paragraph of the Code book to make them more generic and applicable for all cylindrical components under exteral pressure, not only for furnaces and tubes of firetube boilers The symbol for gasket moment arm h[sub g] in PG31.2 has been revised to make it consistent with the way it is shown in Figure PG31.

NO

NO

29

PG-32.1.4(a)

30

PG-33

31

PG-33.1, A-67

The original intent of this paragraph was to limit the maximum opening size(to be exempted from compensation calculations) as the larger of : d max or the smaller of 1/4 times the inside diameter of the shell or header, or 2 3/8(60mm). When a nozzle as shown in Fig. PG-33.2, Sketches (d), (e-1), (f), (g), (h), and (i) is inserted into the vessel wall with the nozzle material of lower strength compared to the vessel wall, the nozzle reinforcement equations in Fig. PG-33.1 for the area available in the shell, A1, do not compensate for the lower strength of the inserted nozzle beyond the nozzle neck(t[sub n]). The words for nozzle wall inserted through the vessel wall in the definition of fr l in PG-33.3 appear to limit fr l only to those situations where the nozzle wall is inserted through the vessel wall, while equations for abutting nozzle in Figure PG-33.1 use the stress ratio fr l.

NO

NO

NO

CODE REVISION REVIEW SHEET (CRRS)


CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA CONTENTS

DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & NECESSITY FOR REVISION PAGE: 5 of 6

32

PG-49.1

A new requirement is added to PG-49.1 to limit the allowable stress to 7500 psi [51.7 MPa] for stays in steam locomotives to make it consistent with US Federal Railroad Administration requirements.

NO

33

PG-52.3

34

PG-53.3

35

PG-60.1.6

36

PG-67.2.7

37

PG-72.2

38

PG-105

39

PG-106

Previously, PG-52.3 did not clearly indicate clearly whether the designer is permitted to establish an equivalent longitudinal efficiency for circumferential ligaments by doubling the circumferential efficiency for use in the design formula of PG-27.2.2, A-125 & A-317. In PG-53.3, the Figure is redesignated as Fig. PG-53.3 in order to keep the figure and the referencing paragraph consistent. A new requirement to provide manual operational access from the floor is added to PG-60.1.6. A new paragraph(PG-67.2.7) was added in the 2010 Edition to address the following condition. (1) An editorial correction is made to the table in PG72.2. (2) Cross-references to A300 are corrected to A301 & A-302. The reference to A-300 has been corrected to A301 & A-302. The word steel is deleted where it used to appear before the word economizer to clarify that Section I rules apply to all Economizers whether they are steel or not, if they are required to be built to Section I requirements.

NO

NO

NO

NO

NO

NO

NO

CODE REVISION REVIEW SHEET (CRRS)


CODE
REVIEW OF CODE REVISION EDITION / ADDENDA / : 2011 Addenda ARTICLE& PARA

DOC. NO. : CRRS-11-001 DATE: 2011.12.13 REVISION OF PROGRAM PARA.OF QA MANUAL & RELATED QA PROCEDURES & NECESSITY FOR REVISION PAGE: 6 of 6

CONTENTS

40

PG-112.2.4

41

Table PG-20

A new paragraph was added to PG-112.2.3 in the 2010 Edition but incorrectly labeled as PG112.2.4. The upper temperature 425 deg. F was changed to 1425 deg. F PW-28.2 is revised to allow volumetric NDE for welder performance qualification. A new Nonmandatory Appendix (A-101) is added to Section I to address subcritical post weld heat treatment heating and cooling rates for Section I materials, as general guidance. In addition to the half bead method, as a result of this revision, Manufacturers and users can now choose from half bead (PW-40.3.4(f)(1)) or temper bead (PW-40.3.4(f)(2)) methods to perform weld repairs to P-No.3 Group Nos. 1 & 2 materials without having to repeat PWHT. PW-53 has been editorially corrected to improve the overall clarity of the paragraph.

NO

NO

42

PW-28.2

NO

43

PW-39.3

NO

44

PW-40.3(f)

NO

45

PW-53

NO

46

Attachment page 4 to 17 except foreword and Numerous Paragraphs

See Attachment page 4 to 17 (Attachment : 2011 Addenda ASME Boiler & Pressure Vessel Code Synopsis Section I Power Boilers)

NO