Version No. 1.0 Modified By Omkar Prayag Reviewed By Ramagiri Srinivasrao Authorized By Sivakumar Kasi Release Date Modifications Done
Table of Contents 1. ICON Details on SAP Screen 1.1 General Information for all transactions 2.0 Long Term Planning 2.1 Creating Inactive PIR version for Simulative Planning 2.2 Create & Change Long Term Planning Scenario 2.3 Executing MRP for Long Term Planning 2.4 Long Term Planning Evaluation
SAP-MTIVer 1.0/15-Oct-11
Page 2 of 11
1.0 ICON Details on SAP Screen General Information for all Transactions
Icons Quick Reference ICON Details (Short Keys) Description Action Taken on Screen
Go back one screen Cancel the activity Display the Details Continue Run Program Exit the Window Create New Window Display the History Save the records Get Help Delete records Copy records Create New Data Change the Records Select the possible Entries Command Field Data Information Search for records
Overview Save Help Delete Copy Create Change Pick List Command Field
(Ctlr+Shift+F2) (Ctlr+F)
Details Search
SAP-MTIVer 1.0/15-Oct-11
Page 3 of 11
SAP-MTIVer 1.0/15-Oct-11
Page 4 of 11
2.1 Creating Inactive PIR version for Simulative Planning Go to t-code MD61 and create inactive version of the demand program for simulative planning. This inactive version is not considered for planning in operative environment.
2.2 Create & Change Long Term Planning Scenario Type the t-code MS31 in command field and press enter, to create planning scenario.
SAP-MTIVer 1.0/15-Oct-11
Page 5 of 11
Enter the name & description of the planning scenario. Press Enter.
SAP-MTIVer 1.0/15-Oct-11
Page 6 of 11
Assign the Plant & Planned Independent Requirement version to the planning scenario.
SAP-MTIVer 1.0/15-Oct-11
Page 7 of 11
Click on Release + Save button to release the planning scenario. Below shown message will appear. Click on Yes.
Below shown message will appear, as separate planning file entries get created for materials allocated to planning scenario. Click on immediately, if you want to see the planning file entries created.
Below screen shows the planning file entries created for a give scenario.
SAP-MTIVer 1.0/15-Oct-11
Page 8 of 11
2.3 Executing MRP for Long Term Planning Type the t-code MS01 in the command filed or select from Long-term planning menu.
MRP run in Long term planning is for a given planning scenario. Enter the name of scenario and press enter twice.
SAP-MTIVer 1.0/15-Oct-11
Page 9 of 11
2.4 Long Term Planning Evaluation Once the Long term planning run is completed, various options are available to evaluate the planning results. Capacity Planning Evaluation is shown below. Go to t-code CM38. Enter the Planning Scenario name and Plant. Press enter.
Output shows the work center wise comparison between available capacity and required capacity for a given planning scenario.