TEST SCHEDULE
GSM PHASEVII RNC Document No
No of Pages Issue No. Issued By: Approved By: Date of Issue: TD/CM/GSM/ Phase VII /1707 08 I Inspection Circle, Jabalpur CGM, Inspection Circle 07.12.2012

Amendment No (If Any) No of Pages: Issued by: Date of Issue:

Restricted use by BSNL Employees only

FIX IT RIGHT AT THE FIRST INSTANCE

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE

INDEX

PART A PART B PART C PART D ANNEXURE-I

INFRASTRUCTURE TEST SYSTEM TEST SYSTEM TEST REPORT MANAGEMENT DIMENSIONING PRE SWITCH ON TEST POST SWITCH ON TEST

TD/CM/GSM/ Phase VII/1707

Page 1 of 8

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE

TEST SCHEDULE FOR RNC


PART A.
S.No. 1 2 3 4 Raised floor and False ceiling or Antistatic flooring (as provided) Layout & floor Plan with Trunking and Dimensioning diagram Lighting and Power outlets Check of earthing systems and its distribution as per Earth layout plan. EI Protection Earthing I-001 Issue III Dated 30.04.05 EI Protection Fire AT 7000 EI Building AC T0002, T0003 As per T & D Test schedule no.TD/SW/ KVA-6322/TS dated 25.04.08, should run continuously for a period of 24 hours As per T & D Test schedule Battery back up minimum 8 Hrs Earth resistance value should be 0.5 ohm

INFRASTRUCTURE TEST
TEST DESCRIPTION

SITE Name ---------------------TEST PROCEDURE / REFERENCE EI- AT-7010 (Digital E 10B) As per approved layout plan REMARKS

5 6 7

Check of Fire Detection System A.C. Plant Engine Alternator

Power Plant & Batteries & Inverter/UPS

TD/CM/GSM/ Phase VII/1707

Page 2 of 8

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE

PART B PRE SWITCH ON TEST


S.No. TEST ITEM 1 2 Location, Alignment & Rigidity (LAR) Cable laying & Terminations & marking on cables REFERENCE /PROCEDRE As per Approved plan Visual check as per cable diagram All cabling should be done by straight wire without having any joint in between. Marking should be at both ends to identify the cable as per documentation and correlate both ends REMARKS

Voltage drop test for DC input for system operating on DC, For AC systems, the proper gauge of cable is to be ensured with proper circuit breakers. QA certificate of all equipment Check of Documentation, Hard / soft copy. ODF: LAR, Cable laying and check of protective devices & earthing General Check points

Voltage drop < 1V from Battery point to equipment. input

4 5

For imported items factory test report is to be submitted As per P.O. Latest version documentation with certificate.

Visual check as per DDF/ODF layout

Visual check, sign writing etc. Identical colour code used for power feeding busbar/cables and earth for a given voltage throughout. Fuses shall have marking for different rating.
Approved network connectivity diagram of associated elements to RNC should be submitted Check the transmission media is having sufficient Bandwidth and capacity as per requirement attached in Annexure-I and as per PO.

Network connectivity diagram

Transmission media between Network Elements

TD/CM/GSM/ Phase VII/1707

Page 3 of 8

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE

PART C

POST SWITCH ON TEST

SYSTEM TEST
S.No. 1 TEST ITEM A. Hardware conformity for all equipments including tools, spares, testers and valid licensed software for operating systems. B. Check of dimensioning of RNC and engineering of interfaces as per PO. Software Conformity Check Software release is to be verified with the referred document. REFERENCE /PROCEDRE As per PO& vetted BOM REMARKS B. Check of dimensioning of RNC as per Annexure-I

The approved software version of RNC shall be provided which shall be verified with the information received from the system. 3.2 Software initialization will be shown from OMC-R. 3.3 System specific command. As per vetted BOM Verification of proper functioning of Internal and external alarms (Fire, Mains fail, High temp, etc.) By LMT or command/ GUI from OMC-R System specific (by command/GUI)

Certificate for latest/ correct version loaded. Software should be in the name of BSNL.

Start up of the RNC with 3.1 System Power OFF/ ON 3.2 Command/GUI from OMC-R 3.3 Backup and Restoration Test Check of optical/electrical ports/links Alarm Handling and Recovery System Alarm Tx Link/GE port alarm Infrastructure Alarm Restart test for Node-B from RNC Diagnostics board test Perform Locking and Unlocking operation

4 5 i) ii) iii) 6 7

Redundancy Test: Check that system has hot standby redundancy of control modules, power supply modules, interface cards, Link redundancy etc.

Taking one module out of service by system specific commands /GUI, Power OFF/ON, PLUGGED OUT/IN Page 4 of 8

Diagnostics shall be tested to run on all the cards/ subsystem/syste m after taking it out of service. Check that existing traffic do not fail.

TD/CM/GSM/ Phase VII/1707

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR 9 Clock Synchronization

GSM PHASE VII RNC TEST SCHEDULE As per planning diagram of the respective Territorial Circle

10 10.1 10.2 10.3 10.4 10.5 10.6

Functionality Check Location Update of MS Mobile originated / Mobile terminated calls to 2G/3G SMS calls Intra RNC Handover Data Attach/Detach HSPA/HSPA+(if applicable) call Verify call handover in Inter Node-Bs Check from signalling trace of a particular IMSI Check from RNC software/OMCR and signalling trace of a particular IMSI Switch off and on MS and check

10.7 10.8

Video call Check of LBS/SMLC Service Status of connectivity can be checked from OMCR Check cell name on MS Make sample calls Display or print out no. of calls and occupancy for radio timeslot, IuCS & IuPS interface. From OMC-R User and terminal management. Check of user domain security Verify creation / modification / deletion of Users & service authorization of user From OMC-R Page 5 of 8 Issue-I Dated 07.12.2012 Detail call test is in MSC Shall be supported by reports from OMC-R

10.9 10.10 11

Check of Cell Broad Casting Service Voice call to PSTN network Check that it is possible to display number of calls and occupancy for a given group of circuit/devices/Links. Alarm Reports Password management

12 13

Event log

Utran cell and Channel management I. Listing of Cells TD/CM/GSM/ Phase VII/1707

14

INSPECTION CIRCLE JABALPUR II. Activate & De-activate III. Addition/modification/deletion of cell IV. Verification of Location and routing area of cells V. Verification of cell neighbors 15 Check of support of IPv6 The system shall support dual IPv4/ v6 stack routing and IPv6 tunneling over IPv4 transport network.

GSM PHASE VII RNC TEST SCHEDULE

PART D

Report Management

RNC Reports - At least one Node-B should be connected with RNC. RNC should be integrated to OMC-R and all relevant counters should be enabled. S.No. TEST ITEM Report on status and congestion condition on junctions and trunks. Report on status and congestion condition on common control devices and processors. Reference/ Procedure Remarks In case of A Interface over IP- Uplink /Downlink Bandwidth Utility Rate over IP CPU load report In case of IP- Report of the occupation status of average number of occupied and number of available UDP ports, Report of the traffic processing board of the A interface. Current and past one week fault report

Report on presence status of the system or designating equipment such as trunk free, blocked, input/output device in use or blocked.

4 5 6 7 8 9

Report of fault detected with identification of faulty units mentioning date and time. Node-B outage report Node-B busy hour cell report Hardware inventory verification from OMC-R Performance report for Radio Access part Performance report for Network Access part Page 6 of 8

TD/CM/GSM/ Phase VII/1707

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE IuPS Uplink/ Downlink Utility Rate Data Resource Timeslot Utility Rate IuPS Uplink/ Downlink Bandwidth Utility Rate Enhanced Full Rate Half-Rate Voice Coding Support for AMR FR Support for AMR HR

10

Performance report of Data

11 12

Performance report of Handover Performance report of voice traffic

TD/CM/GSM/ Phase VII/1707

Page 7 of 8

Issue-I Dated 07.12.2012

INSPECTION CIRCLE JABALPUR

GSM PHASE VII RNC TEST SCHEDULE

ANNEXURE-I
Dimensioning: The RNC shall be dimensioned according to the following guidelines: S.No a. b. c. d. e. f. g. h. i. j. k. l. Parameter Value Voice Usage Per Sub Soft Handover traffic Signalling Overhead ATM overhead E1 capacity utilization STM1 capacity utilization GE/FE utilization for IP traffic [without considering capacity of redundancy port] IuR Traffic BHCA per sub Voice AMR per subscriber Data per 100% of 3G sub (R8 HSDPA) Cell Loading 50 mE 30% 10% 40% 70% 80% 70% 5% 4 12.2 Kbps 20 kilo bits / s 50% 0.0025 Erlang

m. CS Data per subscriber

TD/CM/GSM/ Phase VII/1707

Page 8 of 8

Issue-I Dated 07.12.2012