Beruflich Dokumente
Kultur Dokumente
Evaporation Ratio
The efficiency of a boiler is expressed as the % of useful heat available from the total energy available by burning the fuel. This is expressed on the basis of gross calorific value (GCV) .
Standards
British standards, BS845: 1987 This describes the methods and conditions under which a boiler should be tested.Boiler should be operated under steady load conditions (generally full load) for a period of one hour before taking reading ASME Standard: PTC-4-1 Power Test Code for Steam Generating Units
Part One: Direct method (also called as Input -output method) Part Two: Indirect method (also called as Heat loss method)
IS 8753: Indian Standard for Boiler Efficiency Testing All standards do not include blow down as a loss in the efficiency determination process.
Flue Gas
Boiler
Efficiency =
Boiler Efficiency =
Steam flow rate x (steam enthalpy feed water enthalpy) x 100 Fuel firing rate x Gross calorific value
Water
6. Surface loss
Boiler
Air
Water
8. Bottom ash loss Blow down
Draft gauge
TDS meter
Boiler water TDS, feed water TDS, make-up water TDS. Steam flow, water flow, fuel flow, air flow
Flow meter
As applicable
2 - Fuel analysis details Fuel Fired GCV of fuel Specific gravity of fuel (Liquid) Bulk density of fuel (Solid) Proximate Analysis Date of Test:
1 2 3 4
% % % %
Ultimate Analysis
Carbon Hydrogen Sulphur Nitrogen Ash Moisture Oxygen Water Analysis Feed water TDS Blow down TDS PH of feed water PH of blow down Flue gas Analysis CO2 O2 CO Flue gas temperature
Date of Test:
% % % % % % %
Date of Test: % % %
OC
Pr ess ur e
kg /c m2 g
O C O 2 % 2 %
C O
%
T e m p
0
Boiler Supervisor
Energy Manager
Energy Auditor
= 5599.17 kg/hr = 21937.5 kg/hr = 43 kg/cm2(g) = 377 oC = 96 oC = 14 = 0.55 = 190 oC = 31 oC = 0.0204 kg / kg dry air = 70 oC = 3.5 m/s = 90 m2 = 800 kCal/kg = 452.5 kCal/kg = 90:10
The data collected are for a boiler using coal as the fuel. Find out the boiler efficiency by indirect method.
Steam temperature Feed water temperature %CO2 in Flue gas %CO in flue gas Average flue gas temperature Ambient temperature Humidity in ambient air Surface temperature of boiler Wind velocity around the boiler Total surface area of boiler GCV of Bottom ash GCV of fly ash Ratio of bottom ash to fly ash Fuel Analysis (in %) Ash content in fuel Moisture in coal Carbon content Hydrogen content Nitrogen content Oxygen content GCV of Coal
Boiler efficiency by indirect method Step 1 Find theoretical air requirement Theoretical air required for complete combustion = [(11.43 x C) + {34.5 x (H2 O2/8)} + (4.32 x S)] / 100 kg/kg of coal = [(11.43 x 41.65) + {34.5 x (2.0413 14.48/8)} + (4.32 x 0)] / 100 = 4.84 kg / kg of coal
Step 2 Find theoretical CO2 % Moles of C % CO2 at theoretical condition ( CO2 )t Where, 4.84 x 77/100 Moles of N2 Where moles of C = 28 = 0.4165/12 = 0.0347 0.0347 ( CO2 )t = 0.1332 + 0.0347 + 28 0.016 = 0.1332 = Moles of N2 + Moles of C
= 20.67
Step 3 To find Excess air supplied Actual CO2 measured in flue gas = 14.0%
= 7900 x [ ( CO2)t (CO2)a] (CO2)a x [100 (CO2)t ] = 7900 x [20.67 14 ] 14a x [100 20.67] = 47.44 %
Step 4 to find actual mass of air supplied Actual mass of air supplied = {1 + EA/100} x theoretical air = {1 + 47.44/100} x 4.84 = 7.13 kg/kg of coal
Step 5 to find actual mass of dry flue gas Mass of dry flue gas consists of Mass of CO2 +Mass of N2 content in the fuel+ Mass of N2 in the combustion air supplied + Mass of oxygen in combustion air supplied 0.4165 x 44 Mass of dry flue gas = 12 = 7.562 kg / kg of coal + 0.016 + 100 7.13 x 77 + 100 (7.13-4.84) x 23
Step 6 to find all losses 1. % Heat loss in dry flue gas (L1) = m x cp x (Tf Ta ) x 100 GCV of fuel 7.562 x 0.23 x (190 31) = 3501 L1 = 7.89 % x 100
= 3501 L2 = 3.44 %
x 100
M x {584 + Cp ( Tf Ta )} 3. % Heat loss due to moisture in fuel (L3) = GCV of fuel X 100
AAS x humidity x Cp x (Tf Ta ) x 100 4. % Heat loss due to moisture in air (L4) = GCV of fuel 7.13 x 0.0204 x 0.45 x (190 31) x 100 = 3501 L4 = 0.29 %
%CO x %C 5. % Heat loss due to partial conversion of C to CO (L5) = % CO + (% CO2)a 0.55 x 0.4165 x = 0.55 + 14 3501 5744 x
x 100
L5 = 2.58 %
= 0.548 x [ (343/55.55)4 (304/55.55)4] + 1.957 x (343 - 304)1.25 x sq.rt of [(196.85 x 3.5 + 68.9) / 68.9] = = = = 633.3 w/m2 633.3 x 0.86 544.64 kCal / m2 544.64 x 90
Total radiation and convection loss per hour % radiation and convection loss
L6
7. % Heat loss due to unburnt in fly ash % Ash in coal Ratio of bottom ash to fly ash GCV of fly ash Amount of fly ash in 1 kg of coal Heat loss in fly ash % heat loss in fly ash L7 = = = = = = = = = 8.63 90:10 452.5 kCal/kg 0.1 x 0.0863 0.00863 kg 0.00863 x 452.5 3.905 kCal / kg of coal 3.905 x 100 / 3501 0.11 %
8. % Heat loss due to unburnt in fly ash GCV of bottom ash = 800 kCal/kg Amount of bottom ash in 1 kg of = 0.9 x 0.0863 coal = 0.077 kg Heat loss in bottom ash = 0.077 x 800 = 62.136 kCal/kg of coal % Heat loss in bottom ash = 62.136 x 100 / 3501 L8 = 1.77 %
= 100 (L1+ L2+ L3+ L4+ L5+ L6+ L7+ L8) = 100-(7.89 + 3.44+ 5.91+ 0.29+ 2.58+ 0.25+ 0.11+1.77) = 100-22.24 = 77.76 %
Summary of Heat Balance for Coal Fired Boiler Input/Output Parameter kCal / kg of % loss coal Heat Input = 3501 100 Losses in boiler 1. Dry flue gas, L1 = 276.23 7.89 2. Loss due to hydrogen in fuel, L2 = 120.43 3.44 3. Loss due to moisture in fuel, L3 = 206.91 5.91 4. Loss due to moisture in air, L4 = 10.15 0.29 5. Partial combustion of C to CO, L5 = 90.32 2.58 6. Surface heat losses, L6 = 8.75 0.25 7. Loss due to Unburnt in fly ash, L7 = 3.85 0.11 8. Loss due to Unburnt in bottom ash, = 61.97 1.77 L8 Boiler Efficiency = 100 (L1 + L2+ L3+ L4+ L5+ L6+ L7+ L8) = 77.76 %
Furnace Efficiency,
(kCals) (kCals)
Efficiency
Total Losses
1. Sensible Heat Loss in Flue Gas: O % Corresponding excess air = x100 21 O % (Where O2 is the % of oxygen in flue gas = 12% ) = 12 x 100 / (21 12) = 133% excess air
2 2
Theoretical air required to burn 1 kg of oil=14 kg (Typical value for all fuel oil) Total air supplied = Theoretical air x (1 + excess air/100) Total air supplied = 14 x 2.33 kg / kg of oil = 32.62 kg / kg of oil Sensible heat loss = m x Cp x T m = Weight of flue gas = Actual mass of air supplied / kg of fuel + mass of fuel (1kg) = 32.62 + 1.0 = 33.62 kg / kg of oil. Cp = Specific heat of flue gas = 0.24 kCal/kg/oC T = Temperature difference Heat loss = 33.62 x 0.24 x (750 40) = 5729 kCal / kg of oil % Loss = 5729 = 57.29% 10000 % Heat gain by combustion air = 32.62 x 0.24 x (190 40) ----------------------------------- x 100 10000 = 11.74 % = (57.29 11.74) % = 45.55%
2. Loss Due to Evaporation of Moisture Present in Fuel % Loss Where, M Tfg Tamb GCV
= M {584 + 0.45 (Tfg-Tamb)} x100 GCV of Fuel
% Loss
% Moisture of in 1 kg of fuel oil (0.15 kg/kg of fuel oil) Flue Gas Temperature Ambient temperature Gross Calorific Value of Fuel 0.15 {584 +0.45 (750-40)} = -----------------------------x 100 10000 = 1.36 %
3. Loss Due to Evaporation of Water Formed due to Hydrogen in Fuel % Loss = 9 x H2 {584 + 0.45 (Tfg-Tamb)} ---------------------------------------- x 100 GCV of Fuel
Where, H2 % of H2 in 1 kg of fuel oil (0.1123 kg/kg of fuel oil) = = 9 x 0.1123 {584 + 0.45 (750-40)} ------------------------------------x 100 10000 9.13 %
Factor for Determining the Equivalent of Heat Release from Openings to the Quality of Heat Release from Perfect Black Body
The reheating furnace in example has 460mm thick wall (X) on the billet extraction outlet side, which is 1m high (D) and 1m wide. With furnace temperature of 1340 0C, the quantity (Q) of radiation heat loss from the opening is calculated as follows: The shape of the opening is square and D/X
The factor of radiation (Refer Figure 2.5) Black body radiation corresponding to 1340oC (Refer Figure 2.4 On black body radiation) Area of opening Emissivity
= 1/0.46 = 2.17
= 0.71 = 36.00 kCal/cm2/hr = 100 cm x 100 cm = 10000 cm2 = 0.8
Total heat loss = Black body radiation x area of opening x factor of radiation x emissivity =36 x 10000 x 0.71 x 0.8 = 204480 kCal/hr Equivalent Oil loss % of heat loss = 204480/10,000 = 20.45 kg/hr = 20.45 /368 x 100 = 5.56 %
5a). Heat loss through roof and sidewalls: Total average surface temperature Heat loss at 122 oC Total area of heating + soaking zone Heat loss Equivalent oil loss (a) = 122oC = 1252 kCal / m2 / hr = 70.18 m2 = 1252 kCal / m2 / hr x 70.18 m2 = 87865 kCal/hr = 8.78 kg / hr
6. Unaccounted Loss
These losses comprises of heat storage loss, loss of furnace gases around charging door and opening, heat loss by incomplete combustion, loss of heat by conduction through hearth, loss due to formation of scales.
Furnace Efficiency (Indirect Method) 1. Sensible heat loss in flue gas 2. Loss due to evaporation of moisture in fuel 3. Loss due to evaporation of water formed from H2 in fuel 4. Heat loss due to openings 5. Heat loss through skin 6. Unaccounted losses = 45.55% = 1.36 % = 9.13 % = 5.56 % = 2.64% = 10.76%
(Assessed by subtracting summation of losses 1 to 5 from the losses worked out by direct method i.e. [75 (45.55+1.36+9.13+5.56+2.64) ] ) Total losses Furnace Efficiency = 75% = 100 75 = 25 % = 400 litre /hour (fuel consumption) 6Tonnes/hour (Wt of stock) = 66.6 Litre of fuel /tonne of Material (stock)
Theoretical Heat
Example of melting one tonne of steel from an ambient temperature of 20oC . Specific heat of steel = 0.186 Wh/kg/0C, latent heat for melting of steel = 40 Wh/kg/0C. Melting point of steel = 1600 oC.
Theoretical Total heat = Sensible heat + Latent heat Sensible Heat = 1000 kg x 0.186 Wh /kg oC x (1600-20)oC = 294 kWh Latent heat = 40 Wh/ kg x 1000 kg Total Heat = 294 + 40 = 334 kWh. = 40 kWh
So the theoretical energy needed to melt one tonne of steel from 20o C = 334 kWh.
Power output kW
Boiler
H1
h3 H2 h4 Extraction
2st
H3
Condenser
* Due to wetness of steam in the condensing stage, the enthalpy of steam cannot be considered as equivalent to saturated steam. Typical dryness value is 0.88 0.92. This dryness value can be used as first approximation to estimate heat drop in the last stage. However it is suggested to calculate the last stage efficiency from the overall turbine efficiency and other stage efficiencies.
Heat extraction from 1st 2nd extraction (h6) Heat extraction from 2nd Extraction condenser (h7)
: h1 H1
: H1-H2
: H2-H3
: h5 Heat extraction-actual h8 Heat extraction theoretical : h6 Heat extraction-actual h9 Heat extraction theoretical : h7 h10
h1- h2 h1 H1 h2- h3 H1 H 2
Boiler
Calculation steps
Step 1 : Total heat of steam at turbine inlet conditions at 15kg / cm2 and 250oC, h1 =698kCal/kg Step 2 : Total heat of steam at turbine outlet conditions at 2 kg/cm2 and 130oC, h2 = 648 kCal/kg Step 3 : Heat energy input to turbine per kg of inlet steam (h1- h2) Step 4 : Total steam flow rate, Q1 Power generation Equivalent thermal energy Step 5 : Energy input to the turbine = 5100 x 50 = 2,55,000 kCal/hr. = 5100 kg/hr = 100 kW = 100 x 860 = 86,000 kCal /hr = (698-648) = 50 kCal/kg
Step 6 :
Energy output Power generation efficiency of the turbo alternator = --------------------- x 100 Energy Input 86,000 ------------- x 100 = 34% 2,55,000
=
Step 7 : Efficiency of the turbo alternator Efficiency of Alternator Efficiency of gear transmission
= 34% = 92 % = 98 %
Efficiency ofTurbine =
Power generation efficiency of turbo alternator Efficiency of gear transmissi on * Efficiency of Alternator
Step 8 : Quantity of steam bypassing the turbine Step 9 : Coal consumption of the boiler Step 10: Overall plant heat rate, kCal/kWh
= Mass flow rate of steam x ((Enthalpy of steam, kCal/kg Enthalpy of feed water,kCal/kg)
= Nil
= 1550 kg/hr.
Power output, kW
= 5100 x (698 30) 100 = 34068 kCal/kWh* *Note: The plant heat rate is in the order of 34000 kCal/kWh because of the use of backpressure turbine. This value will be around 3000 kcal/kWh while operating on fully condensing mode. However with backpressure turbine, the energy in the steam is not wasted, as it is utilised in the process. Overall plant fuel rate including boiler = 1550/100 = 15.5 kg coal / kW
Power output, kW x 860 Fuel input for Gas turbine, kg/hr x GCV of fuel, kCal/kg
steam generated, kg/hr x (hs, kCal/kg - hw,kCal/kg) [Mass flow of flue gas, kg/hr x Cp x ( tin - tout)] + [ auxiliary fuel consumption, kg/hr x GCV of fuel, kCal/hr ]
where, hs = Enthalpy of steam hw = Enthalpy of feed water tin = inlet temperature of flue gas tout = outlet temperature of flue gas
Q=UxAx LMTD
Where Q = Heat transferred in kCal/hr A = Heat transfer surface area in m2 LMTD = Log Mean Temperature Difference in 0C U = Overall heat transfer Coefficient kCal/hr/m2/0C
Nomenclature
Cold fluid in w, ti Shell Hot fluid out W, To
Baffles
Hot fluid in W, Ti
Heat Duty
Heat duty of the exchanger can be calculated either on the hot side fluid or cold side fluid as given below. Heat Duty for Hot fluid, Qh = Wx Cph x (Ti-To) Heat Duty for Cold fluid, Qc = Wx Cpc x ( to-ti) ..Eqn-1, ...Eqn-2
If the operating heat duty is less than design heat duty, it may be due to heat losses, fouling in tubes, reduced flow rate (hot or cold) etc. Hence, for simple performance monitoring of exchanger, efficiency may be considered as factor of performance irrespective of other parameter. However, in industrial practice, fouling factor method is more predominantly used.
Step A
Monitoring and reading of steady state parameters of the heat exchanger under evaluation are tabulated as below:
Parameters Hot fluid flow,W Cold fluid flow,w Hot fluid Temp, T Cold fluid Temp,t Hot fluid Pressure,P Cold fluid Pressure, p
Inlet
Outlet
Step B
With the monitored test data, the physical properties of the stream can be tabulated as required for the evaluation of the thermal data
Parameters Hot fluid density, h Cold fluid density, c Hot fluid Viscosity, h Cold fluid Viscosity, c Hot fluid Thermal Conductivity, kh Cold fluid Thermal Conductivity, kc Hot fluid specific heat Capacity, Cph Cold fluid specific heat Capacity, Cpc
* MpaS Mega Pascal Second
Inlet
Outlet
Density and viscosity can be determined by analysis of the samples taken from the flow stream at the recorded temperature in the plant laboratory. Thermal conductivity and specific heat capacity if not determined from the samples can be collected from handbooks.
Step C
Calculate the thermal parameters of heat exchanger and compare with the design data
Parameters Heat Duty, Q Hot fluid side pressure drop, Ph Cold fluid side pressure drop, Pc Temperature Range hot fluid , T Temperature Range cold fluid , t Capacity ratio, R Effectiveness, S Corrected LMTD, MTD Heat Transfer Coefficient, U
Test Data * *
Design Data
* - The pressure drop for the design flow can be rated with the relation , Pressure drop is proportional to (Flow)1.75
Shell Side
787 mm ID Baffle space 787 mm 1 Pass
Parameters Hot fluid flow, W Cold fluid flow, w Hot fluid Temp, T Cold fluid Temp, t Hot fluid Pressure, P Cold fluid Pressure, p
6. 7. 8.
Capacity Ratio Capacity ratio, R = 23.5/43 = 0.547. Effectiveness Effectiveness, S = (to ti) / (Ti ti) =(49 25.5)/(145-25.5) =23.5/119.5 = 0.20. LMTD a). LMTD, Counter Flow = (96 76.5)/ ln (96/76.5) = 85.9 0C. b). Correction Factor to account for Cross flow (R + 1)1/2 x ln ((1- SR)/ (1- S ) F = (R + 1)1/2 x ln ((1- SR)/ (1- S ) ( 1 R) x ln 2- S ( R + 1 (R2 +1)1/2) 2- S ( R + 1 + (R2 +1)1/2) F = 0.977.
9. 10.
Corrected LMTD = F x LMTD = 0.977 x 85.9 = 83.9 oC. Overall Heat Transfer Co-efficient U = Q/ A T = 24477.4/ (264.55 x 83.9) = 1.104 kW/m2. K
C --------O C kW/(m2. K)
Inferences
Heat Duty: Actual duty differences will be practically negligible as these duty differences could be because of the specific heat capacity deviation with the temperature. Also, there could be some heat loss due to radiation from the hot shell side. Pressure drop: Also, the pressure drop in the shell side of the hot fluid is reported normal (only slightly less than the design figure). This is attributed with the increased average bulk temperature of the hot side due to decreased performance of the exchanger. Temperature range: As seen from the data the deviation in the temperature ranges could be due to the increased fouling in the tubes (cold stream), since a higher pressure drop is noticed. Heat Transfer coefficient: The estimated value has decreased to increased fouling that has resulted in minimized active area of heat transfer. Physical properties: If available from the data or Lab analysis can be used for verification with the design data sheet as a cross check towards design considerations. Troubleshooting: Fouled exchanger needs cleaning.
P loss P out = = 1 P in P in
Where Pout Output power of the motor Pin Input power of the motor
Motor Loading :
Motor Loading % = Actual operating load of the motor Rated capacity of the motor
No Load Test
The motor is run at rated voltage and frequency without any shaft load. Input power, current, frequency and voltage are noted. The no load P.F. is quite low and hence low PF watt meters are required. From the input power, stator I2R losses under no load are subtracted to give the sum of Friction and Windage (F&W) and core losses. To separate core and F & W losses, test is repeated at variable voltages. It is worthwhile plotting no-load input kW versus Voltage; the intercept is F & W kW loss component.
F&W and core losses = No load power (watts) (No load current)2 Stator resistance
2 IR
Losses :
The stator winding resistance is directly measured by a bridge or volt amp method. The resistance must be corrected to the operating temperature. For modern motors, the operating temperature is likely to be in the range of 1000C to 1200C and necessary correction should be made. Correction to 750C may be inaccurate. The correction factor is given as follows :
R 2 235 + t 2 = R 1 235 + t 1
where, t1 = ambient temperature, oC & t2 =- operating temperature, oC. The rotor resistance can be determined from locked rotor test at reduced frequency, but rotor I2R losses are measured from measurement of rotor slip. Rotor I2R losses = Slip (Stator Input Stator I2R Losses Core Loss) Accurate measurement of slip is possible by stroboscope or non-contact type tachometer. Slip also must be corrected to operating temperature.
1. 2. 3.
Measure stator resistance and correct to operating temperature. From rated current value, I2R losses are calculated. From rated speed and output, rotor I2R losses are calculated From no load test, core and F & W losses are determined for stray loss
Example
Motor Specifications
= = = = = = =
Calculate stator copper losses at operating temperature of resistance at 1200C Calculate full load slip(s) and rotor input assuming rotor losses are slip times rotor input. Determine the motor input assuming that stray losses are 0.5 % of the motor rated power Calculate motor full load efficiency and full load power factor
Solution
Let Iron plus friction and windage loss, Pi + fw No load power, Pnl = 1063.74 Watts Stator Copper loss, P st-300C (Pst.cu) = 3 (16.1 / 3)2 0.264 = 68.43 Watts Pi + fw = Pnl Pst.cu = 1063.74 68.43 = 995.3 W
Stator copper losses at full load, Pst.cu 120 C = 3 (57 / 3)2 0.354 = 1150.1 Watts
Full load slip S = (1500 1475) / 1500 = 0.0167 Rotor input, Pr = Poutput/ (1-S) = 34000 / (1-0.0167) = 34577.4 Watts
Motor full load input power, P input = Pr + Pst.cu 1200C + (Pi + fw) + Pstray = 34577.4 + 1150.1 + 995.3 + (0.005* 34000) = 36892.8 Watts
*
Poutput Pinput
100
= 0.90
Comments
The measurement of stray load losses is very difficult and not practical even on test beds. The actual value of stray loss of motors up to 200 HP is likely to be 1 % to 3 % compared to 0.5 % assumed by standards. The value of full load slip taken from the nameplate data is not accurate. Actual measurement under full load conditions will give better results. The friction and windage losses really are part of the shaft output; however, in the above calculation, it is not added to the rated shaft output, before calculating the rotor input power. The error however is minor. When a motor is rewound, there is a fair chance that the resistance per phase would increase due to winding material quality and the losses would be higher. It would be interesting to assess the effect of a nominal 10 % increase in resistance per phase.
fl = Efficiency at full-rated load Pir = Input power at full-rated power in kW The percentage loading can now be calculated as follows
Example
The nameplate details of a motor are given as power = 15 kW, efficiency = 0.9. Using a power meter the actual three phase power drawn is found to be 8 kW. Find out the loading of the motor. Input power at full-rated power in kW, Pir = 15 /0.9 = 16.7 kW Percentage loading = 8/16.7 = 48 %
Slip Method
In the absence of a power meter, the slip method can be used which requires a tachometer. This method also does not give the exact loading on the motors. Slip Load = *100% Ss Sr
Where: Load = Output power as a % of rated power Slip = Synchronous speed - Measured speed in rpm Ss = Synchronous speed in rpm at the operating frequency Sr = Nameplate full-load speed
Example: Slip Load Calculation
Given: Synchronous speed in rpm = 1500 at 50 HZ operating frequency. ( Synchronous speed = 120f/P) f: frequency, P: Number of poles Nameplate full load speed = 1450 Measured speed in rpm = 1480 Nameplate rated power = 7.5 kW Determine actual output power. 1500 1480 *100% = 40% 1500 1450 From the above equation, actual output power would be 40% x 7.5 kW = 3 kW
Load =
The speed/slip method of determining motor part-load is often favored due to its simplicity and safety advantages. Most motors are constructed such that the shaft is accessible to a tachometer or a strobe light.
Where: Load = Output power as a % of rated power Slip = Synchronous speed - Measured speed in rpm Ss = Synchronous speed in rpm Sr = Nameplate full-load speed V = RMS voltage, mean line to line of 3 phases Vr = Nameplate rated voltage
There are two basic components, a rectifier and an inverter, to accomplish power conversion. The rectifier receives the 50-Hz AC voltage and converts it to direct current (DC) voltage. A DC bus inside the VSD functions as a "parking lot" for the DC voltage. The DC bus energizes the inverter, which converts it back to AC voltage again. The inverter can be controlled to produce an output frequency of the proper value for the desired motor shaft speed.
Motor Information
Full Load Amperage Rating. Using a motor's horsepower is an inaccurate way to size variable frequency drives. Speed Range. Generally, a motor should not be run at any speed less than 20% of its specified maximum speed allowed. If it is run at a speed less than this without auxiliary motor cooling, the motor will overheat. Auxiliary motor cooling should be used if the motor must be operated at very slow speeds. Multiple Motors. To size a variable frequency drive that will control more than one motor, add together the fullload amp ratings of each of the motors. All motors controlled by a single drive must have an equal voltage rating.
To determine if the equipment under consideration is the right choice for a variable speed drive
The load patterns should be thoroughly studied before exercising the option of VSD. In effect the load should be of a varying nature to demand a VSD
Fan Efficiency: The air power static divided by impeller power Static Fan Efficiency % = Volume in m3 / Sec x total pressure in mmwc 102 x Power input to the shaft in (kW)
Pressures in a duct
Pitot tube
Traverse readings
Example
The following is a typical report on measurements taken and calculations made for a double inlet fan in a palletizing plant. (a) Design Parameters: Volume Static Pressure = = 292 m3/sec. 609.6 mmwc
Volume M3/Sec.
Amps (I)
ANOTHER SIDE 15, 18, 23, 21 Average=19.25 459, 464, 473 479, 480, 470 Avg.=470.83
166.6
220
2127 KW
Average = 70
Instruments used a) Suction pressure, outlet pressure b) For differential pressure c) For temperature d) Fan speed e) Line current
= U tube manometer = Inclined tube manometer = Mercury in glass thermometer = Tachometer = Tong tester
d) P = Power input to the fan shaft = Power input to the motor (kW) x Efficiency of motor (%) at the operating load x transmission efficiency Motor efficiency = 0.94
e)
Fan Efficiency % = Volume in m3 / Sec x total pressure in mmwc (a) x Power input to the shaft in (kW) Where 102 is a conversion constant
For double inlet fan, The total Volume of air,m3 / Sec = 166.6 x 2 = 333.2 Total static pressure, mmwc (U p Static ,across the fan) Fan Efficiency = 468.75- (-22.33) = 491
Performance calculations
a) Gas Density = 273 x 1.293 (Corrected to NTP) 273 + ToC (at site condition) = 273 x 1.293 273 + 32oC (at site condition) = 1.15 kg/m3 b) Volume Cp A p = Cp x A 2 x 9.81 x U p x 1.15 = Pitot tube constant, 0.85 = = Area of rectangular duct in m2, 1.029 x 5.502 Average velocity pressure measured by pitot tube by taking measurement at number of points over the entire cross section of the duct.(see Table) Density at test condition, 1.15 kg/m3 0.85 x 1.029 x 5.502 2 x 9.81 x 70 x 1.15 1.15 v = 166.6 m / Sec
3
Flow (v)
= =
Pump Efficiency
Pump efficiency = Hydraulic power, Ph x 100 Power input to the pump shaft Where, Hydraulic power Ph(kW) = Q (m3/s) x Total head,(hd - hs) (m) x r(kg/m3) x g (m/s2) / 1000 Q = Volume flow rate, r = density of the fluid, g = acceleration due to gravity
Flow Measurement, Q
Tracer method BS5857 Ultrasonic flow measurement Tank filling method Installation of an on-line flowmeter
Tracer Method
The Tracer method is particularly suitable for cooling water flow measurement because of their sensitivity and accuracy. This method is based on injecting a tracer into the cooling water for a few minutes at an accurately measured constant rate. A series of samples is extracted from the system at a point where the tracer has become completely mixed with the cooling water. The mass flow rate is calculated from: qcw where qcw q1 C1 C2 = q1 x C1/C2
= cooling water mass flow rate, kg/s = mass flow rate of injected tracer, kg/s = concentration of injected tracer, kg/kg = concentration of tracer at downstream position during the plateau period of constant concentration, kg/kg
Ensure measurements are taken in a sufficiently long length of pipe free from flow disturbance due to bends, tees and other fittings. The pipe section where measurement is to be taken should be hammered gently to enable scales and rusts to fall out. For better accuracy, a section of the pipe can be replaced with new pipe for flow measurements.
In open flow systems such as water getting pumped to an overhead tank or a sump, the flow can be measured by noting the difference in tank levels for a specified period during which the outlet flow from the tank is stopped. The internal tank dimensions should be preferable taken from the design drawings, in the absence of which direct measurements may be resorted to.
Pump efficiency
Flow delivered by the pump Total head, h2 -(+h1) Hydraulic power Actual power consumption Overall system efficiency Pump efficiency
Specific power requirement: The ratio of power consumption (in kW ) to the volume delivered at ambient conditions.
Receiver pressure Pressure and temperature before the nozzle Pressure drop across the nozzle Speed of the compressor kW, kWh and amps drawn by the compressor
The above readings are taken for the 40%, 60%, 100% and 110% of discharge pressure values.
: : : :
Flow coefficient as per IS d : Nozzle diameter M Absolute inlet temperature oK Absolute inlet pressure kg/cm2 Absolute Pressure before nozzle kg/cm2 Absolute temperature before nozzle oK Gas constant for air 287.1 J/kg k Differential pressure across the nozzle kg/cm2 = Isothermal power/Input power
P1 x Qf x loger 36.7 Absolute intake pressure kg/ cm2 Free air delivered m3/hr. Pressure ratio P2/P1 Power consumption ,kW Free Air Delivered, m3/hr
III.
Volumetric efficiency
IV. Volumetric efficiency = Free air delivered m3/min x 100 Compressor displacement, m3/min x D2 x L x S x x n 4 Cylinder bore, metre Cylinder stroke, metre Compressor speed rpm 1 for single acting and 2 for double acting cylinders No. of cylinders
Compressor Displacement D L S n
= = = = = =
Example
Calculation of Isothermal Efficiency for a Reciprocating Air Compressor. Step 1 : Calculate Volumetric Flow Rate k d P2 P1 T1 P3 T3 P3 P4 Ra : : : : : : : : : Flow coefficient (Assumed as 1) Nozzle diameter : 0.08 metre Receiver Pressure - 3.5 kg / cm2 (a) Inlet Pressure - 1.04 kg / cm2(a) Inlet air temperature 30oC or 303oK Pressure before nozzle 1.08 kg / cm2 Temperature before the nozzle 40oC or 313oK Pressure drop across the nozzle = 0.036 kg / cm2 Gas constant : 287 Joules / kg K
Free Air Delivered Qf = k x x d2 x T1 x 2 (P3-P4) (P3 x Ra) 4 P1 T3 = 1 x ?x (0.08)2 x 303 x 4 1.04 3 = 0.391 m /sec = 1407.6 m3 / h. 2 x 0.036 x 1.08 x 287 313
Step 2 : Calculate Isothermal Power Requirement Isothermal Power (kW) P1 - Absolute intake pressure Qf -Free Air Delivered Compression ratio Isothermal Power = P1 x Qf x loger 36.7 = 1.04 kg / cm2 (a) = 1407.6 m3 / h. r = 3.5 1.04 = 3.36
Step 3 : Calculate Isothermal Efficiency Motor input power Motor and drive efficiency Compressor input power Isothermal efficiency = 100 kW = 86 % = 86 kW = Isothermal Power x 100 Compressor input Power = 48.34 x 100 = 56% 86.0
= 0.071 kW/m3/hr
1.026 4.021 Capacity shortfall with respect to 14.75 m /minute rating is 1.577 m3/minute i.e., 10.69 %, which indicates compressor performance needs to be investigated further.
= 13.17 m3/minute
In case where hot well and cold well are available, the flow can be measured from the tank level dip or rise by switching off the secondary pump. Non invasive method would require a well calibrated ultrasonic flow meter using which the flow can be measured without disturbing the system If the waterside pressure drops are close to the design values, it can be assumed that the water flow of pump is same as the design rated flow.
The compressor power can be measured by a portable power analyser which would give reading directly in kW. If not, the ampere has to be measured by the available on-line ammeter or by using a tong tester. The power can then be calculated by assuming a power factor of 0.9 kW = 3 x V x I
The energy efficiency of a chiller is commonly expressed in one of the three following ratios: 1.Coefficient of performance COP 2. Energy efficiency ratio EER 3. Power per Ton kW/Ton = kW input Tons refrigeration effect
First calculate the kW/ton rating from the measured parameters. a) kW/ton rating = Measured compressor power, kW Net refrigeration Capacity (TR)
Use this data to calculate other energy efficiency parameters with the following relations COP = 0.293 EER kW/Ton = 12 / EER kW/Ton = 3.516 / COP * Source : American Refrigeration Institute b) Coefficient of performance (COP) COP = 3.516 kW/ton rating 12 kW/ton rating EER = 3.413 COP EER = 12 / (kW/Ton) COP = 3.516 / (kW/Ton)
Example
In a brewery chilling system, ethylene glycol is used a secondary refrigerant. The designed capacity is 40 TR. A test was conducted to find out the operating capacity and energy performance ratios. The flow was measured by switching off the secondary pump and measuring the tank level difference in hot well. measurements data:
Temperature of ethylene glycol entering evaporator = (-) 1oC Temperature of ethylene glycol leaving evaporator = (-) 4 oC Ethylene glycol flow rates = 13200 kg/hr Evaporator ethylene glycol pressure drop (inlet to outlet) = 0.7 kg/cm2 Power input to compressor electrical power, kW = 39.5 kW Specific heat capacity of ethylene glycol = 2.34 kCal/kgoC
Calculations Net refrigeration Capacity (TR) = m x cp x (tin tout) 3024 = 13200 x 2.34 x (-1 (-4)) 3024 = 30.65 TR kW/ton rating = Measured compressor power, kW Net refrigeration Capacity (TR) = 39.5 kW 30.65 TR = 1.29 kW/TR Coefficient of performance (COP) = 3.516 kW/ton rating = = Energy Efficiency Ratio (EER) = = = 3.516 1.29 2.73 12 kW/ton rating 12 1.29 9.3
Installed Load Efficacy is the average maintained illuminance provided on a horizontal working plane per circuit watt with general lighting of an interior. Unit: lux per watt per square metre (lux/W/m) Lamp Circuit Efficacy is the amount of light (lumens) emitted by a lamp for each watt of power consumed by the lamp circuit, i.e. including control gear losses. This is a more meaningful measure for those lamps that require control gear. Unit: lumens per circuit watt (lm/W) Installed Power Density. The installed power density per 100 lux is the power needed per square metre of floor area to achieve 100 lux of average maintained illuminance on a horizontal working plane with general lighting of an interior. Unit: watts per square metre per 100 lux (W/m/100
100
Installed load efficacy (lux/W/m)
Average maintained illuminance is the average of lux levels measured at various points in a defined area.
Color Rendering Index (CRI) is a measure of the effect of light on the perceived color of objects. To determine the CRI of a lamp, the color appearances of a set of standard color chips are measured with special equipment under a reference light source with the same correlated color temperature as the lamp being evaluated. If the lamp renders the color of the chips identical to the reference light source, its CRI is 100. If the color rendering differs from the reference light source, the CRI is less than 100. A low CRI indicates that some colors may appear unnatural when illuminated by the lamp.
Where L = length of interior; W = width of interior; Hm = the mounting height, which is the height of the lighting fittings above the horizontal working plane. The working plane is usually assumed to be 0.75m above the floor in offices and at 0.85m above floor level in manufacturing areas.
It does not matter whether these dimensions are in metres, yards or feet as long as the same unit is used throughout. Ascertain the minimum number of measurement points from Table
For example, the dimensions of an interior are: Length = 9m, Width = 5m, Height of luminaires above working plane (Hm) = 2m Calculate RI = 9 x 5 = 1.93 2(9 + 5) From Table 10.1 the minimum number of measurement points is 16
As it is not possible to approximate a square array of 16 points within such a rectangle it is necessary to increase the number of points to say 18, i.e. 6 x 3. These should be spaced as shown below:
Therefore in this example the spacing between points along rows along the length of the interior = 9 6 = 1.5m and the distance of the 'end' points from the wall = 1.5 2 = 0.75m. Similarly the distance between points across the width of the interior = 5 3 = 1.67m with half this value, 0.83m, between the 'end' points and the walls. If the grid of the measurement points coincides with that of the lighting fittings, large errors are possible and the number of measurement points should be increased to avoid such an occurrence.
Calculation of the Installed Load Efficacy and Installed Load Efficacy Ratio of a General Lighting Installation in an Interior
STEP 1 STEP 2 STEP 3 Measure the floor area of the interior: Area = -------------------- m Calculate the Room Index RI Determine the total circuit watts of the installation by a power meter if a separate feeder for lighting is available. If the actual value is not known a reasonable approximation can be obtained by totaling up the lamp wattages including the ballasts: Calculate Watts per square metre, Value of step 3 value of step 1 Ascertain the average maintained illuminance by using lux meter, Eav. Maintained Divide 5 by 4 to calculate lux per watt per square Metre Obtain target Lux/W/m lux for type of the type of interior/application and RI (2): Calculate Installed Load Efficacy Ratio ( 6 7 ). = --------------------
W/m =
------------
Area = 45 m
Calculate the Room Index
RI
Determine the total circuit watts of the installation by a power meter if a separate feeder for lighting is available. If the actual value is not known a reasonable approximation can be obtained by totaling up the lamp wattages including the ballasts: Calculate Watts per square metre, 3 1 :
= 1.93
STEP 4 STEP 5
W/m =
22
Ascertain the average maintained illuminance, Eav. Maintained (average lux levels measured Eav.maint. = 700 at 18 points) STEP 6 Divide 5 by 4 to calculate the actual lux per watt per square Metre Lux/W/m = 31.8 STEP 7 Obtain target Lux/W/m lux for type of the Target Lux/W/m = 46 type of interior/application and RI (2):(Refer Table 10.2) STEP 8 Calculate Installed Load Efficacy Ratio ( 6 7 ILER = 0.7 ). Referring to table 3, ILER of 0.7 means that there is scope for review of the lighting system. Annual energy wastage = (1 ILER) x watts x no. of operating hours = (1 0.7) x 990 x 8 hrs/day x 300 days = 712 kWh/annum
Table 10.4 IES Illuminance Categories and Values - For Generic Indoor Activities ACTIVITY Public spaces with dark surroundings Simple orientation for short temporary visits Working spaces where visual tasks are only occasionally performed Performance of visual tasks of high contrast or large size Performance of visual tasks of medium contrast or small size Performance of visual tasks of low contrast or very small size Performance of visual tasks of low contrast or very small size over a prolonged period Performance of very prolonged and exacting visual tasks Performance of very special visual tasks of extremely low contrast CATEGORY A B C D E F G H I LUX 20-30-50 50-75-100 100-150-200 200-300-500 500-750-1000 1000-1500-2000 2000-3000-5000 5000-7500-10000 10000-1500020000 FOOTCANDLES 2-3-5 5-7.5-10 10-15-20 20-30-50 50-75-100 100-150-200 200-300-500 500-750-1000 1000-1500-2000
A-C for illuminances over a large area (i.e. lobby space) D-F for localized tasks G-I for extremely difficult visual tasks
Interest Charges
SSimple interest: If simple interest is applied, then charges are calculated as a fixed percentage of the capital that is borrowed. A fixed interest percentage is applied to each year of the loan and repayments are calculated using the equation
Compound interest: Compound interest is usually calculated annually (although this is not necessarily the case). The interest charged is calculated as a percentage of the outstanding loan at the end of each time period. It is termed 'compound' because the outstanding loan is the sum of the unpaid capital and the interest charges up to that point. The value of the total repayment can be calculated using the equation.
In order to understand the concept of present vale, consider the case described in Example 3. If instead of installing a new cogeneration system, the company invested Rs.22,20,000 in a bank at an annual interest rate of 8%, then:
The value of the sum at the end of year 2 = 23,97,600 + (0.08 x 23,97,600) = Rs.25,89,4 08
The value of the sum at the end of year 1 = 22,20,000 + (0.08 x 22,20,000) = Rs.23,97,6 00
The value of the investment would grow as compound interest is added, until after n years the value of the sum would be:
FV = D x (1 + IR/100)
Where FV is the future value of investment in Rs., and D is the value of initial deposit (or investment) in Rs., IR is Interest Rate and n is number of years.
The future value of the investment made at present, after 5 years will be:
Present value
The present value of an amount of money at any specified time in the future can be determined by the following equation. Where PV is the present value of S in n years time (Rs.), and S is the value of cash flow in n years time (Rs.).
PV = S x (1 + IR/100)
-n
The net present value method calculates the present value of all the yearly cash flows (i.e. capital costs and net savings) incurred or accrued throughout the life of a project, and summates them. Costs are represented as a negative value and savings as a positive value. The sum of all the present values is known as the net present value (NPV). The higher the net present value, the more attractive the proposed project.
Solution The annual cash flows should be multiplied by the annual discount factors for a rate of 8% to determine the annual present values, as shown in the Table below: Project 1 Project 2 Net Present Net Present savings (Rs.) value (Rs.) savings (Rs.) value (Rs.) (b) (a x b) (c) (a x c) 0 1.000 -30 000.00 -30 000.00 -30 000.00 -30 000.00 1 0.926 +6 000.00 +5 556.00 +6 600.00 +6 111.60 2 0.857 +6 000.00 +5 142.00 +6 600.00 +5 656.20 3 0.794 +6 000.00 +4 764.00 +6 300.00 +5 002.20 4 0.735 +6 000.00 +4 410.00 +6 300.00 +4 630.50 5 0.681 +6 000.00 +4 086.00 +6 000.00 +4 086.00 6 0.630 +6 000.00 +3 780.00 +6 000.00 +3 780.00 7 0.583 +6 000.00 +3 498.00 +5 700.00 +3323.10 8 0.540 +6 000.00 +3 240.00 +5 700.00 +3 078.00 9 0.500 +6 000.00 +3 000.00 +5 400.00 +2 700.00 10 0.463 +6 000.00 +2 778.00 +5 400.00 +2 500.20 NPV = +10 254.00 NPV = +10 867.80 It can be seen that over a 10 year life-span the net present value for Project 1 is Rs.10,254.00, while for Project 2 it is Rs.10,867.80. Therefore Project 2 is the preferential proposal. Year Discount Factor for 8% (a)
Given the above cash flow data, let us find out the internal rate of return for the project.
Solution
Cash flow (Rs.) 0 1 2 3 4 5 6 -20000 6000 5500 5000 4500 4000 4000 8% discount rate Discount factor 1.000 0.926 0.857 0.794 0.735 0.681 0.630 Present value (Rs.) -20000 5556 4713.5 3970 3307.5 2724 2520 12% discount rate Discount factor 1.000 0.893 0.797 0.712 0.636 0.567 0.507 Present value (Rs.) -20000 5358 4383.5 3560 3862 2268 2028 16% discount rate Discount factor 1.000 0.862 0.743 0.641 0.552 0.476 0.410 Present value (Rs.) -20000 5172 4086.5 3205 2484 1904 1640
NPV = 2791
NPV = 459.5
NPV = -1508.5
It can clearly be seen that the discount rate which results in the net present value being zero lies somewhere between 12% and 16%. For12% discount rate, NPV is positive; for 16% discount rate, NPV is negative. Thus for some discount rate between 12 and 16 percent, present value benefits are equated to present value costs. To find the value exactly, one can interpolate between the two rates as follows: 459.5 Internal rate of return = 0.12 + (0.16 - 0.12) x (459.5 - (-1508.5)) 459.5 Internal rate of return = 0.12 + (0.16 - 0.12) x = 12.93% (459.5 + 1508.5) Thus the internal rate of return for the project is 12.93 %.
Solar Energy
Solar energy available is equivalent to 15000 times worlds commercial energy consumption 5-7 kWh/m2 for 300-330 days in a year Applications are heating, lighting, cooking, drying etc. Solar thermal or solar electric (photovoltaic)
Solar Collector
Flat rectangular box with transparent cover Small tubes carrying water or fluid attached to black absorber plate Hot water transferred to storage tank
Solar Cooker
FRP shell lined with SS reflector foil or aluminized polyester film Cooking vessel at focal point Can generate 500 kg of steam enough to cook for 500 people 2 twice a day
Figure 12.2 Box Type solar collector
Wind Energy
Kinetic energy of wind to electrical energy Annual Energy Output = Power x Time Example: For a 100 kW turbine producing 20 kW at an average wind speed of 15 mph, the calculation would be: 100 kW x .20 (CF) = 20 kW x 8760 hours = 175,200 kWh Capacity factor is wind turbine's actual energy output for the year divided by the energy output if the machine operated at its rated power output for the entire year. Reasonable capacity factor would be 0.25 to 0.30. (0.40 will be good) Economic viability of wind power projects is extremely sensitive to the capacity factor and, there fore careful site selection is very important
Biomass Energy
Carbonaceous waste from human and natural activities Byproducts from wood industry, human and animal waste, agricultural crops, forest Main advantage is use of same equipment for combustion as fossil fuel Biomass use does not add to GHG emissions Carbon dioxide
Biogas 60% methane and 40% carbon dioxide Safe for cooking and also produce high grade manure
Biomass Briquetting
Process of densifying loose agro-waste into a solidified biomass of high density for fuel Pollution free and eco-friendly Some agricultural and forestry wastes can be briquetted after suitable treatment Can replace conventional fuels JuteStick, Sawdust, Bagasse, CoffeeSpent, Tamarind, CoffeeHusk, AlmondShell, Groundnutshells, CoirPith, BagaseePith, Barleystraw, Tobaccodust, RiceHusk, Deoiled Bran etc
Biomass gasifers
Conversion of solid Biomass (wood waste, agricultural residues etc) into a combustible gas mixture normally called producer gas. Producer gas is basically CO2, NH4,H2 and Nitrogen gas with calorific value of aroudn 1200 kCal/kg Gasification Efficiency ~ 60% Suitable for IC engines for producing power Use of gasification instead of direct burring leads to 50% savings in fuel Used along with diesel in dual firing mode in DG set (70-80% substitution possible)
Bipower
Direct-fired Cofiring Gasification Anaerobic digestion Pyrolysis Small modular.
What is Waste ?
Waste is a useful Material in wrong form in wrong place Waste can be in form of:
9
9 9 9 9 9 9 9 9 9 9
Defective product Air Emissions Waste Water Discharges Solid Wastes Hazardous Wastes Production Loss Excess Energy Excess Water consumption Inefficient use of labour Inefficient use of raw materials Unusable/Discarded Chemical Residues
Cost of Waste ?
Cost is not only disposal cost, but includes; Disposal cost Inefficient energy use cost Purchase cost of wasted raw material Production cost for the waste material Management time spent on waste material Lost revenue for what could have been a waste Potential liabilities due to waste. product instead of
Wastes Fly ash from power plant Bagasse wastes from sugar manufature
Resources Raw material for cement or brick manufacture Fuel for boiler
CO2 release from ammonia Raw material for Urea plant manufacture
SOURCE REDUCTION
PRODUCT CHANGES
- PRODUCT SUBSTITUTION - PRODUCT CONSERVATION - CHANGE IN PRODUCT COMPOSITION
SOURCE CONTROL -
RECLAMATION
- PROCESSED FOR
RESOURCE RECOVERY - PROCESSED AS A BY PRODUCT
TECHNOLOGY CHANGES
- PROCESS CHANGES
- EQUIPMENT, PIPING -OR LAYOUT CHANGES - ADDITIONAL AUTOMATION - CHANGES IN OPERATIONAL SETTINGS
- LOSS PREVENTION - WASTE STREAM SEGREGATION - MANAGEMENT PRACTICES - MATERIAL HANDLING IMPROVEMENTS - PRODUCTION SCHEDULING
Source Reduction
Good Housekeeping z Preventing leakages and spillages through routine and preventive maintenance z Good working instructions z Good supervisions z Effective training of workforce Regular cleaning of cartridge filters, inspection of tank linings & piping & periodic lubrication and greasing of pumps & blowers
PROCESS CHANGES
Input Material Change z Substitution of input materials by eco-friendly (non-toxic or less toxic than existing and renewable) material preferably having longer service time.
z Mercury
PROCESS CHANGES
Better Process Control z Modifications of the working procedures, machine-operating instructions and process record-keeping in order to run the processes at higher efficiency and with lower waste generation and emissions.
z Excess
control in boilers
PROCESS CHANGES
Equipment Modifications z Modification of existing production equipment and utilities, for instance by the addition of measuring and controlling devices, in order to run the processes at higher efficiency and lower waste and emission generation rates.
z Conversion
PROCESS CHANGES
Technology Change z Replacement of the technology, processing sequence and/or synthesis route in order to minimise waste and emission generation during production.
z Replacement
Recycling
On-site Recovery and Reuse z Reuse of wasted materials in the same process or for another useful application within the industry
z Use
Recycling
Production of Useful by-product Modification of the waste generation process in order to transform the wasted material into a material that can be reused or recycled for another application within or outside the company.
Examples
z Recover
Short fibre in pulp-making and use of etp sludge from paper board industry to make waste paper boards of press mud from sugar mill and treated spent wash from distillery to manufacture bio-compost of tanned leather pieces to make leather board or leather bags
z Use
z Use
Product Modification
Characteristics of the product can be modified to minimize the environmental impacts of its production or those of the product itself during or after its use (disposal) Jute bag instead of plastic bag Electricity or solar driven vehicles in place of petrol or diesel driven vehicles
MATERIAL PURIFICATION
z z z z z
Use of purer anodes Coal Beneficiation De-sulfurisation of fuel Un-leaded petrol Use of lime with less inerts
WASTE AUDIT
PHASE 1 PREASSESSMENT
AUDIT Step 1 Step 2 Step 3 PREPARATION Prepare and organise audit team and resources Divide process into unit operations Construct process flow diagrams linking unit operation
PROCESS INPUTS Step 4 Determine Inputs Step 5 Record water usage Step 6 Measure current levels of waste reuse/recycling
PROCESS OUTPUTS Step 7 Quantify products/by products Step 8 Account for waste water Step 9 Account for gaseous emissions Step 10 Account for off-site wastes
A MATERIAL BALANCE Assemble input and output information Derive a preliminary material balance & 14 Evaluate and refine material balance
IDENTIFY WASTE REDUCTION OPTIONS Step 15 Identify obvious waste reduction measures Step 16 Target and characterise problem wastes Step 17 Investigate the possibility of waste segregation Step 18 Identify long-term waste reduction measures
PHASE 3 SYNTHESIS
EVALUATE WASTE REDUCTION OPTIONS Step 19 Undertake environmental and economic evaluation of waste reduction options List viable options WASTE REDUCTION ACTION PLAN Step 20 Design and implement a waste reduction action action plan to achieve improved process efficiency
RAW MATERIALS
GASEOUS EMISSIONS
WASTE WATER RECYCLE REUSABLE WASTE IN ANOTHER OPERATION LIQUID WASTES FOR STORAGE AND OR OFF-SITE DISPOSAL SOLID WASTES FOR STORAGE AND OR OFF-SITE DISPOSAL
ENERGY IN VAPOURS
CONDENSATE
Carry out a Cause Analysis to locate & pin -point the causes of waste generation It could be as simple as poor house keeping practice to complex technological problems
>
Poor housekeeping
*Operational and maintenance negligence *Poor raw material quality *Poor Process / equipment design *Poor Lay-out Bad Technology
MANAGERIAL CAUSES Inadequately trained personnel Employee De-motivation
Energy Use Waste Quantity Capital Costs of new Pollution Control Systems Waste Treatment Cost Clean-up costs Rejects
IMPROVEMENTS IN
Working Conditions
INDIRECT BENEFITS
Better public image Improved Staff Motivation Improved Customer Loyalty Improved Access to capital Reduced Risk & Liability