PIPING SP3D
2.
MODIFY SITE DATABASE LOCATION Start Modify Site Database Location Site database server = jdsv003\sp3d Site database name = dslng_integtest_sdb
PIPING SP3D 3. PIPING Task Piping 4. MENU PIPING Select Route Pipe Insert Split Insert Component Insert Tap Generate Spools Create Penetration Spools Sequence Objects Group Pipe Parts 5. NEW PIPELINE All Piping (klik), Klik kanan
Klik E = 0, N = 0, El = 0
Route Pipe Run = New Pipe Run Pipeline = 031-GN-1006 Name Rule = Default Name Rule Specification = 6CA1J Nominal Diameter = 24 in Ok
PIPING SP3D
PIPING SP3D
PIPING SP3D Klik Route Pipe N, Tentative, Tarik, Length = 5000 (enter) Klik
8.
CONTINUE RUN Route Pipe Klik Tee Length = 1000 (enter) Klik
PIPING SP3D
9.
NEW PIPE RUN Route Pipe Klik Tee Muncul New Pipe Run Pipeline = 031-GN-1006, Specification = 6CA1J, Nominal Diameter = 24 in Ok Length = 1000 (enter) Klik
PIPING SP3D
PIPING SP3D Route Pipe Run = Select Graphically Klik line Id (031-24-GN-0315-6CA1J) Klik Tee Length = 1000 (enter) Klik
11
PIPING SP3D Klik Select Select Pipe (ujung) Insert Component Type = F Finish
12. TYPE INSERT COMPONENT CA = Cap FB = Blind Flange FO = Orifice Flange SB = Spectacle Blind V = Gate Valve TS = Straigh Tee TR = Tee Reducer 4L = Elbow 45 9L = Elbow 90 RC = Concentric Reducer RE = Ecentric Reducer
12
PIPING SP3D
13. CONCENTRIC REDUCER Klik Select Select Pipe Size 24(ujung) Insert Component Type = RC
Run = New Pipe Run Pipeline = 031-GN-1006, Specification = 6CA1J, Nominal Diameter = 16 in Ok Finish
13
PIPING SP3D
14. ECCENTRIC REDUCER Klik Select Select Pipe Size 24(ujung) Insert Component Type = RE
Run = New Pipe Run Pipeline = 031-GN-1006, Specification = 6CA1J, Nominal Diameter = 16 in Ok Angel = 180 Finish
14
PIPING SP3D
15
PIPING SP3D
15. INSERT COMPONENT VALVE Klik Pin Point Klik Reposition Target (F12) Klik Ujung Elbow (E = 0, N = 0, El = 0)
Klik Enter Insertion Point E = -2000 (enter) Klik Reference Position = 24 in RF 600 1 Finish
16
PIPING SP3D
16. FLANGE Klik Select Select Pipe (ujung) Insert Component Type = F Reference Position = Origin Finish
17. DELETE FLANGE DOUBLE Klik Select Select Flange Delete Flange
17
PIPING SP3D
18. WELDOLET Klik Pin Point Klik Reposition Target (F12) Klik Ujung Elbow (E = 0, N = 0, El = 0)
Run = New Pipe Run Pipeline = 031-GN-1006, Specification = 6CA1J, Nominal Diameter = 2 in Ok Klik Enter Insertion Point 18
19
PIPING SP3D
19. ORIFICE PLATE Klik Select Select Flange (ujung) Insert Component Type = Specify Component Tag Browse Instruments, Orifice Plate, IOP4, Ok
20
PIPING SP3D
21
PIPING SP3D
Properties Category = Standard Name = Orifice Plate Face to face = 10 Instrument Diameter = 600 Instrument Height = 300 Instrument Width = 50
22
PIPING SP3D
Category = Port 1 Nominal Diameter = 24 Termination Class 1 = Bolted Termination Sub Class 1 = Thru-Bolted Without Bolt Holes End Preparation = RF WAFER End Practice 1 = US Practice Rating Practice 1 = US Practice Pressure Rating = CL 600 Category = Port 2 (Sama Port 1) Ok Reference Position = Origin Finish
23
PIPING SP3D
24
PIPING SP3D
20. PIPING SPECIAL Klik Select Select Flange (ujung) Insert Component Type = Specify Component Tag Browse Piping Specialties, Custom Specialty Inline Silincer, CS Inline Silincer 4, Ok
25
PIPING SP3D
26
PIPING SP3D
Properties Category = Standard Name = STR Face 1 to Center = 300 Face 2 to Center = 300 Ok Reference position = VNoz1 Finish
27
PIPING SP3D
21. REDUCER DI TEE Insert Component Klik Tee (ujung) Muncul New Pipe Run Pipeline = 031-GN-1006, Specification = 6CA1J, Nominal Diameter = 24 in Ok
28
PIPING SP3D
29
PIPING SP3D
30
PIPING SP3D Type = Specify Component Tag Browse Instruments, Relief Valve Type 3, IRVT34 Ok
31
PIPING SP3D
32
PIPING SP3D
33
PIPING SP3D
Ok, Finish
34
PIPING SP3D 23. PRESSURE GAUGE Insert Component Klik Valve (FTE-SW) Browse Instruments, Simple Instrument Indicator, IND4, Ok
Properties Name = 021-PG-2001 Instrument Diameter = 100 Instrument Length = 100 Category = Port1 Terminator Class 1 = Male Termination Sub Class 1 = Male Ends, Threaded End Preparation 1 = Male Threded End Schedule Practice 1 = Us Practice Schedule Thickness 1 = Schedule 80S Ok Finish
35
PIPING SP3D
36
PIPING SP3D
24. POINT ELONG Point Along (Klik) Insert Component Klik Pipe Type = Tee Reference Point (Klik) Ujung Elbow (Klik) Enter Insertion Point (klik) Distance = 300 Finish
37