Beruflich Dokumente
Kultur Dokumente
Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
TABLE OF CONTENT
Content Page
TABLE OF CONTENT........................................................................................................................ 1
1. SCOPE ....................................................................................................................................... 5
2. OBJECTIVES ............................................................................................................................ 5
Page |1
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
11. SAFETY INSPECTION (PRE-MOBILIZATION & PERIODICAL SAFETY CHECK) ....... 13
19. ENVIRONMENT...................................................................................................................... 24
Page |2
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
APPENDICES
Appendix 001 Safety induction Training.................................................................................... 28
Appendix 002 Daily Safety Observation.................................................................................... 29
Appendix 003 Toolbox Meeting Record.................................................................................... 30
Appendix 004 Certificate of The Best Safety Performance – Subcontractor............................. 31
Appendix 005 Incident Investigation Report.............................................................................. 32
Appendix 006 Heavy Equipment Check List............................................................................. 36
Appendix 007 Fire Extinguisher Inspection Record.................................................................... 37
Appendix 008 Audit Sheet for Provision of Fire Extinguisher.................................................. 38
Appendix 009 Electrical Work Permit......................................................................................... 39
Appendix 010 Removal of Safety Protection Permit.................................................................. 40
Appendix 011 Hot Work Permit ................................................................................................ 41
Appendix 012 Certificate of Competence.................................................................................. 42
Appendix 013 Hazard Identification, Risk Assessment, and Control Measure.......................... 43
Appendix 014 Safety Violation Sheet........................................................................................ 44
Appendix 015 Temporary Pass Request Form........................................................................... 45
Appendix 016 ID Card Request Form........................................................................................ 46
Appendix 017 Vehicle Gate Pass Request Form........................................................................ 47
Appendix 018 Material Equipment Gate Pass............................................................................ 48
Appendix 019 Monthly Manpower Report................................................................................. 44
Appendix 020 Monthly Safety Statistics....................................................................................... 45
Appendix 021 Sling Inspection Sheet.......................................................................................... 46
Page |3
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
General Statement
Management MES-TSW JO regards health and safety at work as a matter of foremost importance and will
ensure that all reasonably practicable steps are taken for the continuing health, safety, and welfare of our
employees and any other persons who may be affected by our construction activities. Company will
allocate the resource necessary to ensure full implementation of this OHS Policy.
MES-TSW JO re-affirms project site commitment to health and safety and gives effect to the policy
through the safety management system which:
Ensures compliance with relevant statutory legislation and safety requirements.
Promotes safe working practices through regular use of the Construction Safety Manual (CSM)
Provides monthly safety statistics to measure the safety performance.
Sets health and safety objectives.
Engages the cooperation of employees at all levels through consultation, training, personal
examples, the promotion of safety awareness and regular involvement of safety department staff at
all stages of project from inception through design, planning, and execution to completion and
maintenance.
The responsibility of Project Site Management in implementing this OHS Policy is regarded by MES -
TSW JO as fundamental to the company’s main objectives of operation in an efficient and profitable
manner.
A safety manager with responsibility for health and safety is appointed by the company. He will ensure the
provision of an effective organization and arrangement for the implementation of the OHS Policy.
Responsibility of monitoring compliance with this OHS Policy rests with the Safety Manager and his
Project Safety Officer. This is accomplished by regular site inspections from the project management staff,
reports by safety supervisors, and by planned schedules of safety audits conducted by company auditors.
This OHS Policy will be reviewed annually as a minimum and will be revised as often as may be appropriate.
MES-TSW JO
Project Manager
Page |4
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
1. SCOPE
The safety precautions contained in this OHSS Plan will serve as standard reference for all
construction employees and other personnel concerned, to make the new Tanjung Jati B Coal Fired
Power Plant Expansion Project Unit 3 & 4 (2 x 6600 MW) work site as safe place as possible for all
workers during the course of the entire construction period.
2. OBJECTIVES
o Structuring the project HSE Department within the Project Organization to ensure that all
Health Safety & Environment aspects are conscientiously and actively managed.
o To organize Safety Steering Committee comprising of key supervisory staff to coordinate all
Health Safety & Environment (HSE) activities within our project in order to enhance general
safety performance.
o To develop education and training programs throughout the construction period so as to instruct
our workforce in maintaining safe and healthy working conditions.
o To implement and conduct daily toolbox meetings among the workforce aimed to prevent and
reduce accidents. The most cost-effective away of doing this is by concentrating upon human
factors.
o To discuss all incident and accident reports arising from unsafe actions, unsafe conditions, near
misses, serious and minor injuries including first aid cases.
o To promulgate site safety auditing amongst employees and subcontractors aimed at improving
safety and preventing accidents.
o To create safety awareness with all staff personnel including line supervision and
subcontractors by promoting group discussion and problem solving sessions on all issues
pertaining to improved safety, efficiency and relationship.
MES-TSW JO shall strive to complete his work with a zero fatality record. Safety will be an issue in
every meeting on all levels. In taking steps to ensure a safe working environment, MES-TSW JO
Management and Subcontractors shall aim to/for:
a. No Fatality
b. Reducing Lost Time Incident (LTI) and accidents. The rationale behind this is that all accidents
are preventable.
c. Provide a safe working environment so that all employees, staff personnel and subcontractors
are adequately protected.
Page |5
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
4. RESTRICTED AREA
o The area within the boundaries of the Tanjung Jati –B- Expansion Project MES-TSW JO Project
Construction Work site is classified as a “RESTRICTED AREA”.
o All visitors, newly recruited employees and workers are required to report to the Security
Department at the gate entrance for security check prior to entry into the project / construction
office or the restricted area.
o The construction site and the entire restricted area is classify as “HARD HAT AREA”.
o Wearing of appropriate personal protective equipment (PPE) such as helmet, protective footwear,
safety belt and protective eye goggle are mandatory and also a standard safety procedure when a
person is exposed to any risk or hazard within the construction surroundings.
o During the construction period, commissioning or handing over of site facility, no one shall enter
any part of the CLIENT’S PREMISES or PLANT FACILITY including the work site, other than
for the purpose of carrying out the work. All personnel needing access to the restricted area will
be required to obtain a Special Security Pass issued by Project Management and to show it, if
requested.
5. IDENTIFICATION OF PERSONNEL
o All employees engaged at the project construction site must wear identification name badge.
o For employees of Subcontractors, Identification badges will indicate the names of employees
and the subcontractor’s company they belong to.
o Identification badges will be given to all employees by MES-TSW JO when they have
completed safety induction training.
o All personnel employed and working on the Project construction site are required to submit three
(3) copies KTP size photographs to MES-TSW JO for processing of identification badge.
MES-TSW JO Project Management shall ensure that at any times during the performance of the
work, its personnel are neither under the influence of nor partake of any alcoholic liquor, drugs or
other intoxicating substances, other than for bona fide medical reasons. Anyone found under the
influence of alcoholic, drugs or other intoxicating substances will be removed from site.
Chief
PM/SGM
Chief
Chief of Emergency Response Team shall be responsible for the whole process of emergency
activities including trainings for the team, simulation, and drill. Chief of Emergency Response
Team shall lead the team in coping with the emergency situation. Chief of Emergency
Response shall take decision to call for help from fire department, help from hospital, or help
from police station. Chief of Emergency Response Team shall make reports of emergency
situations.
Evacuation Group
Evacuation Group shall arrange evacuation process and guide people to the assembly point.
Evacuation Group shall coordinate with First Aid Group to evacuate injured people.
Evacuation Group shall try to cope with the emergency situation and coordinate with chief to
call for help from related department. Evacuation Group should try to save assets. Evacuation
Group should inventory assets and its defects.
Page |8
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
8.4 Emergency Response Plan
Emergency Response Team shall establish operation method and job description for the team.
Emergency Response Team shall identify the needs of equipments and facilities. Project
Management shall ensure all employees, staff, and management fully aware of emergency
response through conducting sufficient communication and trainings regularly. Emergency
Response Team shall establish schedule of inspection of emergency response readiness,
schedule of training and re-assessment of emergency response readiness, reporting the
readiness of emergency response. Emergency Response Team shall ensure the provision of
sufficient emergency telephone numbers and address as follows: policlinic, hospital, fire
department, police station, electricity department, and rescue department.
Page |9
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Co-ordinate all supporting activities such as induction courses, safety training, toolbox
meeting, weekly safety meeting instruction to the contractor’s supervisors and foreman in
scheduling daily toolbox meeting.
Approve the use of all safety equipment in accordance with proper industrial standards and
subsequence purchase and maintenance.
Ensure that all workers are properly trained and briefed by their supervisors on the hazards
pertaining to their respective work assignments and assure that necessary precautionary
measures are taken to avoid injuries.
Insure that daily tool box meeting are being conducted .and attention is given to younger,
newly engaged, or illiterate workers. Ensure that the workforces are properly informed of
possible work hazards and the precautionary measures to be implemented and inspected by
the supervisor.
Conduct, investigate and report all incidents and accidents with the accident investigation
team.
Inspecting the construction area daily and as often as possible and identify appropriate
corrective actions on any unsafe acts & practices. Prepare daily inspection reports and
submit audit reports to the Construction Manager so that the necessary corrective measures
will be implemented.
Approve and maintain all first aid supplies and medical equipment.
Inspect and approved equipment such as scaffolding, lifting gears, power tools, welding
sets etc. Implement a tagging system to identify both useable and unfit installations and
equipment.
Maintain and update the site Emergency and Casualty Plan with the Safety Manager.
Organize regular safety drills.
Keep and maintain all safety performance (man-hours) records including an incident /
accident logbook.
Attend to all Safety related matters.
P a g e | 10
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Only assign qualified and competent supervisors and workers who are suited by their age,
physique, state of health and skill.
Ensure the instruction and notices should as far as practicable be in the language of the
workers employed, being Bahasa Indonesia and/or English.
Make available at the site office, for the use of workers, copies, drawings, or summaries of
national or local regulations and where appropriate, instruction and notices relating to
protection against accidents and injuries to health, or post such texts up in prominent
positions at suitable places.
In case emergency situation, he will take the leadership of emergency and evacuation
operations and adhere to the Emergency and Evacuation Plan in as much as is practicable.
Ensure that regular safety drills, such as personal transfer over water and man overboard
drill, man down due to fall etc., are being conducted at suitable intervals to test and enhance
the medical evacuation operation.
Do not permit machines, equipment or workplaces in which dangerous defects have been
found to be utilized until the said defect had been remedied or corrective action taken.
Adjust or coordinate construction work, based on the detailed work planning and schedules
taking into account a risk analysis, as well as safety factors, particularly during adverse
weather and rough sea conditions for offshore work.
Take immediate corrective actions when so requested by the client.
9.5 Subcontractors
Subcontractors shall inform MES-TSW JO names of their employees and obtain MES-
TSW JO Project Management approval prior to their assignment.
Subcontractors shall ensure that their employees be informed of, and have the opportunity
to participate in, the safety activities required by MES-TSW JO and which subcontractors
are obliged to initiate in pursuant to the contract.
Subcontractors shall take active steps in the implementation of site safety regulations, as
well as work procedures which are identical to those required from MES-TSW JO. The
project Safety Department shall regularly check the subcontractors to ensure compliance
with safety requirements.
P a g e | 11
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
MES-TSW JO Project Management may refuse access to its work site to any of
subcontractor’s personnel who, in its opinion, do not comply with MES-TSW JO working
standards for safe and good workmanship, for reason of poor work attitude, lack of co-
operation, lack of skill or insufficient training and experience; any or all of which that
might jeopardize safety discipline or pose a safety risk to them and others.
P a g e | 12
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
a. Before starting the work for the first time (Medical checkup before starting the job
emphasize to physical and individual health)
b. Periodically depending on the risks of the tasks.
Data of medical checkup shall be recorded and documented for reference.
Emergency response and first aid plan shall be prepared involving all related local
components as first aid officers, equipments, means of communication, and traffic rout.
First aid in occurrence of accident or illness shall be carried out by doctor, nurse, or
competent person trained in first aid.
Adequate first aid equipments and first aid kits shall be provided in the premises with
condition of free from dust and in an appropriate humidity, etc. First aid kit shall contain,
but not limited to, adhesive bandages, gauze pads, large-triangular bandages, sold pack,
iodine antiseptic, eye lotion, medicine, scissors and cotton clip, etc. Contains of first aid kits
shall be checked regularly so that they remain complete, first aid kits shall not be empty.
If employees designated in areas where hazards of drowning or poisonous gases considered
present, means of rescue shall be located close to their work areas.
Quick response shall be well prepared to evacuate ill or injury employees to the nearest
hospital.
o Prior to commencement of work, all construction equipment shall be checked to ensure their
safety, reliability and in safe operation condition.
o A monthly maintenance plan or inspection schedule shall be implemented to assist the smooth
execution of the work.
12.1 General
Project Management shall provide and operate its equipments in compliance with the company
safety requirements or Local Legislative Safety Pertaining (Building Operation and Works of
Engineering Construction (Regulation) 1985.
P a g e | 13
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
equipment shall be operated where there is danger that it may contact high-voltages lines.
Equipment shall not be oiled while it on operation and shall not be refueled while the
engine running. Employee shall not get "ON" or "OFF" moving equipment.
Subcontractors will be employed at least one week prior to the commencement of the project
construction work. They must submit a copy of a total work plan to MES-TSW JO Project
Management for review and approval. The WORK PLAN should include:
List of personnel to be engaged in the Work
Organogram including safety organization chart, indicating names of supervisory staff and
foreman and number of personnel to be mobilized.
Entire work schedule and / or work procedure
Manpower and equipment mobilization charts.
List of safety protective equipment to be supplied for each job profession.
Chairman
Site General Manager
Secretary
Safety Manager
P a g e | 14
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Responsibility of Chairman:
a. Chairman shall plan, develop, review, and implement health and safety programs,
procedures and standards.
b. Chairman shall ensure provision and maintenance of safe plants, equipments, and
workplaces.
c. Chairman shall ensure that employees, subcontractors, visitors, and public members
on premises under control of the company.
d. Chairman shall ensure safe working practices at all times and in accordance with
relevant statutory regulations, codes of practices, guidance note, or other recognized
advice on safe working procedures.
e. Chairman shall provide for and ensure that employees at all levels receive adequate
training and instruction to enable them to carry out their duties in a competent and
safe manner.
f. Chairman shall create safety culture and safety awareness by promoting safety
meeting and talks, encouraging safety training, enforcing reward and punishment.
g. Chairman shall review reports of inspections, accident investigation includes the
near-misses, unsafe conditions and acts, etc. and make final recommendations.
h. Chairman shall set a personal example on the premises by performing safety
behavior and wearing appropriate PPE at all times.
P a g e | 15
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
15.2 Illumination
Illumination is need of lights in work area to carry out activities effectively. In case of natural
illumination is not adequate, appropriate artificial illumination shall be provided in the whole
area including all passage-ways. Means of illumination shall be safely fixed and able to
provide adequate illumination, and shall be maintained by competent persons to ensure no
occurrence of hazards related to those means. Natural or artificial illumination shall be
arranged effectively to avoid dazzling lights.
15.3 Ventilation
Adequate ventilation for fresh air circulation shall be provided in closed work-area. If
necessary to prevent health hazard due to dust and gases contaminated air, exhaust fan shall be
provided. In case of elimination of hazardous dust and gas is technically impracticable,
employees shall be equipped with appropriate Personal Protective Equipment (PPE) to prevent
hazardous gas penetrating their respiratory system.
15.4 Housekeeping
Waste and unused materials shall be moved to a safe particular place. All protruding nails shall
be removed or bent to prevent accident as punctured by nail. Small materials and equipments
shall not be scattered on the floor to prevent slipping and tripping hazards. Waste of materials,
rubbish, and equipments shall not be accumulated in work area. Work areas and passage-ways
that slippery due to oil spillage shall be immediately cleaned or poured by sands. Easily
moveable tools and equipments shall be returned to storage after being used.
P a g e | 17
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Flammable Materials
Flammable materials as sawdust, oily clothes, and unused pieces of wood shall not be
accumulated on work area. Overall uniform sprayed with oil shall not be kept in a closed area.
Chemical materials that reactive to water shall be kept dry. Inside building, waste of oil shall
be placed in closed-cans. No smoking and no naked flame close to flammable materials.
Flammable Liquid
Flammable liquid shall be stored, transported, and used in a particular safe way to avoid
occurrence of fire. Fuel for heating-appliances shall not be stored inside building or equipment,
except stored inside fire-proof designed can or equipment. Fuel shall not be stored close to
doors and exit way.
P a g e | 18
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Elevated Work-Area
Work-area which is more than two meters high above the floor shall be completed with safety
railings. Elevated work-area shall be completed with particular access as ladder. If necessary
to avoid hazard of working in elevated place more than 2 meter, use full body harness.
15.10 Toilet
Toilet is sanitary facility covering bath room, WC, and wash basin to be used by employees
during work-time. Toilet for ladies shall be separate from toilet for gents. Toilet shall be
cleaned by house-keeper regularly. Toilet shall be free from insects and rats. Water used in
the toilet shall be clean and appropriate with toilet needs.
15.12 Scaffolding
All scaffolds shall be erected or dismantled by competent person. All scaffoldings or
temporary floors materials shall meet the requirements in strength and rigidity.
Scaffoldings or working platforms shall be securely fastened to the building or structure.
All runways, scaffolds, or other working surface more than two meters high above an
adjoining surface shall be effectively guarded with strong railings. Such railings shall be
P a g e | 19
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
minimum one meter high.
Suspended scaffolds shall have railings, intermediate railings and toe boards. Scaffoldings
shall not be used for the storage of materials. Lifting heavy materials shall not be carried
out from ladders of scaffoldings. Scaffoldings shall not be overloaded beyond their
working capacity.
Workers assigned to work in the scaffoldings or temporary floors shall wear safety
harness with lanyards anchored to lifelines. Life-lines shall be in sufficient length to allow
workers moving freely in commencing their works.
Scaffoldings shall be inspected regularly. Scaffoldings and platforms erected by sub-
contractors shall be carefully inspected and certified before used. Supports or braces of
scaffoldings shall not be removed until the works completed.
Workers shall not jump to or from scaffoldings, drop heavy materials from scaffoldings,
throw objects from or to scaffoldings. Workers shall not carry out any tasks during high
wind with speed of 50km/hour.
A safe means of access to the scaffold, either by stair or permanent ladder shall be
provided.
15.13 Ladder
Ladders used shall be in accordance with standards. In placing a ladder, the distance from
foot of ladder to building against which it is leaning shall be approximately one-fourth of
the length of the ladder. In other words, if a 12-feet ladder shall be placed, the foot shall
be three feet away from the building. Ladders with weak rungs shall not be used. Ladder
shall not be placed in front of door without first locking the door or designating a
watchman. Stepladder shall be fully spread before used.
Workers shall grip side rails while using ladder. If it is not practical to grip side rails,
workers shall grip rungs securely with both hands while descending or ascending.
Workers shall not work on a high ladder during wind with speed of 50 km/hour. Workers
shall not carry any tools in both hands when climbing or descending. Workers shall face
ladder when climbing or descending and keep eyes on rungs while climbing, there might
be broken rungs. Workers shall ensure their shoes cleaned and not slippery before
climbing or descending. Workers shall not lean too far to one side of ladder.
Ladder shall not be loaded by more than one person at one time. Ladders shall not be
placed against window glass nor leaned against unsteady backings such as loose boxes or
barrels.
P a g e | 20
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
from hoist way, and floor openings. Stairways, passageways, gangways, and access ways
shall be free from materials, supplies and obstructions at all times.
Storage yards shall be free from unusable combustible materials. Sources of ignition shall
be prohibited in areas where flammable liquids are stored, handled and processed. Suitable
warning and "NO SMOKING" signs shall be posted in all such areas. Rubbish or other
combustible materials shall be kept from areas where flammable and combustible
materials are stored, handled or processed. Spillage of flammable and combustible liquids
shall be cleaned up immediately. Accumulation of combustible and flammable liquids on
floors, walls, etc. is prohibited.
15.16 Painting
Paint soaked rags shall not be left in lockers or in coverall pockets. They shall be spread
out to dry or put into metal containers. Paint in which turpentine has been used as thinner
shall not be used on hot surfaces. This might cause vapors to ignite or the fumes emitted
might suffocate workers.
Spray hose shall be securely fastened to a scaffold so it shall not become loose and hit or
drag a man off.
Adequate ventilation to prevent the accumulation of flammable vapors to hazardous levels
of concentration shall be provided in all areas where painting is done or paints are mixed.
No smoking, open flame, exposed heating elements, or other sources of ignition of any
kind shall be permitted in area or rooms where spray painting is done.
Workers shall clean their skin thoroughly of any coating materials. Do not use thinners to
remove paint from hands or skin. Use only recommended creams and cleaners.
P a g e | 21
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Electrical installation and all electrical equipment shall be periodically inspected and
tested by the authorized persons to assure continued satisfactory performance and to detect
deficiencies. The power supply source shall be disconnected before repairs or services are
performed on power tools. Electrical tools and equipment shall be adequately earthed
Authorized personnel shall be allowed to perform all electrical works. Reparation of
electrical equipments shall be carried out by authorized personnel.
Portable electrics tools and extension leads shall be fitted with proper plugs and sockets
and shall not be connected by inserting bare wires into the sockets. Electric leads shall be
preferable hung in safe positions, not lying on the ground, and especially not in wet area.
15.21 Excavation
Safety barriers shall be installed around excavation to prevent entry of unauthorized
person. Safety signpost warning deep excavation shall be placed around excavation where
it can be easily seen. Heavy vehicle shall not pass near edge of excavation as it may cause
collapse of edge and vehicle. Employee shall wear appropriate PPE for working inside
excavation.
Safe access to excavation shall be provided for employees prior to commencing any work
in the excavation. Material shall not be stacked on the edge of excavation as it may slide
into excavation and causing damage to material and harm to employee. Material shall be
P a g e | 22
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
stacked with safe distance from edge of excavation as engineer recommendation.
Sufficient Illumination shall be provided for the excavation. Means of pumping water out
of excavation when necessary is to be provided.
o Any work involving ionizing radiation shall be executed as much as possible outside normal
working hours.
o A component radiation protection advisor and radiation protection supervisor must be appointed
and procedures established to comply with statutory regulation and be at least as stringent as the
guide lines set out in the Ionizing Radiation Safety Guide. The following points are noted :
a. All activities involving ionizing radiation shall be conducted, by a minimum of two
persons.
b. Qualified / classified persons, authorized by the contractor.
c. Personnel executing activities shall carry calibrated, personnel radiation metering devices
at all times (which must be worn in the correct position).
d. The work area shall be protected against unauthorized entry by adequate barriers or roped-
off by plastic tape including warning signs prior to starting work. Safe distance to be
specified.
e. Radiation matter evaluation and calibration intervals to be specified and recorded. Record
shall be available on site.
f. No radio-active material shall be left unattended unless stored in a designated, fit for
purpose storage.
g. Storage area shall be equipped with relevant warning signs and shall be locked to reduce
the risk of unauthorized access.
h. Established emergency response procedures to handle such events as damaged source
containers and fires in the storage area.
P a g e | 23
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
All life jackets shall be designed to turn and support a floating unconscious wearer face up.
If there is a danger that the employee could be swept away by currents or may not be seen
(if working at night) then the life jackets must be equipped with a whistle and a water
activated light.
Employee shall be given instruction on the use of life jackets, rescue equipment and all
related procedures.
All personnel shall work in pairs or more and be counted frequently.
All equipment is to be checked on a regular basis.
A man overboard or man in the water exercise should be undertaken prior to work
starting.
o A confined space is an enclosed working place which has restricted access and inadequate natural
ventilation. Typical confined spaces are barge manholes of water ballast tanks, sewers, shafts,
funnels & cellars.
o The three main hazards are suffocation (due to lack of oxygen), fire and explosion (flammable
gases) and poisoning (overcome by toxic gases).
o Entering a confined space will only be allowed when safety procedures are being followed in line
with the “Entry into confined Spaces” safety procedure.
o Employees designated to work in confined space shall fully understand the emergency response
procedure in emergency situation.
o Employee shall not work alone in confine space. There shall be one partner designated as
watchman outside confined space who will act immediately in emergency situation exposing
employee working inside confined space.
o Confined space shall be free from fumes, oil, gases, and flammable materials.
o Confined space temperature shall be control by any means to obtain acceptable temperature for
human body
19. ENVIRONMENT
o MES-TSW JO and subcontractors shall pay due regard to the environment by preserving air,
water, soil and plant life from adverse effect of the construction activities, and minimize any
nuisance which may arise from such operations.
o Spillage of oil or chemicals shall be avoided by containment around tanks and other practical
methods, however should spillage occur it must be cleaned up immediately in view of the hazards
from fire, slippery surfaces, toxic substances, etc.
P a g e | 24
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
o Appropriate safety precautions shall be taken during the clearing up operation.
o HSE Department will be the focal point for waste control and monitoring. They will advise the
relevant departments of the approved waste disposal methods and shall keep a record of all
inventories of waste and their movements.
o Dense waste is all disposed materials in dense form included disposable from industrial activities.
o All parties generating waste must inform HSE department of their waste inventories at the end of
each week.
o Store, transportation, an annihilation of domestic waste shall comply with local legislation.
o All hazardous materials and waste generated must be properly sorted, treated if necessary, and
disposed of following the GOI regulations on B3 waste.
o Before B3 waste can be removed or disposed of, the waste transporter must fill in the waste
disposal application form and submit to HSE department for clearance approval.
o The contractor transporters should be licensed. They should understand and be trained on waste
handling safety and disposal procedures.
o All non-toxic and non-hazardous waste including domestic waste must be dumped at approved
local dumping grounds with permission from the local authorities.
o All toxic waste generated shall not be dumped into the drainage system.
o All toxic waste shall be neutralized where possible and stored in secure steel drums marked
“POISON, KEEP OFF” and moved to a safe and secured location for disposal later following
approved methods.
22.1 General
MES – TSW JO Project Management shall ensure provision of qualified PPE and effective
use PPE. Personal Protective Equipment (PPE) is means used by employee to protect a whole
or parts of human body from potential hazards or work-related accident. Use of PPE is the
last effort of hierarchy in controlling hazards after elimination, substitution, engineering
control, and administrative control.
P a g e | 27
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 001
I have attended Safety Induction Training and received information related to:
Tubanan, Date……………………………………..
Acknowledged by,
P a g e | 28
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 002
Name : Date :
Trade : Signature :
Acknowledged by,
…………………………..
Safety Manager
P a g e | 29
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 003
Topic Date
Location Conducted By
ATTENDANCE
1. 23.
2. 24.
3. 25.
4. 26.
5. 27.
6. 28.
7. 29.
8. 30.
9. 31.
10. 32.
11. 33.
12. 34.
13. 35.
14. 36.
15. 37.
16. 38.
17. 39.
18. 40.
19. 41.
20. 42.
21. 43.
22. 44.
P a g e | 30
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 004
SAFETY COMMITTEE
MES – TSW JOINT OPERATION
To Certify
………………………………
As
The Best Safety Performance – Subcontractor
(Periode of …………….…..)
We Thank You for The Outstanding Contribution in Promoting Health and Safety Culture in
Tanjung Jati B Expansion Coal Fired Power Station Project Unit 3 & 4
Jepara,……….,
…………...
…
…………………………
Committee Chairman
P a g e | 31
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 005
1.
2.
3.
4.
5.
INCIDENT DETAILS
DATE/TIME OF OCCURENCE
LOCATION
WEATHER CONDITIONS
□ Work related Shift worked From: From :
□ Day □ Night Shift hours Overtime
To : To :
□ Journey/Work travel related
□ Injury occurred
□ Property damaged □ Near Miss
(Complete Form A-details of injured person)
Fist aid □ Hospitalized □ Fatality □
NOTIFICATIONS
OFF SITE NOTIFICATIONS DATE / TIME HOW
Head Office
Main Contractor
Labor Department
Police
Fire Department
Hospital
Others
P a g e | 32
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Incident Description
Where did the incident
happen?
What was the task?
Description of incident
Detail of injuries/damage
P a g e | 33
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
ROOT CAUSES OF INCIDENT/HAZARD/NEAR MISS (Review the lists below and tick those that are thought to have contributed to the cause of incident)
Poor Lighting Fatigue/ Stress Ambient conditions (wind, Hazardous work method
dust, rain etc) specified
Excessive Noise Physical/disability affecting Excessive Noise Lack of supervision
performance
Difficulty in Operating Culpable Act Terrain Provision of correct safety
(tools, equipment, etc) equipment or clothing
Manual Handling Skylarking or misconduct Temperatures Inadequate training provided
Congested / bad work area Possible personal problem Poor Housekeeping Poor Housekeeping Standard
Hazardous machine, tool or Inexperience in task being Building surface conditions Poorly maintained equipment
equipment performed (stairs, floors)
Malfunction or defect in Failure to use safety clothing Storage/ stacking of material Suitable plant/equipment
machine, equipment unavailable
Unsuitable safety clothing Hazardous work method used Exposure or contact chemicals Inadequate or no documented
or equipment or other harmful material procedures
Difficult to maintain Possible influence of alcohol or Exposure to infectious sickness/ Insufficient inadequate
drugs disease instruction or information
Inadequate guarding or Act or omission of another Visibility Production pressure
protection person
Reported by,
Acknowledged by,
EMS SM …………………………………………………………………… Sign ………………... Date …………………………………………..
FORM A
P a g e | 34
Incident Investigation Report
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
INJURY DETAILS
Body Part Injured
Head/Neck Arms Hands Back Chest
Abdomen Feet Legs Skin Eyes
Internal Organs Others
Type of Injury
Amputation Concussion Fracture Crush Burn
Sprain/Strain Bruising Abrasion Laceration Dermatitis
Exposure Other
Mechanism of Injury
Knocked Chemicals Electricity Flying object Manual Handling
Falling object Vehicles Drowned Tools Knife
Trip/Slip/Fall Machinery Other Moving object
PROTECTIVE CLOTHING & EQUIPMENT (What Protective Clothing and Equipment was being worn at the time of incident/hazard/near miss?)
Safety Glasses Safety Shoes Goggles Gloves Overalls
DAMAGE CLASSIFICATIONS
Initial Treatment Work consequences Work consequences Work consequences
Initial Prognosis - immediate - after 24 hours - after 3 days
First aid Return to pre-injury duties Return to pre-injury duties Return to pre-injury duties
Hospitalized Restricted duties Restricted duties Restricted duties
Fatality Off work Off work Off work
Additional Note:
P a g e | 35
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 006
Type :
Serial No :
Equipment / Machinery :
Operator's Name : Date :
Signature :
NO. ITEMS CHECK REMARK
OK NO
1 Engine Oil
2 Water Cooling
3 Fuel Tank
4 Transmission Oil
5 Hydraulic Oil
6 Brakes System Brake Fluid
Brake Cup
Brake Disk
Hose Brake Systems
Master Brake Systems
Handle Brake Systems
7 Lifting Systems Lifting Disk
Master Lifting Systems
Hose Lifting Systems
Handle Lifting Systems
8 Sling Systems
9 Crawler System Gear Crawler
Crawler Joint
10 Steering Systems
11 Clutch System Clutch Handles
Clutch fluids
Clutch hoses
12 Battery
13 Light Front Light
Signal Light
Cabin Light
Brakes Light
14 Body and Chassis Bolt Tightness
15 Gantry
16 Stay & Stay Cylinder
17 Suspension System
18 Boom
19 Fuse System
20 Alarm & Reverse Light
21 Glass/Mirror
22 Fire Extinguisher
23 Horn
24 Guy Line
25 Adapter
26 Leader Support
27 Counterweight
28 Outrigger
P a g e | 36
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 007
P a g e | 37
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 008
List of question
5. Inspection Record
- Is there any prove of monthly inspection for fire extinguisher? Yes / No
- Is the inspection of fire extinguisher carried out regularly? Yes / No
Comment: ………………………………………………………………………………………………….
..………….…………………………………………………..……………………………….
6. Expire Date
- Is there any tag showing “expire date” on fire extinguisher? Yes / No
- Is the fire extinguisher still valid? Yes / No
Comment: ………………………………………………………………………………………………….
..………….………………………………………………………………………………….
P a g e | 38
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 009
_________________ __________________
Sub-con / Supervisor Safety Department
P a g e | 39
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 010
Section 1
Slab opening cover Toe board
Safety railings / posts Warning Tape
Safety life line Catch plat form
Safety net / catch net Over head protection
Location: _______________________________________________________________________
Sub-con/supervisor: _______________________________________________________________
Section 2
I agreed on behalf of subcontractor/supervisor that all above safety requirements have been provided /
examined, and that any removal of safety barriers will be re-installed immediately after the work.
____________________ ___________________
Sub-con / Supervisor Safety Department
P a g e | 40
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 011
A. PERMIT NUMBER :
B. DATE :
C. WORK DESCRIPTION :
D. LOCATION :
(use attached sketch if necessary)
E. VALIDITY From: To:
F. SAFETY PRECAUTIONS
No. Precautions Yes No. Remark
1 The adjacent areas has been clear of flammable / combustible materials (at least 5 m
distance)
3 Suitable fire extinguishers are available at the point of work (one fire extinguisher for one
point).
4 The fire watch person has been briefed on the hazard of work
5 The water hose in the area has been checked and the system is charged (if not, see point 3)
6 Welding gas / LPG cylinders are in vertical position, secured on trolley, and fitted with
regulator and flash back arrestor
7 The working area is well ventilated or exhaust ventilation has been used for suitable
amount of time
8 Suitable PPE: Eye protection (welding mask), clean flame retardant clothing, welders apron,
welding blanket, welding gloves are provided and used
Requested By,
Approved By,
P a g e | 41
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 012
CERTIFICATE OF COMPETENCE
(…………………….OPERATOR)
Eyesight, Hearing, And Distance Judgment Acceptable / Medical Certificate Attached : Yes/No
On Site Test With Banks-man Carried Out Satisfactorily Using Instruction In English : Yes/No
I Have accessed the ability of Mr. ………………… to operate …………………………………. and found him competent.
P a g e | 42
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 013
Activity :
Job/Task People At Risk Hazard Adverse Effect Likeli-hood Severity RFN Control Residual Risk Assessment PIC
Identified Measure
A B C D E F G=EXF H I J K
P a g e | 43
MES - TSW OCCUPATIONAL Project : TJB Exp. Project #3&4
JOINT OPERATION HEALTH & SAFETY PLAN Doc. Ref : DM-TJST-SSP-001
Date : 11 / Feb / 2009
Rev. : -1-
Appendix 014
2.
3.
Note:
A – Minor safety violation
B – Disobey safety orders / instructions posted at working area / or understood by the workers that resulted to a dangerous
occurrence.
C – Gross Negligence that resulted to serious injuries to persons or damage to properties.
Gravity of Offence First Time Second Time Third Time Fourth Time Fifth Time
A 1 day wage fine 2 days wage fine 3 days wage fine 5 days wage fine Dismissal
(See Note)
B 5 days wage fine 5 days wage fine 5 days wage fine 5 days wage fine Dismissal
(See Note)
C 5 days wage fine Dismissal
(See Note)
Acknowledged By,
Safety Manger
P a g e | 44