Sie sind auf Seite 1von 132

UPGRADING AL SALAM STREET AND

ABU DHABI CITY RING ROAD CONTRACT NO.1


(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

BASELINE
PROGRAMME
Rev.0

27th August 2008

SAMSUNG-SAIF BIN DARWISH


JOINT VENTURE

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 1
Planning Documents
A1-1. Narratives for Baseline Programme Rev.0
A1-2. Method Statement and Work Sequences
(No.5 Submitted on 15th.July.2008)
A1-3. SSBD JVs Amendments for
Parsons comments
A1-4. Sign-off of Participated Subcontractors

SAMSUNG-SAIF BIN DARWISH JV

-1-

A1-1. Narrative for Baseline Rev.0


Upgrading Al Salam Street and Abu Dhabi City Ring Road
Contract Number (1) Al Salam Street Tunnel

August 27, 2008


Samsung-Saif Bin Darwish Joint Venture

Contents

1. Project Overview
2. Detouring Plan
3. Construction Plan

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.1. Project Description
Project Name
Employer
Consultant
Period
Contract Type

Upgrading Al Salam Street and Abu Dhabi City Ring Road Contract (1)
Al Salam Street Tunnel
Abu Dhabi Municipality
Parsons International Ltd
900 Days (15 May 2008 ~ 31 Oct 2010)
Re-measurement
Construction of Tunnels and Others (Temporary Works Design incld)

Work Scope

Box Tunnel
2,400 m
U-Type Depressed Tunnel
1,000 m
Approach Road
200 m
Utility Diversion
(Water, Electricity, Storm Water, Sewer, Irrigation, Telecom etc.)

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.2. Structure Layout

START

END

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.3. Work Volume Summary (Civil Works)
Item

Description

Quantity

Type-A

t650mm D-Wall (Cantilevered)

320 lm

Type-B

t650mm D-Wall (1 Layer of G.A)

5,800 lm

Type-C

t800mm D-Wall (1 Layer of H.S)

1,150 lm

Dewatering

Deep Well (350~600mm, L=18m)

360 nos.

Excavation

Backhoe, Dozer, Ripper

1,925,000 m3

Bored Pile

Tension Pile

Belled Tension Pile, K500

1,739 nos.

Concrete

K250, K415

492,000 m3

Rebar

50,000 ton

PC-Girder & Beam

AASHTO

1,979 nos.

Temporary Retaining Wall

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.3. Work Volume Summary (E&M Works)
Item

Description

Quantity

FAN

Axial Flow Fans(120~150KW)

28 Nos

DUCT

Ventilation Duct in Tunnel

Fire pump

Electric Fire Pump & Controller

Pipe

Fire system pipe

Transformer

1500KVA

Panel

SWGR:6, LV:91, TR:8, Lighting:14

Lighting

Load:223 Nos, Tunnel:4,665 Nos

4,888 Nos

Cable

11KV:1,000m, FR:84,000m

314,990 m

Cable

Video:15,000m, Control:30,000m

54,000 m

VMS

Approach:10, Tunnel:20

30 Nos

Video Wall 4x4, PLC, UPS, ETC

1 Nos

HVAC
50,000 sm
6 Nos

Fire Fighting System


7,330 m
8 Nos
131 Nos

Power & Lighting

Traffic Control System


SCADA

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.3. Work Volume Summary (Utilities Works)
New (m)

Description
Network
Water Works

Trench

Remove

NDRC

7,615

6,775

134,763

3,465

Irrigation Works

5,320

5,320

13,280

33 Kv Cable

1,350

1,350

850

11 Kv Cable

29,000

29,000

9,000

Lv Cable

5,100

5,100

2,100

132 Kv Cable

14,550

4,850

4,850

Sewer

4,263

4,263

650

2,800

1,055

SUM

201,961

60,123

1,537

3,300

105,915

Telecom Works

Samsung Saif Bin Darwish JV

Remarks

Retaining

887

5,335
500

69,445

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.4. Typical Cross
-Sectional Drawings
Cross-Sectional
1.4.1. Type A : Excavation Depth < 5m

Preliminary
Concept
Secant/D-Wall
d=18m

Samsung Saif Bin Darwish JV

Developed
Design
Diaphragm Wall
t=650mm, d=18m

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.4. Typical Cross
-Sectional Drawings
Cross-Sectional
1.4.2. Type B : Building Offset > 15m

Preliminary
Concept

Developed
Design

Secant/D-Wall
d=18m
Ground Anchor

Diaphragm Wall
t=650mm, d=18m
Ground Anchor
l=17m

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

1. Project Overview
1.4. Typical Cross
-Sectional Drawings
Cross-Sectional
1.4.3. Type C : Building Offset < 15m

Preliminary
Concept

Developed
Design

Secant/D-Wall
d=20m
Rock Anchor

Diaphragm Wall
t=800mm, d=20m
Horizontal Strut

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

2. Detouring Plans
2.1. Master Plan of Detour Road

Detour Road A3
Tunnel Construction
Decking Area

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

TENDER

Temporary pavement condition


Utility investigation with relocation

STAGE 1

Traffic flow

St. No.2
St. No.4
St. No.5

St. No.7

St. No.9

St. No.11

St. No.13

IP:36A

IP:12
IP:9

IP:11

IP:36

IP:11A

PROPOSAL

Temporary pavement condition


Utility investigation with relocation

STAGE 1A

Traffic flow

St. No.2
St. No.4
St. No.5

St. No.7

St. No.9

St. No.13

IP:36A

IP:12
IP:9

Samsung Saif Bin Darwish JV

St. No.11

IP:11

IP:11A

IP:36

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.1. Work Section Plan

A.P.
Un
it 1

Section 1

Descriptions

Locations

Length (m)

Units

Section-1

Approach ~ IP 12

956

34 units

Section-2

IP 12 ~ IP 11

846

30 units

Section-3

IP 11 ~ IP 36A

750

25 units

Section-4

IP 36A ~ L.O.C

821

28 units

(st
)~
r.1
it 2
Un
r
(st

Section 2

Section 3

Section 4

L.O.C

.2)

Unit 3 (str.2) ~ Unit 9 (str.3)

Samsung Saif Bin Darwish JV

Unit 10 (str.3) ~ Unit 34 (str.3)

Unit 35 (str.3) ~ Unit 62 (str.3)

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.2 Diaphragm Wall Construction
Diaphragm Wall: t650mm, d=18m for building offset>15m
t800mm, d=20m for building offset<15m
Main Equipment

Capacity

Main Cutter Crane

80~100 ton

Trench Cutter

650~800 mm

Service Crane

50~150 ton

Excavator

0.8 m3

Desander

600 m3/hr

Bentonite Mixer

1.5 m3

Generator

125, 500 kVA

Pump

2~6 inch

Big Silo

172 m3

Bentonite Silo

45 m3

Welding Machine

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.3 Excavation & Support
Earth Anchor (L=17m) for building offset > 15m
Horizontal Strut (L50m) for building offset < 15m
Main Equipment

Capacity

Dozer

D8, D9

Wheel Loader

2.4 m3, 3.5 m3

Backhoe

VAR.

Dump Truck

20 m3, 35 m3

Welding Machine

20 kW

Crane

50 ton, 80 ton

Crawler Drill

Generator

125 kVA, 500 kVA

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.4 Structural Work
Base Slab
Side Wall & Central Column

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.5 PC Fabrication & Installation
AASHTO Girder Beam & Ancillary

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

3. Construction Plan
3.6. Deck Slab(200mm) & Finishing Work

< Illustrative Photo after Completion >

Samsung Saif Bin Darwish JV

Al Salam Street Tunnel Contract No.(1)

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

A1-2. METHOD STATEMENT AND WORK SEQUENCES


1. Traffic Detour Works
Detour Works is Divided into 3 Stages as under :Stage 1 : All works outside Tunnel Area from IP 55D IP 44 (L.O.C.)
Stage 2 : All works to be carried out as Permanent Construction for Tunnel Works, viz.,
Earthworks, Structural Works, Relocation of Utilities, etc., from IP 55D to IP 44
except at Major Intersections,viz., between IP 41A IP 41, IP 41, IP 9, IP 11, IP 11A,
between IP 11A IP 36A, between IP 36 IP 44
Stage 3 : All works to be carried out as Permanent Construction for Tunnel Works, viz.,
Earthworks, Structural Works, Relocation of Utilities, etc., at the following locations
between IP 41A IP 41,
IP 41,
IP 9,
IP 11,
IP 11A,
between IP 11A IP 36A,
between IP 36 IP 44
This Stages are further subdivided into Sub-stages, viz., Stage 1A, 1B & 1C as per site
requirements. Operation scheme and Shifting date for each Sub-stages will be gradually
developed further. Furthermore this baseline programme rev.0 was not reflected by
Detailed Construction Sub-stages.
Detour Works involves the following :
1) Install Precast Concrete barriers, barriers with screen, traffic cones, for
demarcating areas such as medians, parkings where Asphalt Pavement has to be
constructed for making of detour roads as shown in the drawings.

SAMSUNG-SAIF BIN DARWISH JV

-1-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


2) Excavate to Locate shall be carried out to ascertain Protection/Relocation of
Underground Utilities
3) Removal / Relocation of Streetlighting shall be carried out at specified locations
for Construction of Detour Roads. Prior to removal of Streetlights, Temporary
streetlights shall be installed at these locations to ensure uninterrupted traffic
flow. Specialized Subcontractor shall be deployed for carrying out the works.
4) Removal & Replanting of Trees in the affected areas shall be carried out after
approval of ADM Gardening Section.
5) Similarly Pedestrian Fence, Traffic signs, kerbs, barriers, tiles, etc. shall be
removed for Pavement Construction.
6) Protection of Utilities under Detour Road shall be carried out after obtaining
approval from Service Authorities and as per the directives of Engineer.
7) For carrying out all these works, Shop drawings will be submitted for approval of
Engineer alongwith the Method Statements.
8) After completion of all the aforesaid works, Excavation for Preparation of
Formation shall be taken up.
9) Materials for Asphalt Wearing Course, Pipes & Ducts, Temporary Streetlighting,
Temporary Traffic Signals etc. shall be approved by the Engineer
10) Borrow Fill / Subbase shall be laid on the Prepared Formation as per specifications
11) Asphalt Wearing Course shall be paved on top of Subbase as per specifications.
12) Installation of Traffic Signs & Road Marking shall be taken up after Wearing Course
is completed.
13) Temporary Traffic Signal Controllers shall be installed at all specified locations
along the Detour road for ensuring smooth & uninterrupted flow of traffic
14) Temporary Pedestrian Bridges shall be constructed across the Detour Roads as well
as the Permanent Construction Area to avoid any inconvenience for the Pedestrians.
Locations are shown in the drawings. Confirmatory Boreholes shall be done to
ascertain the suitability of constructing Pedestrian bridges.
15) Traffic Safety Cones, Barriers with Screen, Delineator System, Crash Cushion,
Safety beacon, etc. shall be installed along the newly constructed Detour road and
approval obtained from Engineer, Traffic police, Abu Dhabi Municipality.

SAMSUNG-SAIF BIN DARWISH JV

-2-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


16) After Completion of all the above works Detour Road shall be opened to Traffic as
under:a) Stage 1 to Stage 2 : As above
b) Stage 2 to Stage 3 : After completion of Traffic Decking, Tunnel Roof Slab
at the adjoining locations where Stage 3 construction has to be taken up,
Traffic shall be diverted after providing, barriers, cones, etc and installing
Temporary Traffic Signals at the Intersections.

2. Protection of Utilities & Future


For construction of Pavement outside the Tunnel, Utilities need to be protected /
relocated depending upon the depth of Underground utilities. Relocation of Utilities will
be discussed in details in the subsequent sections.
Protection of Water Lines, Sewer Lines, Irrigation Lines & Telephone Cables shall be done
by placing Precast RCC protection slabs on top of these Lines/ducts/conduits. Sometimes
even split ducts shall be utilized to protect the Services. Protection Slabs shall be erected
after laying of Subgrade, duly backfilled and followed by laying of Aggregate Road Base.
Similarly Future Contingency Ducts, viz., Water ducts, Sewer ducts, Irrigation ducts,
Telephone Ducts shall be laid wherever required as per drawings and specifications
subject to the approval of Engineer and Service Authorities. All Service Ducts shall be laid
after completion of Embankment in all designated locations. After laying of Ducts, mass
concrete surround shall be done or the duct shall be backfilled with selected excavated
materials depending upon the type of duct. Duct Markers shall be installed at all locations.
Duct laying shall be approved by Engineer and respective Service Authorities.
GRP Sleeves for Sewer Line Crossing, GRP Sleeve for Irrigation Line Crossing, PVC Sleeve
for Telephone Line Crossing are to be installed at all locations of Utility Crossings for
laying of Pipelines and Ducts. These Sleeves shall be installed after erection of I-Girder.
Arrangements shall then be made for placing of saddles & holding arrangement prior to

SAMSUNG-SAIF BIN DARWISH JV

-3-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


installing the Sleeves. After these Sleeves are installed, Water pipelines, Irrigation
Pipelines / ducts, Telephone ducts shall be laid in these sleeves for crossing from one side
to the opposite side of Tunnel. Details are elaborated in the subsequent sections.

3. Utilities Relocation Works


3.1.

Storm Water Drainage System

Storm Water Drainage is divided into the following sections :- Storm Water Main Line outside Tunnel
- Storm Water Line inside Tunnel
- Storm Water Laterals
- Pavement Subbase Drainage
Approval of Sub Contractor, Shop Drawings, Materials & Method Statements are prerequisites for commencement of works. Order & Supply of materials shall be driving the
commencement of Pipe laying works.
Storm Water Main Line outside Tunnel
Storm water excavation for Main Line shall be taken up on Manhole to Manhole basis.
These work shall be taken up on Work Team basis as under :
Work Team 1 : Line A Line B Line C Line D Line E
Work Team 2 : Line F Line G
Dewatering & Trench Excavation shall commence from Manhole A1 for Work Team 1 and
from Outfall location to MH F1 for Work Team 2.
Pipelaying shall be taken up next after completion of bedding.
Initial backfilling followed by Testing of Line shall be done as per specifications. Final
backfilling shall then be completed.

SAMSUNG-SAIF BIN DARWISH JV

-4-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


Construction of Manhole shall be taken up alongwith Pipelaying. Excavation, Construction
of Manhole base, Shaft and walls are the subsequent activities. Placing of Cover slabs with
Cover & Frame, Ladder & Hand Rail etc., shall be done in sequence. The laid Pipeline is
connected to the Manhole.,e.g. Pipeline A1 A2 is connected to Manhole A1 & A2 and so
on.
NDRC Works shall be taken up at all specified road crossings. Construction of Driving Pit,
Excavation of Reception Pit, Driving of Casing followed by Testing & Grouting are taken up
sequentially. These works shall be carried out by Specialized Sub-contractor after
approval of Engineer.
After the Storm Water lines are tested, connections of these lines to existing lines or
manholes shall be done at all specified locations. Subsequently after the connection is
complete, an existing Storm water line shall be removed or abandoned for carrying out
Excavation Works for Tunnel Construction.
Storm water lines shall be laid from the downstream side for facilitating connection and
removal of existing line, since these are gravity lines.
Work sequence for laying of Storm water main line is attached separately.
Storm Water line inside Tunnel / Base Slab Drainage
DI Drain Pipe shall be laid across Tunnel Base Slab. These lines shall be laid alongwith
construction of Tunnel Base slab at the respective unit. After laying of these lines,
Drainage Main Line (H- Line & J- Line) shall be laid along the Tunnel Base slab. Details are
shown in the Drainage Layout drawing. These main lines are connected to the
underground Storm Water Reservoir and Sump Pump Room as per Scheme in approved
drawings. Water is then Pumped to the top of the Tunnel and connected to the Main line
or lateral line for onward passage of water.The main lines shall be connected to troughs
which in turn are constructed for collection of drainage water from the Pavement sides
inside the Tunnel. Inlet Grates are erected after laying of Kerbstone for passage of
drainage water into the main line.

SAMSUNG-SAIF BIN DARWISH JV

-5-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Storm Water Laterals


There are a number of Storm water lateral line along and across the Main lines for passage
of drainage water from the arterial / collector roads into the Main line and subsequently
into the Outfall near Corniche. These lines shall be laid after completion of Embankment /
Subgrade. These lines are designated from Station to Station , e.g. Storm Water lateral
line from CH 7+940 CH 8+100 EB. Sequence of works from Excavation, Pipelaying, Testing,
Backfilling & Connections to existing lines/manholes are same as that of Storm water main
line.
The existing laterals are removed/abandoned after connection of the new line to the main
line. Precasting of Inlets & Catch basins are carried out in the Precast Yard in the allotted
laydown area. Installation of Inlets & Catch Basins are taken up alongwith the pipelaying.
The Storm water lateral line is connected to the Inlets prior to testing followed by
removal of the existing line.
Pavement Subbase Drainage
Pavement Subbase Drain Pipe are laid after laying of Embankment /Fill subgrade. These
lines are connected to the catch basins which collect drainage water from the Pavement
through grates/inlets. Laying of Aggregate Roadbase shall be done subsequent to the
laying of the Subbase drain pipe.
Construction of Outfall Structure and Pumping Station near Corniche shall commence
alongwith the Storm Water Drainage Pipelaying works. Details of works are described in
the Programme of works.

3.2.

Water Line Relocation Works

Relocation of Waterline can be classified as under :


1. Relocation of ADDC Water Distribution Line
2. Relocation of TRANSCO Water Line

SAMSUNG-SAIF BIN DARWISH JV

-6-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Details are available in the Waterline Relocation Layout.


Approval of SubContractor, Shop Drawings, Materials & Method Statements are prerequisites for commencement of works. Order & Supply of materials shall be driving the
commencement of Pipelaying works.
In some locations, ADDC Water line & TRANSCO waterline has to be laid in the same
trench. Details are shown in the attached layout drawing. Methodology of Execution is as
under:
Water lines are designated from Station to Station and designated by Pipe diameter to
distinguish between TRANSCO Line and ADDC Waterline.
Dewatering & Trench Excavation shall commence from CH 8+380 CH 8+560 EB and
follows the Sequence as attached alongwith.
Pipelaying shall be taken up next after completion of bedding.
Corrosion Protection shall be done for a section of Pipelaying depending upon the
infrastructure availability and approval of Engineer.
Initial backfilling followed by Testing of Water Line shall be done as per specifications.
Final backfilling shall then be completed after approval of Pressure Tests. Sterilization of
Waterline for conforming to the required Residual Chlorine as per the Bacteriological
Tests shall be taken up next.
Construction of Waterline Chambers, viz. Valve Chambers & Flow Meter chambers shall be
taken up alongwith Pipelaying. Excavation, Construction of Chamber walls and beam,
Placing of Cover slabs with Cover & Frame, Ladder & Hand Rail etc., shall be done in
sequence. After completion of the Chamber construction the laid water line is connected

SAMSUNG-SAIF BIN DARWISH JV

-7-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


to the newly constructed chamber within a particular line segment. Installation of Valves,
Strainers, Water Meters, etc shall be taken up next.
NDRC Works shall be taken up at all specified road crossings. Construction of Driving Pit,
Excavation of Reception Pit, Driving of Casing followed by Testing & Grouting are taken up
sequentially. These works shall be carried out by Specialized Sub-contractor after
approval of Engineer.
After the Storm Water lines are Tested and Sterilized as per specifications and approval of
Engineer and Service Authorities, arrangements shall be made for Shutdown & Connection
to an existing line. Prior Notice shall be given to ADDC & TRANSCO for the same.
The New Waterline shall then be connected to an existing line followed by removal of an
existing line segment and commencement of unclassified excavation in a particular unit.
In some locations (crossings), the existing Waterline shall be routed through the Utility
Bridges so as not to delay the commencement of Excavation Works.
CS Pipelines across Tunnel are linked to the Installation of GRP sleeves in the respective
Utility Crossings after installation of I Girder. These pipelines are subsequently connected
to a new line or an existing line outside Tunnel for transportation of Water. Similarly
Water Ducts through Tunnel Crossings are also installed after the GRP Sleeve in the Utility
Crossing is placed.

3.3.

Irrigation Relocation Works

Irrigation Relocation Works consists of Removal of existing Irrigation Distribution Lines


from the Tunnel Construction area and relocating it outside the Tunnel.
Prior to removal of existing Irrigation distribution line from the median or green areas, the
trees has to be removed from those locations. Subsequently the Irrigation Line shall be
removed to facilitate commencement of Unclassified Excavation.

SAMSUNG-SAIF BIN DARWISH JV

-8-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


Approval of SubContractor, Shop Drawings, Materials & Method Statements are prerequisites for commencement of works. Order & Supply of materials shall be driving the
commencement of Pipelaying works.
Irrigation Pipelaying is considered in segment from Valve Chamber to Valve Chamber or
Flow Meter Chamber as shown in the attached Work sequence.
e.g. Excavation for Pipelaying shall commence from VC1 PRVC1 as shown in the work
sequence.
Pipelaying shall be taken up next after completion of bedding.
Construction of Irrigation Valve Chambers and Flowmeter Chambers, viz. Air Valve
Chambers, Pressure Reducing Valve Chambers etc., shall be taken up alongwith Excavation
& Pipelaying. Construction of Chamber walls and beam, Placing of Cover slabs with Cover
& Frame, Ladder & Hand Rail etc., shall be done in sequence. After completion of the
Chamber construction the newly laid Irrigation line is connected to the newly constructed
chamber. Installation of Valves, Strainers, Pressure Reducing Valves, Flow Meters, etc
shall be taken up next.
Thrust Boring works shall be carried out at Irrigation Line between VC9 VC10. These
works shall be carried out by Specialized Sub-contractor after approval of Engineer.
Irrigation Pipeline shall be laid after completion of Testing & Grouting and Laying of
Casing pipe.
After completion of Pipelaying works and valve chamber construction, connection to the
existing lines shall be done after taking necessary shutdown with the approval of Service
Authorities.
Backfilling and Reinstatement Works shall be taken up next.
Irrigation Line Instrumentation Works shall be taken up after laying of Pipeline,
construction of Chambers & installation of valves and Flow meters.

SAMSUNG-SAIF BIN DARWISH JV

-9-

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Irrigation Marker Plates shall be installed as required.

3.4.

Telephone Line Relocation Works

Telephone Line Relocation Works shall be taken up to facilitate Construction of Tunnel.


Relocation works shall commence from IP 55D and proceed towards IP 44 (L.O.C.).
Approval of SubContractor, Shop Drawings, Materials & Method Statements are prerequisites for commencement of works. After approval of Shop Drawings, Request for
Materials shall be placed to Etisalat for issue of Materials, viz, Ducts, conduits, cables etc.
Depending upon receipt of Materials at site, Telephone Duct Laying shall commence.
Sequence of Works for Telephone Line Relocation is attached separately.
Excavation for Duct Laying shall commence from MH@ CH 8+300 EB - MH 65211. NDRC at
CH 8+300 shall also commence parallely as shown in the Programme of Works.
Telephone duct laying shall be taken up next after completion of bedding.
Construction of Telephone Manholes/Chambers, shall be taken up alongwith Duct laying.
Construction of Chamber walls and beam, Placing of Cover slabs with Cover & Frame,
Ladder & Hand Rail etc., shall be done in sequence. Waterproofing shall be taken up next.
After completion of the Chamber, Telephone Duct shall be connected to the chamber. All
chamber appurtenances shall be installed by Etisalat or their Subcontractor.
Backfilling of Telephone Duct and Chamber shall be taken up subsequently. After it is
inspected and approved by Etisalat and Engineer, Telephone Line OFC Cable laying shall
be taken up. This work shall be done by a Specialized Subcontractor of Etisalat.
Upon Completion of Telephone Cable Laying, each Telephone Line shall be tested and
Commissioned by Etisalat. Details of these lines is shown in the Telephone Line Layout
Drawing.

SAMSUNG-SAIF BIN DARWISH JV

- 10 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

After a line is commissioned and connected to a Manhole or a JRC box, existing line can be
removed or abandoned to facilitate unclassified excavation.
Reinstatement Works is taken up after completion of the aforesaid activities. In some
locations existing Manholes has to be adjusted to match the finished Pavement level.

3.5.

Sewerage Line Relocation Works

Sewerage Line relocation works is carried out for Construction of Tunnel.


Sewerage Relocation Works shall be carried out by 2 work teams as under:Work Team1 : From MH 11(L.O.C) towards IP 55D
Work Team 2 : From Manhole 60 (IP 55D) towards L.O.C. at IP 44
Both these work teams meet at Manhole 39 as per work sequence shown in the Programme
of Works. However this sequence may change depending upon site actuals or direction of
Engineer. Work Sequence for Sewerage Relocation Works is attached separately.
Approval of SubContractor, Shop Drawings, Materials & Method Statements are prerequisites for commencement of works. Order & Supply of materials shall be driving the
commencement of Pipelaying works.
At the outset, Sheet Piling and Trench Excavation works are carried out. Bedding followed
by Pipelaying follows subsequently. Sheet piling and Excavation for Construction of Sewer
Manhole is also started simultaneously alongwith Trench excavation. After Completion of
Excavation, Construction of sewer manhole is taken up. Construction of Manhole base,
Shaft and walls are the subsequent activities. Placing of Cover slabs with Cover & Frame,

SAMSUNG-SAIF BIN DARWISH JV

- 11 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


Ladder & Hand Rail etc., shall be done in sequence. The laid Pipeline is connected to the
Manhole., e.g. Pipeline MH 60 MH 59 is connected to Manhole MH 60 and MH 59 and so on.
NDRC Works shall be taken up at all specified road crossings. Construction of Driving Pit,
Excavation of Reception Pit, Driving of Casing followed by Testing & Grouting are taken up
sequentially. These works shall be carried out by Specialized Sub-contractor after
approval of Engineer. In some locations, the Sewer Manhole shall be constructed on the
NDRC pit itself.
Initial Backfilling of Sewer line and Manhole shall be taken up next. Testing of Sewer Line
and Manholes shall be taken up next. If found satisfactory, Final backfilling and Removal
of Sheet Piles of the Sewer line shall be done. In some locations Sheet piles shall be left in
place depending upon the soil conditions and discretion of Engineer.
After a Sewer line is tested, Overpumping from existing Sewer Manhole shall be taken up
upon approval of Service Authorities. This work is carried out for facilitating connection of
newly laid and tested Sewer Line to an existing Manhole.
After the connection of the new Sewer line is completed, the existing Sewer Line shall be
removed or abandoned for facilitating commencement of Tunnel excavation works.

4. Main Tunnel Structural Works


4.1.

Excavation Supporting System (Diaphragm Wall)

We will supply each one working group for each section after completion of utility
relocation and protection works. Diaphragm Wall Driving will be commenced gradually on
the possible area after traffic detour was diverted. Work Sequence for Diaphragm Wall
was based on construction drawing for construction stages. Detailed sequence of each
section is as below. Please refer to Numbering System submitted before regarding the
definition of each unit.
1) Productivity : 6~8 l.m / day (1 ~ 1.5 panel / day) , 1 working group per each section

SAMSUNG-SAIF BIN DARWISH JV

- 12 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

2) Work Sequence
A. Section 1
Unit 16 ~ 15 (SB)

Unit 19 ~ 2(#2) (SB)

Unit 17 ~ 18 (SB)

Unit 9 ~ 1 (SB)
Unit 14 ~ 10 (SB)

Unit 16 ~ 15 (NB)

Unit 19 ~ 2(#2) (NB)

Unit 17 ~ 18 (NB)

Unit 14 ~ 1(#1) (NB)

Unit 14(#2) ~ 3(#2)

Unit 9(#4) ~ 1(#4)

Unit 1(#3)

Unit 13(#3) ~ 14(#3)

Unit 15(#3) ~ 16(#3)

Unit 25(#3) ~ 26(#3)

Unit 12(#3)

Unit 21(#3) ~ 23(#3)

Unit 17(#3) ~ 20(#3)

Unit 24(#3)

Unit 30(#3) ~ 34(#3)

Unit 10(#3) ~ 11(#3)

Unit 27(#3) ~ 29(#3)

B. Section 2
Unit 2(#3) ~ 9(#3)

C. Section 3

D. Section 4
Unit 37(#3) ~ 35(#3)

Unit 55(#3) ~ 48(#3)

Unit 57(#3) ~ 56(#3)

Unit 62(#3) ~ 60(#3)

Unit 47(#3) ~ 38(#3)

SAMSUNG-SAIF BIN DARWISH JV

- 13 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


4.2.

Bored Pile

Bored Piling Works will be executed in parallel with diaphragm wall driving. Basic
productivity for bored pile was considered by 2 numbers in a day if 2 shift operated.
For more detailed cycle time , refer to Productivity Report attached.

5.1.1 Excavation
After supporting system completed, main excavation works will be commenced at each
section. Approximately 4 working groups will be supplied to each section respectively. But
operation of each working group is changeable according to working conditions.
Excavation works will be divided by 2 parts such as 1st Excavation and 2nd Excavation. 1st
Excavation will be reached to 3.0 metre below from G.L. (G.L ~ 3.0m). With completing
1st Excavation earth anchoring should be proceed for protection if required. Some parts
should be installed by Strut system for preventing deflection of existing ground. 2nd
Excavation ranges from 3.0m to formation level around 9.0 ~ 12.0 below. The work
sequence of excavation should be basic direction and successive activities such as base
slab, wall and roof slab will be followed by same direction. Detailed work sequences as
below.

A. Section 1

Unit 16 ~ 15

Unit 11 ~ 10

Unit 17 ~ 18

Unit 19 ~ 29

Unit 30 ~ 2 (#2)

Unit 9 ~ 1

SAMSUNG-SAIF BIN DARWISH JV

Unit 14 ~ 12

- 14 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


B. Section 2
Unit 2 ~ 6 (#3)

Unit 7 ~ 9 (#3)

Unit 9 ~ 1 (#4)

Unit 14 ~10 (#2,SB)

Unit 9 ~ 5 (#2,SB)

Unit 4 ~ 1 (#2,SB)

Unit 12 ~ 9 (#2,NB)

Unit 8 ~ 5 (#2,NB)

Unit 4 ~ 1 (#2,NB)

Unit 13 ~ 14 (#3)

Unit 21 ~ 23 (#3)

Unit 10 ~ 11 (#3)

Unit 15 ~ 20 (#3)

Unit 27 ~ 29 (#3)

Unit 24 ~ 26 (#3)

Unit 12 (#3)

Unit 30 ~ 34 (#3)

C. Section 3

D. Section 4
Unit 44 ~ 38 (#3)

Unit 47 ~ 45 (#3)

Unit 37 ~ 35 (#3)

Unit 57 ~ 56 (#3)

Unit 49 ~ 48 (#3)

Unit 55 ~ 50 (#3)

Unit 62 (#3)

Unit 61 ~ 58 (#3)

SAMSUNG-SAIF BIN DARWISH JV

- 15 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

5.1.2 Reinforced Concrete Works


Reinforce Concrete works will be commenced after completion of pile head treatment and
waterproofing including lean concrete. 4 ~ 6 working groups respectively will be operated
at each section. Base slab, wall and roof slab will be divided as 3 parts separately and will
be completed by 3 times of concrete pouring. Reinforced bar assembling will be critical
path of concrete works, therefore we will operate 2 shift-base. Accordingly installation
works of shutters will be executed by 2 shift-base. Each work sequence is as below. For
more detailed cycle time, refer to attached Productivity Report.
A. Section 1
W/G #1

W/G #2

W/G #3

W/G #4

Unit 16

Unit 15

Unit 19

Unit 20

Unit 21

Unit 22

Unit 23

Unit 24

Unit 25

Unit 26

Unit 27

Unit 28

Unit 29

Unit 30

Unit 31

Unit 32

Unit 1 (#2)

Unit 2 (#2)

Unit 17

Unit 18

Unit 9

Unit 8

Unit 7

Unit 6

Unit 5

Unit 4

Unit 3

Unit 2

Unit 1

Unit 14

Unit 13

Unit 12

Unit 10

Unit 10

SAMSUNG-SAIF BIN DARWISH JV

Remarks

- 16 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


B. Section 2
W/G #1

W/G #2

W/G #3

W/G #4

Remarks

Unit 2 (#3)

Unit 9 (#4)

Unit 14 (#2)

Unit 13 (#2)

Unit 9 (#3)

Unit 6 (#4)

Unit 12 (#2)

Unit 11 (#2)

Unit 7 (#3)

Unit 3 (#4)

Unit 10 (#2)

Unit 9 (#2)

Unit 5 (#3)

Unit 8 (#4)

Unit 8 (#2)

Unit 7 (#2)

Unit 1 (#3)

Unit 5 (#4)

Unit 6 (#2)

Unit 5 (#2)

Unit 3 (#3)

Unit 3 (#4)

Unit 4 (#2)

Unit 3 (#2)

Unit 8 (#3)

Unit 7 (#4)

Unit 6 (#3)

Unit 4 (#4)

Unit 4 (#3)

Unit 1 (#4)

C. Section 3
W/G #1

W/G #2

W/G #3

W/G #4

Unit 13

Unit 14

Unit 21

Unit 22

Unit 23

Unit 10

Unit 11

Unit 15

Unit 16

Unit 17

Unit 18

Unit 19

Unit 20

Unit 27

Unit 28

Unit 29

Unit 25

Unit 26

Unit 24

Unit 12

Unit 30

Unit 31

Unit 32

Unit 33

Remarks

Unit 34
D. Section 4
W/G #1

W/G #2

W/G #3

W/G #4

W/G #5

W/G #6

Unit 44

Unit 43

Unit 42

Unit 41

Unit 40

Unit 39

Unit 38

Unit 47

Unit 46

Unit 45

Unit 37

Unit 36

Unit 35

Unit 57

Unit 56

Unit 49

Unit 48

Unit 55

Unit 54

Unit 53

Unit 52

Unit 51

Unit 50

Unit 62

Unit 61

Unit 60

Unit 59

Unit 58

SAMSUNG-SAIF BIN DARWISH JV

- 17 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


5.2

Pavement Works

5.2.1 Outside tunnel


After completion of Tunnel Retaining Walls, Backfilling shall be taken up for filling
between Retaining Wall and Diaphragm Wall. Filling shall be done in layers as per
specifications,duly tested and approved by Engineer. Construction of Approach Slabs shall
be taken up next in all specified locations as per approved drawings.
Subsequent to the above, Embankment Fill / Subgrade shall be be taken up for
construction of Main Road Pavement, Sector Road Pavement & Truck Road Pavement.
Pervious Backfill shall be done wherever Truck Roads are to be constructed. Prior to
commencement of Subgrade, Geotextile Fabric shall be placed. Adjustment of existing
Manholes, Structures, Inlets etc shall be carried out to match the finished Pavement Level.
Kerbstone shall be placed at all curves, along sidewalks, parkings etc. Concrete barrier
shall also be installed at all locations as per approved construction drawings.
Aggregate Base Course (one lift) course shall be laid over approved Subgrade as per
specifications and compaction requirements.
After design Compaction is achieved, Prime Coat shall be sprayed followed by paving a
layer of Asphalt Base Course. Asphalt Base course shall be laid in 2 layers as per
specifications.
Tack coat shall be sprayed over the approved Asphalt Base Course for receiving the 1st
layer of Asphalt Wearing Course. Wearing Course shall be consisting of 2 layers- 5 cm/7.5
cm depending upon the type of Pavement.
Milling of Asphalt followed by Asphalt Regulatory Course shall be taken up at all Tie-in
locations where new pavement is tied with the adjoining existing Asphalt Pavement.
After required compaction is achieved and curing completed, Road Marking shall be taken
up after approval of Subcontractor, Materials, Drawings & Method Statements.
Installation of Road Studs shall be done in parallel alongwith Road Marking.
Traffic Signboards at all approved locations.

SAMSUNG-SAIF BIN DARWISH JV

- 18 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


Similarly, Pile Foundations for erection of Overhead Tubular Gantry shall be taken up. This
work shall be carried out by a specialized Subcontractor with prior approval of the
Engineer.
Guide Sign panels shall then be installed on the Gantry at specified locations.
Traffic Signals shall be installed at all intersections and Streetlighting works shall also be
taken up. All these works shall be done by specialized Subcontractor duly approved by
Engineer.
After completion of all these works, Road shall be opened to Traffic after approval of
Engineer, Traffic Police Deptt., ADM.
Note : All Pavement activities from Subgrade upto Road Marking & Signs shall be taken up
at all available areas depending upon the completion of Tunnel backfilling. Also for
construction of Sector Road pavement along the Tunnel sides, diversion of Traffic into the
Tunnel is required as the existing Detour Traffic is plying along these roads. After the
traffic is diverted into the Tunnel, Pavement works shall commence with placing of Safety
barriers, cones, delineators etc and approval of Engineer and Traffic Police Deptt., ADM.
For diversion of Traffic into the Tunnel, Pavement works need to be done inside the
Tunnel & Tunnel Top as described in the next Section.

5.2.2 Inside tunnel


After completion of Tunnel Deck Slab with proper Curing as per specifications and
approval of Engineer, Pavement works shall be taken up on top of Tunnel Roof Slab.
Kerbstone and Concrete Barriers shall be placed at all approved locations.
Sand Asphalt Mix (1.8 cm) shall be placed over Tunnel Roof Slab. Subsequently Asphalt
Wearing Course shall be laid over Sand Asphalt to the required Compaction and as per
approved Design Mix.

SAMSUNG-SAIF BIN DARWISH JV

- 19 -

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0


Road Marking & Installation of Road Studs shall be taken up next. Traffic Signs shall be
installed at all approved locations. Traffic Signals shall be installed at all intersections and
Streetlighting works shall also be taken up. All these works shall be done by specialized
Subcontractor duly approved by Engineer.
For Pavement works inside Tunnel, after the Completion of Tunnel Construction,
Kerbstone & Concrete barriers shall be placed on top of Tunnel Base Slab for construction
of Sidewalks and Inlet Drainage Grates. Interlock Tiles shall be placed next after
allowance is made for Electrical Conduits, OFCs .
Asphalt Wearing Course shall be laid after laying of barriers & kerbs and tested to achieve
the design compaction.
Road Markings & Road Studs shall be taken up next alongwith installation of Traffic Sign
boards. Erection of Guide Sign Panels inside Tunnel shall be taken up properly anchored to
the I- Girders.
After completion of all these works, Traffic shall be diverted inside the Tunnel after
approval of Engineer, Traffic Police Deptt., ADM.

SAMSUNG-SAIF BIN DARWISH JV

- 20 -

A1-2. Schematic Diagram for Work Sequence


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

UTILITIES RELOCATION WORKS


STORM WATER DRAINAGE SYSTEM
SEQUENCE OF WORKS - MAIN LINE PIPELAYING FROM MANHOLE TO MANHOLE
TO IP 44

TO IP 55D

WORK TEAM 1

A - LINE
A1

A2

A3

A4

A5

A6

A7

A8

B - LINE
A9

A10

A11 A12 A13

A14

B0

B1

B2

B3

B4

B5

B6

B7

B8

B9

C - LINE
B10 B11 B12

B13 B14 B15 B16

C1

C2

C3

C4

C5

C6

D - LINE
C7

C8

C9

D0

D1

D2

D3

D4

D5

E - LINE
D6

D7

D8

E1

E2

SEQUENCE OF WORKS - MAIN LINE PIPELAYING FROM MANHOLE TO MANHOLE


TO IP 55D

TO IP 44

F - LINE

WORK TEAM 2

F2

OUTFALL

PUMPING STATION

F1

F3

F4

F5

F6

F6A

F7

F8

F9

F10

F11

F12 F12A F13 F14 F15 F16 F17 F18 F19 F20 F21 F22

F23

F24

F25 F26 F27 F28 F29 F30 F31 F32 F33 F34 F35 F36 F37 F38 F39 F40 F41 F42 F43 F44 F45 F46 F47

G - LINE
G1
LEGEND :
A1, A2, A3 : MANHOLES FOR A - LINE
B1, B2, B3... : MANHOLES FOR B - LINE
C1, C2, C3... : MANHOLES FOR C - LINE
D1, D2, D3... : MANHOLES FOR D - LINE
E1, E2, E3 : MANHOLES FOR E - LINE
F1, F2, F3... : MANHOLES FOR F - LINE
G1, G2
: MANHOLES FOR G - LINE

NOTE 1: SEQUENCE OF WORKS FOR STORM WATER MAIN LINE INSIDE TUNNEL IS LINKED TO LAYING OF DI DRAIN PIPE INSIDE TUNNEL ACROSS BASE SLAB AT SPECIFIED LOCATIONS
NOTE 2: LAYING OF DI DRAIN PIPE INSIDE TUNNEL ACROSS TUNNEL BASE SLAB IS LINKED TO THE CONSTRUCTION OF BASE SLAB IN THE RESPECTIVE UNIT
NOTE 3 : EXCAVATION & PIPELAYING FOR STORM WATER LATERALS IS LINKED TO COMPLETION OF EMBANKMENT / SUBGRADE BETWEEN THE RESPECTIVE STATIONS
NOTE 4 : NDRC WORKS SHALL BE CARRIED OUT BY SEPARATE SUB CONTRACTOR AND THE SEQUENCE OF WORKS SHALL BE THE SAME AS EXCAVATION WORKS FOR PIPELAYING

WATERLINE RELOCATION WORKS


TO IP 55D

TO IP 44

11+400 - 11+546 NB

11+250 - 11+400 NB

11+081 - 11+250 NB

11+036 - 11+081 NB

11+036 NB

10+428 - 10+635 NB

10+375 - 10+428 NB

10+200 - 10+375 NB

10+068 - 10+200 NB

10+950 - 11+090 SB

10+800 - 10+950 SB

10+635 - 10+800 SB

10+437 - 10+635 SB

10+335 - 10+437 SB

10+149 - 10+335 SB

10+083 - 10+149 SB

IP 12 9+400 SB (South)

IP 12 9+400 SB (East)

9+428 - 9+668 SB

9+668 - 9+790 SB

9+790 - 9+962 SB

9+962 - 10+062 SB

9+204 - 9+377 EB
(North)
9+204 - 9+377 EB
(East)
9+204 - 9+377 EB
(South)
9+283 - 9+290 WB
(West)
9+283 - 9+290 WB
(South)

8+600 - 8+806 WB

8+380 - 8+600 WB

8+380 - CROSSING

8+380 - 8+560 EB

SEQUENCE OF WORKS - WATER LINE PIPELAYING (CHAINAGEWISE)

WORK TEAM
NOTE : 8+380 - 8+560 EB INDICATES INDICATES PIPELAYING FROM STATION 8+380 - 8+560 EB
NOTE 1 : SEQUENCE OF WORK FOR LAYING CS PIPELINES THROUGH UTILITY CROSSINGS AT THE IP's IS LINKED TO THE ERECTION OF I - GIRDER IN THE RESPECTIVE UNIT.
NOTE 2 : NDRC WORKS SHALL BE CARRIED OUT BY SEPARATE SUB CONTRACTOR AND THE SEQUENCE OF WORKS SHALL BE THE SAME AS EXCAVATION WORKS FOR PIPELAYING

IRRIGATION RELOCATION WORKS


TO IP 55D

TO IP 44

WORK TEAM
LEGEND :
AV - AIR VALVE CHAMBER
FM - FLOW METER CHAMBER
PRVC - PRESSURE REDUCING VALVE CHAMBER
VC - VALVE CHAMBER , VC1 - VALVE CHAMBER No.1
WC - WASH OUT CHAMBER
NOTE 1 : SEQUENCE OF WORK FOR LAYING IRRIGATION PIPELINES THROUGH UTILITY CROSSINGS AT THE IP's IS LINKED TO THE INSTALLATION OF GRP SLEEVE AT THE UTILITY CROSSINGS.
INSTALLATION OF GRP SLEEVE AT UTILITY CROSSINGS IS LINKED TO ERECTION OF I - GIRDER AT THE RESPECTIVE UNIT
NOTE 2 : THRUST BORING WORKS SHALL BE CARRIED OUT BY SEPARATE SUB CONTRACTOR AND THE SEQUENCE OF WORKS SHALL BE THE SAME AS EXCAVATION WORKS FOR PIPELAYING

VC30 - FM7 - VCN4

AV3 - VC30

VC28 - AV3 (East)

VC28 - AV3 (North)

VC28 - AV3 (West)

VC19 - VC20

VC18 - VC19

WC1 - VC18

VC17 - WC1

PRVC11 - FUTURE
CONN @ CH 9+300 EB

PRVC16 - FM6 - VC29

AV2 - PRVC16

VC27 - AV2

VC25 - VC27

VC24 - VC25 - FM4

VC23 - VC24

VC22 - VC23

WC2 - PRVC13

VC16 - WC2

AV1 - VC15 - VC16

PRVC12 - AV1

PRVC12 - AV1

FM3 - PRVC12

FM3 - EXISTING LINE

VC9 - VC10

FM1 - FM2

FM2 - PRVC10

PRVC9 - FUTURE
CONN
PRVC10 - EXISTING
VC

PRVC8 - IP 41

PRVC8 - FUTURE
CONN

VC6 - PRVC8

VC4 - IP 41A

PRVC3 - FUTURE
CONN

PRVC4 - VC3

VC2 - PRVC4

VC1 - PRVC1

SEQUENCE OF WORKS - IRRIGATION PIPELAYING (FROM VALVE CHAMBER TO VALVE CHAMBER)

G2

E3

A1-2. Schematic Diagram for Work Sequence


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

UTILITIES RELOCATION WORKS


TELEPHONE LINE RELOCATION WORKS
TO IP 55D

TO IP 44

MH 8748 - MH 65163

MH 65200 - MH 8748

MH 8747 - MH 65200

MH 65201 - MH 8747

MH 65109 - MH 65201

MH 65108 - MH 65109

MH 65198 - MH 65108

MH 65198 - MH 65197

MH 65194 - MH 65198

MH 20006 - MH 65194

MH 65169 - MH 20006

MH 65197 - MH 65169

MH 8704 - MH 50034

MH 65184 - MH 8740

MH 65185 - MH 65184

MH 65206 - MH 65185

MH 65202 - MH 65206

MH 50035 - MH 8702

MH 65204 - MH 65202

MH 65203 - MH 65204

MH 65205 - MH 65203

MH 8701 - MH 50026

MH 65207 - MH 8723

MH 8677 - MH 65181

MH 65182 - MH 66852

MH 65209 - MH 65182

MH 65464 - MH 65210

MH@8+300 EB - MH 65211

CROSSING @ CH 8+300

SEQUENCE OF WORKS - TELEPHONE DUCT LAYING (FROM MANHOLE TO MANHOLE)

WORK TEAM
NOTE 1 : SEQUENCE OF WORK FOR LAYING TELEPHONE DUCTS THROUGH UTILITY CROSSINGS AT THE IP's IS LINKED TO THE INSTALLATION OF PVC SLEEVE AT THE UTILITY CROSSINGS.
INSTALLATION OF PVC SLEEVE AT UTILITY CROSSINGS IS LINKED TO ERECTION OF I - GIRDER AT THE RESPECTIVE UNIT
NOTE 2 : NDRC WORKS SHALL BE CARRIED OUT BY SEPARATE SUB CONTRACTOR AND THE SEQUENCE OF WORKS SHALL BE THE SAME AS EXCAVATION WORKS FOR LAYING OF TELEPHONE DUCTS
LEGEND :
MH 65464, MH 65210 : TELEPHONE MANHOLE / JRC BOX

SEWERAGE LINE RELOCATION WORKS


SEQUENCE OF WORKS - SEWER LINE PIPELAYING FROM MANHOLE TO MANHOLE
TO IP 55D

TO IP 44

SEQUENCE OF PIPELAYING WORKS FROM MANHOLE TO MANHOLE


60

59

58

57

56

55

54

53

52

51

50

49

48

47

46

45

44

43

42

41

40

39

38

37

36

35

34

33

32

31

WORK TEAM 1

30

29

28

27

26

25

24

23

22

21

20

19

18

17

16

15

14

13

12

11

WORK TEAM 2

LEGEND :
60,59,58 . : SEWER MANHOLES
NOTE 1: DETAILS OF OVERPUMPING & CONNECTION WORKS ARE SHOWN IN THE SEWER RELOCATION LAYOUT DRAWING
NOTE 2 : NDRC WORKS SHALL BE CARRIED OUT BY SEPARATE SUB CONTRACTOR AND THE SEQUENCE OF WORKS SHALL BE THE SAME AS EXCAVATION & SHEET PILING FOR SEWER PIPELAYING

A1-3. SSBD JVs Amendments for Parsons Comments

Some comments which were not revised in the Baseline Programme this time will be
amended in earlier. Rectification based on Parson Review Comment as follows;
1. The Planning Documents attached to the Programme do not meet the requirements
of sub clause 1-c-4-d:
a. The Narrative shall include the phasing plan, zoning chart, staging diagram,
scope and sequencing of all tasks to meet the completion date.
Attached to Appendix 8 Narratives for Baseline Rev.0
b. The phasing plan should reflect how SSBD will execute the work in compliance
with the contract requirements.
Attached to Appendix 8 Narratives for Baseline Rev.0
c. The Narrative shall include sign-off by all major Subcontractors indicating they
participated in the schedules development.
We selected subcontractors which can meet our schedule requirement.
Furthermore nominated subcontractors made their own programme based on
Baseline Programme. This indicates provisionally sign-off for our Baseline
Programme. Major Subcontractors which were nominated will be submitted
gradually.
d. Quantity loading of BOQ by month up to Item level.
Attached to Appendix 2 Quantity Loading of BOQ by month
e. Key Activities quantities per months.
Attached to Appendix 3 Monthly Quantity Distribution for Key Activities
f. Cost monthly distribution of BOQ items.
Attached to Appendix 4 Monthly Budgeted Cost by BOQ
g. Cost monthly distribution of BOQ by Bill
Attached to Appendix 5 Monthly Cost Distribution based on Resources
h. All resources histograms.
Attached to Appendix 6 All Resources Histogram. This Histogram contains
Direct, Indirect Labour and Equipment respectively.

1 of 10

i.

Cash Flow S-Curve


Attached to Appendix 7. Cash Flow

2. The table shown below represents the construction durations calculated from your
submitted programme:
Work Duration cant depend on ONLY Length. It depends on workability and
work conditions. Excavation supporting system for Section 2 is Strut System. It
takes much more time to complete. Revised Durations for Bored Piles as
below;
Bored Piles

Length

Duration

Section No.1 (L.O.C. St. 9+381)

933

266

Section No.2 (St. 9+381 St. 9+954)

573

216

Section No.3 (St. 9+954 St. 10+704)

750

200

Section No.4 (St. 10+704 St. 11+525)

821

230

Remarks
Revised

3. Add the following start and finish milestones:


a. Detour construction
Start and Finish Milestones for Detour Construction added
b. Asphalt works for all sections.
Start and Finish Milestones for Asphalt Works added

c. Stages of major traffic changes.


Finish Milestones for Traffic Detour added as below

Activity
No.

SECTION 1

SECTION 2

SECTION 3

SECTION 4

CNS110341

CNS210371

CNS310351

CNS410381

CNS110351
CNS110361

CNS210381
CNS210391

CNS310361
CNS310371

CNS410391
CNS410401

2 of 10

4. Sub clause 1.05-a-3-a-2 requires the contractor to observe in his schedule the
interface with adjacent projects. Include all interfaces.
Interface with adjacent Projects identified and included already as below.
1) SW0089A0

Sewer Line : Manhole MH11 to be Ready (by Nurol)

2) IR008R01

VC N4

3) IR008R00

VC 30 - FM 7- VC N4 (by Nurol) : Irrigation Line - Excavation

to be Ready by Nurol : Irrigation Line

& Pipelaying
4) IR008R20

VC 30 - FM 7-VC N4 (by Nurol) : Connection to Existing Line

5) IR008R30

VC 30 - FM 7-VC N4 (by Nurol) : Irrigation Line Backfilling

6) IR008R40

VC 30 - FM 7-VC N4(by Nurol) : Reinstatement of Pavement

5. The schedule has 15 constraints. As per sub clause 1.05-a-2-g, constraints are not
permitted (the only two constraints allowed are the start and completion date of the
project).
All Constraints were removed.
6. Sub clause 1.05-a-2-f states the float rules. However the schedule shows activities
with large total float, some even exceed the total contract duration! Also some
critical activities bars with zero float are not shown as critical. Please correct.
Corrected
7. The Critical Path does not appear correct. Please review the logical ties and
durations.
Reviewed the logical ties and revised

8. Activities with duration of one day are placed on the Critical Path, which makes it
almost impossible to avoid negative total float in the project.
Critical Path runs from Commencement to Completion of the Project,
different activities being critical at different points in time. Duration of the
Activity cannot be the sole criterion why an activity is critical. In other words we
cannot control the critical path based on activity duration.
9. Milestone showing delivery of 132 KV cable is indicated as critical, while the
activities related to this milestone are not, please correct.
Milestone EL000650 had a constraint as Mandatory Finish. This constraint
and logical ties were removed and corrected respectively.

3 of 10

10. Long-lead items procurement and delivery should be listed and logical ties analyzed
to determine whether they are critical activities in the programme.
These items were listed already, and they had relationships logically.
Ex.) EL000650 132 KV XLPE Cable : Delivery on Site - 132 KV Cable etc.
11. Productivity report attached does not cover all construction activities.
Attached to Appendix 9 Productivity Report
12. As per Sub clause 1.05-a-3-a-12 (x), please include Mobilization of Personnel and
Equipment (e.g. cranes).
Our provisional plan for precast girder installation is using Straddle Carrier.
Procurement and delivery activities related with straddle carrier were listed up
already and this equipment resource was loaded to addressing activities
(PF0000080).
13. Contract handling over & close-out activities should include punch lists / snagging
lists.
Added
14. The sub-total duration shown on page 1 of the Programme should reflect the
contract period of 900 calendar days.
If you can use only one calendar without holidays, you can resolve this
matter. Currently we use some kinds of calendars, it is impossible to show 900
calendar days.
15. Shift the following activities and all other activities related to Close Out and Handing
Over Section: GE008300, ST000050, ST000880, HN000010
Done (ST000050 and ST000880 were shifted to Close Out and Handing
Over Section)

16. Activities not related to construction should be eliminated from the programme.
(ex.:GE008200, GE009000, GE008000, ST000020, ST000830, WT0089F0)
These activities are needed for describing Contract Amount in programme.
Maintenance Costs for Contractor, Consultant and Employer is important factor
for progress calculation, so that these items should be described in programme.

4 of 10

17. Detail activity IS007210 and break it down into 2 stages at least.
Done
18. Activities codes should have clear description, activities DG000050 and DG000090
are assigned to codes without description, redefine the following code values to
reflect their assigned activities properly.
a. NO DIR
Activity ID DT003000 and GE008300 were redefined.
b. NO AREA 1
Done
c. New Code Value.
Done
19. Activities EL000510, and EL000570 are assigned wrongly to Design and Shop
Drawing Section, please shift it to Procurement Section.
Done
20. Supply of Materials-Utility Markers description is repeated for activities MA001890
and MA001430. Please correct.
Activity ID MA001430 refers to Submit Material Utility Markers and
Activity ID MA001890 refers to Supply of Materials Utility Markers. There is
no repetition.
21. Correct the duration of the following activities: DG000800, DG000900, DT000300,
SW0089F0, SW0089E0, WT0089F0, WT0089B0, WT0089H0, WT0089L0,
WT0089J0, WT0089K0, and WT0089C0.

Activity ID

Previous

New

Duration

Duration

Description

Remarks

DG000800

Submit Shop drawings Removal of Trees

12 days

12 days

DG000900

Approve Shop drawings Removal of Trees

14 days

14 days

DT003000

Precasting of Concrete Barriers

100 days

100 days

SW0089F0

Sewer Future Connections at Manholes

300 days

30 days

SW0089E0

Sheet Piles left in Place

300 days

30 days

WT0089F0

Water line Relocation - Dayworks

450 days

300 days

WT0089B0

Water line Relocation Works Protection

450 days

300 days

Slabs
WT0089H0

Deleted

WT0089L0

Deleted

WT0089J0

Deleted

WT0089K0

Deleted

WT0089C0

Waterline through Utility Bridges

5 of 10

400 days

300 days

22. Delete activity DT008900.


Not deleted. This activity needs to calculate progress.

23. Activity EA008900 should be broken down to four sections and assign each to the
relative section.
Activity EA008900 has been broken down to Activities EA008910,
EA008920, EA008930 and EA008940 and relationships between these
activities were rectified (Successors of these activities were changed to Base
Slab).

24. Clarify DRG 1, 2, 3 and 4 which are shown in the programme.


DRG 1, 2, 3 and 4 has been removed from the Programme.
Accordingly code values related with DRG such as 1, 2, etc were removed
from activity code system.

25. Correct description of activities SW008280, SW008480 and all activities containing
? in its description.
Activity ID SW008280 and SW008480 Sewer Manhole Nos. are not shown
in the drawings. Unidentified manholes were defined name as below.
-

Unidentified Manhole in SW008280 : X1

Unidentified Manhole in SW008480 : X2

26. Correct the relationship of the following activities: ST013100, ST015800, ST013110,
ST015810, ST013140, WT005130, WT005230, RD008900, and ST003680.
Relationships were checked. Time gaps between activities came from
relationship of predecessors especially allocated Backfill activities. Provided
that you traced the logics you could find the reason why these time gaps
happened.
27. Correct the predecessor of activity ST008700.
Done
28. Identify/correct the description of activity code value Pavement Sub base Drainage
Pipe Laying which includes activity ST014480.
The description of activity code value Pavement Sub base Drainage was
derived from Bill of Quantity No. 6.48. We regarded this work as kind of pipe

6 of 10

laying.
29. Duration assigned for materials approval is 18 days; please explain why it exceeds
14 days.
Material Approval duration is corrected to 14 days
30. Correct the late finish dates of all activities in the following sections:
Remove/Abandon Existing Ducts / Cables.
Corrected as below
Activity ID

Description
Crossing

CH

8+636

Late Start

Late Finish

24-Jul-10

05-Aug-10

07-Aug-10

19-Aug-10

21-Aug-10

02-Sep-10

04-Sep-10

19-Sep-10

04-Sep-10

19-Sep-10

04-Sep-10

19-Sep-10

20-Sep-10

03-Oct-10

04-Oct-10

17-Oct-10

18-Oct-10

31-Oct-10

21-Aug-10

02-Sep-10

07-Aug-10

19-Aug-10

10-Jul-10

22-Jul-10

Remove/Abandon

TL003560
Existing Ducts
Crossing

CH

8+788

Remove/Abandon

TL003660
Existing Ducts
Crossing

CH

8+872

Remove/Abandon

TL003760
Existing Ducts
Crossing

CH

9+275

Remove/Abandon

TL003960
Existing Ducts
Crossing

CH

1+200

Remove/Abandon

TL004060
Existing Ducts
Crossing

CH

9+665

Remove/Abandon

TL004560
Existing Ducts
Crossing @ CH 10+085 : Remove/Abandon
TL005060
Existing Ducts
Crossing @ CH 10+360 : Remove/Abandon
TL005560
Existing Ducts
Crossing @ CH 10+450 : Remove/Abandon
TL006060
Existing Ducts
MH 8747 - MH 8748 : Remove/Abandon Existing
TL007260
Ducts
Crossing @ CH 10+935 : Remove/Abandon
TL007560
Existing Ducts
Crossing @ CH 11+100 : Remove/Abandon
TL007860
Existing Ducts

7 of 10

31. Follow up logical construction sequence for sorting sub-sections, like Site
Clearance which shown at the end of each construction section while it should be
at the beginning of each section.
Done

32. Correct the description of activity CNS210411; str#2 and replace it by str#3.
Replaced Correctly as below ;
-

Traffic Decking Removal [Sec. #2] : Unit 14 (Str.2)

Unit 14 in Structure No.3 should be addressed in Section 3.

33. Correct the predecessor of activities CNS230180 and CNS23023.


Existing Relationships for CNS230180 and CNS230230 are correct. The
logic between CNS230170 and CNS230180 was corrected in addition. (Time
gap came from Strut Installation was removed.)
34. Re-link all activities at Base Slab Section with its related activities at Water Proofing
and its predecessors in the same section, example: activity CNS250960.
These all logics between base slab and water proofing had been properly
related with each other.

35. All activities of Precast Box Beam Installation and Precast Girder Installation
should be linked to its relative activities in Fabrication section.
Activity ID PF000060 were connected with the earliest Installation activities
in each section.
36. Break down Civil Work activities shown in Electrical Work Section.
Civil Works for Electrical Works represents civil part works for executing
the electrical works. i.e. Excavation for cabling, concrete pouring and
foundation for traffic signal etc.Accordingly these activities were broken
down.
37. Add the following activities:
a. Method statements: should be submitted and approved before starting
construction activities, include and complete the same.

8 of 10

Added as below
1) Traffic Decking : DG000240 / DG000250
2) Utility Hanging Bridge : DG000270 / DG000280
3) Pedestrian Bridge : DG000300 / DG000430
4) Excavation Supporting System : DG000210 / DG000220
5) Pile Foundation : DG000760 / DG000770 / DG000780 / DG000790
6) Reinforced Concrete Works
DG000810 / DG000820 / DG000870 / DG000920 / DG000980
DG000880 / DG000890 / DG000910 / DG000970 / DG000990
7) Prestressed Concrete Works
DG001020 / DG001030 / DG001031
DG001040 / DG001050 / DG001060
8) Building Survey / Investigation : DG000051 / DG000052
b. Painting Concrete Structures.
Added as below
1) Section #1 : CNS160860 ~ CNS160970
2) Section #2 : CNS260840 ~ CNS260940
3) Section #3 : CNS360820 ~ CNS360910
4) Section #4 : CNS460900 ~ CNS461000

c. Lift Station.
Added: MCS40381
d. Metal Guard Railing.
Added: CNS461010
e. Aluminum Median Railing.
Added: CNS461070 ~ CNS461100
f. 11KV Switchgear
Added: EL001090

9 of 10

g. Smoke Detectors.
Added: ELS43000 ~ ELS43030
h. Elevators Installation.
Added: MCS40382
i.

Blinding slab below tunnel base slab.


Activities related with blinding slab were already included in water proofing
(base slab) activities.

38. The attached AD-01 Activity Status Report includes all activities with duration more
than 14 days; please break down activities to conform to the contract requirements,
or justify the assigned duration for each activity to us for approval.
All activities which needed detailed control were broken down to conform to
the contract requirements. Furthermore remaining activities over 21days are
not critical activities, it is no need to break down.

10 of 10

A1-4. Sign-off of Participated Subcontractors

SAMSUNGSAIFBINDARWISHJV
P.O.Box42654,AbuDhabi,UAE
Tel:+97126735073
Fax:+97126735065

Our Ref

: SSBD/PIL/SUB/0534/08

Electro Mechanical Company


P.O. Box 732
Abu Dhabi, U.A.E.
ATTENTION : Mr. A. R. Nixon / Project Manager
PROJECT
SUBJECT

Date : August 19, 2008

Tel. 02 672 21 64
Fax 02 626 98 71

: Upgrading Al Salam Street and Abu Dhabi City Ring Road


Contract No.1 (Al Salam Street Tunnel)
: Sign-off for Construction Program Submission

Reference Only

Sir,

With reference to Particular Specification clause 1.05 Construction Schedule, sub-clause


4. Submission d), 1) as attached herewith, we request your sign-off for participation and agreed
with the schedule development for our Construction Program which was submitted to the
consultant and the client.

SUBCONTRACTOR

TYPE OF WORK

Al Jurf

Tree Removal

Electro Mechanical Company

Temporary TCS

Heliopolis

132 KV

SIGNATURE

33KV,11KV,LV
MATAR

Telephone Work
Civil Works

MACE

Water Line Relocation


Sewer Line Relocation

Tetra

Irrigation
Storm Water

Sambo

Diaphragm Wall

Spaceage

Temporary Steel Lighting

PS/Janneth

1PageofTotal2Page

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 2
Basic Data
A2-1. Work Breakdown Structure
A2-2. Activity ID Structure
A2-3. Activity Coding System
A2-4. Numbering System & Type of Section
A2-5. Productivity Report
- Main Tunnel
- MEP
- Utilities & Detour works

SAMSUNG-SAIF BIN DARWISH JV

-2-

A2-1. Work Breakdown Structure


WBS LEVEL

.
1

.
2

.
3

.
4

.
5

Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
1st Level

2nd Level

3rd Level

4th Level

5th Level

6th Level

PHASE

AREA

MAJOR ITEMS

MINOR ITEMS

DIRECTION

LOCATION DETAILS

Description

Value

MILESTONES & PRELIMINARIES

AK

SITE ESTABLISHMENT
& MAINTENANCE

BS

Description

Value

GENERAL
SECTION NO.1

10
20

SECTION NO.2

30

SECTION NO.3
SECTION NO.4

40
50

Description

Value

GENERAL
etc

10

EMPLOYER'S OFFICE
SERVICES FOR EMPLOYER
DESIGNATED CONSULTANT'S OFFICE
SERVICES FOR DESIGNATED CONSULTANT
CONTRACTOR'S OFFICE
SERVICE FOR CONTRACTOR
ANCILLARY WORKS / MISC

10
20
30
40
50
60
70

SITE LABORATORY

80

PROVISIONAL SUM

CP

MARINE TRANSPORTATION FOR EXCAVATED MATERIALS


PARTITION WALL (CIP)

10
20

FINANCIAL

DF

PERFORMANCE BOND
ADVANCED PAYMENT BOND
INSURANCE

10
20
30

INITIAL SURVEY (TOPOGRAPHIC SURVEY)


SOIL INVESTIGATION
INSTRUMENTALS FOR MONITORING
BUILDING SURVEY / INVESTIGATION
UTILITY SURVEY / INVESTIGATION
PILE LOAD TEST
BACHYMETRY SURVEY (IF REQUIRED)

10
20
30
40
50
60
70

EXCAVATION SUPPORTING SYSTEM


TRAFFIC DECKING (TRAFFIC DETOUR SCHEME)
UTILITY HANGING BRIDGE
PEDESTRIAN ACCESS BRIDGE
DETOUR WORKS
SITE CLEARANCE & REMOVAL OF OBSTRUCTIONS
EARTHWORKS
PROTECTION OF UTILITIES & FUTURE DUCTS
STORM WATER DRAINAGE SYSTEM
WATERLINE RELOCATION WORKS
IRRIGATION RELOCATION WORKS
TELEPHONE LINE RELOCATION WORKS
SEWERAGE RELOCATION WORKS
PAVEMENT WORKS
TRAFFIC MARKINGS & SIGNS
STREET FURNITURE
SUBMISSION OF MAIN MATERIALS
APPROVAL OF MAIN MATERIALS

PROCUREMENT

SURVEY & INVESTIGATION

DS

DESIGN & SHOP DRAWING

ED

MATERIAL SUBMITTALS

EM

PROCUREMENT & FABRICATION

FP

10

GENERAL

10

Description
GENERAL / MISC
etc.

Value
10

Value

Description

Value

GENERAL / MISC
SOUTH & NORTH BOUND

Description

10
20

10
20

NORTH BOUND

30

SOUTH BOUND
WEST & EAST BOUND
WEST BOUND
EAST BOUND
SECTION OF UNIT WIDE
- PART "A" OF Units
- PART "B" OF Units
- PART "C" OF Units

40
50
60
70

GENERAL / MISC
MILESTONES
WATER PROOFING INCL. LEAN
CONCRETE
REBAR ERECTION
FORMWORKS
CONCRETE PLACING & CURING
FORM REMOVAL

Refer to "Remarks"

CONTRACTOR'S ALL RISKS


THIRD PARTITIES LIABILITY
WORKMEN'S COMPENSATION
CONTRACTOR'S EQUIPMENT & PLANT INSURANCE
AUTOMOBILE THIRD PARTIES INSURANCE

10
20
30
40
50

10
20
30
40
50
60
70
80
1A
1B
1C
1D
1E
2A
2B
2C
10
20

SUBMIT SHOP DRAWING


APPROVE SHOP DRAWING
SUBMIT METHOD STATEMENT
APPROVE METHOD STATEMENT

10
20
30
40

CONCRETE
REBAR
WATERPROOFING
FIRE PROTECTION
DETOUR WORKS
SITE CLEARANCE & REMOVAL OF OBSTRUCTIONS
EARTHWORKS
PROTECTION OF UTILITIES & FUTURE DUCTS
STORM WATER DRAINAGE SYSTEM
WATERLINE RELOCATION WORKS
IRRIGATION RELOCATION WORKS
TELEPHONE LINE RELOCATION WORKS
SEWERAGE RELOCATION WORKS
PAVEMENT WORKS
TRAFFIC MARKINGS & SIGNS
STREET FURNITURE

10
20
30
40
50
60
70
80
1A
1B
1C
1D
1E
2A
2B
2C

10

PROCUREMENT RELATED WITH PRECAST


PROCUREMENT RELATED WITH RC STRUCTURE
DETOUR WORKS
SITE CLEARANCE & REMOVAL OF OBSTRUCTIONS
EARTHWORKS

10
20
50
60
70

XXA
XXB
XXC

30
40
50
60
70

A2-1. Work Breakdown Structure


WBS LEVEL

.
1

.
2

.
3

.
4

.
5

Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
1st Level

2nd Level

3rd Level

4th Level

5th Level

6th Level

PHASE

AREA

MAJOR ITEMS

MINOR ITEMS

DIRECTION

LOCATION DETAILS

Description

Value

Description

Value

SHIPMENT & DELIVERY

GS

SUBCONTRACT PROCESS

HS

GENERAL

10

CONSTRUCTION

IC

GENERAL

10

GENERAL
MISCELLANEOUS
SECTION NO.1
SECTION NO.2
SECTION NO.3
SECTION NO.4

10
15
20
30
40
50

Description

Value

FABRICATION

10

DETOUR WORKS
SITE CLEARANCE & REMOVAL OF OBSTRUCTIONS
EARTHWORKS
PROTECTION OF UTILITIES & FUTURE DUCTS
STORM WATER DRAINAGE SYSTEM
WATERLINE RELOCATION WORKS
IRRIGATION RELOCATION WORKS
TELEPHONE LINE RELOCATION WORKS
SEWERAGE RELOCATION WORKS
PAVEMENT WORKS
TRAFFIC MARKINGS & SIGNS
STREET FURNITURE
GENERAL
MILESTONES
ENVIRONMENTAL CONSIDERATION : SAFETY & SECURITY
TEMPORARY FACILITIES
TRAFFIC CONTROL & DETOUR
EXCAVATE TO LOCATE
REMOVAL OF STREETLIGHT COLUMNS
REMOVAL OF STREETLIGHT FOUNDATIONS
REMOVAL OF PEDESTRIAN FENCE
REMOVAL OF BARRIERS, SIGNS, DISPLAYS
REMOVE / REPLANT TREES
REMOVAL OF SIGNAL CONTRIOLLER & MASTS
PROTECTION OF UTILITIES & FUTURE DUCTS

50
60
70
80
1A
1B
1C
1D
1E
2A
2B
2C
10
20
30
40
50
60
70
72
75
76
77
78
85

GENERAL

10

MILESTONES
SITE PREPARATION
EXCAVATION SUPPORTING SYSTEM

20
30
40

EARTHWORKS

50

PILE FOUNDATION

60

REINFORCED CONCRETE WORKS

70

Description

Value

PROTECTION OF UTILITIES & FUTURE DUCTS


STORM WATER DRAINAGE SYSTEM
WATERLINE RELOCATION WORKS
IRRIGATION RELOCATION WORKS
TELEPHONE LINE RELOCATION WORKS
SEWERAGE RELOCATION WORKS
PAVEMENT WORKS
TRAFFIC MARKINGS & SIGNS
STREET FURNITURE
PRECAST GIRDER
PRECAST BOX BEAM

80
1A
1B
1C
1D
1E
2A
2B
2C
10
20

PRECAST YARD
TRAFFIC DETOUR : CONSTRUCTION STAGE 1
TRAFFIC DETOUR : CONSTRUCTION STAGE 2
TRAFFIC DETOUR : CONSTRUCTION STAGE 3
TRIAL PITS

10
10
20
30
10

WATER DUCTS
IRRIGATION DUCTS
TELEPHONE DUCTS
SEWER DUCTS
PROTECTION OF WATER LINE
PROTECTION OF IRRIGATION LINE
PROTECTION OF TELEPHONE LINE
PROTECTION OF SEWER LINE
GRP SLEEVE FOR WATER LINE CROSSING
GRP SLEEVE FOR IRRIGATION LINE CROSSING
PVC SLEEVE FOR TELEPHONE LINE CROSSING
GENERAL / MISCELLANEOUS

10
20
30
40
50
60
70
80
1A
1B
1C
1D

SITE CLEARANCE & ACCESS


KING POST & STRUT INSTALLATION
KING POST & STRUT REMOVAL
DIAPHRAGM WALL
DEWATERING WORKS
EXCAVATION
BACKFILL
GRANULAR FILL
STRUCTURAL EXCAVATION
REMOVAL OF PEDESTRIAN UNDERPASS
GENERAL / MISCELLANEOUS
BORED PILE
PILE HEAD TREATMENT
WATER PROOFING INCL. LEAN CONCRETE
BASE SLAB
RETAINING WALL (1ST)

10
10
20
30
40
10
20
70
80
90
9A
10
20
30
10
20

Description

1ST LAYER
2ND LAYER

Value

10
20

Description

Value

A2-1. Work Breakdown Structure


WBS LEVEL

.
1

.
2

.
3

.
4

.
5

Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
1st Level

2nd Level

3rd Level

4th Level

5th Level

6th Level

PHASE

AREA

MAJOR ITEMS

MINOR ITEMS

DIRECTION

LOCATION DETAILS

Description

UTILITY RELOCATION & INSTALLATION

Value

JU

Description

GENERAL

Value

10

Description

Value

PRESTRESSED CONCRETE WORKS

80

ROAD PAVEMENT

90

ANCILLARY WORKS

100

Description

Value

RETAINING WALL (2ND)


CENTER WALL
ROOF SLAB
WATER PROOFING (WALL)
WATER PROOFING (ROOF)

30
40
50
60
70

PRECAST GIRDER INSTALLATION


PRECAST BOX BEAM INSTALLATION
EMBANKMENT/SUBGRADE WITH GEOTEXTILE
AGGREGATE ROAD BASE
ASPHALT BASE COURSE
ASPHALT WEARING COURSE
MILLING OF EXISTING ASPHALT
ASPHALT REGULATORY COURSE
ADJUST MANHOLES, INLETS, STRUCTURES etc
SAND ASPHALT
ASPHALT WEARING COURSE ON TUNNEL DECK
SLAB
ASPHALT
WEARING COURSE ON TUNNEL BASE
SLAB
GENERAL / MISCELLANEOUS

10
20
10
20
30
40
50
60
70
80
8A
8B
8C

EXPANSION & FIXED JOINTS


STREET FURNITURE
TRAFFIC MARKINGS & SIGNS
FIRE PROTECTION & FINISHES
ARCHITECTURAL FINISHES

10
20
30
50
60

STORM WATER DRAINAGE SYSTEM

10

EXCAVATION
PIPELAYING
MANHOLES / CHAMBERS
INLETS / CATCH BASINS
SLOTTED TRENCH DRAIN
PAVEMENT SUBBASE DRAINAGE
DI DRAIN PIPE
EXCAVATION AND PERFORATED PIPELAYING
NDRC DUCTS

10
20
30
40
50
60
70
80
90

WATER LINE RELOCATION WORKS

20

TRENCH EXCAVATION
PIPELAYING
BACKFILLING / REINSTATEMENT
VALVES, STRAINERS, etc
CHAMBERS
HOUSE CONNECTIONS
ANCHOR / THRUST BLOCKS
ABANDON / REMOVE EXISTING PIPELINES
CORROSION PROTECTION

10
20
30
40
50
60
70
80
90

IRRIGATION RELOCATION WORKS

30

EXCAVATION AND PIPELAYING


CONNECTION TO EXISTING LINE
VALVE CHAMBERS
MARKER PLATES
INSTRUMENTATION WORKS
REMOVE EXISTING IRRIGATION LINES

10
20
30
40
50
60

TELEPHONE LINE RELOCATION WORKS

40

LAYING OF TELEPHONE DUCTS


THRUST BORING
MANHOLES / CHAMBERS
ADJUSTMENT OF MANHOLE COVER LEVEL

10
20
30
40

SLEW / LOWER EXISTING TELEPHONE DUCTS

50

BACKFILLING / REINSTATEMENT WORKS


TELEPHONE LINE - CABLE LAYING

60
70

Description

Value

PUBLIC TELEPHONE BOOTH FOUNDATIONS


REMOVE EXISTING BUS SHELTER

10
20

ROAD MARKING OUTSIDE TUNNEL


ROAD STUDS OUTSIDE TUNNEL
TRAFFIC SIGNS OUTSIDE TUNNEL
GUIDE SIGNS / OVERHEAD TUBULAR SIGNS
ROAD MARKING INSIDE TUNNEL
ROAD STUDS INSIDE TUNNEL
TRAFFIC SIGNS INSIDE TUNNEL

10
20
30
40
50
60
70

Description

Value

A2-1. Work Breakdown Structure


WBS LEVEL

.
1

.
2

.
3

.
4

.
5

Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
1st Level

2nd Level

3rd Level

4th Level

5th Level

6th Level

PHASE

AREA

MAJOR ITEMS

MINOR ITEMS

DIRECTION

LOCATION DETAILS

Description

Value

Description

Value

Description

Value

Description
TELEPHONE LINE - CABLE TESTING AND
COMMISSIONING

SEWERAGE RELOCATION WORKS

TRANSCO SERVICES

ADDC SERVICES

MECHANICAL & ELECTRICAL WORKS

KM

GENERAL

10

50

100

110

MILITARY COMMUNICATION WORKS

120

MECHANICAL WORKS

10

LIGHTING & ELECTRICAL DISTRIBUTION WORKS

SCADA SYSTEM

20

30

Value

EXCAVATION AND SHEET PILE FOR PIPELAYING

10

PIPELAYING
BACKFILLING OF SEWER LINE
TESTING OF SEWER LINE
EXCAVATION AND SHEET PILE FOR MANHOLE
CONSTRUCTION OF MANHOLE
BACKFILLING OF MANHOLE
REINSTATEMENT OF SEWER LINE
OVERPUMPING OF SEWERLINE

20
30
40
50
60
70
80
90

RELOCATION OF EXISTING132KV XLPE CABLE


CIRCUIT "A"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "B"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "C"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "D"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "E"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "F"
RELOCATION OF EXISTING132KV XLPE CABLE
CIRCUIT "G"
RELOCATION OF EXISTING 33KV XLPE CABLE
CIRCUIT
RELOCATION OF EXISTING 11KV XLPE CABLE
CIRCUIT
RELOCATION OF EXISTING LV XLPE CABLE
CIRCUIT

Description

Value

ANCHORING & SUPPORTING


MAIN MISTING & FIRE LANDING VALVE PIPE
STEEL FRAME FOR DUCT & SMOKE DAMPERS
TUNNEL FIRE RATED DUCT
DUCT PRESSURE TESTING
MECHNICAL FIXTURES
VENTILATION FANS
TUNNEL DAMPER
DRAINAGE PUMP & PIPING
FIRE FIGHTING & MISTING PUMP
UTILITY BUILDING PIPING
INSTALLATION OF LIFT
PLUMBING & SANITARY WORKS

10
20
30
40
50
60
10
20
30
40
50
60
70

ANCHORING & SUPPORTING


CABLE TRAY & CONDUIT
CONTROL & POWER CABLES
ELECTRICAL FIXTURE
CONDUIT & WALL BOX
EMERGENCY GENERATOR & TR
CABLE TRAY & CONDUIT
CONTROL PANEL & FIXTURES
CABLING & CONNECTION WORKS
ELECTRICAL FIXTURES

10
20
30
40
10
20
30
40
50
60

80

10
20
30
40
50
60
70
10
20
30

DEVELOPMENT OF EXISTING 11KV CABLE CIRCUIT

40

DEVELOPMENT OF EXISTING LV CABLE CIRCUIT

50

PRECONSTRUCTION FOR MECHANICAL WORKS


MECHANICAL WORKS FOR TUNNEL

10
20

MECHANICAL WORKS FOR UTILITY ROOMS

30

TESTING

40

PRECONSTRUCTION FOR ELECTRICAL WORKS


ELECTRICAL WORKS FOR TUNNEL

10
20

ELECTRICAL WORKS FOR UTILITY ROOMS

30

TESTING

40

SCADA SYSTEM PROGRAM


INSTALLATION OF SCADA CABLE
INSTALLATION OF SCADA EQUIPMENT

10
20
30

Description

Value

A2-1. Work Breakdown Structure


WBS LEVEL

.
1

.
2

.
3

.
4

.
5

Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
1st Level

2nd Level

3rd Level

4th Level

5th Level

6th Level

PHASE

AREA

MAJOR ITEMS

MINOR ITEMS

DIRECTION

LOCATION DETAILS

Description

Value

Description

Value

Description

Value

TRAFFIC CONTROL SYSTEM

40

SITE TESTING & COMMISSIONING

LS

GENERAL

10

TUNNEL OPERATIONS & MAINTENANCE


INSPECTION
TESTING & COMMISSIONING
DAILY WORKS

10
20
30
40

HAND OVER

MH

PRELIMINARY

10

GENERAL

10

FINAL

20

Remarks)
- Naming of Parts for each Units as below :
Unit 25

Part "A"
25A

Part "B"
25B

Construction
j i t

Part "C"
25C

Expansion joint

Description

Value

TRAFFIC CONTROL SYSTEM PROGRAM


INSTALLATION OF TCS CABLE
INSTALLATION OF TCS EQUIPMENT
INSTALLATION OF VMS / CCTV / LSCS

10
20
30
40

GENERAL / MISC

10

Description

Value

Description

Value

A2-2. Activity ID Structure & Numbering System


Project : Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

1. Activity ID Structure
K

Work Type

Zone

Serial No.

a) Type of Works
Code
KD
ST
PS
FN
IS
DG
PF
SD
SU
CN
DT
ST
SW
WT
IR
EL
TL
MC
SC
HN

Description
MILESTONES
SITE ESTABLISHMENT
PROVISIONAL SUM
FINANCIAL
INITIAL TESTING / SURVEY / IINVESTIGATION
DESIGN
PROCUREMENT & FABRICATION
SHIPMENT & DELIVERY
SUBCONTRACT PROCESS
CONSTRUCTION
DETOUR WORKS
STORM WATER
SEWER
WATER
IRRIGATION
ELECTRICAL WORKS
TELEPHONE
MECHANICAL WORKS
SITE TESTING & COMMISSIONING
HAND OVER

b) Zone
Code
00
S1
S2
S3
S4

Description
General & Milestones
Section 1 (Section Wide)
Section 2
Section 3
Section 4

2. Numbering System for Activity Description


a) Abbreviation
D
B
K
S
B
L
G
R
N
S
E
W

Diaphragm Wall
Bored Pile
King Post
Strut & Wales
Base Slab
Wall
PC Girder
Roof Slab
Direction - North
Direction - South
Direction - East
Direction - West

b) Detail Information of Numbering System & Design Units


Refer to attached "Appendix 2-4"

Example
KD000010
CNS10010 / DGS20010
CNS21010 / FN000010
CNS30010
CNS40010

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
PHAS
KD
PR
ST
PS
FN
IS
DG
PF
SD
SU
DT
CN
UT
ME
EL
SC
HN
AREA1
GEN
MS
SEC1
SEC2
SEC3
SEC4
AREA2
PROJ
IP41A
37
IP41
IP12
IP9
IP11
IP11A
IP36
IP56
37A37B
37B38C
38C38A
38A39A
39A41A
41-39
39-38
38-38A
38-38B
38B11A
11-38
9 - 39
9-17
11-10
11A11B
4436NB
4436SB
3611AN
3611AS
1241EB
1241WB
4141A5
4141AD
55D41A
5541AE
5541AW
41A
41A-41
41A41E
41A41W
41
41-12
4112EB
4112WB

Description

MILESTONES
PRELIMINARY ACTIVITIES
SITE ESTABLISHMENT & MAINTENANCE
PROVISIONAL SUM
FINANCIAL
INVESTIGATION & SURVEY
DESIGN & SHOP DRAWINGS
PROCUREMENT & FABRICATION
SHIPMENT & DELIVERY
SUBCONTRACT PROCESS
DETOUR WORKS
CONSTRUCTION
UTILITY RELOCATION & INSTALLATION
MECHANICAL WORKS
ELECTRICAL WORKS
SITE TESTING & COMMISSIONING
HAND OVER
General
Milestones
Section No.1 (L.O.C ~ STA. 9+381)
Section No.2 (STA. 9+381 ~ STA. 9+954)
Section No.3 (STA. 9+954 ~ STA. 10+704)
Section No.4 (STA. 10+704 ~ STA. 11+525)
PROJECT WIDE
Intersection Point : IP-41A
IP 37
Intersection Point : IP-41
Intersection Point : IP-12
Intersection Point : IP-9
Intersection Point : IP-11
Intersection Point : IP-11A
Intersection Point : IP-36
Intersection Point : IP-56
IP37A - IP37B
IP37B - IP38C
IP38C - IP38A
IP38A - IP39A
IP39A - IP41A
IP41 - IP39
IP39 - IP38
IP38 - IP38A
IP38 - IP38B
IP38B - IP11A
IP11 - IP38
IP9 - IP39
IP9 - IP17
IP11- IP10
IP11A - IP11B
IP44 - IP36 NB
IP44 - IP36 SB
IP36 - IP11A NB
IP36 - IP11A SB
IP12 - IP41 EB
IP12 - IP41 WB
IP41 - IP41A - IP55D EB
IP41- IP 41A - IP 55D WB
IP55D - IP 41A
IP55D - IP41A EB
IP55D - IP41A WB
IP 41A
IP41A - IP41
IP41A - IP41 EB
IP41A - IP41 WB
IP41
IP41 - IP12
IP41 - IP12 EB
IP41 - IP12 WB

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
12-56
1256NB
1256SB
12
12-9
129NB
129SB
9
9-11
911NB
911SB
11
11-11A
1111AN
1111AS
11A
11A36A
1136AN
1136AS
36A
36A-36
36A36N
36A36S
36
36-44
3644NB
3644SB
11A-36
GEN
AREA3
S1112
EMT
GEN
S1231A
S13A13
S1314
S1415
S1516
S1617
S1718
S1819
S1920
S2021
S2122
S2223
S2324
S2425
S2526
S2627
S2728
S2829
S2930
S3031
S3132
S3233
S3334
S3435
S3536
S3637
S3738
S3839
S3940
S4041
S4142
S4243
S4344
S4445
S4546
S4647
S4748
S4849

Description
IP12 - IP56
IP12 - IP56 NB
IP12 - IP56 SB
IP12
IP12 - IP9
IP12 - IP9 NB
IP12 - IP9 SB
IP 9
IP9 - IP11
IP9 - IP11 NB
IP9 - IP11 SB
IP 11
IP11 - IP11A
IP11 - IP11A NB
IP11 - IP11A SB
IP 11A
IP11A - IP36A
IP11A - IP36A NB
IP11A - IP36A SB
IP36A
IP36A - IP36
IP36A - IP36 NB
IP36A - IP36 SB
IP36
IP36 - IP44
IP36 - IP44 NB
IP36 - IP44 SB
IP11A - IP36
GENERAL
MH 11 - MH 12
General
MH 12 - MH 13A
MH 13A - MH 13
MH 13 - MH 14
MH 14 - MH 15
MH 15 - MH 16
MH 16 - MH 17
MH 17 - MH 18
MH 18 - MH 19
MH 19 - MH 20
MH 20 - MH 21
MH 21 - MH 22
MH 22 - MH 23
MH 23 - MH 24
MH 24 - MH 25
MH 25 - MH 26
MH 26 - MH 27
MH 27 - MH 28
MH 28 - MH 29
MH 29 - MH 30
MH 30 - MH 31
MH 31 - MH 32
MH 32 - MH 33
MH 33 - MH 34
MH 34 - MH 35
MH 35 - MH 36
MH 36 - MH 37
MH 37 - MH 38
MH 38 - MH 39
MH 39 - MH 40
MH 40 - MH 41
MH 41 - MH 42
MH 42 - MH 43
MH 43 - MH 44
MH 44 - MH 45
MH 45 - MH 46
MH 46 - MH 47
MH 47 - MH 48
MH 48 - MH 49

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
S4950
S50501
S5051
S5152
S5253
S5354
S5455
S5556
S5657
S5758
S5859
S5960
S58DC
SMH12
SMH13A
SMH13
SMH14
SMH15
SMH16
SMH17
SMH18
SMH19
SMH20
SMH21
SMH22
SMH23
SMH24
SMH25
SMH26
SMH27
SMH28
SMH29
SMH30
SMH31
SMH32
SMH33
SMH34
SMH35
SMH36
SMH37
SMH38
SMH39
SMH40
SMH41
SMH42
SMH43
SMH44
SMH45
SMH46
SMH47
SMH48
SMH49
SMH50
SMH501
SMH51
SMH52
SMH53
SMH54
SMH55
SMH56
SMH57
SMH58
MS
SMH59
SMH60
DA1A2
DA2A3
DA3A4
DA4A5
DA5A6
DA6A7

Description
MH 49 - MH 50
MH 50 - MH 50/1
MH 50 - MH 51
MH 51 - MH 52
MH 52 - MH 53
MH 53 - MH 54
MH 54 - MH 55
MH 55 - MH 56
MH 56 - MH 57
MH 57 - MH 58
MH 58 - MH 59
MH 59 - MH 60
MH 58 - DC
SEWER MANHOLE No.12
SEWER MANHOLE No.13A
SEWER MANHOLE No.13
SEWER MANHOLE No.14
SEWER MANHOLE No.15
SEWER MANHOLE No.16
SEWER MANHOLE No.17
SEWER MANHOLE No.18
SEWER MANHOLE No.19
SEWER MANHOLE No.20
SEWER MANHOLE No.21
SEWER MANHOLE No.22
SEWER MANHOLE No.23
SEWER MANHOLE No.24
SEWER MANHOLE No.25
SEWER MANHOLE No.26
SEWER MANHOLE No.27
SEWER MANHOLE No.28
SEWER MANHOLE No.29
SEWER MANHOLE No.30
SEWER MANHOLE No.31
SEWER MANHOLE No.32
SEWER MANHOLE No.33
SEWER MANHOLE No.34
SEWER MANHOLE No.35
SEWER MANHOLE No.36
SEWER MANHOLE No.37
SEWER MANHOLE No.38
SEWER MANHOLE No.39
SEWER MANHOLE No.40
SEWER MANHOLE No.41
SEWER MANHOLE No.42
SEWER MANHOLE No.43
SEWER MANHOLE No.44
SEWER MANHOLE No.45
SEWER MANHOLE No.46
SEWER MANHOLE No.47
SEWER MANHOLE No.48
SEWER MANHOLE No.49
SEWER MANHOLE No.50
SEWER MANHOLE No. 50/1
SEWER MANHOLE No.51
SEWER MANHOLE No.52
SEWER MANHOLE No.53
SEWER MANHOLE No.54
SEWER MANHOLE No.55
SEWER MANHOLE No.56
SEWER MANHOLE No.57
SEWER MANHOLE No.58
Milestones
SEWER MANHOLE No.59
SEWER MANHOLE No.60
MH A1 - MH A2
MH A2 - MH A3
MH A3 - MH A4
MH A4 - MH A5
MH A5 - MH A6
MH A6 - MH A7

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
DA7A8
DA8A9
DA9A10
DA1011
DA1112
DA1213
DA1314
DB0B1
DB1B2
DB2B3
DB3B4
DB4B5
DB5B6
DB6B7
DB7B8
DB8B9
DB9B10
DB1011
DB1112
DB1213
DB1314
DB1415
DB1516
DB0C1
DC1C2
DC2C3
DC3C4
DC4C5
DC5C6
DC6C7
DC7C8
DC8C9
DD0D1
DD1D2
DD2D3
DD3D4
DD4D5
DD5D6
DD6D7
DD7D8
DD0E1
DE1E2
DE2E3
OUTFAL
DOUTF1
DF1PUM
DPUMF2
DF2F3
DF3F4
DF4F5
DF5F6
DF6F6A
DF6AF7
DF7F8
DF8F9
DF9F10
DF1011
DF1112
D1212A
D12A13
DF1314
DF1415
DF1516
DF1617
DF1718
DF1819
DF1920
DF2021
DF2122
DF2223
DF2324

Description
MH A7 - MH A8
MH A8 - MH A9
MH A9 - MH A10
MH A10 - MH A11
MH A11 - MH A12
MH A12 - MH A13
MH A13 - MH A14
MH B0 - MH B1
MH B1 - MH B2
MH B2 - MH B3
MH B3 - MH B4
MH B4 - MH B5
MH B5 - MH B6
MH B6 - MH B7
MH B7 - MH B8
MH B8 - MH B9
MH B9 - MH B10
MH B10 - MH B11
MH B11 - MH B12
MH B12 - MH B13
MH B13 - MH B14
MH B14 - MH B15
MH B15 - MH B16
MH B0 - MH C1
MH C1 - MH C2
MH C2 - MH C3
MH C3 - MH C4
MH C4 - MH C5
MH C5 - MH C6
MH C6 - MH C7
MH C7 - MH C8
MH C8 - MH C9
MH D0 - MH D1
MH D1 - MH D2
MH D2 - MH D3
MH D3 - MH D4
MH D4 - MH D5
MH D5 - MH D6
MH D6 - MH D7
MH D7 - MH D8
MH D0 - MH E1
MH E1 - MH E2
MH E2 - MH E3
OUTFALL
OUTFALL - MH F1
MH F1 - PUMP STATION
PUMP STATION - MH F2
MH F2 - MH F3
MH F3 - MH F4
MH F4 - MH F5
MH F5 - MH F6
MH F6 - MH F6A
MH F6A - MH F7
MH F7 - MH F8
MH F8 - MH F9
MH F9 - MH F10
MH F10 - MH F11
MH F11 - MH F12
MH F12 - MH F12A
MH F12A - MH F13
MH F13 - MH F14
MH F14 - MH F15
MH F15 - MH F16
MH F16 - MH F17
MH F17 - MH F18
MH F18 - MH F19
MH F19 - MH F20
MH F20 - MH F21
MH F21 - MH F22
MH F22 - MH F23
MH F23 - MH F24

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
DF2425
DF2526
DF2627
DF2728
DF2829
DF2930
DF3031
DF3132
DF3233
DF3334
DF3435
DF3536
DF3637
DF3738
DF3839
DF3940
DF4041
DF4142
DF4243
DF4344
DF4445
BA
DF4546
DF4647
PSOUT1
PSOUT2
DF36G1
DG1DG2
DRESH1
DH1H2
DH2H3
DH3H4
DH4H5
DH5H6
DH6H7
DH7H8
DH8H9
DH9H10
DH1011
DJ6J5
DJ5J5A
DJ5J4
DJ4J4A
DJ4J3
DJ3J3A
DJ3J2
DJ2J1
DJ1RES
DJ7RES
DJ8J7
DA1
DA2
DA3
DA4
DA5
DA6
DA7
DA8
DA9
DA10
DA11
DA12
DA13
DA14
DB0
DB1
DB2
DB3
DB4
DB5
DB6

Description
MH F24 - MH F25
MH F25 - MH F26
MH F26 - MH F27
MH F27 - MH F28
MH F28 - MH F29
MH F29 - MH F30
MH F30 - MH F31
MH F31 - MH F32
MH F32 - MH F33
MH F33 - MH F34
MH F34 - MH F35
MH F35 - MH F36
MH F36 - MH F37
MH F37 - MH F38
MH F38 - MH F39
MH F39 - MH F40
MH F40 - MH F41
MH F41 - MH F42
MH F42 - MH F43
MH F43 - MH F44
MH F44 - MH F45
Base
MH F45 - MH F46
MH F46 - MH F47
PUMP STATION - OUTFALL (500 mm dia)
PUMP STATION - OUTFALL (300 mm dia)
MH F36 - MH G1
MH G1 - MH G2
RESERVOIR @ CH 8+700 - MH H1
MH H1 - MH H2
MH H2 - MH H3
MH H3 - MH H4
MH H4 - MH H5
MH H5 - MH H6
MH H6 - MH H7
MH H7 - MH H8
MH H8 - MH H9
MH H9 - MH H10
MH H10 - MH H11
MH J6 - MH J5
MH J5 - MH J5A
MH J5 - MH J4
MH J4 - MH J4A
MH J4 - MH J3
MH J3 - MH J3A
MH J3 - MH J2
MH J2 - MH J1
MH J1 - RESERVOIR @ CH 9+650
MH J7 - RESERVOIR @ CH 9+650
MH J8- MH J7
STORM WATER MANHOLE No. A1
STORM WATER MANHOLE No. A2
STORM WATER MANHOLE No. A3
STORM WATER MANHOLE No. A4
STORM WATER MANHOLE No. A5
STORM WATER MANHOLE No. A6
STORM WATER MANHOLE No. A7
STORM WATER MANHOLE No. A8
STORM WATER MANHOLE No. A9
STORM WATER MANHOLE No. A10
STORM WATER MANHOLE No. A11
STORM WATER MANHOLE No. A12
STORM WATER MANHOLE No. A13
STORM WATER MANHOLE No. A14
STORM WATER MANHOLE No. B0
STORM WATER MANHOLE No. B1
STORM WATER MANHOLE No. B2
STORM WATER MANHOLE No. B3
STORM WATER MANHOLE No. B4
STORM WATER MANHOLE No. B5
STORM WATER MANHOLE No. B6

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
DB7
DB8
DB9
DB10
DB11
DB12
DB13
DB14
DB15
DB16
DC1
DC2
DC3
DC4
DC5
DC6
DC7
DC8
DC9
DD0
DD1
DD2
DD3
DD4
DD5
DD6
DD7
DD8
DE1
DE2
DE3
DF1
DF2
DF3
DF4
DF5
DF6
DF6A
DF7
DF8
DF9
DF10
DF11
DF12
DF12A
DF13
DF14
DF15
DF16
DF17
DF18
SW
DF19
DF20
DF21
DF22
DF23
DF24
DF25
DF26
DF27
DF28
DF29
DF30
DF31
DF32
DF33
DF34
DF35
DF36
DF37

Description
STORM WATER MANHOLE No. B7
STORM WATER MANHOLE No. B8
STORM WATER MANHOLE No. B9
STORM WATER MANHOLE No. B10
STORM WATER MANHOLE No. B11
STORM WATER MANHOLE No. B12
STORM WATER MANHOLE No. B13
STORM WATER MANHOLE No. B14
STORM WATER MANHOLE No. B15
STORM WATER MANHOLE No. B16
STORM WATER MANHOLE No. C1
STORM WATER MANHOLE No. C2
STORM WATER MANHOLE No. C3
STORM WATER MANHOLE No. C4
STORM WATER MANHOLE No. C5
STORM WATER MANHOLE No. C6
STORM WATER MANHOLE No. C7
STORM WATER MANHOLE No. C8
STORM WATER MANHOLE No. C9
STORM WATER MANHOLE No. D0
STORM WATER MANHOLE No. D1
STORM WATER MANHOLE No. D2
STORM WATER MANHOLE No. D3
STORM WATER MANHOLE No. D4
STORM WATER MANHOLE No. D5
STORM WATER MANHOLE No. D6
STORM WATER MANHOLE No. D7
STORM WATER MANHOLE No. D8
STORM WATER MANHOLE No. E1
STORM WATER MANHOLE No. E2
STORM WATER MANHOLE No. E3
STORM WATER MANHOLE No. F1
STORM WATER MANHOLE No. F2
STORM WATER MANHOLE No. F3
STORM WATER MANHOLE No. F4
STORM WATER MANHOLE No. F5
STORM WATER MANHOLE No. F6
STORM WATER MANHOLE No. F6A
STORM WATER MANHOLE No. F7
STORM WATER MANHOLE No. F8
STORM WATER MANHOLE No. F9
STORM WATER MANHOLE No. F10
STORM WATER MANHOLE No. F11
STORM WATER MANHOLE No. F12
STORM WATER MANHOLE No. F12A
STORM WATER MANHOLE No. F13
STORM WATER MANHOLE No. F14
STORM WATER MANHOLE No. F15
STORM WATER MANHOLE No. F16
STORM WATER MANHOLE No. F17
STORM WATER MANHOLE No. F18
Side Wall
STORM WATER MANHOLE No. F19
STORM WATER MANHOLE No. F20
STORM WATER MANHOLE No. F21
STORM WATER MANHOLE No. F22
STORM WATER MANHOLE No. F23
STORM WATER MANHOLE No. F24
STORM WATER MANHOLE No. F25
STORM WATER MANHOLE No. F26
STORM WATER MANHOLE No. F27
STORM WATER MANHOLE No. F28
STORM WATER MANHOLE No. F29
STORM WATER MANHOLE No. F30
STORM WATER MANHOLE No. F31
STORM WATER MANHOLE No. F32
STORM WATER MANHOLE No. F33
STORM WATER MANHOLE No. F34
STORM WATER MANHOLE No. F35
STORM WATER MANHOLE No. F36
STORM WATER MANHOLE No. F37

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
DF38
DF39
DF40
DF41
DF42
DF43
DF44
DF45
DF46
DF47
DG1
DG2
DH1
DH2
DH3
DH4
DH5
DH6
DH7
DH8
DH9
DH10
DH11
DJ6
DJ5
DJ5A
DJ4
DJ4A
DJ3
DJ3A
DJ2
DJ1
DJ7
DJ8
J1J2
J2J3
J3J4
J3J5
J6J7
J8J9
J9J10
J10J11
J11J12
J13J14
J15J16
J16J17
J17J18
J19J20
J20J21
J21J22
J22J23
J23J24
J24J25
J25J26
J24J27
J27J28
J28J29
J29J30
J31J32
J32J33
J33J34
J34J35
J35J36
J36J37
J37J33
J37J38
J38J39
J39J40
J40J41
J40J42
J42J43

Description
STORM WATER MANHOLE No. F38
STORM WATER MANHOLE No. F39
STORM WATER MANHOLE No. F40
STORM WATER MANHOLE No. F41
STORM WATER MANHOLE No. F42
STORM WATER MANHOLE No. F43
STORM WATER MANHOLE No. F44
STORM WATER MANHOLE No. F45
STORM WATER MANHOLE No. F46
STORM WATER MANHOLE No. F47
STORM WATER MANHOLE No. G1
STORM WATER MANHOLE No. G2
STORM WATER MANHOLE No. H1
STORM WATER MANHOLE No. H2
STORM WATER MANHOLE No. H3
STORM WATER MANHOLE No. H4
STORM WATER MANHOLE No. H5
STORM WATER MANHOLE No. H6
STORM WATER MANHOLE No. H7
STORM WATER MANHOLE No. H8
STORM WATER MANHOLE No. H9
STORM WATER MANHOLE No. H10
STORM WATER MANHOLE No. H11
STORM WATER MANHOLE No. J6
STORM WATER MANHOLE No. J5
STORM WATER MANHOLE No. J5A
STORM WATER MANHOLE No. J4
STORM WATER MANHOLE No. J4A
STORM WATER MANHOLE No. J3
STORM WATER MANHOLE No. J3A
STORM WATER MANHOLE No. J2
STORM WATER MANHOLE No. J1
STORM WATER MANHOLE No. J7
STORM WATER MANHOLE No. J8
CROSSING @ CH 8+300
MH @CH 8+300 EB - MH 65211
MH 65211 - MH 65104
MH 65211 - MH 15465
MH 65212 - MH 65105
MH 65464 - MH 65210
MH 65210 - MH 65209
MH 65209 - MH 65182
MH 65182 - MH 66852
MH 65208 - MH 11280
MH 8677 - MH 65181
MH 65181 - MH 65207
MH 65207 - MH 8723
MH 8701 - MH 50036
MH 50036 - MH 65205
MH 65205 - MH 65203
MH 65203 - MH 65204
MH 65204 - MH 65202
MH 65202 - MH 50035
MH 50035 - MH 8702
MH 65202 - MH 65206
MH 65206 - MH 65185
MH 65185 - MH 65184
MH 65184 - MH 8740
MH 8704 - MH 50034
MH 50034 - MH 65197
MH 65197 - MH 65169
MH 65169 - MH 20006
MH 20006 - MH 65194
MH 65194 - MH 65198
MH 65198 - MH 65197
MH 65198 - MH 65108
MH 65108 - MH 65109
MH 65109 - MH 65201
MH 65201 - MH 8708
MH 65201 - MH 8747
MH 8747 - MH 65200

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
J43J44
J44J45
J45J46
J45J47
J49J50
J1
J2
J3
J4
J6
CW
J7
J9
J10
J11
J12
J13
J16
J17
J20
J21
J22
J23
J24
J25
J27
J28
J29
J32
J33
J34
J36
J37
J38
J39
J40
J43
J45
J46
83856
8380CR
838600
860806
92377N
92377E
93377S
92390W
92390S
9387CR
9400SS
9400SE
942668
966790
979962
996062
10105C
10149S
104935
103537
103735
1035C1
1035C2
10638A
10638B
10895A
10895B
10959A
10959B
106820
102037
103742

Description
MH 65200 - MH 8748
MH 8748 - MH 65163
MH 65163 - MH 50027
MH 65163 - MH 20355
MH 50026 - MH 5290
MH @ CH 8+300 WB
MH @ CH 8+300 EB
MH 65211
MH 65104
MH 65212
Center Wall
MH 65105
MH 65210
MH 65209
MH 65182
MH 66852
MH 65208
MH 65181
MH 65207
MH 50036
MH 65205
MH 65203
MH 65204
MH 65202
MH 50035
MH 65206
MH 65185
MH 65184
MH 50034
MH 65197
MH 65169
MH 65194
MH 65198
MH 65108
MH 65109
MH 65201
MH 65200
MH 65163
MH 50027
CH 8+380 - CH 8+560 EB
CH 8+380 CROSSING
CH 8+380 - CH 8+600 WB
CH 8+600 - CH 8+806 WB
CH 9+204 - CH 9+377 EB NORTH
CH 9+204 - CH 9+377 EB EAST
CH 9+204 - CH 9+377 EB SOUTH
CH 9+283 - CH 9+390 WB WEST
CH 9+283 - CH 9+390 WB SOUTH
CH 9+387 UTILITY CROSSING - CS PIPELINE
CH 9+400 SB SOUTH
CH 9+400 SB EAST
CH 9+428 - CH 9+668 SB
CH 9+668 - CH 9+790 SB
CH 9+790 - CH 9+962 SB
CH 9+962 - CH 10+062 SB
CH 10+105 UTILITY CROSSING
CH 10+083 - CH 10+149 SB
CH 10+149 - CH 10+335 SB
CH 10+335 - CH 10+437 SB
CH 10+437 - CH 10+635 SB
CH 10+635 UTILITY CROSSING (300 mm dia.)
CH 10+635 UTILITY CROSSING (900 mm dia.)
CH 10+635 - CH 10+800 SB (600 mm dia.)
CH 10+635 - CH 10+800 SB (900 mm dia.)
CH 10+800 - CH 10+950 SB (600 mm dia.)
CH 10+800 - CH 10+950 SB (900 mm dia.)
CH 10+950 - CH 11+090 SB (600 mm dia.)
CH 10+950 - CH 11+090 SB (900 mm dia.)
CH 10+068 - CH 10+200 NB
CH 10+200 - CH 10+375 NB
CH 10+375 - CH 10+428 NB

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
104235
11036N
113681
118125
112540
114046
11090C
VC1PR1
VC2PR4
PR4VC3
PR3FC
VC441A
VC541A
VC6PR8
PR8FC
PR841
VC741
PR9FC
FM12
FM2P10
PR10VC
VC10E
VC910
FM3EX
FM3P12
P12AV1
AV1V16
PR11FC
V17V16
V17WC1
WC1V18
V18V19
V19V20
V16WC2
W2PR13
V21V22
V22V23
V23V24
V24FM4
RF
V25V27
V26V27
V27AV2
AV2P16
P16V29
V28A3W
V28A3N
V28A3E
A3VC30
V30V29
V30VN4
(New)-12
(New)-7
(New)-8
(New)-11
PART-1
PART-2
PART-3
STAGE2
STAGE3
7495
7495-1
8000
8100
8200
8300
8400
8500
8600
8650
8700

Description
CH 10+428 - CH 10+635 NB
CH 11+036 NB
CH 11+036 - CH 11+081 NB
CH 11+081 - CH 11+250 NB
CH 11+250 - CH 11+400 NB
CH 11+400 - CH 11+546 NB
CH 11+090 UTILITY CROSSING
VC 1 - PRVC 1
VC 2 - PRVC 4
PRVC 4 - VC 3
PRVC 3 - FUTURE CONNECTION
VC 4 - IP 41A
VC 5 - IP 41A
VC 6 - PRVC 8
PRVC 8 - FUTURE CONNECTION
PRVC 8 - IP 41
VC 7 - IP 41
PRVC9 - FUTURE CONNECTION
FLOWMETER 1 - 2
FLOWMETER 2 - PRVC 10
PRVC 10 - EXISTING VC
VC10E
VC 9 - VC 10
FLOWMETER 3 - EXISTING LINE
FLOWMETER 3 - PRVC 12
PRVC 12 - AV 1
AV 1 - VC 15 - VC 16
PRVC 11 - FUTURE CONNECTION @ 9+300 EB
VC 17 - VC 16
VC 17 - WC 1
WC 1 - VC 18
VC 18 - VC 19
VC 19 - VC 20
VC 16 - WC 2
WC 2 - PRVC 13
VC 21 - VC 22
VC 22 - VC 23
VC 23 - VC 24
VC 24 - VC 25 - FM 4
Roof Slab
VC 25 - VC 27
VC 26 - VC 27
VC 27 - AV 2
AV 2 - PRVC 16
PRVC 16 - FM 6 - VC 29
VC 28 - AV 3 WEST
VC 28 - AV 3 NORTH
VC 28 - AV 3 EAST
AV 3 - VC 30
VC 30 - VC 29
VC 30 - FM 7 - VC N4
(New Code Value)
(New Code Value)
(New Code Value)
(New Code Value)
STAGE 1 : PART - 1
STAGE 1 : PART - 2
STAGE 1 : PART - 3
STAGE 2
STAGE 3
CH 7+495 - 8+000
CH 7+495 - 9+000
CH 8+000 - 8+100
CH 8+100 - 8+200
CH 8+200 - 8+300
CH 8+300 - 8+400
CH 8+400 - 8+500
CH 8+500 - 8+600
CH 8+600 - 8+650
CH 8+650 - 8+700
CH 8+700 - 8+810

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
8810
8890
9000
Jan-00
9100
9200
9300
9380
9500
9600
9670
9750
9800
9900
9980
10000
10080
10200
10300
10350
10450
10500
10600
10700
10780
10900
11000
11020
11100
11200
11300
11400
1000
1000-1
RAMP
1100
S2U1
WIDE3
SECT3
MH
CH
MAJOR
EMT
MOBI
GEN
NOCAPP
SURVEY
MS
NOC
ENV
SHOPDR
MATERL
DELMAT
MAR
PAR
PFB
APB
ISR
PRE
SIL
SUR
SIT
MOR
BSI
UTS
PLT
BYS
TWS
DEK
UHB
PAB

Description
CH 8+810 - 8+890
CH 8+890 - 9+000
CH 9+000 - 9+100
CH 9+000 - 10+000
CH 9+100 - 9+200
CH 9+200 - 9+300
CH 9+300 - 9+380
CH 9+380 - 9+500
CH 9+500 - 9+600
CH 9+600 - 9+670
CH 9+670 - 9+750
CH 9+750 - 9+800
CH 9+800 - 9+900
CH 9+900 - 9+980
CH 9+980 - 10+080
CH 10+000 - 11+000
CH 10+080 - 10+200
CH 10+200 - 10+300
CH 10+300 - 10+350
CH 10+350 - 10+450
CH 10+450 - 10+500
CH 10+500 - 10+600
CH 10+600 - 10+700
CH 10+700 - 10+780
CH 10+780 - 10+900
CH 10+900 - 11+020
CH 11+000 - 11+525
CH 11+020 - 11+100
CH 11+100 - 11+200
CH 11+200 - 11+300
CH 11+300 - 11+400
CH 11+400 - 11+525
CH 1+000 - 1+100
CH 1+000 - 1+220
IP12 - IP9 NB - RAMP
CH 1+100 - 1+220
STRUCTURE NO.2 UNIT-1
PROJECT WIDE
SECTION WIDE
Manhole
Chainage (or Station)

SITE PREPARATION, ESTABLISHMENT OF OFFICE, CAMP & YARD


General
RECEIPT OF NOC's
PRELIMINARY & DETAILED SURVEYING
Milestones
NOC Process
Environmental Consideration : Safety & Security
SHOP DRAWINGS
MATERIAL APPROVALS
MANUFACTURE & DELIVERY OF MATERIALS
Marine Transportation for Excavated Materials
Partition Wall (CIP)
Performance Bond
Advance Payment Bond
Insurance
Site Preparation
Site Laboratory
Survey
Site Investigation
Instrumentals for Monitoring
Building Survey / Investigation
Utility Survey / Investigation
Pile Load Test
Bachymetry Survey
Temporary Wall System
Traffic Decking (Traffic Detour Scheme)
Utility Hanging Bridge
Pedestrian Access Bridge

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
MAT
PRC
FAB
TMF
TCD
UTD
EXC
ETW
FDN
RCW
PCW
URO
PAV
UTR
UTI
TSCO
ADDC
MEC
ELE
TCS
SCA
MIL
MSC
TOM
MNA
DAY
SUBCON
METHOD
INVEST
CLEAR
EARTH
SEWER
STORM
WATER
TELE
IRRIG
UTILS
BASE
ASPHAL
MARK
STFURN
HAND
MINOR
GEN1
EMT
MOBI
GEN
NOC1
NOC2
SUR1
SSDD
ASDD
SSDR
ASDR
SSDE
ASDE
SSCP
ASCP
AWSC
MOSC
SSDS
ASDS
SMTS
AMTS
SMLD
SMSS
AMSS
SMSD
AMSD
SMSE
AMSE

Description
Approval of Main Materials
Procurement
Fabrication
Temporary Facilities
Traffic Control & Detour
Utility Diversion (Interfered with Main Line)
Excavation Supporting System
Earthworks
Pile Foundation
Reinforced Concrete Works
Prestressed Concrete Works
Structural Works for Utility / Ventilation / Control Rooms
Road Pavement
Utility Relocation
Utility Installation
TRANSCO Services
ADDC Services
Mechanical Works
Lighting & Electrical Works
Traffic Control System
SCADA System
Military Communication System
Anicillary Works / Misc
Tunnel Operation & Maintenance
Mechanical & Electrical Works
Daily Works
SUBCONTRACTING
METHOD STATEMENTS
SITE INVESTIGATION, TESTING & PRELIMINARIES
SITE CLEARANCE & REMOVAL OF OBSTRUCTIONS
EARTHWORKS
SEWERAGE LINE RELOCATION WORKS
STORM WATER DRAINAGE SYSTEM
WATERLINE RELOCATION WORKS
TELEPHONE LINE RELOCATION WORKS
IRRIGATION RELOCATION WORKS
PROTECTION OF UTILITIES & UTILITY DUCTS
SUBBASE & BASE COURSES
ASPHALT WORKS
TRAFFIC MARKINGS AND SIGNS
STREET FURNITURE
CLOSE OUT & HANDING OVER
MILESTONES
MOBILISATION
General / Misc
SUBMIT FOR NOC
RECEIPT OF NOC
DETAILED SURVEYING & SETTING OUT
SUBMIT SHOP DRAWINGS - DETOUR WORKS
APPROVE SHOP DRAWINGS - DETOUR WORKS
SUBMIT SHOP DRAWINGS - REMOVAL OF OBSTRUCTIONS
APPROVE SHOP DRAWINGS - REMOVAL OF OBSTRUCTIONS
SUBMIT SHOP DRAWINGS - EARTHWORKS & ROADWORKS
APPROVE SHOP DRAWINGS - EARTHWORKS & ROADWORKS
SUBMIT SUBCONTRACTOR PROPOSAL
APPROVE SUBCONTRACTOR PROPOSAL
AWARD OF SUBCONTRACT
MOBILISATION OF SUBCONTRACTOR
SUBMIT SHOP DRAWINGS
APPROVE SHOP DRAWINGS
SUBMIT MATERIALS
APPROVE MATERIALS
SUPPLY OF MATERIALS
SUBMIT METHOD STATEMENTS
APPROVE METHOD STATEMENTS
SUBMIT METHOD STATEMENTS - DETOUR WORKS
APPROVE METHOD STATEMENTS - DETOUR WORKS
SUBMIT METHOD STATEMENTS - EARTHWORKS
APPROVE METHOD STATEMENTS - EARTHWORKS

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
SMSR
AMSR
SMTD
AMTD
SMTP
AMTP
TECB
TESL
MS
REM3
REM4
REM1
REM2
TREE
PROT
DEEX
DEFL
DEWC
TESI
TERM
PJ
NOC
SF
EPO
SFE
DCO
SFD
CTO
SFC
LAB
DEW
CAR
TPL
WCS
EAP
ATI
MST
SD
SUP
MAT
SUB
MCO
MRB
MWP
MFP
MGP
RD
TCB
TSL1
TSL2
PNT
REX
PSS
EXC
PAV
TRF
PG
PB
YD
TD1
TD2
TD3
WL
IR
TL
SE
SW
ML
SC
KP
ST

Description
SUBMIT METHOD STATEMENTS - ROADWORKS
APPROVE METHOD STATEMENTS - ROADWORKS
SUBMIT MATERIALS - DETOUR WORKS
APPROVE MATERIALS - DETOUR WORKS
SUBMIT MATERIALS - PAVEMENT WORKS
APPROVE MATERIALS - PAVEMENT WORKS
TEMPORARY CONCRETE BARRIERS
TEMPORARY STREETLIGHTING
Milestones
REMOVE STREETLIGHT COLUMNS
REMOVE STREETLIGHT FOUNDATIONS
REMOVE PEDESTRIAN FENCE
REMOVE KERB, BARRIER, TILES, SIGNS, etc
REMOVE / REPLANT TREES
PROTECTION OF SERVICES & STRUCTURES
EXCAVATION / PREPARATION OF FORMATION
BORROW FILL / SUBBASE
ASPHALT WEARING COURSE
TEMPORARY CONSTRUCTION SIGNS
TEMPORARY ROAD MARKING
Project Wide
NOC's Process
Site Facilities
Employer's Office
Services for Employer
Designated Consultant's Office
Services for Designated Consultant's Office
Contractor's Office
Services for Contractor's Office
Site Laboratory
Dewatering Works
Contractor's All Risks
Third Parth Liability
Workmen's Compensation
Contractor's Equipment & Plant Insurance
Automobile Third Parties Insurance
Method Statement
Shop Drawing
Supplier of Material
Approval of Materials
Subcontract Process
Material : Concrete
Material : Rebar
Material : Waterproofing
Material : Fire Protection
Material : G.I & GRP Pipes
Road Detour
Temporary Concrete Barriers
Installation of Temporary Street Light
Removal of Temporary Street Light
Removal of Trees & Transplanting
Removal of Exist. Kerb, Barrier,Signs etc
Protection of Services & Structures
Excavation / Subbase Filling
Temporary Pavement & Road Marking
Temporary Traffic Signals
Precast Girder
Precast Box Beam
Precast Yard
Traffic Detour : Construction Stage 1
Traffic Detour : Construction Stage 2
Traffic Detour : Construction Stage 3
Water Line Diversion
Irrigation Diversion
Telephone Line Diversion
Sewerage Line Diversion
Storm Water Drainage System
Military Communication System
Site Clearance & Access
King Post Installation / Removal
Strut Installation / Removal

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
DW
EX1
EX2
EA
BF
BP
PREC
PT
WP
BASE
RWA1
RWA2
CW1
CW2
ROOF
TECO
RE
TESG
FM
TESC
CP
BORE
GI
TEPB
BI
BA
REM5
AS
EJ
CONT
BC
TD
TM
TEFE
AL
MEP
FIR
MW
LOCA
ED
TR
AD1
AD2
CA
FILL
TS
S21
GEOT
S22
S23
S24
S25
DIAP
S26
S5
UNEX
S6
S7
S8
S9
COPP
S10
S11
CLEX
S12
S13
GRFL
S14
S15
STEX
S16

Description
Diaphragm Wall
Excavation - 1st layer ( GL ~ 3.0m )
Excavation - 2nd layer ( 3.0m ~ FL )
Earth Anchor Driving
Backfill
Bored Pile
PRECAST YARD
Pile Head Treatment
Water Proofing
Base Slab
Retaining Wall (1st)
Retaining Wall (2nd)
Center Wall (Column, H=5.4m)
Center Wall (Cap Beam, H=1.5m)
Roof Slab
TRAFFIC CONES, BARRICADES
Rebar Erection
TEMPORARY TRAFFIC SIGNAL CONTROLLERS
Form Works
TEMPORARY SIGHT SCREEN FENCING
Concrete Pouring & Curing
BOREHOLE
Precast Girder Installation
TEMPORARY PEDESTRIAN BRIDGES OVER DETOUR
Precast Box Beam Installation
Sub-base & Base Courses
REMOVE BARRIERS, SIGNS, DISPLAYS, etc.
Asphalt Works
Expansion Joint
REMOVE SIGNAL CONTROLLERS AND MASTS
Concrete Barrier & Curb
Traffic Decking
Traffic Marking & Signs & Street Furniture
TEMPORARY FENCING
Achitectural & Landscaping Works
Tunnel Mechanical Works
Fire Protection
Metal Works
EXCAVATE TO LOCATE
Lighting & Electrical Distribution Works
TRANSCO Services, 132KV XLPE Cable Relocation
ADDC Services, Relocation of 33KV / 11KV / LV XLPE Cable
ADDC Services, Development of 33KV / 11KV / LV XLPE Cable
SCADA System
BORROW FILL / SUBGRADE
Traffic Control System
Utility Room #19 (STR-21)
PERVIOUS BACKFILL WITH GEOTEXTILE
Utility Room #20 (STR-22)
Utility Room #21 (STR-23)
Utility Room #18 (STR-24)
Utility Room #22 (STR-25)
CONSTRUCTION OF DIAPHRAGM WALL
Utility Room #17 (STR-26)
Control Room #9 (STR-5)
UNCLASSIFIED EXCAVATION
Utility Room #8 (STR-6)
Ventilation Room #10 (STR-7)
Ventilation Room #11 (STR-8)
Ventilation Room #7 (STR-9)
COPING BEAM AND TIE BACK ANCHORS FOR DIAPHRAGM WALL
Ventilation Room #6 (STR-10)
Utility Room #12 (STR-11)
CLASSIFIED EXCAVATION
Ventilation Room #5 (STR-12)
Ventilation Room #13 (STR-13)
GRANULAR BACKFILL
Ventilation Room #14 (STR-14)
Utility Room #4 (STR-15)
STRUCTURAL EXCAVATION
Utility Room #15 (STR-16)

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
PEDE
S17
S18
FIL1
S19
S20
GRAD
AGGB
SAND
WEA2
WEA3
ABAS
WEA1
MILL
REGL
ADJU
MAR1
STD1
SIG1
GSNP
GSNG
GSNS
MAR2
STD2
SIG2
GSN1
GSN2
WDUC
IDUC
TDUC
SDUC
GRPW
GRPI
PVCT
PRO1
PRO2
PRO3
PRO4
SEEX
SEPL
SEBK
SETE
SEME
SEMC
SEMB
SERE
SEOP
SEAB
NSDP
NSRP
NSDR
NSTE
SANI
SWEX
SWPL
SWBK
SWTE
SWMH
SWCN
SWRE
NDDP
NDRP
NDDR
NDTE
BDEX
BDPL
BDBK
BDTE
BD6C
BD4C
BD4A

Description
REMOVAL OF PEDESTRIAN UNDERPASS @ CH. 10+660
Ventilation Room #3 (STR-17)
Ventilation Room #16 (STR-18)
BACKFILLING BEHIND RETAINING WALL
Ventilation Room #2 (STR-19)
Control Room #1 (STR-20)
SUBGRADE (WITH GEOTEXTILE)
AGGREGATE BASE COURSE
SAND ASPHALT ON TUNNEL DECK SLAB - 1.8 cm
ASPHALT WEARING COURSE (ON TUNNEL DECK SLAB)
ASPHALT WEARING COURSE (ON TUNNEL BASE SLAB)
ASPHALT BASE COURSE
ASPHALT WEARING COURSE (OUTSIDE TUNNEL)
MILLING EXISTING ASPHALT
ASPHALT REGULATORY COURSE
ADJUST EXISTING MANHOLES, INLETS, SERVICES
ROAD MARKING OUTSIDE TUNNEL
ROAD STUDS OUTSIDE TUNNEL
TRAFFIC SIGNS OUTSIDE TUNNEL
PILE FOUNDATIONS FOR INSTALLATION OF GUIDE SIGN GANTRY
INSTALLATION OF GUIDE SIGN GANTRY
INSTALLATION OF GUIDE SIGN PANEL
ROAD MARKING INSIDE TUNNEL
ROAD STUDS INSIDE TUNNEL
TRAFFIC SIGNS INSIDE TUNNEL
ERECTION OF GUIDE SIGN SUPPORTS INSIDE TUNNEL
INSTALLATION OF GUIDE SIGN PANEL INSIDE TUNNEL
WATER DUCTS (GRP)
IRRIGATION DUCTS (PVC / GRP)
TELEPHONE DUCTS (PVC)
SEWER DUCTS
GRP SLEEVE FOR WATERLINE CROSSING
GRP SLEEVE FOR IRRIGATION LINE CROSSING
PVC SLEEVE FOR TELEPHONE LINE CROSSING
PROTECTION SLAB FOR WATER LINES
PROTECTION FOR IRRIGATION LINES
PROTECTION FOR TELEPHONE CABLES
PROTECTION FOR SEWER LINES
SEWER LINE - SHEET PILES, EXCAVATION & BEDDING
SEWER LINE - PIPELAYING (WITH SURROUND)
SEWER LINE - BACKFILLING & REMOVE SHEET PILES
SEWER LINE - TESTING
SEWER MANHOLES / CHAMBERS - SHEET PILES & EXCAVATION
SEWER MANHOLES / CHAMBERS - CONSTRUCTION
SEWER MANHOLES / CHAMBERS - BACKFILLING & REMOVE SHEET PILES
SEWER LINE - REINSTATEMENT WORKS
SEWER LINE - OVERPUMPING & CONNECTION TO NEW LINE
SEWER LINE - REMOVE / ABANDON EXISTING SEWERS
NDRC FOR SEWER LINE - DRIVING PIT CONSTRUCTION
NDRC FOR SEWER LINE - RECEPTION PIT EXCAVATION
NDRC FOR SEWER LINE - DRIVING
NDRC FOR SEWER LINE - TESTING & GROUTING
SANITARY PIPES
STORM WATER MAIN LINE - EXCAVATION & BEDDING
STORM WATER MAIN LINE - PIPELAYING & SURROUND
STORM WATER MAIN LINE - BACKFILLING
STORM WATER MAIN LINE - TESTING
STORM WATER MAIN LINE - MANHOLE CONSTRUCTION
STORM WATER MAIN LINE - CONNECTION TO EXISTING DRAINAGE LINE
STORM WATER MAIN LINE - REMOVE EXISTING SW LINES/MANHOLES
NDRC SW MAIN LINE - DRIVING PIT CONSTRUCTION
NDRC SW MAIN LINE - RECEPTION PIT EXCAVATION
NDRC SW MAIN LINE - DRIVING
NDRC SW MAIN LINE - TESTING & GROUTING
BASE SLAB DRAINAGE MAIN LINE - EXCAVATION & BEDDING
BASE SLAB DRAINAGE MAIN LINE - PIPELAYING & SURROUND
BASE SLAB DRAINAGE MAIN LINE - BACKFILLING
BASE SLAB DRAINAGE MAIN LINE - TESTING
BASE SLAB DRAINAGE- DI PIPE CROSSING TUNNEL BASE
BASE SLAB DRAINAGE - DI PIPE CROSSING (400 mm dia)
BASE SLAB DRAINAGE - DI PIPE ALONG TUNNEL BASE

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
INLG
LTEX
LTPL
LTBK
LTTE
LTCB
LTCN
LTRE
PSPL
PSCB
OUTF
PUMP
WTEX
WTPL
WTCS
WTCP
WTCH
WTBK
WTTE
WTSE
WTST
WTRM
WTN1
WTN2
WTN3
WTN4
WTDT
TEDT
TECR
TEBK
TEMH
MHBK
TETB
TBDT
TECL
TEST
TERE
TERS
IRPL
IRTB
IRVC
IRCN
IRBK
IRRE
IRRM
STFR
GEN2
TRAF
HNTU
GEN3
OVER
DIR
EMT
MS
GEN
SUB
APR
SNB
SB
NB
WEB
WB
EB
INN
OUT
132
33
11
LV
SW
S21

Description
BASE SLAB DRAINAGE - INLET GRATES
STORM WATER LATERALS - EXCAVATION & BEDDING
STORM WATER LATERALS - PIPELAYING & SURROUND
STORM WATER LATERALS - BACKFILLING
STORM WATER LATERALS - TESTING
STORM WATER LATERALS - CONSTRUCTION OF INLETS/CATCH BASINS
STORM WATER LATERALS - CONNECTION TO EXISTING DRAINAGE LINE
STORM WATER LATERALS - REMOVE EXISTING LINES/STRUCTURES
PAVEMENT SUBBASE DRAINAGE - PIPE LAYING
PAVEMENT SUBBASE DRAINAGE - CATCH BASINS
CONSTRUCTION OF OUTFALL STRUCTURE
CONSTRUCTION OF PUMP STATION
WATER LINE - TRENCH EXCAVATION
WATER LINE - PIPELAYING
WATER LINE - CS PIPELINE ACROSS TUNNEL
WATER LINE - CORROSION PROTECTION
WATER LINE - CHAMBERS
WATER LINE - BACKFILLING
WATER LINE - TESTING
WATER LINE - STERILIZATION
WATER LINE - SHUTDOWN & CONNECTION
WATER LINE - REMOVAL OF EXISTING WATER LINES
WATER LINE - NDRC DRIVING PIT CONSTRUCTION
WATER LINE - NDRC RECEPTION PIT EXCAVATION
WATER LINE - NDRC DRIVING
WATER LINE - NDRC TESTING & GROUTING
WATER DUCT CROSSING TUNNEL
TELEPHONE DUCTS - EXCAVATION & LAYING
TELEPHONE DUCTS - LAYING THROUGH UTILITY CROSSINGS
TELEPHONE DUCTS - BACKFILLING
CONSTRUCTION OF TELEPHONE MANHOLES / CHAMBERS
BACKFILLING FOR TELEPHONE MANHOLES / CHAMBERS
TELEPHONE DUCTS - THRUST BORING
THRUST BORING - LAYING OF TELEPHONE DUCT
TELEPHONE CABLE LAYING
TELEPHONE LINE - TESTING & COMMISSIONING
REMOVE / ABANDON EXISTING DUCTS / CABLES
TELEPHONE LINE - REINSTATEMENT WORKS
IRRIGATION LINE - EXCAVATION & PIPELAYING
IRRIGATION LINE - THRUST BORING
IRRIGATION LINE - VALVE CHAMBERS
CONNECTION TO EXISTING IRRIGATION LINE
IRRIGATION LINE - BACKFILLING
REINSTATEMENT OF PAVEMENT
REMOVAL OF EXISTING IRRIGATION LINE
STREET FURNITURE
GENERAL / MISCELLANEOUS
TRAFFIC DIVERSION INTO DETOUR ROADS
HANDING OVER OF STRUCTURAL WORKS
MILESTONES
COMPLETION & HANDING OVER

Milestones
General
Submission
Approval
South & North Bound
South Bound
North Bound
West & East Direction
West Direction
East Direction
Inner parts of Tunnel
Outer parts of Tunnel
132 KV XLPE Cable Relocation
33 KV XLPE Cable Relocation
11 KV XLPE Cable Relocation
LV XLPE Cable Relocation
SOUTH WEST
Utility Room #19 (STR-21)

Remarks

A2-3. Activity Coding System


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity Code Value
S22
S23
S24
S25
S26
S5
S6
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
BILL NUMBER
1
2
3
4
5
6
07A
07B
8
9
10
11
12
14
15A
15B
16A
16B
16C
17
18
19A
19B
20A
20B
21
24
25
26
27
28
30

Description
Utility Room #20 (STR-22)
Utility Room #21 (STR-23)
Utility Room #18 (STR-24)
Utility Room #22 (STR-25)
Utility Room #17 (STR-26)
Control Room #9 (STR-5)
Utility Room #8 (STR-6)
Ventilation Room #10 (STR-7)
Ventilation Room #11 (STR-8)
Ventilation Room #7 (STR-9)
Ventilation Room #6 (STR-10)
Utility Room #12 (STR-11)
Ventilation Room #5 (STR-12)
Ventilation Room #13 (STR-13)
Ventilation Room #14 (STR-14)
Utility Room #4 (STR-15)
Utility Room #15 (STR-16)
Ventilation Room #3 (STR-17)
Ventilation Room #16 (STR-18)
Ventilation Room #2 (STR-19)
Control Room #1 (STR-20)
General
Earthworks
Subbase & Base Courses
Asphalt Works
Concrete Works
Storm Water Drainage System
Water Works
Water Line Relocation Works
Prestressed Concrete Works
Traffic Markings & Signs
Site Laboratory
Concrete Pile Foundations
Metal Works
Expansion & Fixed Joints
Irrigation Works
Irrigation Relocation Works
Lighting & Electrical Distribution Works
TRANSCO Services, 132KV Electrical Works
ADDC Services, LV, 11KV & 33KV Electrical Works
Traffic Control System
Daily Works
Telephone Works
Telephone Line Relocation Works
Sewerage Works
Sewerage Line Relocation Works
Street Furniture
Mechanical Works
Architectural & Hard Landscaping Works
Military Communication Works
SCADA System
Tunnel Operations & Maintenance
ITEMS NOT INCLUDED IN THE PROGRAMME

Remarks

A2-4. Numbering System (Baseline Rev.0)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No.

STR SEC

STATION

Unit

South Bound
(SB)
0

STA.

8+425.226

STA.

8+435.226

STA.

STA.

STA.

4
5

STA.

STA.

STA.

STA.

STA.

17
18
19

STA.

Section No.1

16

STRUCTURE NO.1

15

20

STA.
STA.

21

23
24

STA.
STA.

25

STA.

26

STA.

27

STA.

28

STA.

29

STA.

30

STA.

31

STA.

32

STA.

33

42
43

STRUCTURE NO.2

41

45
46
47

Section No.2

44

STA.

9+510.344

STA.

9+539.298

STA.

9+568.240

STA.

9+597.183

AP1B

AP1K

AP1S

AP1A

AP1L

AP1G

AP1R

U1D

U1B

U1K

U1S

U1A

U1L

U1G

U1R

S1

U2

S1U2

U2E

U2W

U2D

U2B

U2K

U2S

U2A

U2L

U2G

U2R

29.19

S1

U3

S1U3

U3E

U3W

U3D

U3B

U3K

U3S

U3A

U3L

U3G

U3R

Unit -4

29.19

S1

U4

S1U4

U4E

U4W

U4D

U4B

U4K

U4S

U4A

U4L

U4G

U4R

Unit -5

29.19

S1

U5

S1U5

U5E

U5W

U5D

U5B

U5K

U5S

U5A

U5L

U5G

U5R

Unit -6

29.19

S1

U6

S1U6

U6E

U6W

U6D

U6B

U6K

U6S

U6A

U6L

U6G

U6R

Unit -7

29.23

S1

U7

S1U7

U7E

U7W

U7D

U7B

U7K

U7S

U7A

U7L

U7G

U7R

Unit -8

29.15

S1

U8

S1U8

U8E

U8W

U8D

U8B

U8K

U8S

U8A

U8L

U8G

U8R

Unit -9

35.16

S1

U9

S1U9

U9E

U9W

U9D

U9B

U9K

U9S

U9A

U9L

U9G

U9R

Unit -10

26.45

S1

U10

S1U10

U10E

U10W

U10D

U10B

U10K

U10S

U10A

U10L

U10G

U10R

Unit -11

26.45

S1

U11

S1U11

U11E

U11W

U11D

U11B

U11K

U11S

U11A

U11L

U11G

U11R

Unit -12

27.45

S1

U12

S1U12

U12E

U12W

U12D

U12B

U12K

U12S

U12A

U12L

U12G

U12R

Unit -13

25.45

S1

U13

S1U13

U13E

U13W

U13D

U13B

U13K

U13S

U13A

U13L

U13G

U13R

Unit -14

26.45

S1

U14

S1U14

U14E

U14W

U14D

U14B

U14K

U14S

U14A

U14L

U14G

U14R

Unit -15

25.67

S1

U15

S1U15

U15E

U15W

U15D

U15B

U15K

U15S

U15A

U15L

U15G

U15R

Unit -16

25.67

S1

U16

S1U16

U16E

U16W

U16D

U16B

U16K

U16S

U16A

U16L

U16G

U16R

Unit -17

28.51

S1

U17

S1U17

U17E

U17W

U17D

U17B

U17K

U17S

U17A

U17L

U17G

U17R

Unit -18

28.50

S1

U18

S1U18

U18E

U18W

U18D

U18B

U18K

U18S

U18A

U18L

U18G

U18R

Unit -19

28.50

S1

U19

S1U19

U19E

U19W

U19D

U19B

U19K

U19S

U19A

U19L

U19G

U19R

Unit -20

28.50

S1

U20

S1U20

U20E

U20W

U20D

U20B

U20K

U20S

U20A

U20L

U20G

U20R

Unit -21

28.50

S1

U21

S1U21

U21E

U21W

U21D

U21B

U21K

U21S

U21A

U21L

U21G

U21R

Unit -22

28.50

S1

U22

S1U22

U22E

U22W

U22D

U22B

U22K

U22S

U22A

U22L

U22G

U22R

Unit -23

28.50

S1

U23

S1U23

U23E

U23W

U23D

U23B

U23K

U23S

U23A

U23L

U23G

U23R

Unit -24

28.50

S1

U24

S1U24

U24E

U24W

U24D

U24B

U24K

U24S

U24A

U24L

U24G

U24R

Unit -25

28.50

S1

U25

S1U25

U25E

U25W

U25D

U25B

U25K

U25S

U25A

U25L

U25G

U25R

Unit -26

28.50

S1

U26

S1U26

U26E

U26W

U26D

U26B

U26K

U26S

U26A

U26L

U26G

U26R

Unit -27

28.50

S1

U27

S1U27

U27E

U27W

U27D

U27B

U27K

U27S

U27A

U27L

U27G

U27R

Unit -28

28.50

S1

U28

S1U28

U28E

U28W

U28D

U28B

U28K

U28S

U28A

U28L

U28G

U28R

Unit -29

28.50

S1

U29

S1U29

U29E

U29W

U29D

U29B

U29K

U29S

U29A

U29L

U29G

U29R

Unit -30

28.50

S1

U30

S1U30

U30E

U30W

U30D

U30B

U30K

U30S

U30A

U30L

U30G

U30R

Unit -31

28.50

S1

U31

S1U31

U31E

U31W

U31D

U31B

U31K

U31S

U31A

U31L

U31G

U31R

Unit -32

28.68

S1

U32

S1U32

U32E

U32W

U32D

U32B

U32K

U32S

U32A

U32L

U32G

U32R

Unit -1

24.66

SB1W

SB1D

SB1B

SB1K

SB1S

SB1A

SB1L

SB1G

SB1R

Unit -2

24.66

SB2R

Unit -2

23.38

Unit -3

75.95

DR-1

145.95

DR-2

35.16

TN-1

132.25

DR-3

Same as
South Bound
51.34

TN-1

456.17

9+774.011

51

STA.

9+804.011

IP-41A
(STA. 8+675.061)

IP-41
(STA. 8+850.737)

STA. 3+405.628
49.32

TN-2D

STA.

Unit -1

24.14

Unit -2

25.50

Unit -3

29.26

49.64

3+381.486

S2

SB1

NB1

S2SU1 S2NU1

SB1E

NB2

S2SU2 S2NU2

SB2E

SB2W

SB2D

SB2B

SB2K

SB2S

SB2A

SB2L

SB2G

S2SU3

SB3E

SB3W

SB3D

SB3B

SB3K

SB3S

SB3A

SB3L

SB3G

SB3R

SB4E

SB4W

SB4D

SB4B

SB4K

SB4S

SB4A

SB4L

SB4G

SB4R

SB5E

SB5W

SB5D

SB5B

SB5K

SB5S

SB5A

SB5L

SB5G

SB5R

SB6E

SB6W

SB6D

SB6B

SB6K

SB6S

SB6A

SB6L

SB6G

SB6R

SB7E

SB7W

SB7D

SB7B

SB7K

SB7S

SB7A

SB7L

SB7G

SB7R

SB8E

SB8W

SB8D

SB8B

SB8K

SB8S

SB8A

SB8L

SB8G

SB8R

SB9E

SB9W

SB9G

SB9R

TN-2T
S2

SB2

S2

SB3

S2

SB4

S2

SB5

S2

SB6

S2

SB7

S2

SB8

STA. 3+355.987
Unit -3

20.45

Unit -4

20.45

Unit -5

20.26

Unit -6

17.33

40.90

TN-3

STA.

3+326.723

STA.

3+297.458

Unit -4
37.59

TN-4

Unit -7

24.99

STA.

3+268.193

Unit -8

25.51

STA.

3+238.928

STA.

3+209.978

Unit -9

28.95

Unit -10

28.94

Unit -11

28.94

224.16

Unit -12

28.94

Unit -13

28.94

Unit -14

28.94

Unit -1

30.51

Unit -2

29.50

Unit -3

30.00

Unit -4

Unit -5

TN-5

STA.

3+181.036

STA.

3+152.094

STA.
STA.

29.26
117.06

Unit -5

29.26

Unit -6

29.27

Unit -7

28.95

Unit -8

28.94

TN-3

NB3

S2NU3

S2SU4
NB4

NB5

S2SU5
S2SU6

S2NU4

S2NU5

S2SU7
S2NU6

NB6
S2SU8
NB7

S2

SB9

S2

SB10

S2NU7

SB9D

SB9B

SB9K

SB9S

SB9A

SB9L

NB8

S2SU10 S2NU8 SB10E SB10W SB10D

SB10B

SB10K

SB10S

SB10A

SB10L SB10G SB10R

S2SU11 S2NU9 SB11E SB11W SB11D

S2SU9

Unit -9

28.94

S2

SB11

NB9

SB11B

SB11K

SB11S

SB11A

SB11L SB11G SB11R

Unit -10

28.93

S2

SB12

NB10 S2SU12 S2NU10 SB12E SB12W SB12D SB12B

SB12K

SB12S

SB12A

SB12L SB12G SB12R

Unit -11

28.94

S2

SB13

NB11 S2SU13 S2NU11 SB13E SB13W SB13D SB13B

SB13K

SB13S

SB13A

SB13L SB13G SB13R

Unit -12

28.94

S2

SB14

NB12 S2SU14 S2NU12 SB14E SB14W SB14D SB14B

SB14K

SB14S

SB14A

SB14L SB14G SB14R

U1K

U1S

U1A

173.65

TN-5

3+123.159
3+094.217

STA. 3+065.275

Length :

340.35 m

S3

U1

S3U1

U1E

U1W

U1D

U1B

S3

U2

S3U2

U2E

U2W

U2D

U2B

U2K

U2S

S3

U3

S3U3

U3E

U3W

U3D

U3B

U3K

U3S

30.00

S3

U4

S3U4

U4E

U4W

U4D

U4B

U4K

U4S

30.00

S3

U5

S3U5

U5E

U5W

U5D

U5B

U5K

U5S

90.01

IP-12
(STA. 9+450.000)

TN-6

U1L

U1G

U1R

U2A

U2L

U2G

U2R

U3A

U3L

U3G

U3R

U4A

U4L

U4G

U4R

U5A

U5L

U5G

U5R

IP-9
(STA. 9+704.935)

9+834.010
150.00

TN-7

Unit -6

30.00

S3

U6

S3U6

U6E

U6W

U6D

U6B

U6K

U6S

U6A

U6L

U6G

U6R

Unit -7

30.00

S3

U7

S3U7

U7E

U7W

U7D

U7B

U7K

U7S

U7A

U7L

U7G

U7R

Unit -8

30.00

S3

U8

S3U8

U8E

U8W

U8D

U8B

U8K

U8S

U8A

U8L

U8G

U8R

Unit -9

30.00

S3

U9

S3U9

U9E

U9W

U9D

U9B

U9K

U9S

U9A

U9L

U9G

U9R

Unit -10

30.00

S3

U10

S3U10

U10E

U10W

U10D

U10B

U10K

U10S

U10A

U10L

U10G

U10R

Unit -11

30.00

S3

U11

S3U11

U11E

U11W

U11D

U11B

U11K

U11S

U11A

U11L

U11G

U11R

Unit -12

30.00

S3

U12

S3U12

U12E

U12W

U12D

U12B

U12K

U12S

U12A

U12L

U12G

U12R

Unit -13

30.09

S3

U13

S3U13

U13E

U13W

U13D

U13B

U13K

U13S

U13A

U13L

U13G

U13R

Unit -14

29.91

S3

U14

S3U14

U14E

U14W

U14D

U14B

U14K

U14S

U14A

U14L

U14G

U14R

Unit -15

30.00

S3

U15

S3U15

U15E

U15W

U15D

U15B

U15K

U15S

U15A

U15L

U15G

U15R

Unit -16

30.00

S3

U16

S3U16

U16E

U16W

U16D

U16B

U16K

U16S

U16A

U16L

U16G

U16R

9+864.010
9+894.010
9+924.009
9+954.009

57

STA.

58

STA. 10+014.009

9+984.010

59

STA. 10+044.009

60

STA. 10+074.101
STA. 10+104.009

Same as
South Bound

STA. 10+134.009
STA

Remarks

DR-3

9+684.002

STA.

63

AP1D

U1W

9+655.067

50

62

AP1W

U1E

9+626.125

9+744.011

61

AP1E

S1-U1

23.38

9+401.802

9+484.833

STA.

S1AP1

U1

Unit -1

AP

9+332.038

STA.

56

9+303.363

STA.

STA.

9+274.863

49

55

9+246.364

9+459.844

STA.

9+217.865

9+714.510

54

9+189.366

STA.

STA.

9+160.867

STA.

53

9+132.368

9+442.513

STA.

STA. 8+425.226

9+103.869

48

52

AP1

10.00

Type

9+075.370

9+422.251

STA.

S1

10.00

Length

9+046.871

STA.

STA.

Roof
Slab

9+018.372

STA.

STA.

PC
Girder

8+989.873

9+381.354

40

Wall

8+961.374

9+356.695

39

Base
Slab

8+875.870

STA.

38

Strut
& Wale

S1

Approach

8+850.198

STA.

37

King
Post

WEST

Unit

Type

8+824.527

35

STA.

Bored
Pile

EAST

ST

Length

8+798.076

34

36

D/Wall

8+772.625

8+932.876

STA.

Direction

8+745.176

8+904.376

STA.

22

Unique
Unit Name

8+657.117

STA.

STA.

Numbering System
Design Unit

Type

8+627.972

STA.

STA.

Length
of

8+598.739

8+718.724

STA.

North Bound
(NB)

Unit

8+569.550

STA.

14

Unit

8+540.361

11

STA.

STATION

8+511.172

8+692.273

13

Type

8+481.983

STA.

STA.

Length
of

8+458.604

10

12

Unit

10+164 009

IP-11
(STA. 10+000.000)

No.

STR SEC

STATION

63

South Bound
(SB)
STA. 10+164.009

64

STA. 10+194.009

Section No.3

67
68
69
70

Base
Slab

Wall

PC
Girder

Roof
Slab

Unit -17

30.00

S3

U17

S3U17

U17E

U17W

U17D

U17B

U17K

U17S

U17A

U17L

U17G

U17R

Unit -18

30.00

S3

U18

S3U18

U18E

U18W

U18D

U18B

U18K

U18S

U18A

U18L

U18G

U18R

Unit -19

30.00

S3

U19

S3U19

U19E

U19W

U19D

U19B

U19K

U19S

U19A

U19L

U19G

U19R

Unit -20

30.00

S3

U20

S3U20

U20E

U20W

U20D

U20B

U20K

U20S

U20A

U20L

U20G

U20R

Unit -21

30.00

S3

U21

S3U21

U21E

U21W

U21D

U21B

U21K

U21S

U21A

U21L

U21G

U21R

Unit -22

30.00

S3

U22

S3U22

U22E

U22W

U22D

U22B

U22K

U22S

U22A

U22L

U22G

U22R

Unit -23

30.00

S3

U23

S3U23

U23E

U23W

U23D

U23B

U23K

U23S

U23A

U23L

U23G

U23R

Unit -24

30.08

S3

U24

S3U24

U24E

U24W

U24D

U24B

U24K

U24S

U24A

U24L

U24G

U24R

Unit -25

29.92

S3

U25

S3U25

U25E

U25W

U25D

U25B

U25K

U25S

U25A

U25L

U25G

U25R

Unit -26

30.00

S3

U26

S3U26

U26E

U26W

U26D

U26B

U26K

U26S

U26A

U26L

U26G

U26R

Unit -27

30.00

S3

U27

S3U27

U27E

U27W

U27D

U27B

U27K

U27S

U27A

U27L

U27G

U27R

Unit -28

30.00

S3

U28

S3U28

U28E

U28W

U28D

U28B

U28K

U28S

U28A

U28L

U28G

U28R

Unit -29

30.00

S3

U29

S3U29

U29E

U29W

U29D

U29B

U29K

U29S

U29A

U29L

U29G

U29R

Unit -30

30.00

S3

U30

S3U30

U30E

U30W

U30D

U30B

U30K

U30S

U30A

U30L

U30G

U30R

Unit -31

30.00

S3

U31

S3U31

U31E

U31W

U31D

U31B

U31K

U31S

U31A

U31L

U31G

U31R

Unit -32

30.00

S3

U32

S3U32

U32E

U32W

U32D

U32B

U32K

U32S

U32A

U32L

U32G

U32R

Unit -33

30.00

S3

U33

S3U33

U33E

U33W

U33D

U33B

U33K

U33S

U33A

U33L

U33G

U33R

Unit -34

30.00

S3

U34

S3U34

U34E

U34W

U34D

U34B

U34K

U34S

U34A

U34L

U34G

U34R

Unit -35

30.00

S3

U35

S3U35

U35E

U35W

U35D

U35B

U35K

U35S

U35A

U35L

U35G

U35R

Unit -36

30.00

S3

U36

S3U36

U36E

U36W

U36D

U36B

U36K

U36S

U36A

U36L

U36G

U36R

Unit -37

30.00

S3

U37

S3U37

U37E

U37W

U37D

U37B

U37K

U37S

U37A

U37L

U37G

U37R

Unit -38

30.00

S3

U38

S3U38

U38E

U38W

U38D

U38B

U38K

U38S

U38A

U38L

U38G

U38R

Unit -39

30.00

S3

U39

S3U39

U39E

U39W

U39D

U39B

U39K

U39S

U39A

U39L

U39G

U39R

Unit -40

30.00

S3

U40

S3U40

U40E

U40W

U40D

U40B

U40K

U40S

U40A

U40L

U40G

U40R

Unit -41

30.00

S3

U41

S3U41

U41E

U41W

U41D

U41B

U41K

U41S

U41A

U41L

U41G

U41R

Unit -42

30.00

S3

U42

S3U42

U42E

U42W

U42D

U42B

U42K

U42S

U42A

U42L

U42G

U42R

Unit -43

30.00

S3

U43

S3U43

U43E

U43W

U43D

U43B

U43K

U43S

U43A

U43L

U43G

U43R

Unit -44

30.00

S3

U44

S3U44

U44E

U44W

U44D

U44B

U44K

U44S

U44A

U44L

U44G

U44R

Unit -45

30.00

S3

U45

S3U45

U45E

U45W

U45D

U45B

U45K

U45S

U45A

U45L

U45G

U45R

Unit -46

30.00

S3

U46

S3U46

U46E

U46W

U46D

U46B

U46K

U46S

U46A

U46L

U46G

U46R

Unit -47

30.00

S3

U47

S3U47

U47E

U47W

U47D

U47B

U47K

U47S

U47A

U47L

U47G

U47R

Unit -48

30.00

S3

U48

S3U48

U48E

U48W

U48D

U48B

U48K

U48S

U48A

U48L

U48G

U48R

Unit -49

30.00

S3

U49

S3U49

U49E

U49W

U49D

U49B

U49K

U49S

U49A

U49L

U49G

U49R

Unit -50

30.00

S3

U50

S3U50

U50E

U50W

U50D

U50B

U50K

U50S

U50A

U50L

U50G

U50R

Unit -51

30.00

S3

U51

S3U51

U51E

U51W

U51D

U51B

U51K

U51S

U51A

U51L

U51G

U51R

Unit -52

30.00

S3

U52

S3U52

U52E

U52W

U52D

U52B

U52K

U52S

U52A

U52L

U52G

U52R

Unit -53

30.00

S3

U53

S3U53

U53E

U53W

U53D

U53B

U53K

U53S

U53A

U53L

U53G

U53R

Unit -54

30.00

S3

U54

S3U54

U54E

U54W

U54D

U54B

U54K

U54S

U54A

U54L

U54G

U54R

Unit -55

30.00

S3

U55

S3U55

U55E

U55W

U55D

U55B

U55K

U55S

U55A

U55L

U55G

U55R

Unit -56

30.00

S3

U56

S3U56

U56E

U56W

U56D

U56B

U56K

U56S

U56A

U56L

U56G

U56R

Unit -57

30.00

S3

U57

S3U57

U57E

U57W

U57D

U57B

U57K

U57S

U57A

U57L

U57G

U57R

Unit -58

30.00

S3

U58

S3U58

U58E

U58W

U58D

U58B

U58K

U58S

U58A

U58L

U58G

U58R

Unit -59

30.00

S3

U59

S3U59

U59E

U59W

U59D

U59B

U59K

U59S

U59A

U59L

U59G

U59R

Unit -60

30.00

S3

U60

S3U60

U60E

U60W

U60D

U60B

U60K

U60S

U60A

U60L

U60G

U60R

Unit -61

31.05

S3

U61

S3U61

U61E

U61W

U61D

U61B

U61K

U61S

U61A

U61L

U61G

U61R

Unit -62

9.94

S3

U62

S3U62

U62E

U62W

U62D

U62B

U62K

U62S

U62A

U62L

U62G

U62R

Remarks

IP-11A
(STA. 10+400.000)

1591.05

TN-8

STRUCTURE NO.3

IP-36A
(STA. 10+700.000)

STA. 10+794.010
STA. 10+824.009
STA. 10+854.009
STA. 10+884.010

87
88

STA. 10+914.010

89

STA. 10+944.010

90

STA. 10+974.010

91

STA. 11+004.009

92

STA. 11+034.009

93

Section No.4

STA. 11+064.010

94
95
96

IP-36
(STA. 11+058.529)

STA. 11+094.010

Same as
South Bound

STA. 11+124.010
STA. 11+154.010
STA. 11+184.010

97

STA. 11+214.009

98

STA. 11+244.009

99

STA. 11+274.009

100

STA. 11+304.009

101

STA. 11+334.010

102

STA. 11+364.010

103

STA. 11+394.010

104

STA. 11+424.009

105

STA. 11+454.010

106

STA. 11+484.010

107

STA. 11+515.057

108

STA. 11+525.000

110

STA.

1+016.320

111

STA.

1+037.719

STA.

Section No.2

STRUCTURE NO.4

109

120

Strut
& Wale

STA. 10+704.009

86

119

King
Post

STA. 10+674.009

85

118

Bored
Pile

STA. 10+644.009

84

117

D/Wall

WEST

STA. 10+614.009

STA. 10+764.010

116

Unit

Direction
EAST

STA. 10+584.009

STA. 10+734.009

115

ST

Unique
Unit Name

STA. 10+554.009

83

114

Design Unit

STA. 10+524.009

82

113

Type

Type

STA. 10+494.010

81

112

Length

Length
of

STA. 10+464.010

73

80

Type

Unit

STA. 10+374.010

STA. 10+434.009

79

Unit

STA. 10+344.009

72

78

STATION
North Bound
(NB)

STA. 10+314.009

STA. 10+404.090

77

Type

STA. 10+284.009

71

76

Length

Length
of

STA. 10+254.009

66

75

Unit

STA. 10+224.009

65

74

Unit

1+091.254

STA.

1+118.104

1+171.792

STA.

1+199.945

STA.
STA.

STA. 11+525.000

3099.77 m

Approach

21.40

S4

AP2

S4AP2

AP2E

AP2W

AP2D

AP2B

AP2K

AP2S

AP2A

AP2L

AP2G

AP2R

Unit -1

26.68

S4

U1

S4U1

U1E

U1W

U1D

U1B

U1K

U1S

U1A

U1L

U1G

U1R

Unit -2

26.85

S4

U2

S4U2

U2E

U2W

U2D

U2B

U2K

U2S

U2A

U2L

U2G

U2R

Unit -3

26.85

U3R

21.40

AP

Same as
South Bound

S4

U3

S4U3

U3E

U3W

U3D

U3B

U3K

U3S

U3A

U3L

U3G

Unit -4

26.85

S4

U4

S4U4

U4E

U4W

U4D

U4B

U4K

U4S

U4A

U4L

U4G

U4R

Unit -5

26.84

S4

U5

S4U5

U5E

U5W

U5D

U5B

U5K

U5S

U5A

U5L

U5G

U5R

Unit -6

28.15

S4

U6

S4U6

U6E

U6W

U6D

U6B

U6K

U6S

U6A

U6L

U6G

U6R

Unit -7

29.88

S4

U7

S4U7

U7E

U7W

U7D

U7B

U7K

U7S

U7A

U7L

U7G

U7R

Unit -8

30.69

S4

U8

S4U8

U8E

U8W

U8D

U8B

U8K

U8S

U8A

U8L

U8G

U8R

Unit -9

29.29

S4

U9

S4U9

U9E

U9W

U9D

U9B

U9K

U9S

U9A

U9L

U9G

U9R

162.23

DR-5

1+144.954

STA.

STA.

DR-4

1+064.404

STA.

STA.

Length :

9.94

1+229.822
89.86

TN-9

1+260.510
1+289.804

Length :

273.48 m

Remarks)
1) Definition of Direction
: The definition of direction will be added to some descriptions in Baseline as below.

Direction : ex) D/Wall


U1D (NB)

Direction

Abbreviation

Example

SOUTH

SB

D/Wall (650mm) [Sec.#2] : U1D~U3D , SB

NORTH

NB

D/Wall (650mm) [Sec.#2] : U1D~U3D , NB

Traffic
Direction

W100VUnit 1
U1D (SB)

U1D (NB)
)
Unit 2
U2D (SB)

Traffic
Direction

IP-56
(STA.1+050.000)

A2-4. Type of Section (According to Structure No.)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

Typical Section

STR
Name

Dpress Road

Length

DR-1

75.95 m

DR-2

145.95 m

Remarks

Name

Tunnel

TN-1

86.50 m

STRUCTURE NO.1

DR-3

637.74 m

Sub-Total : 859.63 m

Length

Sub-Total : 86.50 m

Typical Section

STR
Name

Dpress Road

Length

Remarks

Name

Tunnel

Length

STRUCTURE NO.2

TN-2

127.81 m

TN-3

224.16 m

Sub-Total : 351.97 m
DR-4

9.94 m

TN-3

90.01 m

150.0 m

TN-5

1591.05 m

STRUCTURE NO.3

TN-4

STRUCTURE NO.4

Sub-Total : 9.94 m

Sub-Total : 1831.06 m

DR-5

162.23 m

Approach

21.40 m

Sub-Total : 183.63 m

TN-6

89.86 m

Sub-Total : 89.86 m

Total of Each Type

1,053.20 m

Grand Total

3,412.58 m

2,359.39 m

A2-5. Productivity Report (Main Tunnel)


No

Description

1ST Excavation

2ND Excavation

Type of Section

Activity

Qty

Diaphragm Wall

2 days / unit
3472 m3 / unit
2
3480
2
1038
2
3700
2
2300
2
3000
2
4710
2
4050
3
1260
3
8103 m3 / unit
5
5800 / 4640 (S)
11
1730 /1384 (S)
10
6160 / 4930 (S)
7
2980 / 2390 (S)
10
5000 / 4000 (S)
9
7850 / 6280 (S)
7
6750 / 5400 (S)
10
2100 / 1680 (S)
Variable

Earth Anchor

Variable

Strut Installation & King Post

D/R 1&2
D/R 3&4
D/R 5
T/L 1
T/L 2
T/L 3
T/L 4
T/L 5
T/L 6
D/R 1&2
D/R 3&4
D/R 5
T/L 1
T/L 2
T/L 3
T/L 4
T/L 5
T/L 6

Used Cycle Time

Bored Pile

Bracket Installation
Runner beam
Waler
Strut Install
Pre-loading
Subtotal
Casing & Excavation
Excavation (soft rock)
Install rebar cage
Concrete placing
Subtotal

2 days / unit
2
4
1
9
1 hrs
5
3
1
10
4 days / unit

Pile Head

W/Proofing (Incl.Lean)

6 days / unit

W/Proofing (Wall)

6 days / unit

10 Base Slab
(4 Working Groups
will be operated)

D/R 1&2

D/R 3&4
T/L 1

Rebar install (1st, L=15m)


Form install (1st, L=15m)
Concrete placing (1st, L=15m)
Curing for mass concrete
Form dismantle
Construction joint treatment
Rebar install (2nd, L=15m)
Form install (2nd, L=15m)
Concrete placing (2nd, L=15m)
Curing for mass concrete
Form dismantle
Subtotal
Rebar install (1st, L=15m)
Form install (1st, L=15m)
Concrete placing (1st, L=15m)
Curing for mass concrete
Form dismantle
Construction joint treatment
Rebar install (2nd, L=15m)

4 days / unit
2
1
2
1
1
4
2
1
2
1
21
5
2
1
2
1
2
5

9m
10 m
4 m3
16 nr

Basic Productivity Req'd Team


500 m3 / team

300
200
300
300
300
300
300
300
8
200

m / day
m / mon

3
3
1
3
2
2
3
3
1
3
3
1
3
2
2
3
3
1

Required Manpower & Equipment per Team-Shift

Shift
Double
Double
Single
Double
Double
Double
Double
Double
Single
Double
Double
Single
Double
Double
Double
Double
Double
Single
Double

Foreman
Dozer
Excavator
Dump Truck

1
1
1
4

Skilled
Operator

3
6

Common

Foreman
Dozer
Excavator
Dump Truck

1
1
1
3

Skilled
Operator

3
5

Common

Foreman
1
Trench Cutter 1
Excavator
1
Foreman
1
Crawler Drill
1
Foreman
1
Crawler Crane 1
Welding Machin 1
Boring Rig
1

4 No / day

Double

9 day / layer

Single
Single
Single
Single
Single

9
2

Double Foreman
1
Crawler Crane 1
Boring Rig
1

4
1 shfit : 1 nr, 2 shift : 2 nr
1 nr / team

62 ton
140 m2
770 m3

15.5 ton / day


70 m2 / day
770 m3 / day

62 ton
140 m2
770 m3

15.5 ton / day


70 m2 / day
770 m3 / day

93 ton
212 m2
1165 m3

18.6 ton / day


106 m2 / day
1165 m3 / day

93 ton

18.6 ton / day

Remarks

2 Double Foreman
Air Compressor
Single Foreman
Mobile Crane
Single Foreman
Mobile Crane
Double Foreman
Single Foreman
Single Foreman
Single Crawler Crane
Single Fork Lift
Single Cargo Crane
Double
Single
Single
Single
Single
Double Foreman
Single Foreman
Single Foreman
Single
Single
Single
Double

1
1
1
1
1
1
3
2
2
1
1
1

3
2
2

Soft Rock
Soft Rock
Soft Rock

Common
7
Crawler Crane 1
Dump Truck 2
Common
4
Grouting Pump 1
Common
6
Operator
1

1.5 panel / day

Drill Operator 1
Welder

Skilled

Common

Skilled

Common

Skilled

Common

10

Skilled

Common

10

Steel Fitter
Carperter
Concrete

32
18
24

Steel Fitter
Carperter
Concrete

32
18
24

A2-5. Productivity Report (Main Tunnel)


No

Description

Type of Section

Activity

Form install (2nd, L=15m)


Concrete placing (2nd, L=15m)
Curing for mass concrete
Form dismantle
Subtotal
D/R 5
Rebar install (1st, L=15m)
Form install (1st, L=15m)
Concrete placing (1st, L=15m)
Curing for mass concrete
Form dismantle
Construction joint treatment
Rebar install (2nd, L=15m)
Form install (2nd, L=15m)
Concrete placing (2nd, L=15m)
Curing for mass concrete
Form dismantle
Subtotal
T/L 3
Rebar install (1st, L=15m)
T/L 6
Form install (1st, L=15m)
Concrete placing (1st, L=15m)
Curing for mass concrete
Form dismantle
Construction joint treatment
Rebar install (2nd, L=15m)
Form install (2nd, L=15m)
Concrete placing (2nd, L=15m)
Curing for mass concrete
Form dismantle
Subtotal
T/L 4
Rebar install (1st, L=15m)
T/L 5
Form install (1st, L=15m)
Concrete placing (1st, L=15m)
Curing for mass concrete
Form dismantle
Construction joint treatment
Rebar install (2nd, L=15m)
Form install (2nd, L=15m)
Concrete placing (2nd, L=15m)
Curing for mass concrete
Form dismantle
Subtotal
11 1ST Wall
Rebar install (1st, L=10m)
(4 Working Groups will be operated) Form install (1st, L=10m)
Concrete placing (1st, L=10m)
Rebar install (2nd, L=10m)
Form install (2nd, L=10m)
Concrete placing (2nd, L=10m)
Curing
Form dismantle
Construction joint treatment
Rebar install (3rd, L=10m)
Form install (3rd, L=10m)
Concrete placing (3rd, L=10m)
Curing
Subtotal
12 2nd Wall
Form dismantle
(4 Working Groups will be operated) Injection for construction joint
2nd stage rebar, form, concrete work
Subtotal

Used Cycle Time


2
1
2
1
24
2
2
1
2
1
1
2
2
1
1
1
16
3
2
1
2
1
1
3
2
1
2
1
19
6
3
2
2
1
1
6
3
2
2
1
29
3
2
1
3
2
1
2
1
1
3
2
1
2
24
1
2
12
15

Qty

Basic Productivity Req'd Team

Shift

Required Manpower & Equipment per Team-Shift

212 m2
1165 m3

106 m2 / day
1165 m3 / day

Single
Single
Single
Single

22 ton
81 m2
271 m3

11 ton / day
40.5 m2 / day
271 m3 / day

2
1
1

Steel Fitter
Carperter
Concrete

24
9
10

22 ton
81 m2
271 m3

11 ton / day
40.5 m2 / day
271 m3 / day

Double Foreman
Single Foreman
Single Foreman
Single
Single
Single
Double
Single
Single
Single
Single

56 ton
177 m2
697 m3

18.67 ton / day


88.5 m2 / day
697 m3 / day

3
2
2

Steel Fitter
Carperter
Concrete

32
18
24

56 ton
177 m2
697 m3

18.67 ton / day


88.5 m2 / day
697 m3 / day

Double Foreman
Single Foreman
Single Foreman
Single
Single
Single
Double
Single
Single
Single
Single

148 ton
295 m2
1851 m3

24.67 ton / day


98.33 m2 / day
925.5 m3 / day

4
2
2

Steel Fitter
Carperter
Concrete

42
20
31

148 ton
295 m2
1851 m3

24.67 ton / day


98.33 m2 / day
925.5 m3 / day

Double Foreman
Single Foreman
Single Foreman
Single
Single
Single
Double
Single
Single
Single
Single
Double Foreman
Double Foreman
Single Foreman
Double
Double
Single
Single
Double
Double
Double
Double
Single
Single

2
1
1

Steel Fitter
Carperter
Concrete

19
14
6

Double Foreman
Double Foreman
Double Foreman

2
1
1

Steel Fitter
Carperter
Concrete

19
14
6

28
396
218
28
396
218

ton
m2
m3
ton
m2
m3

28 ton
396 m2
218 m3

9.33
198
218
9.33
198
218

ton
m2
m3
ton
m2
m3

/ day
/ day
/ day
/ day
/ day
/ day

9.33 ton / day


198 m2 / day
218 m3 / day

Remarks

A2-5. Productivity Report (Main Tunnel)


No

Description

Type of Section

Activity

13 Roof Slab
Form install
(4 Working Groups will be operated) Rebar install
Concrete placing (both side, L=20m)
Curing
Concrete placing (center, L=10m)
Curing
Form dismantle
Subtotal
14 C/Wall (Column)
Rebar install (Column), h=5.4m
Form install (Column), h=5.4m
Concrete placing (Column), h=5.4m
Curing
Form dismantle
Subtotal
15 C/Wall (Cap Beam)
Staging install (beam), h=5.4m
Form install (beam), h=1.5m
Rebar install (beam), h=1.5m
Concrete placing (beam), h=1.5m
Curing
Form dismantle
Staging & Scaffolding dismantle
Subtotal

Used Cycle Time


4
7
1
1
1
2
2
18
2
2
1
2
1
8
2
2
2
1
14
1
2
24

Qty

Basic Productivity Req'd Team

Required Manpower & Equipment per Team-Shift

1747 m2
76 ton
220 m3

436.75 m2 / day
10.86 ton / day
220 m3 / day

Double Foreman
Double Foreman
Single Foreman
Single
Single
Single
Double

2
2
1

Carperter
Steel Fitter
Concrete

20
17
10

9 ton
143 m2
59 m3

4.5 ton / day


71.5 m2 / day
59 m3 / day

Double Foreman
Double Foreman
Single Foreman
Single
Double

1
1
1

Steel Fitter
Carperter
Concrete

11
9
5

145 m2
10 ton
68 m3

72.5 m2 / day
5 ton / day
68 m3 / day

Double
Double
Double
Single
Single
Double
Double

10
1
1
1

Steel Fitter
Carperter
Concrete

11
9
5

Shift

Scaffolder
Foreman
Foreman
Foreman

Remarks

A2-5. Productivity Report (Utilities & Detour Works)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
S.No.

ACTIVITY

ESTIMATED
QUANTITY

UNIT

REMARKS
DAILY PRODUCTION PLANNED (Estimated No. of
Work Teams)

DETOUR WORKS

1.1

INSTALLATION OF TEMPORARY CONCRETE BARRIERS

1.2

INSTALLATION OF TEMPORARY STREET LIGHTING

1.3

REMOVE / REPLANT TREES

1.4

EXCAVATION/ PREPARATION OF FORMATION

68440 Sqm.

1800

1.5

BORROW FILL / SUBBASE

68440 Sqm.

1200

1.6

ASPHALT WEARING COURSE

68440 Sqm.

1200

1.7

INSTALLATION TEMPORARY TRAFFIC SIGNS

1.8

TEMPORARY ROAD MARKING

1.9

INSTALL TEMPORARY TRAFFIC SIGNAL CONTROLLER

1.10 INSTALL TEMPORARY PEDESTRIAN BRIDGES OVER


DETOUR

20000

LM

300

270

Nos.

800

Nos.

550
8040
15

14

15

Nos.

30

LM

600

Nos. 1 No. to be constructed in 24

Nos.

working days, however work will be


started parallely depending upon
area availability after completion of
Wearing Course in that area.
1 No. to be constructed in 24
working days, however work will be
started parallely depending upon
area availability.Construction of
foundations, structural fabrication &
erection, handrails & finishings will
be taken up in sequence by
individual sub-working teams

3 WORK
TEAMS

UTILITIES RELOCATION WORKS

3.1 STORM WATER DRAINAGE SYSTEM


3.1.1 STORM WATER MAINLINE - EXCAVATION & BEDDING

34000 Cum.

150

3.1.2 STORM WATER MAINLINE - PIPELAYING

5917

LM

24

3.1.3 STORM WATER MAINLINE - BACKFILLING

5016

LM

24

3.1.4 STORM WATER MAINLINE - TESTING

5917

3.1.5 STORM WATER MAINLINE - MANHOLE CONSTRUCTION

124

LM Each line to be tested in 6 days


Nos. Each Manhole to be constructed in

3.1.6 STORM WATER MAINLINE - CONNECTION TO EXISTING


LINES
3.1.7 STORM WATER MAINLINE - NDRC WORKS

30

Nos. Each connection to an existing line

10 days
to be completed in 4 days

901

LM

Construction of Driving Pit - 18


days
Construction of Reception Pit - 5
days
Driving / Testing & Grouting 6 ~ 10 days depending upon length
of NDRC crossing

3.1.8 DI PIPE LAYING UNDER TUNNEL BASE

4095

LM

12

3.1.9 PAVEMENT SUBBASE DRAIN PIPELAYING

2980

LM

20

3.1.10 PAVEMENT SUBBASE DRAINAGE - CATCH BASINS

38

Nos. Duration for installation of Catch


Basins is same as that of
Pipelaying for a particular line, as
the Catch Basins will be installed
alongwith Pipelaying

3.1.11 STORM WATER LATERALS - EXCAVATION & BEDDING

20998 Cum.

100

3.1.12 STORM WATER LATERALS - PIPELAYING

4486

LM

20

3.1.13 STORM WATER LATERALS - BACKFILLING

4486

LM

20

3.1.14 STORM WATER LATERALS - TESTING

4486

LM

3.1.15 STORM WATER LATERALS - INLETS / CATCH BASINS

3.1.16 STORM WATER LATERALS - CONNECTION TO EXISTING


LINES

261

49

Each line to be tested in 3 days

Nos. Productivity same as Pipelaying for

Nos.

a particular line as the Inlets &


Catch Basins will be installed
alongwith Pipelaying
Each connection to an existing line
to be completed in 2 days

2 WORK
TEAMS

A2-5. Productivity Report (Utilities & Detour Works)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
S.No.

ACTIVITY

ESTIMATED
QUANTITY

UNIT

REMARKS
DAILY PRODUCTION PLANNED (Estimated No. of
Work Teams)

3.2 WATER LINE RELOCATION WORKS


3.2.1 WATER LINE - EXCAVATION & BEDDING

4264

LM

20

3.2.2 WATER LINE - PIPELAYING

4975

LM

20

3.2.3 WATER LINE - CORROSION PROTECTION

4975

LM

20

3.2.4 WATER LINE - BACKFILLING

4264

LM

20

3.2.5 WATER LINE - CHAMBER CONSTRUCTION

63

Nos. Duration for construction of Valve

3.2.6 WATER LINE - TESTING

4975

LM

3.2.7 WATER LINE - STERILIZATION

4975

LM

3.2.8 WATER LINE - SHUTDOWN & CONNECTION

28

Nos.

3.2.9 WATER LINE - NDRC WORKS

321

LM

3.2.10 WATER LINE - C.S. PIPELINE ACROSS TUNNEL

329

LM

Chambers in a particular line is


between 10 ~ 24 days depending
upon the Nos. of chambers .
Testing duration is 6 ~ 10 days
depending upon length of the
pipeline
Planned duration same as Testing
of Water Line
Duration for each Shutdown &
Connection is considered as 6 days
for Pipe dia upto 800 mm and 8
days for Pipe dia from 900 mm 1200 mm
Construction of Driving Pit - 18
days
Construction of Reception Pit - 5
days
Driving / Testing & Grouting - 8 ~
10 days depending upon length of
NDRC crossing
Duration for laying C.S. Pipeline
through each Utility Crossing is
considered as 6 days

1 WORK
TEAM

3.3 IRRIGATION RELOCATION WORKS


3.3.1 IRRIGATION LINE - EXCAVATION & PIPELAYING

5664

LM

20

3.3.2 IRRIGATION LINE - BACKFILLING

5146

LM

20

3.3.3 IRRIGATION VALVE CHAMBERS

47

Nos. Duration for construction of each


chamber = 6 days
Duration considered for each
connection is 4 days

3.3.4 CONNECTION TO EXISTING IRRIGATION LINE


3.3.5 REMOVAL OF EXISTING IRRIGATION LINE

13280

LM

60

1550

LM

10

3.4.1 TELEPHONE DUCTS - EXCAVATION & LAYING

1860

LM

12

3.4.2 TELEPHONE DUCTS - BACKFILLING

12

3.3.6 IRRIGATION - REINSTATEMENT OF PAVEMENT

1 WORK
TEAM

3.4 TELEPHONE LINE RELOCATION WORKS


1860

LM

3.4.3 TELEPHONE DUCTS - THROUGH UTILITY CROSSINGS

783

LM

3.4.4 TELEPHONE DUCTS - THROUGH THRUST BORING

229

LM

33

Nos.

3.4.5 TELEPHONE MANHOLES / CHAMBERS


3.4.6 TELEPHONE LINE - CABLELAYING

114880

LM

500
Duration considered for Testing &
Commissioning of each line = 12
days

3.4.7 TELEPHONE CABLE - TESTING & COMMISSIONING

3.4.8 TELEPHONE LINE - REINSTATEMENT WORKS

12
Duration considered for laying of
Telephone duct through Thrust
boring = 24 days
Duration for Construction of each
Telephone Manhole = 7 days

5100 Sqm.

50

1 WORK
TEAM

A2-5. Productivity Report (Utilities & Detour Works)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
S.No.

ACTIVITY

ESTIMATED
QUANTITY

UNIT

REMARKS
DAILY PRODUCTION PLANNED (Estimated No. of
Work Teams)

3.5 SEWERAGE LINE RELOCATION WORKS


3.5.1 SEWERAGE LINE - EXCAVATION & SHEET PILING

3310

LM

3.5.2 SEWERAGE LINE - PIPELAYING

4016

LM

3.5.3 SEWERAGE LINE - TESTING


3.5.4 SEWERAGE LINE - BACKFILLING & REMOVE SHEET PILE

4016
3310

LM
LM

3.5.5 SEWER MANHOLES/CHAMBER - EXCAVATION & SHEET


PILING

48

3.5.6 SEWER MANHOLES/CHAMBER - CONSTRUCTION

57

Nos. Duration for Excavation & Sheet

Nos.

3.5.7 SEWER MANHOLES/CHAMBER - BACKFILLING & REMOVE


SHEET PILE
3.5.8 SEWER LINE - NDRC WORKS

57

Nos.

706

LM

3.5.9 REMOVE / ABANDON EXISTING SEWER LINE

890

LM

Each line to be tested in 2 days

Piling for Manhole Construction =


3 days
Duration for Construction of Sewer
Manhole is considered between 12
~ 18 days, depending upon depth
of Manhole
Backfilling duration varies from 12~
18 days

2 WORK
TEAMS

Construction of Driving Pit - 25


days
Construction of Reception Pit - 5
days
Driving / Testing & Grouting - 10 ~
20 days depending upon length of
NDRC crossing
Duration for Removal of existing
Sewer Line varies from 4 ~ 6 days
depending upon length of line

UTILITY CROSSINGS & FUTURE DUCTS

4.1 FUTURE / CONTINGENCY DUCTS


4.1.1 WATER DUCTS

900

LM

20

1 WORK TEAM

4.1.2 IRRIGATION DUCTS

2175

LM

20

1 WORK TEAM

4.1.3 TELEPHONE DUCTS

7000

LM

50

1 WORK TEAM

350

LM

850

LM

4.1.4 SEWER DUCTS

Duration for Laying each Sewer


Duct = 2 days

1 WORK TEAM

4.2 UTILITY CROSSINGS


4.2.1 GRP SLEEVE FOR WATER LINE CROSSING

12

1 WORK TEAM

4.2.2 GRP SLEEVE FOR IRRIGATION LINE CROSSING

900

LM

10

1 WORK TEAM

4.2.3 PVC SLEEVE FOR TELEPHONE LINE CROSSING

6000

LM

50

1 WORK TEAM

400

1 WORK TEAM

PAVEMENT WORKS

5.1

EMBANKMENT / SUBGRADE (WITH GEOTEXTILE)

5.2

AGGREGATE BASE COURSE

41263

Sqm

1500

1 WORK TEAM

5.3

SAND ASPHALT ON TUNNEL DECK SLAB

92000

Sqm

2500

1 WORK TEAM

5.4

ASPHALT BASE COURSE

5230 Cum.

150

5.5

ASPHALT WEARING COURSE (OUTSIDE TUNNEL)

3980 Cum.

150

5.6

ASPHALT WEARING COURSE (ON TUNNEL)

10580 Cum.

150

40000 Cum.

1 WORK TEAM

TRAFFIC MARKING & SIGNS

6.1

ROAD MARKING

35960

LM

500

1 WORK TEAM

6.2

INSTALLATION OF ROAD STUDS

25000

Nos.

250

1 WORK TEAM

6.3

INSTALLATION OF TRAFFIC SIGNS

605

Sqm

10

1 WORK TEAM

A2-5. Productivity Report(MEP)


Required Manpower (Nos.)
No.

Sch Item

Foreman Mechanic Electrician

Required Equipment (Nos.)

Helper

Scissor
Lift

Moval
Crane

Fork
Lift

Cargo
Truck

Mechanical Works
2,001
2,002
2,003
2,004
2,005
2,006
2,011
2,012
2,013
2,014
2,015
2,016
2,017

Survey and Installation of Anchoring, Supporting


Installation of Main Misting and Fire Landing Valve Pipe
Installation of Steel Frame for Duct and Smoke Dampers
Installation of Tunnel Fire Rated Duct
Duct Pressure Testing
Installation of Mech. Fixture
Installation Tunnel Ventilation Fan and Control Panels
Installation Tunnel Dampers and Sound Attenuator
Installation of Drainage Pumps and Piping
Installation of Fire Fighting Pump and Misting Pump
Installation of Lift at Stru. No. 20
Installation of Utility Building Piping
Installation of Misc. Mech. Fixture
Subtotal for Mechanical Works

Electrical Works
2,201
Survey and Installation of Anchoring, Supporting for Tunnel
2,202
Installation of Cable Tray and Conduit for Tunnel
2,203
Installation of Control and Power Cables for Tunnel
2,204
Installation of Street Lighting
2,205
Installation of Tunnel Elec Fixture
2,301
TCS program
2,302
Installation of TCS Cable
2,303
Installation of TCS equipment in the Stru. No. 5 & 20
2,304
Installation of Tunnel VMS, CCTV, LSCS
2,401
SCDA program
2,402
Installation of SCADA Cable
2,403
Installation of SCADA equipment in the Stru. No. 5 & 20
3,006
Individual Fan, Pump, Lighting, FAS, Control Testing
3,007
Individual Zone Testing & Commissioning
Subtotal for Electrical Works
Total MEP

3
1
4
1
1
1
11

20
4
40
3
3
2
1
8
1
4
10
96

2
1
1
1
1
1
1
1
9
20

96

20
4
40
3
3
2
1
7
1
4
9
94

2
4
1
1
1
9

2
1
4
1
1
2
1
12

2
4
1
1
1
9

2
1
4
1
1
1
1
11

10
8
7
11
5
8
7
1
3
6
2
68
68

10
8
6
10
4
7
6
1
2
5
2
61
155

2
1
1
1
1
1
7
16

2
1
2
1
1
1
1
9
21

2
1
1
1
1
1
7
16

2
1
2
1
1
1
1
9
20

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 3
Scheduling Report

SAMSUNG-SAIF BIN DARWISH JV

-3-

SCHEDLOG
Scheduling/Leveling Report - 28-Aug-08 - PM.exe
===============================================
Default Project..................................................1801BF7
Projects:
1801BF7..........................................................UPGRADING AL SALAM
TUNNEL_Change Logics
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calendar for scheduling Relationship Lag ........................Predecessor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................7257
# Not Started....................................................7257
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................15043
# Activities with Constraint.....................................1
Project:
1801BF7 Activity:
KD000010
Commencement of Project
Errors:
------Warnings:
--------Activities without predecessors..................................1
Project:
1801BF7 Activity:
KD000010
Commencement of Project
Activities without successors....................................1
Project:
1801BF7 Activity:
KD000020
Completion of Project
Out-of-sequence activities.......................................0
Activities with Actual Dates > Data Date.........................0
Milestone Activities with invalid relationships..................17
Project:
1801BF7 Activity:
CNS110360
[Sec. #1] Commencement of
Construction Stage 3
Project:
1801BF7 Activity:
CNS210380
[Sec. #2] Commencement of
Construction Stage 2
Project:
1801BF7 Activity:
CNS210390
[Sec. #2] Commencement of
Construction Stage 3
Project:
1801BF7 Activity:
CNS310360
[Sec #3] Commencement of
Construction Stage 2
Project:
1801BF7 Activity:
CNS310370
[Sec #3] Commencement of
Construction Stage 3
Project:
1801BF7 Activity:
CNS410390
[Sec. #4] Commencement of
Construction Stage 2
Project:
1801BF7 Activity:
CNS410400
[Sec. #4] Commencement of
Construction Stage 3
Project:
1801BF7 Activity:
CNS410401
[Sec. #4] Completion of
Construction Stage 3
Project:
1801BF7 Activity:
HN000010
Hand-Over of All Structures
Project:
1801BF7 Activity:
KD000070
[Sec. #1] Completion of Main
1

SCHEDLOG
Construction Works
Project:
Construction Works
Project:
Construction Works
Project:
Construction Works
Project:
Project:
Project:
Project:

1801BF7 Activity:

KD000080

[Sec. #2] Completion of Main

1801BF7 Activity:

KD000090

[Sec. #3] Completion of Main

1801BF7 Activity:

KD000100

[Sec. #4] Completion of Main

1801BF7
1801BF7
1801BF7
1801BF7

KD000300
KD000520
KD000760
KD000980

[Sec.
[Sec.
[Sec.
[Sec.

Activity:
Activity:
Activity:
Activity:

#1]
#2]
#3]
#4]

Completion
Completion
Completion
Completion

of
of
of
of

Roof
Roof
Roof
Roof

Slab
Slab
Slab
Slab

Scheduling/Leveling Results:
---------------------------# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................7257
# Relationships with other projects..............................0
Data Date........................................................15-May-08
Earliest Early Start Date........................................15-May-08
Latest Early Finish Date.........................................31-Oct-10
Exceptions:
----------Critical Activities..............................................188
Project:
1801BF7 Activity:
CNS310070
D/Wall [Sec. #3]: Unit 10 (Str.3) ~
Unit 11 (Str.3) , SB
Project:
1801BF7 Activity:
CNS310080
D/Wall [Sec. #3]: Unit 13 (Str.3) ~
Unit 14 (Str.3) , SB
Project:
1801BF7 Activity:
CNS310110
D/Wall [Sec. #3]: Unit 21 (Str.3) ~
Unit 23 (Str.3) , SB
Project:
1801BF7 Activity:
CNS310170
D/Wall [Sec. #3]: Unit 10 (Str.3) ~
Unit 11 (Str.3) , NB
Project:
1801BF7 Activity:
CNS310180
D/Wall [Sec. #3]: Unit 13 (Str.3) ~
Unit 14 (Str.3) , NB
Project:
1801BF7 Activity:
CNS310210
D/Wall [Sec. #3]: Unit 21 (Str.3) ~
Unit 23 (Str.3) , NB
Project:
1801BF7 Activity:
CNS320170
Pile Head [Sec. #3] : Unit 17
(Str.3) ~ Unit 20 (Str.3)
Project:
1801BF7 Activity:
CNS330000
1ST - Excavation [Sec. #3] : Unit
10 (Str.3) ~ Unit 11 (Str.3)
Project:
1801BF7 Activity:
CNS330010
1ST - Excavation [Sec. #3] : Unit
13 (Str.3) ~ Unit 14 (Str.3)
Project:
1801BF7 Activity:
CNS330040
1ST - Excavation [Sec. #3] : Unit
21 (Str.3) ~ Unit 23 (Str.3)
Project:
1801BF7 Activity:
CNS330100
2ND - Excavation [Sec. #3] : Unit
10 (Str.3) ~ Unit 11 (Str.3)
Project:
1801BF7 Activity:
CNS330110
2ND - Excavation [Sec. #3] : Unit
13 (Str.3) ~ Unit 14 (Str.3)
Project:
1801BF7 Activity:
CNS330120
2ND - Excavation [Sec. #3] : Unit
15 (Str.3) ~ Unit 16 (Str.3)
Project:
1801BF7 Activity:
CNS330130
2ND - Excavation [Sec. #3] : Unit
17 (Str.3) ~ Unit 20 (Str.3)
Project:
1801BF7 Activity:
CNS330140
2ND - Excavation [Sec. #3] : Unit
21 (Str.3) ~ Unit 23 (Str.3)
Project:
1801BF7 Activity:
CNS330330
Earth Anchor [Sec. #3] : Unit 21
(Str.3) ~ Unit 23 (Str.3)
Project:
1801BF7 Activity:
CNS340030
W/Proofing (Incl.Lean) [Sec. #3] :
Unit 17 (Str.3) ~ Unit 20 (Str.3)
Project:
1801BF7 Activity:
CNS350210
Base Slab [Sec. #3] : Unit 17A
(Str.3)
Project:
1801BF7 Activity:
CNS350220
Base Slab [Sec. #3] : Unit 17B
(Str.3)
Project:
1801BF7 Activity:
CNS350230
Base Slab [Sec. #3] : Unit 17C
(Str.3)
Project:
1801BF7 Activity:
CNS350480
Base Slab [Sec. #3] : Unit 26A
(Str.3)
Project:
1801BF7 Activity:
CNS350490
Base Slab [Sec. #3] : Unit 26B
(Str.3)
Project:
1801BF7 Activity:
CNS350500
Base Slab [Sec. #3] : Unit 26C
(Str.3)
Project:
1801BF7 Activity:
CNS350510
Base Slab [Sec. #3] : Unit 27A
(Str.3)
Project:
1801BF7 Activity:
CNS350520
Base Slab [Sec. #3] : Unit 27B
(Str.3)
Project:
1801BF7 Activity:
CNS350530
Base Slab [Sec. #3] : Unit 27C
(Str.3)
2

Project:

1801BF7 Activity:

SCHEDLOG
CNS350630

Base Slab [Sec. #3] : Unit 31A

Project:

1801BF7 Activity:

CNS350640

Base Slab [Sec. #3] : Unit 31B

Project:

1801BF7 Activity:

CNS350650

Base Slab [Sec. #3] : Unit 31C

Project:

1801BF7 Activity:

CNS350960

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS350970

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS350980

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351230

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351240

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351250

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351260

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351270

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351280

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351380

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351390

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351400

1ST-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351710

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351720

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351730

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351980

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS351990

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352000

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352010

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352020

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352030

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352130

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352140

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352150

2ND-Retaining Wall [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352320

C/Wall (Column) [Sec. #3] : Unit 17

Project:

1801BF7 Activity:

CNS352410

C/Wall (Column) [Sec. #3] : Unit 26

Project:

1801BF7 Activity:

CNS352420

C/Wall (Column) [Sec. #3] : Unit 27

Project:

1801BF7 Activity:

CNS352460

C/Wall (Column) [Sec. #3] : Unit 31

Project:

1801BF7 Activity:

CNS352960

I-Girder Install [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS352970

I-Girder Install [Sec. #3] : Unit

Project:

1801BF7 Activity:

CNS353660

Roof Slab [Sec. #3] : Unit 32A

Project:

1801BF7 Activity:

CNS353670

Roof Slab [Sec. #3] : Unit 32B

Project:

1801BF7 Activity:

CNS353680

Roof Slab [Sec. #3] : Unit 32C

Project:
1801BF7 Activity:
#3] : Unit 10 (Str.3) ~ Unit 11 (Str.3)
Project:
1801BF7 Activity:

CNS360190

Fire Protection & Finishes [Sec.

CNS360200

Fire Protection & Finishes [Sec.

(Str.3)
(Str.3)
(Str.3)
17A (Str.3)
17B (Str.3)
17C (Str.3)
26A (Str.3)
26B (Str.3)
26C (Str.3)
27A (Str.3)
27B (Str.3)
27C (Str.3)
31A (Str.3)
31B (Str.3)
31C (Str.3)
17A (Str.3)
17B (Str.3)
17C (Str.3)
26A (Str.3)
26B (Str.3)
26C (Str.3)
27A (Str.3)
27B (Str.3)
27C (Str.3)
31A (Str.3)
31B (Str.3)
31C (Str.3)
(Str.3)
(Str.3)
(Str.3)
(Str.3)
31 (Str.3)
32 (Str.3)
(Str.3)
(Str.3)
(Str.3)

SCHEDLOG
#3] : Unit 12 (Str.3) ~ Unit 14 (Str.3)
Project:
1801BF7
#3] : Unit 15 (Str.3) ~ Unit 16 (Str.3)
Project:
1801BF7
#3] : Unit 17 (Str.3) ~ Unit 19 (Str.3)
Project:
1801BF7
#3] : Unit 20 (Str.3) ~ Unit 22 (Str.3)
Project:
1801BF7
#3] : Unit 23 (Str.3) ~ Unit 24 (Str.3)
Project:
1801BF7
#3] : Unit 25 (Str.3) ~ Unit 26 (Str.3)
Project:
1801BF7
#3] : Unit 27 (Str.3) ~ Unit 29 (Str.3)
Project:
1801BF7
#3] : Unit 30 (Str.3) ~ Unit 32 (Str.3)
Project:
1801BF7
#3] : Unit 33 (Str.3) ~ Unit 34 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 47 (Str.3)
Project:
1801BF7
Unit 56 (Str.3) , SB
Project:
1801BF7
Unit 45 (Str.3) , SB
Project:
1801BF7
Unit 42 (Str.3) , SB
Project:
1801BF7
Unit 40 (Str.3) , SB
Project:
1801BF7
Unit 38 (Str.3) , SB
Project:
1801BF7
Unit 35 (Str.3) , SB
Project:
1801BF7
Unit 56 (Str.3) , NB
Project:
1801BF7
Unit 45 (Str.3) , NB
Project:
1801BF7
Unit 42 (Str.3) , NB
Project:
1801BF7
Unit 40 (Str.3) , NB
Project:
1801BF7
Unit 38 (Str.3) , NB
Project:
1801BF7
Unit 35 (Str.3) , NB
Project:
1801BF7
(Str.3) ~ Unit 48 (Str.3)
Project:
1801BF7
47 (Str.3) ~ Unit 45 (Str.3)
Project:
1801BF7
39 (Str.3) ~ Unit 38 (Str.3)
Project:
1801BF7
37 (Str.3) ~ Unit 35 (Str.3)
Project:
1801BF7
49 (Str.3) ~ Unit 48 (Str.3)
Project:
1801BF7
(Str.3)
Project:
1801BF7
(Str.3) ~ Unit 60 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 58 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 56 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 52 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 50 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 45 (Str.3)
Project:
1801BF7
(Str.3) ~ Unit 35 (Str.3)
Project:
1801BF7
Unit 49 (Str.3) ~ Unit 48 (Str.3)
Project:
1801BF7
(Str.3)
Project:
1801BF7
(Str.3)

Activity:

CNS360210

Fire Protection & Finishes [Sec.

Activity:

CNS360220

Fire Protection & Finishes [Sec.

Activity:

CNS360230

Fire Protection & Finishes [Sec.

Activity:

CNS360240

Fire Protection & Finishes [Sec.

Activity:

CNS360250

Fire Protection & Finishes [Sec.

Activity:

CNS360260

Fire Protection & Finishes [Sec.

Activity:

CNS360270

Fire Protection & Finishes [Sec.

Activity:

CNS360280

Fire Protection & Finishes [Sec.

Activity:

CNS410060

Strut Removal [Sec. #4] : Unit 49

Activity:

CNS410110

D/Wall [Sec. #4]: Unit 57 (Str.3) ~

Activity:

CNS410150

D/Wall [Sec. #4]: Unit 47 (Str.3) ~

Activity:

CNS410160

D/Wall [Sec. #4]: Unit 44 (Str.3) ~

Activity:

CNS410170

D/Wall [Sec. #4]: Unit 41 (Str.3) ~

Activity:

CNS410180

D/Wall [Sec. #4]: Unit 39 (Str.3) ~

Activity:

CNS410190

D/Wall [Sec. #4]: Unit 37 (Str.3) ~

Activity:

CNS410230

D/Wall [Sec. #4]: Unit 57 (Str.3) ~

Activity:

CNS410270

D/Wall [Sec. #4]: Unit 47 (Str.3) ~

Activity:

CNS410280

D/Wall [Sec. #4]: Unit 44 (Str.3) ~

Activity:

CNS410290

D/Wall [Sec. #4]: Unit 41 (Str.3) ~

Activity:

CNS410300

D/Wall [Sec. #4]: Unit 39 (Str.3) ~

Activity:

CNS410310

D/Wall [Sec. #4]: Unit 37 (Str.3) ~

Activity:

CNS420200

Pile Head [Sec. #4] : Unit 49

Activity:

CNS430060

1ST - Excavation [Sec. #4] : Unit

Activity:

CNS430090

1ST - Excavation [Sec. #4] : Unit

Activity:

CNS430100

1ST - Excavation [Sec. #4] : Unit

Activity:

CNS430160

2ND - Excavation [Sec. #4] : Unit

Activity:

CNS430330

Earth Anchor [Sec. #4] : Unit 62

Activity:

CNS430331

Earth Anchor [Sec. #4] : Unit 61

Activity:

CNS430340

Earth Anchor [Sec. #4] : Unit 59

Activity:

CNS430350

Earth Anchor [Sec. #4] : Unit 57

Activity:

CNS430360

Earth Anchor [Sec. #4] : Unit 55

Activity:

CNS430370

Earth Anchor [Sec. #4] : Unit 51

Activity:

CNS430380

Earth Anchor [Sec. #4] : Unit 46

Activity:

CNS430410

Earth Anchor [Sec. #4] : Unit 37

Activity:

CNS440060

W/Proofing (Incl.Lean) [Sec. #4]

Activity:

CNS450390

Base Slab [Sec. #4] : Unit 49A

Activity:

CNS450400

Base Slab [Sec. #4] : Unit 49B

Project:

1801BF7 Activity:

SCHEDLOG
CNS450410

Project:

1801BF7 Activity:

CNS451230

1ST-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS451240

1ST-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS451250

1ST-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS451800

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS451810

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS451820

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452010

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452020

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452030

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452070

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452080

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS452090

2ND-Retaining Wall [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS453080

I-Girder Install [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS453100

I-Girder Install [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS453110

I-Girder Install [Sec. #4] : Unit

Project:

1801BF7 Activity:

CNS453440

Roof Slab [Sec. #4] : Unit 58A

Project:

1801BF7 Activity:

CNS453450

Roof Slab [Sec. #4] : Unit 58B

Project:

1801BF7 Activity:

CNS453460

Roof Slab [Sec. #4] : Unit 58C

Activity:

CNS460220

Fire Protection & Finishes [Sec.

Activity:

CNS460230

Fire Protection & Finishes [Sec.

Activity:

CNS460250

Fire Protection & Finishes [Sec.

Activity:

CNS460260

Fire Protection & Finishes [Sec.

Activity:

CNS460270

Fire Protection & Finishes [Sec.

Activity:

CNS460320

Fire Protection & Finishes [Sec.

Activity:

DG000010

Design for Excavation Support

1801BF7 Activity:

DG000020

Design for Excavation Support

1801BF7 Activity:

DG000030

Design for Excavation Support

1801BF7 Activity:

DG000040

Design for Excavation Support

1801BF7 Activity:

DG000200

Shop Drawing Submission :

1801BF7 Activity:

DG000440

Shop Drawing Approval : Excavation

1801BF7 Activity:

DT000130

IP37 : Install Temporary

1801BF7 Activity:

DT000330

IP37A-IP37B :

1801BF7 Activity:

DT000530

IP37B-IP38C : Install Temporary

1801BF7 Activity:

DT000730

IP38C-IP38A : Install Temporary

1801BF7 Activity:

DT000930

IP38A-IP39A :

1801BF7 Activity:

DT001130

IP39A-IP41A :

1801BF7 Activity:

DT001330

IP41-IP39 :

Base Slab [Sec. #4] : Unit 49C

(Str.3)
49A (Str.3)
49B (Str.3)
49C (Str.3)
58A (Str.3)
58B (Str.3)
58C (Str.3)
51A (Str.3)
51B (Str.3)
51C (Str.3)
49A (Str.3)
49B (Str.3)
49C (Str.3)
61 (Str.3)
59 (Str.3)
58 (Str.3)
(Str.3)
(Str.3)
(Str.3)
Project:
#4] : Unit 62 (Str.3) ~ Unit
Project:
#4] : Unit 59 (Str.3) ~ Unit
Project:
#4] : Unit 54 (Str.3) ~ Unit
Project:
#4] : Unit 51 (Str.3) ~ Unit
Project:
#4] : Unit 49 (Str.3) ~ Unit
Project:
#4] : Unit 37 (Str.3) ~ Unit
Project:
System
Project:
System : Submmission
Project:
System : Review
Project:
System : Approval
Project:
Excavation Supporting System
Project:
Supporting System
Project:
Streetlights
Project:
Streetlights
Project:
Streetlights
Project:
Streetlights
Project:
Streetlights
Project:
Streetlights
Project:

1801BF7
60 (Str.3)
1801BF7
58 (Str.3)
1801BF7
52 (Str.3)
1801BF7
50 (Str.3)
1801BF7
47 (Str.3)
1801BF7
35 (Str.3)
1801BF7

Install Temporary

Install Temporary
Install Temporary
Install Temporary

SCHEDLOG
Streetlights
Project:

1801BF7 Activity:

DT001530

IP39-IP38 : Install Temporary

Project:

1801BF7 Activity:

DT001730

IP38-IP38A :Install Temporary

Project:

1801BF7 Activity:

DT001930

IP38-IP38B :Install Temporary

Project:

1801BF7 Activity:

DT002030

IP38B-IP11A :Remove Streetlight

Project:

1801BF7 Activity:

DT002040

IP38B-IP11A : Remove Streetlight

Project:
Preparation of Formation
Project:
Project:
Project:
Sign Boards
Project:
Streetlights
Project:
Stage 2
Project:
Project:
Reporting
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Investigation
Project:
Project:
Project:
Construction Works
Project:
Construction Works
Project:
Construction Works
Project:
Wall (2nd)
Project:
Streetlight Foundations
Project:
columns
Project:
lanterns
Project:
cables
Project:
Project:
Streetlight columns
Project:
Streetlight lanterns
Project:
Streetlight cables
Project:
Over for Construction
Project:
(Structure)
Project:
Project:

1801BF7 Activity:

DT002060

IP38B-IP11A : Excavation /

1801BF7 Activity:
1801BF7 Activity:
1801BF7 Activity:

DT002070
DT002080
DT002100

IP38B-IP11A : Borrow fill / Subbase


IP38B-IP11A :Asphalt Wearing Course
IP38B-IP11A :Temporary Detour -

1801BF7 Activity:

DT002130

IP38B-IP11A :Install Temporary

1801BF7 Activity:

DT0030A0

Traffic Diversion from Stage 1 to

1801BF7 Activity:
1801BF7 Activity:

HN000010
IS000010

Hand-Over of All Structures


Site Investigation : Execution &

1801BF7 Activity:

IS003000

IP55D-IP41A : Borehole / Soil

1801BF7 Activity:

IS003300

IP41A-IP41 : Borehole / Soil

1801BF7 Activity:

IS003600

IP41-IP12 : Borehole / Soil

1801BF7 Activity:

IS003900

IP12-IP9 : Borehole / Soil

1801BF7 Activity:

IS004200

IP9-IP11 : Borehole / Soil

1801BF7 Activity:

IS004500

IP11-IP11A : Borehole / Soil

1801BF7 Activity:

IS004800

IP11A-IP36A : Borehole / Soil

1801BF7 Activity:

IS005100

IP36A-IP36 : Borehole / Soil

1801BF7 Activity:

IS005400

IP36-IP44 : Borehole / Soil

1801BF7 Activity:

IS006000

IP12-IP56 : Borehole / Soil

1801BF7 Activity:
1801BF7 Activity:
1801BF7 Activity:

KD000010
KD000020
KD000050

Commencement of Project
Completion of Project
[Sec. #3] Commencement of Main

1801BF7 Activity:

KD000060

[Sec. #4] Commencement of Main

1801BF7 Activity:

KD000090

[Sec. #3] Completion of Main

1801BF7 Activity:

KD000920

[Sec. #4] Completion of Retaining

1801BF7 Activity:

MA000050

Submit Material - Anchor Bolts for

1801BF7 Activity:

MA000060

Submit Material - Temp Streetlight

1801BF7 Activity:

MA000070

Submit Material - Temp Streetlight

1801BF7 Activity:

MA000080

Submit Material - Temp Streetlight

1801BF7 Activity:
1801BF7 Activity:

MA000750
MA000760

Supply of Materials - Anchor Bolts


Supply of Materials - Temp

1801BF7 Activity:

MA000770

Supply of Materials - Temp

1801BF7 Activity:

MA000780

Supply of Materials - Temp

1801BF7 Activity:

MB000100

Project Commencement & Site Handing

1801BF7 Activity:

SC000010

Tunnel Testing & Commissioning

1801BF7 Activity:
1801BF7 Activity:

SC000100
SC000200

Final Acceptance Inspection


Submit Subcontract Proposal -

Streetlights
Streetlights
Streetlights
columns
Foundations

SCHEDLOG
Temporary Streetlighting
Project:
Temporary Streetlighting
Project:
Streetlighting
Project:
Holes & Soil Investigation
Project:
Holes & Soil Investigation
Project:
& Soil Investigation
Project:
Bore Holes & Soil Investigation
Project:
Project:
Locations

1801BF7 Activity:

SC000210

ApproveSubcontract Proposal -

1801BF7 Activity:

SC000220

Award of Subcontract

1801BF7 Activity:

SC000600

Submit Subcontract Proposal - Bore

1801BF7 Activity:

SC000610

Approve Subcontract Proposal - Bore

1801BF7 Activity:

SC000620

Award of Subcontract

1801BF7 Activity:

SC000630

Mobilisation of Subcontractor -

1801BF7 Activity:
1801BF7 Activity:

SU000010
SY00CN20

Sub-Contract : Site Investigation


Survey : Bore hole & Trial Pit

Activities with unsatisfied constraints..........................0


Activities with unsatisfied relationships........................0
Activities with external dates...................................0

- Temporary

- Bore Holes

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 4
Critical Path Report
A4-1. Tabulation Report
A4-2. Graphical Report

SAMSUNG-SAIF BIN DARWISH JV

-4-

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

Original Duration

Remaining Duration

Activity % Complete Primary Resource

Early Start

Early Finish

UPGRADING AL SALAM TUNNEL_Change Logics


DG000020 Design for Excavation
Support System :
Submmission

0%

15-Sep-08

DG000040 Design for Excavation


Support System :
Approval

0%

29-Sep-08

KD000920 [Sec. #4] Completion


of Retaining Wall
d)
HN000010 (2
Hand-Over
of All

0%

31-May-10

0%

31-Oct-10

DG000030 Design for Excavation


Support System :
Review

14

14

0%

16-Sep-08

29-Sep-08

DG000440 Shop Drawing


Approval : Excavation
Supporting System

14

14

0%

18-Oct-08

31-Oct-08

DG000200 Shop Drawing


Submission :
Excavation Supporting
System

18

18

0%

30-Sep-08

17-Oct-08

SU000010 Sub-Contract : Site


Investigation

30

30

0%

15-May-08

13-Jun-08

SC000010 Tunnel Testing &


Commissioning
(Structure)

40

40

0%

22-Sep-10

31-Oct-10

SC000100 Final Acceptance


Inspection

40

40

0%

22-Sep-10

31-Oct-10

IS000010 Site Investigation :


Execution & Reporting

45

45

0%

14-Jun-08

12-Aug-08

DG000010 Design for Excavation


Support System

69

69

0%

09-Jul-08

15-Sep-08

MB000100 Project
Commencement &
Site Handing Over for
Construction

0%

15-May-08

KD000090 [Sec. #3] Completion


of Main Construction
Works

0%

KD000010 Commencement of
Project

0%

Structures

MILESTONES & PRELIMINARIES

21-Sep-10

15-May-08

KD000020 Completion of Project

0%

KD000050 [Sec. #3]


Commencement of
Main Construction
Works

0%

01-Nov-08

KD000060 [Sec. #4]


Commencement of
Main Construction
Works

0%

01-Nov-08

DT0030A0 Traffic Diversion from


Stage 1 to Stage 2

0%

01-Nov-08

IS006000 IP12-IP56 : Borehole /


Soil Investigation

0%

14-Aug-08

17-Aug-08

IS003300 IP41A-IP41 : Borehole


/ Soil Investigation

0%

27-Jul-08

03-Aug-08

SY00CN20 Survey : Bore hole &


Trial Pit Locations

0%

06-Jul-08

12-Jul-08

IS005400 IP36-IP44 : Borehole /


Soil Investigation

0%

22-Oct-08

30-Oct-08

IS003600 IP41-IP12 : Borehole /


Soil Investigation

0%

04-Aug-08

13-Aug-08

IS003900 IP12-IP9 : Borehole /


Soil Investigation

0%

18-Aug-08

27-Aug-08

31-Oct-10

01-Nov-08

SURVEY & INVESTIGATION

IS004500 IP11-IP11A : Borehole


/ Soil Investigation

0%

11-Sep-08

21-Sep-08

IS003000 IP55D-IP41A :
Borehole / Soil
Investigation

12

12

0%

13-Jul-08

26-Jul-08

IS004200 IP9-IP11 : Borehole /


Soil Investigation

12

12

0%

28-Aug-08

10-Sep-08

IS004800 IP11A-IP36A :
Borehole / Soil
Investigation

12

12

0%

22-Sep-08

07-Oct-08

IS005100 IP36A-IP36 : Borehole


/ Soil Investigation

12

12

0%

08-Oct-08

21-Oct-08

0%

07-Jun-08

12-Jun-08

0%

07-Jun-08

12-Jun-08

MATERIAL SUBMITTALS
MA000050 Submit Material Anchor Bolts for
Streetlight
Foundations
MA000060 Submit Material -

Page 1 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

MA000070 Submit Material Temp Streetlight


t
MA000080 lSubmit
Material -

Original Duration

Remaining Duration

Activity % Complete Primary Resource

Early Start

Early Finish

0%

07-Jun-08

12-Jun-08

0%

07-Jun-08

12-Jun-08

Temp Streetlight
bl & FABRICATION
PROCUREMENT
MA000750 Supply of Materials Anchor Bolts

24

24

0%

21-Jun-08

17-Jul-08

MA000760 Supply of Materials Temp Streetlight


columns

24

24

0%

21-Jun-08

17-Jul-08

MA000770 Supply of Materials Temp Streetlight


lanterns

24

24

0%

21-Jun-08

17-Jul-08

MA000780 Supply of Materials Temp Streetlight


cables

24

24

0%

21-Jun-08

17-Jul-08

SC000220 Award of Subcontract


- Temporary
Streetlighting

0%

04-Jun-08

06-Jun-08

SC000200 Submit Subcontract


Proposal - Temporary
Streetlighting

0%

21-May-08

27-May-08

SC000620 Award of Subcontract


- Bore Holes & Soil
Investigation

0%

16-Jun-08

21-Jun-08

SC000210 ApproveSubcontract
Proposal - Temporary
Streetlighting

0%

28-May-08

03-Jun-08

SC000600 Submit Subcontract


Proposal - Bore Holes
& Soil Investigation

12

12

0%

19-May-08

01-Jun-08

SC000630 Mobilisation of
Subcontractor - Bore
Holes & Soil
Investigation

12

12

0%

22-Jun-08

05-Jul-08

SC000610 Approve Subcontract


Proposal - Bore Holes
& Soil Investigation

14

14

0%

02-Jun-08

15-Jun-08

DT001530 IP39-IP38 : Install


Temporary Streetlights

0%

21-Aug-08

24-Aug-08

DT001730 IP38-IP38A :Install


Temporary Streetlights

0%

25-Aug-08

27-Aug-08

DT001930 IP38-IP38B :Install


Temporary Streetlights

0%

28-Aug-08

31-Aug-08

DT002100 IP38B-IP11A
:Temporary Detour Sign Boards

0%

27-Oct-08

30-Oct-08

DT001330 IP41-IP39 : Install


Temporary Streetlights

0%

17-Aug-08

20-Aug-08

DT000130 IP37 : Install


Temporary Streetlights

0% 1HFORE2.FOREMAN 08-Jul-08

13-Jul-08

DT000330 IP37A-IP37B : Install


Temporary Streetlights

0%

14-Jul-08

19-Jul-08

DT000530 IP37B-IP38C : Install


Temporary Streetlights

0%

20-Jul-08

24-Jul-08

CNS35296 I-Girder Install [Sec.


#3] : Unit 31 (Str.3)

0%

29-Mar-10

04-Apr-10

CNS35297 I-Girder Install [Sec.


#3] : Unit 32 (Str.3)

0%

05-Apr-10

11-Apr-10

DT000730 IP38C-IP38A : Install


Temporary Streetlights

0%

26-Jul-08

02-Aug-08

DT000930 IP38A-IP39A : Install


Temporary Streetlights

0%

03-Aug-08

09-Aug-08

DT001130 IP39A-IP41A : Install


Temporary Streetlights

0%

10-Aug-08

16-Aug-08

CNS45308 I-Girder Install [Sec.


#4] : Unit 61 (Str.3)

0%

01-Jun-10

07-Jun-10

CNS45310 I-Girder Install [Sec.


#4] : Unit 59 (Str.3)

0%

08-Jun-10

14-Jun-10

CNS45311 I-Girder Install [Sec.


#4] : Unit 58 (Str.3)

0%

15-Jun-10

21-Jun-10

CNS43033 Earth Anchor [Sec. #4]


: Unit 62 (Str.3)

0% 2YJETT.Jet Grouting
Pump

10-Sep-09

17-Sep-09

CNS45344 Roof Slab [Sec. #4] :


Unit 58A (Str.3)

0%

22-Jun-10

28-Jun-10

CNS45345 Roof Slab [Sec. #4] :


Unit 58B (Str.3)

0%

29-Jun-10

05-Jul-10

CNS45346 Roof Slab [Sec. #4] :


Unit 58C (Str.3)

0%

07-Jul-10

15-Jul-10

DT002030 IP38B-IP11A :Remove


Streetlight columns

0%

17-Sep-08

24-Sep-08

SUBCONTRACT PROCESS

CONSTRUCTION

Page 2 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

Original Duration

Remaining Duration

Early Start

Early Finish

0%

25-Sep-08

05-Oct-08

0%

27-Jul-10

03-Aug-10

CNS46027 Fire Protection &


Finishes [Sec. #4] :
Unit 49 (Str.3) ~ Unit
47 (Str.3)

0%

04-Aug-10

15-Aug-10

CNS46032 Fire Protection &


Finishes [Sec. #4] :
Unit 37 (Str.3) ~ Unit
35 (Str.3)

0%

17-Jul-10

25-Jul-10

CNS41011 D/Wall [Sec. #4]: Unit


57 (Str.3) ~ Unit 56
(Str.3) , SB

0%

27-Nov-08

06-Dec-08

CNS41015 D/Wall [Sec. #4]: Unit


47 (Str.3) ~ Unit 45
(Str.3) , SB

0%

18-Dec-08

25-Dec-08

CNS41023 D/Wall [Sec. #4]: Unit


57 (Str.3) ~ Unit 56
(Str.3) , NB

0%

10-Dec-08

17-Dec-08

CNS35096 1ST-Retaining Wall


[Sec. #3] : Unit 17A
(Str.3)

0%

11-Oct-09

19-Oct-09

CNS35097 1ST-Retaining Wall


[Sec. #3] : Unit 17B
(Str.3)

0%

20-Oct-09

28-Oct-09

CNS35098 1ST-Retaining Wall


[Sec. #3] : Unit 17C
(Str.3)

0%

29-Oct-09

07-Nov-09

CNS35123 1ST-Retaining Wall


[Sec. #3] : Unit 26A
(Str.3)

0%

16-Dec-09

26-Dec-09

CNS35124 1ST-Retaining Wall


[Sec. #3] : Unit 26B
(Str.3)

0%

27-Dec-09

04-Jan-10

CNS35125 1ST-Retaining Wall


[Sec. #3] : Unit 26C
(Str.3)

0%

05-Jan-10

13-Jan-10

CNS35126 1ST-Retaining Wall


[Sec. #3] : Unit 27A
(Str.3)

0%

11-Nov-09

19-Nov-09

CNS35127 1ST-Retaining Wall


[Sec. #3] : Unit 27B
(Str.3)

0%

21-Nov-09

01-Dec-09

CNS35128 1ST-Retaining Wall


[Sec. #3] : Unit 27C
(Str.3)

0%

03-Dec-09

12-Dec-09

CNS35138 1ST-Retaining Wall


[Sec. #3] : Unit 31A
(Str.3)

0%

18-Jan-10

26-Jan-10

CNS35139 1ST-Retaining Wall


[Sec. #3] : Unit 31B
(Str.3)

0%

27-Jan-10

04-Feb-10

CNS35140 1ST-Retaining Wall


[Sec. #3] : Unit 31C
(Str.3)

0%

06-Feb-10

14-Feb-10

CNS35366 Roof Slab [Sec. #3] :


Unit 32A (Str.3)

0%

12-Apr-10

20-Apr-10

CNS35367 Roof Slab [Sec. #3] :


Unit 32B (Str.3)

0%

21-Apr-10

29-Apr-10

CNS35368 Roof Slab [Sec. #3] :


Unit 32C (Str.3)

0%

01-May-10

09-May-10

CNS35232 C/Wall (Column) [Sec.


#3] : Unit 17 (Str.3)

0%

08-Nov-09

16-Nov-09

CNS35241 C/Wall (Column) [Sec.


#3] : Unit 26 (Str.3)

0%

14-Jan-10

23-Jan-10

CNS35242 C/Wall (Column) [Sec.


#3] : Unit 27 (Str.3)

0%

13-Dec-09

22-Dec-09

CNS35246 C/Wall (Column) [Sec.


#3] : Unit 31 (Str.3)

0%

15-Feb-10

23-Feb-10

CNS31007 D/Wall [Sec. #3]: Unit


10 (Str.3) ~ Unit 11
(Str.3) , SB

0%

21-Dec-08

30-Dec-08

CNS31017 D/Wall [Sec. #3]: Unit


10 (Str.3) ~ Unit 11
(Str.3) , NB

0%

31-Dec-08

10-Jan-09

CNS31021 D/Wall [Sec. #3]: Unit


21 (Str.3) ~ Unit 23
(Str.3) , NB

0%

11-Dec-08

20-Dec-08

CNS42020 Pile Head [Sec. #4] :


Unit 49 (Str.3) ~ Unit
48 (Str.3)

0%

11-Nov-09

19-Nov-09

DT002040 IP38B-IP11A : Remove


Streetlight
d ti
CNS46025 F
Fire Protection
&

Activity % Complete Primary Resource

Finishes [Sec. #4] :


Unit 54 (Str.3) ~ Unit
52 (Str.3)

Page 3 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

Original Duration

Remaining Duration

CNS46022 Fire Protection &


Finishes [Sec. #4] :
Unit 62 (Str.3) ~ Unit
60 (Str.3)

CNS46023 Fire Protection &


Finishes [Sec. #4] :
Unit 59 (Str.3) ~ Unit
58 (Str.3)

CNS46026 Fire Protection &


Finishes [Sec. #4] :
Unit 51 (Str.3) ~ Unit
50 (Str.3)

Activity % Complete Primary Resource

Early Start

Early Finish

0%

13-Sep-10

21-Sep-10

0%

01-Sep-10

12-Sep-10

0%

17-Aug-10

31-Aug-10

CNS41027 D/Wall [Sec. #4]: Unit


47 (Str.3) ~ Unit 45
(Str.3) , NB

0%

27-Dec-08

06-Jan-09

CNS41029 D/Wall [Sec. #4]: Unit


41 (Str.3) ~ Unit 40
(Str.3) , NB

0%

15-Feb-09

23-Feb-09

CNS41030 D/Wall [Sec. #4]: Unit


39 (Str.3) ~ Unit 38
(Str.3) , NB

0%

07-Mar-09

16-Mar-09

CNS45123 1ST-Retaining Wall


[Sec. #4] : Unit 49A
(Str.3)

0%

10-Jan-10

18-Jan-10

CNS45124 1ST-Retaining Wall


[Sec. #4] : Unit 49B
(Str.3)

0%

19-Jan-10

27-Jan-10

CNS45125 1ST-Retaining Wall


[Sec. #4] : Unit 49C
(Str.3)

0%

28-Jan-10

06-Feb-10

CNS35021 Base Slab [Sec. #3] :


Unit 17A (Str.3)

0%

03-Sep-09

16-Sep-09

CNS35022 Base Slab [Sec. #3] :


Unit 17B (Str.3)

0%

17-Sep-09

29-Sep-09

CNS35023 Base Slab [Sec. #3] :


Unit 17C (Str.3)

0%

30-Sep-09

10-Oct-09

CNS35048 Base Slab [Sec. #3] :


Unit 26A (Str.3)

0%

11-Nov-09

21-Nov-09

CNS35049 Base Slab [Sec. #3] :


Unit 26B (Str.3)

0%

22-Nov-09

05-Dec-09

CNS35050 Base Slab [Sec. #3] :


Unit 26C (Str.3)

0%

06-Dec-09

15-Dec-09

CNS35051 Base Slab [Sec. #3] :


Unit 27A (Str.3)

0%

11-Oct-09

20-Oct-09

CNS35052 Base Slab [Sec. #3] :


Unit 27B (Str.3)

0%

21-Oct-09

31-Oct-09

CNS35053 Base Slab [Sec. #3] :


Unit 27C (Str.3)

0%

01-Nov-09

10-Nov-09

CNS35063 Base Slab [Sec. #3] :


Unit 31A (Str.3)

0%

16-Dec-09

27-Dec-09

CNS35064 Base Slab [Sec. #3] :


Unit 31B (Str.3)

0%

28-Dec-09

06-Jan-10

CNS35065 Base Slab [Sec. #3] :


Unit 31C (Str.3)

0%

07-Jan-10

17-Jan-10

CNS35171 2ND-Retaining Wall


[Sec. #3] : Unit 17A
(Str.3)

0%

17-Nov-09

29-Nov-09

CNS35172 2ND-Retaining Wall


[Sec. #3] : Unit 17B
(Str.3)

0%

30-Nov-09

10-Dec-09

CNS35173 2ND-Retaining Wall


[Sec. #3] : Unit 17C
(Str.3)

0%

12-Dec-09

22-Dec-09

CNS35198 2ND-Retaining Wall


[Sec. #3] : Unit 26A
(Str.3)

0%

24-Jan-10

02-Feb-10

CNS35199 2ND-Retaining Wall


[Sec. #3] : Unit 26B
(Str.3)

0%

03-Feb-10

13-Feb-10

CNS35200 2ND-Retaining Wall


[Sec. #3] : Unit 26C
(Str.3)

0%

14-Feb-10

23-Feb-10

CNS35201 2ND-Retaining Wall


[Sec. #3] : Unit 27A
(Str.3)

0%

23-Dec-09

02-Jan-10

CNS35202 2ND-Retaining Wall


[Sec. #3] : Unit 27B
(Str.3)

0%

03-Jan-10

12-Jan-10

CNS35203 2ND-Retaining Wall


[Sec. #3] : Unit 27C
(Str.3)

0%

13-Jan-10

23-Jan-10

CNS35213 2ND-Retaining Wall


[Sec. #3] : Unit 31A
(Str.3)

0%

25-Feb-10

07-Mar-10

CNS35214 2ND-Retaining Wall


[Sec. #3] : Unit 31B

0%

08-Mar-10

17-Mar-10

Page 4 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

Original Duration

Remaining Duration

CNS35215 2ND-Retaining Wall


[Sec. #3] : Unit 31C
(Str.3)

CNS31011 D/Wall [Sec. #3]: Unit


21 (Str.3) ~ Unit 23
(Str.3) , SB

CNS41017 D/Wall [Sec. #4]: Unit


41 (Str.3) ~ Unit 40
(Str.3) , SB

Activity % Complete Primary Resource

Early Start

Early Finish

0%

18-Mar-10

28-Mar-10

0%

26-Nov-08

10-Dec-08

0%

04-Feb-09

14-Feb-09

CNS41018 D/Wall [Sec. #4]: Unit


39 (Str.3) ~ Unit 38
(Str.3) , SB

0%

24-Feb-09

05-Mar-09

CNS45041 Base Slab [Sec. #4] :


Unit 49C (Str.3)

0%

30-Dec-09

09-Jan-10

CNS45182 2ND-Retaining Wall


[Sec. #4] : Unit 58C
(Str.3)

0%

22-May-10

31-May-10

CNS45203 2ND-Retaining Wall


[Sec. #4] : Unit 51C
(Str.3)

0%

18-Apr-10

27-Apr-10

CNS45209 2ND-Retaining Wall


[Sec. #4] : Unit 49C
(Str.3)

0%

15-Mar-10

24-Mar-10

CNS31008 D/Wall [Sec. #3]: Unit


13 (Str.3) ~ Unit 14
(Str.3) , SB

10

10

0%

01-Nov-08

11-Nov-08

CNS36019 Fire Protection &


Finishes [Sec. #3] :
Unit 10 (Str.3) ~ Unit
11 (Str.3)

10

10

0%

22-May-10

01-Jun-10

CNS36020 Fire Protection &


Finishes [Sec. #3] :
Unit 12 (Str.3) ~ Unit
14 (Str.3)

10

10

0%

02-Jun-10

13-Jun-10

CNS36021 Fire Protection &


Finishes [Sec. #3] :
Unit 15 (Str.3) ~ Unit
16 (Str.3)

10

10

0%

14-Jun-10

24-Jun-10

CNS36022 Fire Protection &


Finishes [Sec. #3] :
Unit 17 (Str.3) ~ Unit
19 (Str.3)

10

10

0%

26-Jun-10

07-Jul-10

CNS36023 Fire Protection &


Finishes [Sec. #3] :
Unit 20 (Str.3) ~ Unit
22 (Str.3)

10

10

0%

10-May-10

20-May-10

CNS36024 Fire Protection &


Finishes [Sec. #3] :
Unit 23 (Str.3) ~ Unit
24 (Str.3)

10

10

0%

22-Jul-10

04-Aug-10

CNS36025 Fire Protection &


Finishes [Sec. #3] :
Unit 25 (Str.3) ~ Unit
26 (Str.3)

10

10

0%

05-Aug-10

22-Aug-10

CNS36026 Fire Protection &


Finishes [Sec. #3] :
Unit 27 (Str.3) ~ Unit
29 (Str.3)

10

10

0%

08-Jul-10

21-Jul-10

CNS36027 Fire Protection &


Finishes [Sec. #3] :
Unit 30 (Str.3) ~ Unit
32 (Str.3)

10

10

0%

24-Aug-10

09-Sep-10

CNS36028 Fire Protection &


Finishes [Sec. #3] :
Unit 33 (Str.3) ~ Unit
34 (Str.3)

10

10

0%

11-Sep-10

21-Sep-10

CNS41006 Strut Removal [Sec.


#4] : Unit 49 (Str.3) ~
Unit 47 (Str.3)

10

10

0%

07-Feb-10

17-Feb-10

CNS44006 W/Proofing (Incl.Lean)


[Sec. #4] : Unit 49
(Str.3) ~ Unit 48 (Str.3)

10

10

0%

21-Nov-09

05-Dec-09

CNS45039 Base Slab [Sec. #4] :


Unit 49A (Str.3)

10

10

0%

06-Dec-09

16-Dec-09

CNS45040 Base Slab [Sec. #4] :


Unit 49B (Str.3)

10

10

0%

19-Dec-09

29-Dec-09

CNS45180 2ND-Retaining Wall


[Sec. #4] : Unit 58A
(Str.3)

10

10

0%

28-Apr-10

09-May-10

CNS45181 2ND-Retaining Wall


[Sec. #4] : Unit 58B
(Str.3)

10

10

0%

10-May-10

20-May-10

CNS45201 2ND-Retaining Wall


[Sec. #4] : Unit 51A
(Str.3)

10

10

0%

25-Mar-10

05-Apr-10

Page 5 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Activity Name

Original Duration

Remaining Duration

CNS45202 2ND-Retaining Wall


[Sec. #4] : Unit 51B
(Str.3)

10

10

CNS45207 2ND-Retaining Wall


[Sec. #4] : Unit 49A
(Str.3)

10

CNS45208 2ND-Retaining Wall


[Sec. #4] : Unit 49B
(Str.3)

Activity % Complete Primary Resource

Early Start

Early Finish

0%

06-Apr-10

17-Apr-10

10

0%

18-Feb-10

02-Mar-10

10

10

0%

03-Mar-10

14-Mar-10

CNS41019 D/Wall [Sec. #4]: Unit


37 (Str.3) ~ Unit 35
(Str.3) , SB

11

11

0%

01-Nov-08

12-Nov-08

CNS31018 D/Wall [Sec. #3]: Unit


13 (Str.3) ~ Unit 14
(Str.3) , NB

12

12

0%

12-Nov-08

25-Nov-08

CNS33001 1ST - Excavation [Sec.


#3] : Unit 13 (Str.3) ~
Unit 14 (Str.3)

12

12

0%

11-Jan-09

24-Jan-09

DT002070 IP38B-IP11A : Borrow


fill / Subbase

12

12

0%

09-Oct-08

22-Oct-08

DT002060 IP38B-IP11A :
Excavation /
Preparation of
Formation

12

12

0%

06-Oct-08

19-Oct-08

DT002080 IP38B-IP11A :Asphalt


Wearing Course

12

12

0%

13-Oct-08

26-Oct-08

CNS41016 D/Wall [Sec. #4]: Unit


44 (Str.3) ~ Unit 42
(Str.3) , SB

12

12

0%

07-Jan-09

20-Jan-09

CNS41028 D/Wall [Sec. #4]: Unit


44 (Str.3) ~ Unit 42
(Str.3) , NB

12

12

0%

21-Jan-09

03-Feb-09

CNS41031 D/Wall [Sec. #4]: Unit


37 (Str.3) ~ Unit 35
(Str.3) , NB

12

12

0%

13-Nov-08

26-Nov-08

CNS34003 W/Proofing (Incl.Lean)


[Sec. #3] : Unit 17
(Str.3) ~ Unit 20 (Str.3)

14

14

0%

13-Aug-09

02-Sep-09

CNS33011 2ND - Excavation


[Sec. #3] : Unit 13
(Str.3) ~ Unit 14 (Str.3)

14

14

0%

09-Mar-09

24-Mar-09

DT002130 IP38B-IP11A :Install


Temporary Streetlights

14

14

0%

01-Sep-08

16-Sep-08

CNS43016 2ND - Excavation


[Sec. #4] : Unit 49
(Str.3) ~ Unit 48 (Str.3)

14

14

0%

26-Oct-09

10-Nov-09

CNS43033 Earth Anchor [Sec. #4]


: Unit 61 (Str.3) ~ Unit
60 (Str.3)

14

14

0% 2YJETT.Jet Grouting
Pump

21-Sep-09

06-Oct-09

CNS43009 1ST - Excavation [Sec.


#4] : Unit 39 (Str.3) ~
Unit 38 (Str.3)

15

15

0%

17-Mar-09

02-Apr-09

CNS32017 Pile Head [Sec. #3] :


Unit 17 (Str.3) ~ Unit
20 (Str.3)

16

16

0%

21-Jul-09

12-Aug-09

CNS33000 1ST - Excavation [Sec.


#3] : Unit 10 (Str.3) ~
Unit 11 (Str.3)

16

16

0%

17-Feb-09

07-Mar-09

CNS43010 1ST - Excavation [Sec.


#4] : Unit 37 (Str.3) ~
Unit 35 (Str.3)

16

16

0%

27-Apr-09

14-May-09

CNS43034 Earth Anchor [Sec. #4]


: Unit 59 (Str.3) ~ Unit
58 (Str.3)

16

16

0% 2YJETT.Jet Grouting
Pump

07-Oct-09

25-Oct-09

CNS43035 Earth Anchor [Sec. #4]


: Unit 57 (Str.3) ~ Unit
56 (Str.3)

16

16

0% 2YJETT.Jet Grouting
Pump

13-Jun-09

30-Jun-09

CNS43037 Earth Anchor [Sec. #4]


: Unit 51 (Str.3) ~ Unit
50 (Str.3)

16

16

0% 2YJETT.Jet Grouting
Pump

18-Aug-09

09-Sep-09

CNS43038 Earth Anchor [Sec. #4]


: Unit 46 (Str.3) ~ Unit
45 (Str.3)

16

16

0% 2YJETT.Jet Grouting
Pump

27-Apr-09

14-May-09

CNS33004 1ST - Excavation [Sec.


#3] : Unit 21 (Str.3) ~
Unit 23 (Str.3)

20

20

0%

25-Jan-09

16-Feb-09

CNS43006 1ST - Excavation [Sec.


#4] : Unit 47 (Str.3) ~
Unit 45 (Str.3)

20

20

0%

04-Apr-09

26-Apr-09

CNS33010 2ND - Excavation


[Sec. #3] : Unit 10
(Str.3) ~ Unit 11 (Str.3)

21

21

0%

27-Apr-09

20-May-09

CNS33012 2ND - Excavation


[Sec. #3] : Unit 15
(Str.3) ~ Unit 16 (Str.3)

21

21

0%

21-May-09

14-Jun-09

Page 6 of 7

UPGRADING AL SALAM TUNNEL_Change


Logics
Report Date 28-Aug-08 20:23

Project Start 15-May-08


Project Finish 31-Oct-10
Data Date 15-May-08

A4-1 Tabulation Report - Critical Path

WBS
Activity
ID

Original Duration

Remaining Duration

Activity % Complete Primary Resource

Early Start

Early Finish

CNS43041 Earth Anchor [Sec. #4]


: Unit 37 (Str.3) ~ Unit
35 (Str.3)

24

24

0% 2YJETT.Jet Grouting
Pump

16-May-09

11-Jun-09

CNS33013 2ND - Excavation


[Sec. #3] : Unit 17
(Str.3) ~ Unit 20 (Str.3)

28

28

0%

15-Jun-09

20-Jul-09

CNS33014 2ND - Excavation


[Sec. #3] : Unit 21
(Str.3) ~ Unit 23 (Str.3)

28

28

0%

25-Mar-09

26-Apr-09

CNS33033 Earth Anchor [Sec. #3]


: Unit 21 (Str.3) ~ Unit
23 (Str.3)

30

30

0% 2YJETT.Jet Grouting
Pump

17-Feb-09

24-Mar-09

CNS43036 Earth Anchor [Sec. #4]


: Unit 55 (Str.3) ~ Unit
52 (Str.3)

32

32

0% 2YJETT.Jet Grouting
Pump

01-Jul-09

16-Aug-09

750

750

15-May-08

31-Oct-10

Total

Activity Name

Page 7 of 7

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
750
0
0% 15-May-08 31-Oct-10

MILESTONES
General

KD000010

Commencement of Project

KD000020

Completion of Project

General
MILESTONES
MB000100

Project Commencement & Site Handing Over for Construction

Section No.3 (STA.


(S
9+954 ~ STA. 10+704)

KD000050

[Sec. #3] Commencement of Main Construction Works

KD000090

[Sec. #3] Completion of Main Construction Works

Section No.4 (STA.


(S
10+704 ~ STA. 11+525)

KD000060

[Sec. #4] Commencement of Main Construction Works

Reinforced Concrete
Conc
Works
Retaining Wall ((2nd)
KD000920

[Sec. #4] Completion of Retaining Wall (2nd)

INVESTIGATION & SURVEY


General
Site Investigation

IS000010

Site Investigation : Execution & Reporting

SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES
DETAILED SURVEYING
SURV
& SETTING OUT
General
SY00CN20 Survey : Bore hole & Trial Pit Locations

Section No.1 (L.O.C


(L
~ STA. 9+381)
SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES
BOREHOLE
General
IS003000

IP55D-IP41A : Borehole / Soil Investigation

Start

Finish

VAR
VAR
START FINISH

15-May-08

31-Oct-10

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
0

750

0%

15-May-... 31-Oct-10

15-May-08

31-Oct-10

750

0%

15-May-... 31-Oct-10

15-May-08

31-Oct-10

750
750
0

0
0
0

15-May-... 31-Oct-10
15-May-... 31-Oct-10
15-May-...

15-May-08
15-May-08
15-May-08*

31-Oct-10
31-Oct-10

0%

0%
0%
100%

0
0
0

0
0
0

0
0
0 NA

0%

0%

31-Oct-10

31-Oct-10

0 NA

0%

15-May-... 15-May-...

15-May-08

15-May-08

0
0
0

0
0
0

0%
0%
100%

15-May-... 15-May-...
15-May-... 15-May-...
15-May-...

15-May-08
15-May-08
15-May-08

15-May-08
15-May-08

0
0
0

0
0
0

0
0
0 NA

574

0% 01-Nov-08 21-Sep-10

01-Nov-08

21-Sep-10

574

0% 01-Nov-08 21-Sep-10

01-Nov-08

21-Sep-10

574
574
0

0
0
0

01-Nov-08
01-Nov-08
01-Nov-08

21-Sep-10
21-Sep-10

0%

0% 01-Nov-08 21-Sep-10
0% 01-Nov-08 21-Sep-10
0% 01-Nov-08

0
0
0

0
0
0

0
0
0 NA

[Sec. #3] Commencement of Main Construction Work

0%

0%

21-Sep-10

21-Sep-10

0 NA

[Sec. #

480

0% 01-Nov-08

31-May-...

01-Nov-08

31-May-10

0% 01-Nov-08 01-Nov-08

01-Nov-08

01-Nov-08

0
0
0

0
0
0

0% 01-Nov-08 01-Nov-08
0% 01-Nov-08 01-Nov-08
0% 01-Nov-08

01-Nov-08
01-Nov-08
01-Nov-08

01-Nov-08
01-Nov-08

0
0
0

0
0
0

0
0
0 NA

0%

31-May-... 31-May-...

31-May-10

31-May-10

0
0
0

0
0
0

0%
0%
0%

31-May-... 31-May-...
31-May-... 31-May-...
31-May-...

31-May-10
31-May-10

31-May-10
31-May-10
31-May-10

0
0
0

0
0
0

0
0
0 NA

117

0% 14-Jun-08 30-Oct-08

14-Jun-08

30-Oct-08

800

51

0% 14-Jun-08 12-Aug-08

14-Jun-08

12-Aug-08

51

0% 14-Jun-08 12-Aug-08

14-Jun-08

12-Aug-08

51
51
45

0
0
0

0% 14-Jun-08 12-Aug-08
0% 14-Jun-08 12-Aug-08
0% 14-Jun-08 12-Aug-08

14-Jun-08
14-Jun-08
14-Jun-08

12-Aug-08
12-Aug-08
12-Aug-08

0
0
0

0
0
0

0
0
0

0% 06-Jul-08

12-Jul-08

06-Jul-08

12-Jul-08

6
6
6

0
0
0

0% 06-Jul-08
0% 06-Jul-08
0% 06-Jul-08

12-Jul-08
12-Jul-08
12-Jul-08

06-Jul-08
06-Jul-08
06-Jul-08

12-Jul-08
12-Jul-08
12-Jul-08

0
0
0

0
0
0

0
0
0

27

0% 13-Jul-08

13-Aug-08

13-Jul-08

13-Aug-08

225

27

0% 13-Jul-08

13-Aug-08

13-Jul-08

13-Aug-08

225

27
27
12

0
0
0

0%

0% 13-Jul-08
0% 13-Jul-08
0% 13-Jul-08

13-Aug-08
13-Aug-08
26-Jul-08

13-Jul-08
13-Jul-08
13-Jul-08

13-Aug-08
13-Aug-08
26-Jul-08

0
0
0

0
0
0

225
225
100 L.M

IP55D-IP41A : Borehole / Soil Investigation

0%

0%

0%

0%

0%

Commencement of Project
Com

Project Commencement & Site Handing Over for Construction

[Sec. #4] Commencement of Main Construction Work

[Sec. #4] Comp

Site Investigation : Execution & Reporting

Survey : Bore hole & Trial Pit Locations

IS003300

IP41A-IP41 : Borehole / Soil Investigation

0%

0% 27-Jul-08

03-Aug-08

27-Jul-08

03-Aug-08

50 L.M

IP41A-IP41 : Borehole / Soil Investigation

IS003600

IP41-IP12 : Borehole / Soil Investigation

0%

0% 04-Aug-08 13-Aug-08

04-Aug-08

13-Aug-08

75 L.M

IP41-IP12 : Borehole / Soil Investigation

24

0% 14-Aug-08 10-Sep-08

14-Aug-08

10-Sep-08

200

24

0% 14-Aug-08 10-Sep-08

14-Aug-08

10-Sep-08

200

24
24
9

0
0
0

0% 14-Aug-08 10-Sep-08
0% 14-Aug-08 10-Sep-08
0% 18-Aug-08 27-Aug-08

14-Aug-08
14-Aug-08
18-Aug-08

10-Sep-08
10-Sep-08
27-Aug-08

0
0
0

0
0
0

200
200
75 L.M

Section No.2 (S
(STA. 9+381 ~ STA. 9+954)
SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES
BOREHOLE
General
IS003900
Project Start : 15-May-08
Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 1 / 8

IP12-IP9 : Borehole / Soil Investigation


Actual Work
Remaining Work

0%

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

IP12-IP9 : Borehole / Soil Investigation

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

IS004200

IP9-IP11 : Borehole / Soil Investigation

IS006000

IP12-IP56 : Borehole / Soil Investigation

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
100 L.M
IP9-IP11 : Borehole / Soil Investigation

10-Sep-08

17-Aug-08

0% 11-Sep-08 07-Oct-08

11-Sep-08

07-Oct-08

175

21

0% 11-Sep-08 07-Oct-08

11-Sep-08

07-Oct-08

175

IP11-IP11A : Borehole / Soil Investigation

21
21
9

0
0
0

0%

0% 11-Sep-08 07-Oct-08
0% 11-Sep-08 07-Oct-08
0% 11-Sep-08 21-Sep-08

11-Sep-08
11-Sep-08
11-Sep-08

07-Oct-08
07-Oct-08
21-Sep-08

0
0
0

0
0
0

175
175
75 L.M

IP11A-IP36A : Borehole / Soil Investigation

12

0%

0% 22-Sep-08 07-Oct-08

22-Sep-08

07-Oct-08

100 L.M

20

0% 08-Oct-08 30-Oct-08

08-Oct-08

30-Oct-08

200

20

0% 08-Oct-08 30-Oct-08

08-Oct-08

30-Oct-08

200

20
20
12

0
0
0

0%

0% 08-Oct-08 30-Oct-08
0% 08-Oct-08 30-Oct-08
0% 08-Oct-08 21-Oct-08

08-Oct-08
08-Oct-08
08-Oct-08

30-Oct-08
30-Oct-08
21-Oct-08

0
0
0

0
0
0

200
200
100 L.M

IP36A-IP36 : Borehole / Soil Investigation

0%

0% 22-Oct-08 30-Oct-08

22-Oct-08

30-Oct-08

100 L.M

IP36-IP44 : Borehole / Soil Investigation

95

0% 09-Jul-08

31-Oct-08

09-Jul-08

31-Oct-08

95

0% 09-Jul-08

31-Oct-08

09-Jul-08

31-Oct-08

95

0% 09-Jul-08

31-Oct-08

09-Jul-08

31-Oct-08

70
70
69

0
0
0

0%

0% 09-Jul-08
0% 09-Jul-08
0% 09-Jul-08

29-Sep-08
29-Sep-08
15-Sep-08

09-Jul-08
09-Jul-08
09-Jul-08

29-Sep-08
29-Sep-08
15-Sep-08

0
0
0

0
0
0

0
0
0

Design for Excavation Support System

15-Sep-08

15-Sep-08

Design for Excavation Support System : Submmission

29-Sep-08

Design for Excavation Support System : Review

29-Sep-08

Design for Excavation Support System : Approval

SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES

IS005400

VAR
VAR
START FINISH

14-Aug-08

Section No.4 (STA.


(S
10+704 ~ STA. 11+525)
BOREHOLE
General
IS005100

Finish

28-Aug-08

SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES

IS004800

Start

0% 14-Aug-08 17-Aug-08

Section No.3 (STA.


(S
9+954 ~ STA. 10+704)
BOREHOLE
General
IS004500

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
12
0
0%
0% 28-Aug-08 10-Sep-08

IP36A-IP36 : Borehole / Soil Investigation


IP36-IP44 : Borehole / Soil Investigation

DESIGN & SHOP DRAWINGS


General
Excavation Supporting
Supp
System

DG000010

Design for Excavation Support System

DG000020

Design for Excavation Support System : Submmission

DG000030

Design for Excavation Support System : Review

DG000040

Design for Excavation Support System : Approval

21

0%

25 L.M

0%

0%

14

0%

0% 16-Sep-08 29-Sep-08

0%

0%

0
0
0

0%

0% 30-Sep-08 31-Oct-08
0% 30-Sep-08 31-Oct-08
0% 30-Sep-08 17-Oct-08

30-Sep-08
30-Sep-08
30-Sep-08

31-Oct-08
31-Oct-08
17-Oct-08

0
0
0

0
0
0

0
0
0

0%

0% 18-Oct-08 31-Oct-08

18-Oct-08

31-Oct-08

16-Sep-08

29-Sep-08

IP12-IP56 : Borehole / Soil Investigation

IP11-IP11A : Borehole / Soil Investigation


IP11A-IP36A : Borehole / Soil Investigation

DG000200

Shop Drawing Submission : Excavation Supporting System

25
25
18

DG000440

Shop Drawing Approval : Excavation Supporting System

14

36

0% 07-Jun-08

17-Jul-08

07-Jun-08

17-Jul-08

36

0% 07-Jun-08

17-Jul-08

07-Jun-08

17-Jul-08

36

0% 07-Jun-08

17-Jul-08

07-Jun-08

17-Jul-08

6
6
6

0
0
0

07-Jun-08
07-Jun-08
07-Jun-08

12-Jun-08
12-Jun-08
12-Jun-08

0
0
0

0
0
0

0
0
0

Submit Material - Anchor Bolts for Streetlight Foundations

Shop Drawing

PROCUREMENT & FABRICATION


General
Traffic Control & Detour

Shop Drawing Submission : Excavation Supporting Sy


Shop Drawing Approval : Excavation Supporting Syste

0%

0% 07-Jun-08 12-Jun-08
0% 07-Jun-08 12-Jun-08
0% 07-Jun-08 12-Jun-08

MA000060

Submit Material - Temp Streetlight columns

0%

0% 07-Jun-08 12-Jun-08

07-Jun-08

12-Jun-08

Submit Material - Temp Streetlight columns

MA000070

Submit Material - Temp Streetlight lanterns

0%

0% 07-Jun-08 12-Jun-08

07-Jun-08

12-Jun-08

Submit Material - Temp Streetlight lanterns

MA000080

Submit Material - Temp Streetlight cables

Submit Material - Temp Streetlight cables

SUBMIT MATERIALS
MATER
General
MA000050 Submit Material - Anchor Bolts for Streetlight Foundations

0%

0% 07-Jun-08 12-Jun-08

07-Jun-08

12-Jun-08

24
24
24

0
0
0

17-Jul-08
17-Jul-08
17-Jul-08

21-Jun-08
21-Jun-08
21-Jun-08

17-Jul-08
17-Jul-08
17-Jul-08

0
0
0

0
0
0

0
0
0

Supply of Materials - Anchor Bolts

0%

0% 21-Jun-08
0% 21-Jun-08
0% 21-Jun-08

MA000760

Supply of Materials - Temp Streetlight columns

24

0%

0% 21-Jun-08

17-Jul-08

21-Jun-08

17-Jul-08

Supply of Materials - Temp Streetlight columns

MA000770

Supply of Materials - Temp Streetlight lanterns

24

0%

0% 21-Jun-08

17-Jul-08

21-Jun-08

17-Jul-08

Supply of Materials - Temp Streetlight lanterns

MA000780

Supply of Materials - Temp Streetlight cables

24

0%

0% 21-Jun-08

17-Jul-08

21-Jun-08

17-Jul-08

Supply of Materials - Temp Streetlight cables

44

0% 15-May-08 05-Jul-08

15-May-08

05-Jul-08

44

0%

15-May-... 05-Jul-08

15-May-08

05-Jul-08

25

0%

15-May-... 13-Jun-08

15-May-08

13-Jun-08

25
25

0
0

0%
0%

15-May-... 13-Jun-08
15-May-... 13-Jun-08

15-May-08
15-May-08

13-Jun-08
13-Jun-08

0
0

0
0

0
0

SUPPLY OF MA
MATERIALS
General
MA000750 Supply of Materials - Anchor Bolts

SUBCONTRACT PROCESS
General
Site Investigation

Project Start : 15-May-08


Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 2 / 8

Actual Work
Remaining Work

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

SU000010

Sub-Contract : Site Investigation

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
30
0
0%
0% 15-May-... 13-Jun-08

Start

Finish

VAR
VAR
START FINISH

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
0
Sub-Contract : Site Investigation

15-May-08

13-Jun-08

14

0%

21-May-... 06-Jun-08

21-May-08

06-Jun-08

SUBMIT SUBCONTRACTOR
SUBCO
PROPOSAL
General
SC000200 Submit Subcontract Proposal - Temporary Streetlighting

6
6
6

0
0
0

0%

0%
0%
0%

21-May-... 27-May-...
21-May-... 27-May-...
21-May-... 27-May-...

21-May-08
21-May-08
21-May-08

27-May-08
27-May-08
27-May-08

0
0
0

0
0
0

0
0
0

Submit Subcontract Proposal - Temporary Streetlighting

APPROVE SUBCONTRACTOR
SUBC
PROPOSAL
General
SC000210 ApproveSubcontract Proposal - Temporary Streetlighting

6
6
7

0
0
0

0%

0%
0%
0%

28-May-... 03-Jun-08
28-May-... 03-Jun-08
28-May-... 03-Jun-08

28-May-08
28-May-08
28-May-08

03-Jun-08
03-Jun-08
03-Jun-08

0
0
0

0
0
0

0
0
0

ApproveSubcontract Proposal - Temporary Streetlighting

AWARD OF SUBCONTRACT
SUB
General
SC000220 Award of Subcontract - Temporary Streetlighting

2
2
3

0
0
0

0%

0% 04-Jun-08 06-Jun-08
0% 04-Jun-08 06-Jun-08
0% 04-Jun-08 06-Jun-08

04-Jun-08
04-Jun-08
04-Jun-08

06-Jun-08
06-Jun-08
06-Jun-08

0
0
0

0
0
0

0
0
0

Award of Subcontract - Temporary Streetlighting

41

0%

19-May-... 05-Jul-08

19-May-08

05-Jul-08

SUBMIT SUBCONTRACTOR
SUBCO
PROPOSAL
General
SC000600 Submit Subcontract Proposal - Bore Holes & Soil Investigation

12
12
12

0
0
0

0%

0%
0%
0%

19-May-... 01-Jun-08
19-May-... 01-Jun-08
19-May-... 01-Jun-08

19-May-08
19-May-08
19-May-08

01-Jun-08
01-Jun-08
01-Jun-08

0
0
0

0
0
0

0
0
0

APPROVE SUBCONTRACTOR
SUBC
PROPOSAL
General
SC000610 Approve Subcontract Proposal - Bore Holes & Soil Investigation

12
12
14

0
0
0

0%

0% 02-Jun-08 15-Jun-08
0% 02-Jun-08 15-Jun-08
0% 02-Jun-08 15-Jun-08

02-Jun-08
02-Jun-08
02-Jun-08

15-Jun-08
15-Jun-08
15-Jun-08

0
0
0

0
0
0

0
0
0

Approve Subcontract Proposal - Bore Holes & Soil Investigation

5
5
6

0
0
0

0%

0% 16-Jun-08 21-Jun-08
0% 16-Jun-08 21-Jun-08
0% 16-Jun-08 21-Jun-08

16-Jun-08
16-Jun-08
16-Jun-08

21-Jun-08
21-Jun-08
21-Jun-08

0
0
0

0
0
0

0
0
0

Award of Subcontract - Bore Holes & Soil Investigation

12
12
12

0
0
0

0%

0% 22-Jun-08
0% 22-Jun-08
0% 22-Jun-08

05-Jul-08
05-Jul-08
05-Jul-08

22-Jun-08
22-Jun-08
22-Jun-08

05-Jul-08
05-Jul-08
05-Jul-08

0
0
0

0
0
0

0
0
0

97

0% 08-Jul-08 01-Nov-08

08-Jul-08

01-Nov-08

19762

97

0% 08-Jul-08 01-Nov-08

08-Jul-08

01-Nov-08

19762

97

0% 08-Jul-08 01-Nov-08

08-Jul-08

01-Nov-08

19762

60
60
5

0
0
0

16-Sep-08
16-Sep-08
13-Jul-08

08-Jul-08
08-Jul-08
08-Jul-08

16-Sep-08
16-Sep-08
13-Jul-08

0
0
0

0
0
0

97
97
1 Nos.

Traffic Control & Detour

SITE INVESTIGATION,
INVESTIGAT
TESTING & PRELIMINARIES

AWARD OF SUBCONTRACT
SUB
General
SC000620 Award of Subcontract - Bore Holes & Soil Investigation
MOBILISATION OF SUBCONTRACTOR
General
SC000630 Mobilisation of Subcontractor - Bore Holes & Soil Investigation

DETOUR WORKS
General
Traffic Control & Detour

Submit Subcontract Proposal - Bore Holes & Soil Investigation

Mobilisation of Subcontractor - Bore Holes & Soil Investigation

0%

0% 08-Jul-08
0% 08-Jul-08
0% 08-Jul-08

DT000330

IP37A-IP37B : Install Temporary Streetlights

0%

0% 14-Jul-08

19-Jul-08

14-Jul-08

19-Jul-08

5 Nos.

IP37A-IP37B : Install Temporary Streetlights

DT000530

IP37B-IP38C : Install Temporary Streetlights

0%

0% 20-Jul-08

24-Jul-08

20-Jul-08

24-Jul-08

6 Nos.

IP37B-IP38C : Install Temporary Streetlights

DT000730

IP38C-IP38A : Install Temporary Streetlights

0%

0% 26-Jul-08

02-Aug-08

26-Jul-08

02-Aug-08

10 Nos.

IP38C-IP38A : Install Temporary Streetlights

DT000930

IP38A-IP39A : Install Temporary Streetlights

0%

0% 03-Aug-08 09-Aug-08

03-Aug-08

09-Aug-08

14 Nos.

IP38A-IP39A : Install Temporary Streetlights

DT001130

IP39A-IP41A : Install Temporary Streetlights

0%

0% 10-Aug-08 16-Aug-08

10-Aug-08

16-Aug-08

10 Nos.

IP39A-IP41A : Install Temporary Streetlights

DT001330

IP41-IP39 : Install Temporary Streetlights

0%

0% 17-Aug-08 20-Aug-08

17-Aug-08

20-Aug-08

8 Nos.

IP41-IP39 : Install Temporary Streetlights

DT001530

IP39-IP38 : Install Temporary Streetlights

0%

0% 21-Aug-08 24-Aug-08

21-Aug-08

24-Aug-08

5 Nos.

IP39-IP38 : Install Temporary Streetlights

DT001730

IP38-IP38A :Install Temporary Streetlights

0%

0% 25-Aug-08 27-Aug-08

25-Aug-08

27-Aug-08

5 Nos.

IP38-IP38A :Install Temporary Streetlights

DT001930

IP38-IP38B :Install Temporary Streetlights

0%

0% 28-Aug-08 31-Aug-08

28-Aug-08

31-Aug-08

5 Nos.

IP38-IP38B :Install Temporary Streetlights

DT002130

IP38B-IP11A :Install Temporary Streetlights

14

0%

0% 01-Sep-08 16-Sep-08

01-Sep-08

16-Sep-08

28 Nos.

IP38B-IP11A :Install Temporary Streetlights

REMOVE STREETLIGHT
STREE
COLUMNS
General
DT002030 IP38B-IP11A :Remove Streetlight columns

7
7
7

0
0
0

0%

0% 17-Sep-08 24-Sep-08
0% 17-Sep-08 24-Sep-08
0% 17-Sep-08 24-Sep-08

17-Sep-08
17-Sep-08
17-Sep-08

24-Sep-08
24-Sep-08
24-Sep-08

0
0
0

0
0
0

0
0
0 Nos.

IP38B-IP11A :Remove Streetlight columns

REMOVE STREETLIGHT
STREE
FOUNDATIONS
General
DT002040 IP38B-IP11A : Remove Streetlight Foundations

7
7
7

0
0
0

0%

0% 25-Sep-08 05-Oct-08
0% 25-Sep-08 05-Oct-08
0% 25-Sep-08 05-Oct-08

25-Sep-08
25-Sep-08
25-Sep-08

05-Oct-08
05-Oct-08
05-Oct-08

0
0
0

0
0
0

0
0
0 Nos.

EXCAVATION / P
PREPARATION OF FORMATION
General
DT002060 IP38B-IP11A : Excavation / Preparation of Formation

12
12
12

0
0
0

0%

0% 06-Oct-08 19-Oct-08
0% 06-Oct-08 19-Oct-08
0% 06-Oct-08 19-Oct-08

06-Oct-08
06-Oct-08
06-Oct-08

19-Oct-08
19-Oct-08
19-Oct-08

0
0
0

0
0
0

6541
6541
6541 Sqm

BORROW FILL / SUBBASE

12

0% 09-Oct-08 22-Oct-08

09-Oct-08

22-Oct-08

6541

TEMPORARY STREETLIGHTING
ST
General
DT000130 IP37 : Install Temporary Streetlights

Project Start : 15-May-08


Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 3 / 8

Actual Work
Remaining Work

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

IP37 : Install Temporary Streetlights

IP38B-IP11A : Remove Streetlight Foundations

IP38B-IP11A : Excavation / Preparation of Formation

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

General
DT002070

IP38B-IP11A : Borrow fill / Subbase

Start

Finish

09-Oct-08
09-Oct-08

22-Oct-08
22-Oct-08

0
0

0
0

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
6541
6541 Sqm
IP38B-IP11A : Borrow fill / Subbase

0%

0% 13-Oct-08 26-Oct-08
0% 13-Oct-08 26-Oct-08
0% 13-Oct-08 26-Oct-08

13-Oct-08
13-Oct-08
13-Oct-08

26-Oct-08
26-Oct-08
26-Oct-08

0
0
0

0
0
0

6541
6541
6541 Sqm

0%

0% 27-Oct-08 30-Oct-08
0% 27-Oct-08 30-Oct-08
0% 27-Oct-08 30-Oct-08

27-Oct-08
27-Oct-08
27-Oct-08

30-Oct-08
30-Oct-08
30-Oct-08

0
0
0

0
0
0

42
42
42 Nos.

0%

0% 01-Nov-08 01-Nov-08
0% 01-Nov-08 01-Nov-08
0% 01-Nov-08 01-Nov-08

01-Nov-08
01-Nov-08
01-Nov-08

01-Nov-08
01-Nov-08
01-Nov-08

0
0
0

0
0
0

0
0
0

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
12
0
0% 09-Oct-08 22-Oct-08
12
0
0%
0% 09-Oct-08 22-Oct-08

VAR
VAR
START FINISH

12
12
12

0
0
0

TEMPORARY CONSTRUCTION
CO
SIGNS
General
DT002100 IP38B-IP11A :Temporary Detour - Sign Boards

4
4
4

0
0
0

TRAFFIC DIVERSION
DIVER
INTO DETOUR ROADS
General
DT0030A0 Traffic Diversion from Stage 1 to Stage 2

1
1
1

0
0
0

574

0% 01-Nov-08 21-Sep-10

01-Nov-08

21-Sep-10

363294

574

0% 01-Nov-08 21-Sep-10

01-Nov-08

21-Sep-10

274525

ASPHALT WEARING
WEAR
COURSE
General
DT002080 IP38B-IP11A :Asphalt Wearing Course

CONSTRUCTION
Section No.3 (STA.
(S
9+954 ~ STA. 10+704)

IP38B-IP11A :Asphalt Wearing Course

IP38B-IP11A :Temporary Detour - Sign Boards

Traffic Diversion from Stage 1 to Stage 2

117

0% 01-Nov-08 24-Mar-09

01-Nov-08

24-Mar-09

530

Diaphragm Wall
South Bound
CNS310070 D/Wall [Sec. #3]: Unit 10 (Str.3) ~ Unit 11 (Str.3) , SB

55
47
8

0
0
0

0%

0% 01-Nov-08 10-Jan-09
0% 01-Nov-08 30-Dec-08
0% 21-Dec-08 30-Dec-08

01-Nov-08
01-Nov-08
21-Dec-08

10-Jan-09
30-Dec-08
30-Dec-08

0
0
0

0
0
0

418
201
56 m

D/Wall [Sec. #3]: Unit 10 (Str.3) ~ Unit 11 (Str.3) ,

CNS310080 D/Wall [Sec. #3]: Unit 13 (Str.3) ~ Unit 14 (Str.3) , SB

10

0%

0% 01-Nov-08 11-Nov-08

01-Nov-08

11-Nov-08

81 m

D/Wall [Sec. #3]: Unit 13 (Str.3) ~ Unit 14 (Str.3) , SB


D/Wall [Sec. #3]: Unit 21 (Str.3) ~ Unit 23 (Str.3) , S

Excavation Supporting
Supp
System

CNS310110 D/Wall [Sec. #3]: Unit 21 (Str.3) ~ Unit 23 (Str.3) , SB

0%

0% 26-Nov-08 10-Dec-08

26-Nov-08

10-Dec-08

64 m

North Bound
CNS310170 D/Wall [Sec. #3]: Unit 10 (Str.3) ~ Unit 11 (Str.3) , NB

45
8

0
0

0%

0% 12-Nov-08 10-Jan-09
0% 31-Dec-08 10-Jan-09

12-Nov-08
31-Dec-08

10-Jan-09
10-Jan-09

0
0

0
0

217
56 m

D/Wall [Sec. #3]: Unit 10 (Str.3) ~ Unit 11 (Str.3)

CNS310180 D/Wall [Sec. #3]: Unit 13 (Str.3) ~ Unit 14 (Str.3) , NB

12

0%

0% 12-Nov-08 25-Nov-08

12-Nov-08

25-Nov-08

97 m

D/Wall [Sec. #3]: Unit 13 (Str.3) ~ Unit 14 (Str.3) , N

0%

0% 11-Dec-08 20-Dec-08

11-Dec-08

20-Dec-08

64 m

D/Wall [Sec. #3]: Unit 21 (Str.3) ~ Unit 23 (Str.3) ,

0%

0% 17-Feb-09 24-Mar-09
0% 17-Feb-09 24-Mar-09
0% 17-Feb-09 24-Mar-09

17-Feb-09
17-Feb-09
17-Feb-09

24-Mar-09
24-Mar-09
24-Mar-09

0
0
0

0
0
0

112
112
112 Nos

CNS310210 D/Wall [Sec. #3]: Unit 21 (Str.3) ~ Unit 23 (Str.3) , NB

30
30
30

0
0
0

162

0% 11-Jan-09

20-Jul-09

11-Jan-09

20-Jul-09

Excavation - 1st layer ( GL ~ 3.0m )


South & North
Nort Bound
CNS330000 1ST - Excavation [Sec. #3] : Unit 10 (Str.3) ~ Unit 11 (Str.3)

48
48
16

0
0
0

0%

0% 11-Jan-09 07-Mar-09
0% 11-Jan-09 07-Mar-09
0% 17-Feb-09 07-Mar-09

11-Jan-09
11-Jan-09
17-Feb-09

07-Mar-09
07-Mar-09
07-Mar-09

0
0
0

0
0
0

CNS330010 1ST - Excavation [Sec. #3] : Unit 13 (Str.3) ~ Unit 14 (Str.3)

12

0%

0% 11-Jan-09 24-Jan-09

11-Jan-09

24-Jan-09

CNS330040 1ST - Excavation [Sec. #3] : Unit 21 (Str.3) ~ Unit 23 (Str.3)

20

0%

0% 25-Jan-09 16-Feb-09

25-Jan-09

16-Feb-09

Excavation - 2nd layer ( 3.0m ~ FL )


South & North
Nort Bound
CNS330100 2ND - Excavation [Sec. #3] : Unit 10 (Str.3) ~ Unit 11 (Str.3)

114
114
21

0
0
0

0%

0% 09-Mar-09 20-Jul-09
0% 09-Mar-09 20-Jul-09
0% 27-Apr-09 20-May-...

09-Mar-09
09-Mar-09
27-Apr-09

20-Jul-09
20-Jul-09
20-May-09

CNS330110 2ND - Excavation [Sec. #3] : Unit 13 (Str.3) ~ Unit 14 (Str.3)

14

0%

0% 09-Mar-09 24-Mar-09

09-Mar-09

CNS330120 2ND - Excavation [Sec. #3] : Unit 15 (Str.3) ~ Unit 16 (Str.3)

21

0%

0%

21-May-09

CNS330130 2ND - Excavation [Sec. #3] : Unit 17 (Str.3) ~ Unit 20 (Str.3)

28

0%

0% 15-Jun-09

20-Jul-09

CNS330140 2ND - Excavation [Sec. #3] : Unit 21 (Str.3) ~ Unit 23 (Str.3)

28

0%

0% 25-Mar-09 26-Apr-09

Earth Anchor Driving


Dr
South & North
Nort Bound
CNS330330 Earth Anchor [Sec. #3] : Unit 21 (Str.3) ~ Unit 23 (Str.3)

Earthworks

21-May-... 14-Jun-09

35067
35067
11689 m3

1ST - Excavation [Sec. #3] : Unit 10 (Str.3) ~

8767 m3

1ST - Excavation [Sec. #3] : Unit 13 (Str.3) ~ Un

14611 m3

1ST - Excavation [Sec. #3] : Unit 21 (Str.3) ~ U

0
0
0

0
0
0

185851
185851
34847 m3

2ND - Excavation [Sec. #3] : Unit 10 (St

24-Mar-09

23231 m3

2ND - Excavation [Sec. #3] : Unit 13 (Str.3)

14-Jun-09

34847 m3

15-Jun-09

20-Jul-09

46463 m3

2ND - Excavation [Sec. #3] : Unit 17

25-Mar-09

26-Apr-09

46463 m3

2ND - Excavation [Sec. #3] : Unit 21 (Str.3

38

0% 21-Jul-09

02-Sep-09

21-Jul-09

02-Sep-09

Pile Head Treatment


Treatm
South & North
Nort Bound
CNS320170 Pile Head [Sec. #3] : Unit 17 (Str.3) ~ Unit 20 (Str.3)

20
20
16

0
0
0

0%

0% 21-Jul-09
0% 21-Jul-09
0% 21-Jul-09

12-Aug-09
12-Aug-09
12-Aug-09

21-Jul-09
21-Jul-09
21-Jul-09

12-Aug-09
12-Aug-09
12-Aug-09

0
0
0

0
0
0

Water Proofing
South & North
Nort Bound
CNS340030 W/Proofing (Incl.Lean) [Sec. #3] : Unit 17 (Str.3) ~ Unit 20 (Str.3)

18
18
14

0
0
0

0%

0% 13-Aug-09 02-Sep-09
0% 13-Aug-09 02-Sep-09
0% 13-Aug-09 02-Sep-09

13-Aug-09
13-Aug-09
13-Aug-09

02-Sep-09
02-Sep-09
02-Sep-09

0
0
0

0
0
0

206

0% 03-Sep-09

09-May-...

03-Sep-09

09-May-10

17882

111
111
9

0
0
0

0% 03-Sep-09 17-Jan-10
0% 03-Sep-09 17-Jan-10
0% 03-Sep-09 16-Sep-09

03-Sep-09
03-Sep-09
03-Sep-09

17-Jan-10
17-Jan-10
16-Sep-09

0
0
0

0
0
0

14256
14256
1188 m3

Pile Foundation

Reinforced Concrete
Conc
Works
Base Slab
General
CNS350210 Base Slab [Sec. #3] : Unit 17A (Str.3)
Project Start : 15-May-08
Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 4 / 8

Actual Work
Remaining Work

0%

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

Earth Anchor [Sec. #3] : Unit 21 (Str.3) ~ Un

220918

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

2ND - Excavation [Sec. #3] : Unit 15 (S

6992
64
64
64 Nos.
6928
6928
6928 m2

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Pile Head [Sec. #3] : Unit 17 (Str.3

W/Proofing (Incl.Lean) [Sec. #3]

Base Slab [Sec. #3] : Unit 17A (


Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1

17-Sep-09

29-Sep-09

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
1188 m3
Base Slab [Sec. #3] : Unit 17B

CNS350230 Base Slab [Sec. #3] : Unit 17C (Str.3)

0%

0% 30-Sep-09 10-Oct-09

30-Sep-09

10-Oct-09

1188 m3

Base Slab [Sec. #3] : Unit 17C

CNS350480 Base Slab [Sec. #3] : Unit 26A (Str.3)

0%

0% 11-Nov-09 21-Nov-09

11-Nov-09

21-Nov-09

1188 m3

Base Slab [Sec. #3] : Unit 2

CNS350490 Base Slab [Sec. #3] : Unit 26B (Str.3)

0%

0% 22-Nov-09 05-Dec-09

22-Nov-09

05-Dec-09

1188 m3

Base Slab [Sec. #3] : Unit

CNS350500 Base Slab [Sec. #3] : Unit 26C (Str.3)

0%

0% 06-Dec-09 15-Dec-09

06-Dec-09

15-Dec-09

1188 m3

CNS350510 Base Slab [Sec. #3] : Unit 27A (Str.3)

0%

0% 11-Oct-09 20-Oct-09

11-Oct-09

20-Oct-09

1188 m3

Base Slab [Sec. #3] : Unit 27A

CNS350520 Base Slab [Sec. #3] : Unit 27B (Str.3)

0%

0% 21-Oct-09 31-Oct-09

21-Oct-09

31-Oct-09

1188 m3

Base Slab [Sec. #3] : Unit 27

CNS350530 Base Slab [Sec. #3] : Unit 27C (Str.3)

0%

0% 01-Nov-09 10-Nov-09

01-Nov-09

10-Nov-09

1188 m3

Base Slab [Sec. #3] : Unit 27

CNS350630 Base Slab [Sec. #3] : Unit 31A (Str.3)

0%

0% 16-Dec-09 27-Dec-09

16-Dec-09

27-Dec-09

1188 m3

Base Slab [Sec. #3] : Uni

CNS350640 Base Slab [Sec. #3] : Unit 31B (Str.3)

0%

0% 28-Dec-09 06-Jan-10

28-Dec-09

06-Jan-10

1188 m3

Base Slab [Sec. #3] : Un

CNS350650 Base Slab [Sec. #3] : Unit 31C (Str.3)

0%

0% 07-Jan-10 17-Jan-10

07-Jan-10

17-Jan-10

1188 m3

Retaining Wall ((1st)


South & North
Nort Bound
CNS350960 1ST-Retaining Wall [Sec. #3] : Unit 17A (Str.3)

105
105
8

0
0
0

0%

0% 11-Oct-09 14-Feb-10
0% 11-Oct-09 14-Feb-10
0% 11-Oct-09 19-Oct-09

11-Oct-09
11-Oct-09
11-Oct-09

14-Feb-10
14-Feb-10
19-Oct-09

0
0
0

0
0
0

2472
2472
206 m3

1ST-Retaining Wall [Sec. #3]

CNS350970 1ST-Retaining Wall [Sec. #3] : Unit 17B (Str.3)

0%

0% 20-Oct-09 28-Oct-09

20-Oct-09

28-Oct-09

206 m3

1ST-Retaining Wall [Sec. #3]

CNS350980 1ST-Retaining Wall [Sec. #3] : Unit 17C (Str.3)

0%

0% 29-Oct-09 07-Nov-09

29-Oct-09

07-Nov-09

206 m3

1ST-Retaining Wall [Sec. #3

CNS351230 1ST-Retaining Wall [Sec. #3] : Unit 26A (Str.3)

0%

0% 16-Dec-09 26-Dec-09

16-Dec-09

26-Dec-09

206 m3

1ST-Retaining Wall [Sec.

CNS351240 1ST-Retaining Wall [Sec. #3] : Unit 26B (Str.3)

0%

0% 27-Dec-09 04-Jan-10

27-Dec-09

04-Jan-10

206 m3

1ST-Retaining Wall [Sec

CNS351250 1ST-Retaining Wall [Sec. #3] : Unit 26C (Str.3)

0%

0% 05-Jan-10 13-Jan-10

05-Jan-10

13-Jan-10

206 m3

1ST-Retaining Wall [Sec

CNS351260 1ST-Retaining Wall [Sec. #3] : Unit 27A (Str.3)

0%

0% 11-Nov-09 19-Nov-09

11-Nov-09

19-Nov-09

206 m3

1ST-Retaining Wall [Sec. #3

CNS351270 1ST-Retaining Wall [Sec. #3] : Unit 27B (Str.3)

0%

0% 21-Nov-09 01-Dec-09

21-Nov-09

01-Dec-09

206 m3

1ST-Retaining Wall [Sec. #

CNS351280 1ST-Retaining Wall [Sec. #3] : Unit 27C (Str.3)

0%

0% 03-Dec-09 12-Dec-09

03-Dec-09

12-Dec-09

206 m3

1ST-Retaining Wall [Sec.

CNS351380 1ST-Retaining Wall [Sec. #3] : Unit 31A (Str.3)

0%

0% 18-Jan-10 26-Jan-10

18-Jan-10

26-Jan-10

206 m3

1ST-Retaining Wall [Se

CNS351390 1ST-Retaining Wall [Sec. #3] : Unit 31B (Str.3)

0%

0% 27-Jan-10 04-Feb-10

27-Jan-10

04-Feb-10

206 m3

1ST-Retaining Wall [S

Activity ID

Activity Name

CNS350220 Base Slab [Sec. #3] : Unit 17B (Str.3)

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
9
0
0%
0% 17-Sep-09 29-Sep-09

Start

Finish

VAR
VAR
START FINISH

Base Slab [Sec. #3] : Unit

Base Slab [Sec. #3] : Un

CNS351400 1ST-Retaining Wall [Sec. #3] : Unit 31C (Str.3)

0%

0% 06-Feb-10 14-Feb-10

06-Feb-10

14-Feb-10

206 m3

1ST-Retaining Wall [S

Retaining Wall ((2nd)


South & North
Nort Bound
CNS351710 2ND-Retaining Wall [Sec. #3] : Unit 17A (Str.3)

108
108
9

0
0
0

0%

0% 17-Nov-09 28-Mar-10
0% 17-Nov-09 28-Mar-10
0% 17-Nov-09 29-Nov-09

17-Nov-09
17-Nov-09
17-Nov-09

28-Mar-10
28-Mar-10
29-Nov-09

0
0
0

0
0
0

276
276
23 m3

2ND-Retaining Wall [Sec. #

CNS351720 2ND-Retaining Wall [Sec. #3] : Unit 17B (Str.3)

0%

0% 30-Nov-09 10-Dec-09

30-Nov-09

10-Dec-09

23 m3

2ND-Retaining Wall [Sec.

CNS351730 2ND-Retaining Wall [Sec. #3] : Unit 17C (Str.3)

0%

0% 12-Dec-09 22-Dec-09

12-Dec-09

22-Dec-09

23 m3

2ND-Retaining Wall [Sec.

CNS351980 2ND-Retaining Wall [Sec. #3] : Unit 26A (Str.3)

0%

0% 24-Jan-10 02-Feb-10

24-Jan-10

02-Feb-10

23 m3

2ND-Retaining Wall [S

CNS351990 2ND-Retaining Wall [Sec. #3] : Unit 26B (Str.3)

0%

0% 03-Feb-10 13-Feb-10

03-Feb-10

13-Feb-10

23 m3

2ND-Retaining Wall [S

CNS352000 2ND-Retaining Wall [Sec. #3] : Unit 26C (Str.3)

0%

0% 14-Feb-10 23-Feb-10

14-Feb-10

23-Feb-10

23 m3

2ND-Retaining Wall [

CNS352010 2ND-Retaining Wall [Sec. #3] : Unit 27A (Str.3)

0%

0% 23-Dec-09 02-Jan-10

23-Dec-09

02-Jan-10

23 m3

2ND-Retaining Wall [Sec

CNS352020 2ND-Retaining Wall [Sec. #3] : Unit 27B (Str.3)

0%

0% 03-Jan-10 12-Jan-10

03-Jan-10

12-Jan-10

23 m3

2ND-Retaining Wall [Se

CNS352030 2ND-Retaining Wall [Sec. #3] : Unit 27C (Str.3)

0%

0% 13-Jan-10 23-Jan-10

13-Jan-10

23-Jan-10

23 m3

CNS352130 2ND-Retaining Wall [Sec. #3] : Unit 31A (Str.3)

0%

0% 25-Feb-10 07-Mar-10

25-Feb-10

07-Mar-10

23 m3

2ND-Retaining Wall

CNS352140 2ND-Retaining Wall [Sec. #3] : Unit 31B (Str.3)

0%

0% 08-Mar-10 17-Mar-10

08-Mar-10

17-Mar-10

23 m3

2ND-Retaining Wal

CNS352150 2ND-Retaining Wall [Sec. #3] : Unit 31C (Str.3)

0%

0% 18-Mar-10 28-Mar-10

18-Mar-10

28-Mar-10

23 m3

2ND-Retaining Wa

Center Wall (Column,


(Co
H=5.4m)
South & North
Nort Bound
CNS352320 C/Wall (Column) [Sec. #3] : Unit 17 (Str.3)

89
89
8

0
0
0

0%

0% 08-Nov-09 23-Feb-10
0% 08-Nov-09 23-Feb-10
0% 08-Nov-09 16-Nov-09

08-Nov-09
08-Nov-09
08-Nov-09

23-Feb-10
23-Feb-10
16-Nov-09

0
0
0

0
0
0

512
512
128 m3

C/Wall (Column) [Sec. #3] :

CNS352410 C/Wall (Column) [Sec. #3] : Unit 26 (Str.3)

0%

0% 14-Jan-10 23-Jan-10

14-Jan-10

23-Jan-10

128 m3

CNS352420 C/Wall (Column) [Sec. #3] : Unit 27 (Str.3)

0%

0% 13-Dec-09 22-Dec-09

13-Dec-09

22-Dec-09

128 m3

C/Wall (Column) [Sec. #3


C/Wall (Column) [Sec

CNS352460 C/Wall (Column) [Sec. #3] : Unit 31 (Str.3)

2ND-Retaining Wall [Se

C/Wall (Column) [Sec.

0%

0% 15-Feb-10 23-Feb-10

15-Feb-10

23-Feb-10

128 m3

Roof Slab
South & North
Nort Bound
CNS353660 Roof Slab [Sec. #3] : Unit 32A (Str.3)

24
24
8

0
0
0

0%

0% 12-Apr-10 09-May-...
0% 12-Apr-10 09-May-...
0% 12-Apr-10 20-Apr-10

12-Apr-10
12-Apr-10
12-Apr-10

09-May-10
09-May-10
20-Apr-10

0
0
0

0
0
0

366
366
122 m3

Roof Slab [Sec. #

CNS353670 Roof Slab [Sec. #3] : Unit 32B (Str.3)

0%

0% 21-Apr-10 29-Apr-10

21-Apr-10

29-Apr-10

122 m3

Roof Slab [Sec. #

Project Start : 15-May-08


Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 5 / 8

Actual Work
Remaining Work

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

CNS353680 Roof Slab [Sec. #3] : Unit 32C (Str.3)

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
8
0
0%
0% 01-May-... 09-May-...

Start

Finish

VAR
VAR
START FINISH

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
122 m3
Roof Slab [Sec.

01-May-10

09-May-10

12

0% 29-Mar-10 11-Apr-10

29-Mar-10

11-Apr-10

988

Precast Girder Installation


I
South & North
Nort Bound
CNS352960 I-Girder Install [Sec. #3] : Unit 31 (Str.3)

12
12
6

0
0
0

0%

0% 29-Mar-10 11-Apr-10
0% 29-Mar-10 11-Apr-10
0% 29-Mar-10 04-Apr-10

29-Mar-10
29-Mar-10
29-Mar-10

11-Apr-10
11-Apr-10
04-Apr-10

0
0
0

0
0
0

988
988
494 m

I-Girder Install [Sec

CNS352970 I-Girder Install [Sec. #3] : Unit 32 (Str.3)

0%

0% 05-Apr-10 11-Apr-10

05-Apr-10

11-Apr-10

494 m

I-Girder Install [Se

113

0%

10-May-... 21-Sep-10

10-May-10

21-Sep-10

27215

Achitectural & L
Landscaping Works
Inner parts of Tunnel
CNS360190 Fire Protection & Finishes [Sec. #3] : Unit 10 (Str.3) ~ Unit 11 ...

113
113
10

0
0
0

0%

0%
0%
0%

10-May-... 21-Sep-10
10-May-... 21-Sep-10
22-May-... 01-Jun-10

10-May-10
10-May-10
22-May-10

21-Sep-10
21-Sep-10
01-Jun-10

0
0
0

0
0
0

27215
27215
2177 m2

CNS360200 Fire Protection & Finishes [Sec. #3] : Unit 12 (Str.3) ~ Unit 14 ...

10

0%

0% 02-Jun-10 13-Jun-10

02-Jun-10

13-Jun-10

3266 m2

Fire Protection

CNS360210 Fire Protection & Finishes [Sec. #3] : Unit 15 (Str.3) ~ Unit 16 ...

10

0%

0% 14-Jun-10 24-Jun-10

14-Jun-10

24-Jun-10

2177 m2

Fire Protectio

CNS360220 Fire Protection & Finishes [Sec. #3] : Unit 17 (Str.3) ~ Unit 19 ...

10

0%

0% 26-Jun-10

26-Jun-10

07-Jul-10

3266 m2

CNS360230 Fire Protection & Finishes [Sec. #3] : Unit 20 (Str.3) ~ Unit 22 ...

10

0%

0%

10-May-10

20-May-10

3266 m2

CNS360240 Fire Protection & Finishes [Sec. #3] : Unit 23 (Str.3) ~ Unit 24 ...

10

0%

0% 22-Jul-10

04-Aug-10

22-Jul-10

04-Aug-10

2177 m2

CNS360250 Fire Protection & Finishes [Sec. #3] : Unit 25 (Str.3) ~ Unit 26 ...

10

0%

0% 05-Aug-10 22-Aug-10

05-Aug-10

22-Aug-10

2177 m2

CNS360260 Fire Protection & Finishes [Sec. #3] : Unit 27 (Str.3) ~ Unit 29 ...

10

0%

0% 08-Jul-10

21-Jul-10

08-Jul-10

21-Jul-10

3266 m2

Fire Protec

CNS360270 Fire Protection & Finishes [Sec. #3] : Unit 30 (Str.3) ~ Unit 32 ...

10

0%

0% 24-Aug-10 09-Sep-10

24-Aug-10

09-Sep-10

3266 m2

Fire Pro

0%

Prestressed Concrete
Conc
Works

Anicillary Works / Misc

CNS360280 Fire Protection & Finishes [Sec. #3] : Unit 33 (Str.3) ~ Unit 34 ...

07-Jul-10

10-May-... 20-May-...

Fire Protection

Fire Protecti
Fire Protection
Fire Protec
Fire Prote

10

0% 11-Sep-10 21-Sep-10

11-Sep-10

21-Sep-10

574

0% 01-Nov-08 21-Sep-10

01-Nov-08

21-Sep-10

88769

393

0% 01-Nov-08 17-Feb-10

01-Nov-08

17-Feb-10

1331

10
10
10

0
0
0

0%

0% 07-Feb-10 17-Feb-10
0% 07-Feb-10 17-Feb-10
0% 07-Feb-10 17-Feb-10

07-Feb-10
07-Feb-10
07-Feb-10

17-Feb-10
17-Feb-10
17-Feb-10

0
0
0

0
0
0

Diaphragm Wall
South Bound
CNS410110 D/Wall [Sec. #4]: Unit 57 (Str.3) ~ Unit 56 (Str.3) , SB

110
102
7

0
0
0

0%

0% 01-Nov-08 16-Mar-09
0% 01-Nov-08 05-Mar-09
0% 27-Nov-08 06-Dec-08

01-Nov-08
01-Nov-08
27-Nov-08

16-Mar-09
05-Mar-09
06-Dec-08

0
0
0

0
0
0

770
381
49 m

D/Wall [Sec. #4]: Unit 57 (Str.3) ~ Unit 56 (Str.3) , S

CNS410150 D/Wall [Sec. #4]: Unit 47 (Str.3) ~ Unit 45 (Str.3) , SB

0%

0% 18-Dec-08 25-Dec-08

18-Dec-08

25-Dec-08

49 m

D/Wall [Sec. #4]: Unit 47 (Str.3) ~ Unit 45 (Str.3) ,

CNS410160 D/Wall [Sec. #4]: Unit 44 (Str.3) ~ Unit 42 (Str.3) , SB

12

0%

0% 07-Jan-09 20-Jan-09

07-Jan-09

20-Jan-09

85 m

D/Wall [Sec. #4]: Unit 44 (Str.3) ~ Unit 42 (Str.3)

CNS410170 D/Wall [Sec. #4]: Unit 41 (Str.3) ~ Unit 40 (Str.3) , SB

0%

0% 04-Feb-09 14-Feb-09

04-Feb-09

14-Feb-09

64 m

D/Wall [Sec. #4]: Unit 41 (Str.3) ~ Unit 40 (Str.

CNS410180 D/Wall [Sec. #4]: Unit 39 (Str.3) ~ Unit 38 (Str.3) , SB

0%

0% 24-Feb-09 05-Mar-09

24-Feb-09

05-Mar-09

56 m

D/Wall [Sec. #4]: Unit 39 (Str.3) ~ Unit 38 (St

CNS410190 D/Wall [Sec. #4]: Unit 37 (Str.3) ~ Unit 35 (Str.3) , SB

11

0%

0% 01-Nov-08 12-Nov-08

01-Nov-08

12-Nov-08

78 m

D/Wall [Sec. #4]: Unit 37 (Str.3) ~ Unit 35 (Str.3) , SB

North Bound
CNS410230 D/Wall [Sec. #4]: Unit 57 (Str.3) ~ Unit 56 (Str.3) , NB

99
7

0
0

0%

0% 13-Nov-08 16-Mar-09
0% 10-Dec-08 17-Dec-08

13-Nov-08
10-Dec-08

16-Mar-09
17-Dec-08

0
0

0
0

389
49 m

D/Wall [Sec. #4]: Unit 57 (Str.3) ~ Unit 56 (Str.3) ,

CNS410270 D/Wall [Sec. #4]: Unit 47 (Str.3) ~ Unit 45 (Str.3) , NB

0%

0% 27-Dec-08 06-Jan-09

27-Dec-08

06-Jan-09

56 m

D/Wall [Sec. #4]: Unit 47 (Str.3) ~ Unit 45 (Str.3)

CNS410280 D/Wall [Sec. #4]: Unit 44 (Str.3) ~ Unit 42 (Str.3) , NB

12

0%

0% 21-Jan-09 03-Feb-09

21-Jan-09

03-Feb-09

85 m

D/Wall [Sec. #4]: Unit 44 (Str.3) ~ Unit 42 (Str.3

CNS410290 D/Wall [Sec. #4]: Unit 41 (Str.3) ~ Unit 40 (Str.3) , NB

0%

0% 15-Feb-09 23-Feb-09

15-Feb-09

23-Feb-09

56 m

D/Wall [Sec. #4]: Unit 41 (Str.3) ~ Unit 40 (Str

CNS410300 D/Wall [Sec. #4]: Unit 39 (Str.3) ~ Unit 38 (Str.3) , NB

0%

0% 07-Mar-09 16-Mar-09

07-Mar-09

16-Mar-09

56 m

D/Wall [Sec. #4]: Unit 39 (Str.3) ~ Unit 38 (S

CNS410310 D/Wall [Sec. #4]: Unit 37 (Str.3) ~ Unit 35 (Str.3) , NB

12

0%

0% 13-Nov-08 26-Nov-08

13-Nov-08

26-Nov-08

87 m

D/Wall [Sec. #4]: Unit 37 (Str.3) ~ Unit 35 (Str.3) , N

153
153
6

0
0
0

0%

0% 27-Apr-09 25-Oct-09
0% 27-Apr-09 25-Oct-09
0% 10-Sep-09 17-Sep-09

27-Apr-09
27-Apr-09
10-Sep-09

25-Oct-09
25-Oct-09
17-Sep-09

0
0
0

0
0
0

558
558
24 Nos

Earth Anchor [Sec. #4] : Unit 62

CNS430331 Earth Anchor [Sec. #4] : Unit 61 (Str.3) ~ Unit 60 (Str.3)

14

0%

0% 21-Sep-09 06-Oct-09

21-Sep-09

06-Oct-09

56 Nos

Earth Anchor [Sec. #4] : Unit 6

CNS430340 Earth Anchor [Sec. #4] : Unit 59 (Str.3) ~ Unit 58 (Str.3)

16

0%

0% 07-Oct-09 25-Oct-09

07-Oct-09

25-Oct-09

64 Nos

CNS430350 Earth Anchor [Sec. #4] : Unit 57 (Str.3) ~ Unit 56 (Str.3)

16

0%

0% 13-Jun-09 30-Jun-09

13-Jun-09

30-Jun-09

64 Nos

Earth Anchor [Sec. #4] : Unit 57 (Str.3

CNS430360 Earth Anchor [Sec. #4] : Unit 55 (Str.3) ~ Unit 52 (Str.3)

32

0%

0% 01-Jul-09

16-Aug-09

01-Jul-09

16-Aug-09

128 Nos

Earth Anchor [Sec. #4] : Unit 55 (S

CNS430370 Earth Anchor [Sec. #4] : Unit 51 (Str.3) ~ Unit 50 (Str.3)

16

0%

0% 18-Aug-09 09-Sep-09

18-Aug-09

09-Sep-09

64 Nos

CNS430380 Earth Anchor [Sec. #4] : Unit 46 (Str.3) ~ Unit 45 (Str.3)

16

0%

0% 27-Apr-09

14-May-...

27-Apr-09

14-May-09

64 Nos

Earth Anchor [Sec. #4] : Unit 46 (Str.3) ~

CNS430410 Earth Anchor [Sec. #4] : Unit 37 (Str.3) ~ Unit 35 (Str.3)

24

0%

0%

16-May-... 11-Jun-09

16-May-09

11-Jun-09

94 Nos

Earth Anchor [Sec. #4] : Unit 37 (Str.3)

Section No.4 (STA.


(S
10+704 ~ STA. 11+525)
Excavation Supporting
Supp
System
Strut Installation / Removal
General
CNS410060 Strut Removal [Sec. #4] : Unit 49 (Str.3) ~ Unit 47 (Str.3)

Earth Anchor Driving


Dr
South & North
Nort Bound
CNS430330 Earth Anchor [Sec. #4] : Unit 62 (Str.3)

Project Start : 15-May-08


Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 6 / 8

Actual Work
Remaining Work

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

2177 m2

Fire Pro

3
3
3 Unit

Strut Removal [Sec. #

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Earth Anchor [Sec. #4] : Unit

Earth Anchor [Sec. #4] : Unit 51

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

17-Mar-09

10-Nov-09

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
61313

0%

0% 17-Mar-09 14-May-...
0% 17-Mar-09 14-May-...
0% 04-Apr-09 26-Apr-09

17-Mar-09
17-Mar-09
04-Apr-09

14-May-09
14-May-09
26-Apr-09

0
0
0

0
0
0

38321
38321
15328 m3

0%

0% 17-Mar-09 02-Apr-09

17-Mar-09

02-Apr-09

11496 m3

1ST - Excavation [Sec. #4] : Unit 39 (Str.3)

0%

0% 27-Apr-09

14-May-...

27-Apr-09

14-May-09

11497 m3

1ST - Excavation [Sec. #4] : Unit 37 (Str

0%

0% 26-Oct-09 10-Nov-09
0% 26-Oct-09 10-Nov-09
0% 26-Oct-09 10-Nov-09

26-Oct-09
26-Oct-09
26-Oct-09

10-Nov-09
10-Nov-09
10-Nov-09

0
0
0

0
0
0

22992
22992
22992 m3

2ND - Excavation [Sec. #4] :

0% 11-Nov-09 05-Dec-09

11-Nov-09

05-Dec-09

8
8
8

0
0
0

0%

0% 11-Nov-09 19-Nov-09
0% 11-Nov-09 19-Nov-09
0% 11-Nov-09 19-Nov-09

11-Nov-09
11-Nov-09
11-Nov-09

19-Nov-09
19-Nov-09
19-Nov-09

0
0
0

0
0
0

10
10
10

0
0
0

0%

0% 21-Nov-09 05-Dec-09
0% 21-Nov-09 05-Dec-09
0% 21-Nov-09 05-Dec-09

21-Nov-09
21-Nov-09
21-Nov-09

05-Dec-09
05-Dec-09
05-Dec-09

0
0
0

0
0
0

3268
3268
3268 m2

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
202
0
0% 17-Mar-09 10-Nov-09

Earthworks
Excavation - 1st layer ( GL ~ 3.0m )
South & North
Nort Bound
CNS430060 1ST - Excavation [Sec. #4] : Unit 47 (Str.3) ~ Unit 45 (Str.3)

51
51
20

0
0
0

CNS430090 1ST - Excavation [Sec. #4] : Unit 39 (Str.3) ~ Unit 38 (Str.3)

15

CNS430100 1ST - Excavation [Sec. #4] : Unit 37 (Str.3) ~ Unit 35 (Str.3)

16

Excavation - 2nd layer ( 3.0m ~ FL )


South & North
Nort Bound
CNS430160 2ND - Excavation [Sec. #4] : Unit 49 (Str.3) ~ Unit 48 (Str.3)

14
14
14

0
0
0

18

Pile Foundation
Pile Head Treatment
Treatm
South & North
Nort Bound
CNS420200 Pile Head [Sec. #4] : Unit 49 (Str.3) ~ Unit 48 (Str.3)
Water Proofing
South & North
Nort Bound
CNS440060 W/Proofing (Incl.Lean) [Sec. #4] : Unit 49 (Str.3) ~ Unit 48 (St...

Start

Finish

VAR
VAR
START FINISH

1ST - Excavation [Sec. #4] : Unit 47 (Str.3

3299
31
31
31 Nos.

Pile Head [Sec. #4] : Unit 49

W/Proofing (Incl.Lean) [Se

188

0% 06-Dec-09 15-Jul-10

06-Dec-09

15-Jul-10

4707

Base Slab
General
CNS450390 Base Slab [Sec. #4] : Unit 49A (Str.3)

29
29
10

0
0
0

0%

0% 06-Dec-09 09-Jan-10
0% 06-Dec-09 09-Jan-10
0% 06-Dec-09 16-Dec-09

06-Dec-09
06-Dec-09
06-Dec-09

09-Jan-10
09-Jan-10
16-Dec-09

0
0
0

0
0
0

3540
3540
1221 m3

Base Slab [Sec. #4] : Unit

CNS450400 Base Slab [Sec. #4] : Unit 49B (Str.3)

10

0%

0% 19-Dec-09 29-Dec-09

19-Dec-09

29-Dec-09

1221 m3

Base Slab [Sec. #4] : Uni

CNS450410 Base Slab [Sec. #4] : Unit 49C (Str.3)

0%

0% 30-Dec-09 09-Jan-10

30-Dec-09

09-Jan-10

1098 m3

Base Slab [Sec. #4] : Un

Retaining Wall ((1st)


South & North
Nort Bound
CNS451230 1ST-Retaining Wall [Sec. #4] : Unit 49A (Str.3)

24
24
8

0
0
0

0%

0% 10-Jan-10 06-Feb-10
0% 10-Jan-10 06-Feb-10
0% 10-Jan-10 18-Jan-10

10-Jan-10
10-Jan-10
10-Jan-10

06-Feb-10
06-Feb-10
18-Jan-10

0
0
0

0
0
0

600
600
200 m3

1ST-Retaining Wall [Se

CNS451240 1ST-Retaining Wall [Sec. #4] : Unit 49B (Str.3)

0%

0% 19-Jan-10 27-Jan-10

19-Jan-10

27-Jan-10

200 m3

1ST-Retaining Wall [Se


1ST-Retaining Wall [S

Reinforced Concrete
Conc
Works

CNS451250 1ST-Retaining Wall [Sec. #4] : Unit 49C (Str.3)

0%

0% 28-Jan-10 06-Feb-10

28-Jan-10

06-Feb-10

200 m3

Retaining Wall ((2nd)


South & North
Nort Bound
CNS451800 2ND-Retaining Wall [Sec. #4] : Unit 58A (Str.3)

87
87
10

0
0
0

0%

0% 18-Feb-10
0% 18-Feb-10
0% 28-Apr-10

31-May-...
31-May-...
09-May-...

18-Feb-10
18-Feb-10
28-Apr-10

31-May-10
31-May-10
09-May-10

0
0
0

0
0
0

201
201
23 m3

2ND-Retaining W

CNS451810 2ND-Retaining Wall [Sec. #4] : Unit 58B (Str.3)

10

0%

0%

10-May-... 20-May-...

10-May-10

20-May-10

23 m3

2ND-Retaining

CNS451820 2ND-Retaining Wall [Sec. #4] : Unit 58C (Str.3)

0%

0%

22-May-... 31-May-...

22-May-10

31-May-10

21 m3

2ND-Retaining

CNS452010 2ND-Retaining Wall [Sec. #4] : Unit 51A (Str.3)

10

0%

0% 25-Mar-10 05-Apr-10

25-Mar-10

05-Apr-10

23 m3

2ND-Retaining Wa

CNS452020 2ND-Retaining Wall [Sec. #4] : Unit 51B (Str.3)

10

0%

0% 06-Apr-10 17-Apr-10

06-Apr-10

17-Apr-10

23 m3

2ND-Retaining W

CNS452030 2ND-Retaining Wall [Sec. #4] : Unit 51C (Str.3)

0%

0% 18-Apr-10 27-Apr-10

18-Apr-10

27-Apr-10

21 m3

CNS452070 2ND-Retaining Wall [Sec. #4] : Unit 49A (Str.3)

10

0%

0% 18-Feb-10 02-Mar-10

18-Feb-10

02-Mar-10

23 m3

CNS452080 2ND-Retaining Wall [Sec. #4] : Unit 49B (Str.3)

10

0%

0% 03-Mar-10 14-Mar-10

03-Mar-10

14-Mar-10

23 m3

2ND-Retaining Wall
2ND-Retaining Wal

CNS452090 2ND-Retaining Wall [Sec. #4] : Unit 49C (Str.3)

2ND-Retaining W
2ND-Retaining Wall

0%

0% 15-Mar-10 24-Mar-10

15-Mar-10

24-Mar-10

21 m3

Roof Slab
South & North
Nort Bound
CNS453440 Roof Slab [Sec. #4] : Unit 58A (Str.3)

20
20
6

0
0
0

0%

0% 22-Jun-10 15-Jul-10
0% 22-Jun-10 15-Jul-10
0% 22-Jun-10 28-Jun-10

22-Jun-10
22-Jun-10
22-Jun-10

15-Jul-10
15-Jul-10
28-Jun-10

0
0
0

0
0
0

366
366
122 m3

Roof Slab [Se

CNS453450 Roof Slab [Sec. #4] : Unit 58B (Str.3)

0%

0% 29-Jun-10

05-Jul-10

29-Jun-10

05-Jul-10

122 m3

Roof Slab [S

CNS453460 Roof Slab [Sec. #4] : Unit 58C (Str.3)

0%

0% 07-Jul-10

15-Jul-10

07-Jul-10

15-Jul-10

122 m3

Roof Slab [S

18

0% 01-Jun-10 21-Jun-10

01-Jun-10

21-Jun-10

1485

Precast Girder Installation


I
South & North
Nort Bound
CNS453080 I-Girder Install [Sec. #4] : Unit 61 (Str.3)

18
18
6

0
0
0

0%

0% 01-Jun-10 21-Jun-10
0% 01-Jun-10 21-Jun-10
0% 01-Jun-10 07-Jun-10

01-Jun-10
01-Jun-10
01-Jun-10

21-Jun-10
21-Jun-10
07-Jun-10

0
0
0

0
0
0

1485
1485
495 m

I-Girder Install

CNS453100 I-Girder Install [Sec. #4] : Unit 59 (Str.3)

0%

0% 08-Jun-10 14-Jun-10

08-Jun-10

14-Jun-10

495 m

I-Girder Instal

CNS453110 I-Girder Install [Sec. #4] : Unit 58 (Str.3)

0%

0% 15-Jun-10 21-Jun-10

15-Jun-10

21-Jun-10

495 m

I-Girder Insta

56

0% 17-Jul-10

17-Jul-10

21-Sep-10

Prestressed Concrete
Conc
Works

Anicillary Works / Misc


Project Start : 15-May-08
Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 7 / 8

Actual Work
Remaining Work

21-Sep-10

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

16634

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Approved

UPGRADING AL SALAM STREET AND ABU DHABI CITY RING ROAD CONTRACT NO.1
Activity ID

Activity Name

Achitectural & L
Landscaping Works
Inner parts of Tunnel
CNS460220 Fire Protection & Finishes [Sec. #4] : Unit 62 (Str.3) ~ Unit 60 ...

Original Total Float Complete % Schedule %


Target
Target
Complete
Start
Finish
Duration
56
0
0% 17-Jul-10 21-Sep-10
56
0
0% 17-Jul-10 21-Sep-10
8
0
0%
0% 13-Sep-10 21-Sep-10

Start

Finish

VAR
VAR
START FINISH

17-Jul-10
17-Jul-10
13-Sep-10

21-Sep-10
21-Sep-10
21-Sep-10

0
0
0

0
0
0

2009
2010
11
QTY Unit 2008
J J A S ND J FMA J J A S ND J FMA J J A S ND J
1 2 3 4 5 6 7 8 9 11 11 1 1 1 1 1 1 2 2 22 22 2 2 2 2 3 3 3 3
16634
16634
2506 m2
Fire Pro

CNS460230 Fire Protection & Finishes [Sec. #4] : Unit 59 (Str.3) ~ Unit 58 ...

0%

0% 01-Sep-10 12-Sep-10

01-Sep-10

12-Sep-10

2278 m2

Fire Pro

CNS460250 Fire Protection & Finishes [Sec. #4] : Unit 54 (Str.3) ~ Unit 52 ...

0%

0% 27-Jul-10

03-Aug-10

27-Jul-10

03-Aug-10

2734 m2

Fire Protec

CNS460260 Fire Protection & Finishes [Sec. #4] : Unit 51 (Str.3) ~ Unit 50 ...

0%

0% 17-Aug-10 31-Aug-10

17-Aug-10

31-Aug-10

2278 m2

Fire Prot

CNS460270 Fire Protection & Finishes [Sec. #4] : Unit 49 (Str.3) ~ Unit 47 ...

0%

0% 04-Aug-10 15-Aug-10

04-Aug-10

15-Aug-10

3418 m2

Fire Prote

0%

0% 17-Jul-10

Fire Protec

CNS460320 Fire Protection & Finishes [Sec. #4] : Unit 37 (Str.3) ~ Unit 35 ...

SITE TESTING & COMMISSIONING


General
Tunnel Operation & Maintenance
Inner parts of Tunnel
SC000010 Tunnel Testing & Commissioning (Structure)

Mechanical & Ele


Electrical Works
Inner parts of Tunnel
SC000100 Final Acceptance Inspection

HAND OVER
General
CLOSE OUT & HANDING
HA
OVER
COMPLETION & HANDING OVER
HN000010

Project Start : 15-May-08


Project Finish : 31-Oct-10
Data Date : 15-May-08
Page : 8 / 8

Hand-Over of All Structures

Actual Work
Remaining Work

25-Jul-10

17-Jul-10

25-Jul-10

3420 m2

34

0% 22-Sep-10 31-Oct-10

22-Sep-10

31-Oct-10

34

0% 22-Sep-10 31-Oct-10

22-Sep-10

31-Oct-10

34

0% 22-Sep-10 31-Oct-10

22-Sep-10

31-Oct-10

34
34
40

0
0
0

0% 22-Sep-10 31-Oct-10
0% 22-Sep-10 31-Oct-10
0% 22-Sep-10 31-Oct-10

22-Sep-10
22-Sep-10
22-Sep-10

31-Oct-10
31-Oct-10
31-Oct-10

0
0
0

0
0
0

0
0
0

34

0% 22-Sep-10 31-Oct-10

22-Sep-10

31-Oct-10

34
34
40

0
0
0

0% 22-Sep-10 31-Oct-10
0% 22-Sep-10 31-Oct-10
0% 22-Sep-10 31-Oct-10

22-Sep-10
22-Sep-10
22-Sep-10

31-Oct-10
31-Oct-10
31-Oct-10

0
0
0

0
0
0

1
1
1 L/S

0% 31-Oct-10 31-Oct-10

31-Oct-10

31-Oct-10

0% 31-Oct-10 31-Oct-10

31-Oct-10

31-Oct-10

0% 31-Oct-10 31-Oct-10

31-Oct-10

31-Oct-10

0
0
0

0
0
0

0% 31-Oct-10 31-Oct-10
0% 31-Oct-10 31-Oct-10
0%
31-Oct-10

31-Oct-10
31-Oct-10

31-Oct-10
31-Oct-10
31-Oct-10

0
0
0

0
0
0

0
0
0

0%

0%

0%

BASELINE PROGRAMME REV.0


Updated As of 31st July 08

Critical Remaining Work


Milestone

UPGRADING AL SALAM STREET &


ABU DHABI CITY RING ROAD CONTRACT NO.1

Date
08/07/15

Revision
Checked
Submitted on 15TH JU... Randy, Seo

Tunn

Fina

Hand

Approved

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 5
Quantity Loading of BOQ
by month

SAMSUNG-SAIF BIN DARWISH JV

-5-

A5. Quantity Loading of BOQ by month


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

Resource ID

Unit of
Measure

01DTBARR SAFETY BARRIER

Nos

01DTBARR1 TEMPORARY CONCRETE BARRIER

LM

01DTBARR2 TEMPORARY CONCRETE BARRIER WITH SCREEN

LM

01DTCONE TRAFFIC CONES, BARRICADES

Nos

2008
May

Jun

Jul

Aug

2009
Sep

Oct

1,259

4,260

8,489

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

3,461

Period Total

4,720

6,077

1,174

20,000

500

6,500

3,500

10,500

996

1,564

2,560

01DTCRASH CRASH CUSHION

Nos

43

117

160

01DTDELIN DELINEATOR SYSTEM

LM

373

1,027

1,400

01DTFENCE TEMPORARY FENCING

LM

1,800

4,320

01DTMAINT TRAFFIC DETOUR MAINTENANCE

DHS

01DTMARK TEMPORARY ROAD MARKING

Nos

264

1,755

2,938

3,083

8,040

10

01DTPAVE TEMPORARY DETOUR PAVEMENT

SqM

2,964

24,115

21,340

20,022

68,440

11

01DTPED1 TEMPORARY PEDESTRIAN BRIDGE

Nos

12

01DTPED2 TEMPORARY PEDESTRIAN BRIDGE OVER DETOUR

Nos

14

13

01DTSCFEN TEMPORARY SIGHT SCREEN FENCING

LM

1,167

1,833

3,000

14

01DTSCR TEMPORARY SCREEN

LM

1,556

2,444

4,000

15

01DTSG TEMPORARY TRAFFIC SIGNAL CONTROLLER

Nos

15

16

01DTSIGN TEMPORARY CONSTRUCTION SIGNS

Nos

173

187

190

550

17

01DTSL1 TEMPORARY STREETLIGHTING

Nos

110

64

18

01DTSL2 RELOCATE EXISTING STREETLIGHT

Nos

68

19

01DTTREE REMOVE/REPLANT TREE

Nos

20

01GEBILL1 BILL No. 1 - ITEMS NOT INCLUDED

DHS

21

01GEOFFSITE1 ESTABLISH SITE OFFICE / CAMP FACILITIES

DHS

22

01GEOFFSITE2 MAINTAIN SITE OFFICE / VEHICLES

DHS

23

01GEOFFSITE3 REMOVAL SITE OFFICE / CAMP FACILITIES

DHS

24

02BILL2 BILL No. 2 - ITEMS NOT INCLUDED

DHS

25

02BORE BOREHOLE

26

02CUT3 STRUCTURAL EXCAVATION

CuM

CuM

LM

27

02DISPOS1 DISPOSAL OF SURPLUS SOIL BY ROAD

28

02DW D/Wall

LM

29

02EA Earth Anchor

30

31

2,880

10,316

96

243

108

265

27

3,162

3,162

3,162

3,162

3,549,126

4,194,421

319,638

319,638

9,000

11,027

11,027

9,960

11,027

10,671

11,027

10,671

11,027

11,027

10,671

11,027

10,671

11,027

11,027

9,960

11,027

10,671

11,027

10,671

11,027

11,027

10,671

256,110

60

270

57

130

115

111

38

2,919

3,162

2,676

3,041

295,050

319,638

270,463

307,344

115

18

800

2,919

3,162

3,162

2,554

36,490

295,050

319,638

319,638

319,638

7,743,547

319,638

307,344

331,932

295,050

319,638

295,050

307,344

319,638

282,756

331,932

307,344

331,932

319,638

307,344

331,932

196,700

259,862

1,061

183

7,826

217

217

26,524

28,646

25,463

27,585

25,463

26,524

27,585

24,402

26,524

28,646

49,498

21,219

850

813

912

351

1,093

800

1,108

2,174

1,485

550

1,014

1,463

272,000

283,333

11,763

181,333

294,667

294,667

294,667

294,667

283,333

306,000

272,000

294,667

752

828

795

863

864

871

587

322

237

161

90

Nos

32

76

281

303

201

362

458

370

240

251

144

02EX1 1ST Excavation

CuM

6,098

19,802

46,507

48,221

75,209

83,477

83,811

45,501

30,517

11,103

9,423

831

02EX2 2ND Excavation

CuM

8,869

16,471

109,688

115,441

119,736

132,775

163,087

151,261

155,061

193,780

143,595

68,451

3,285

32

02FILL2 PERVIOUS BACKFILL

CuM

70

1,750

1,890

1,680

1,820

1,680

1,750

1,820

1,610

33

02FILL3 GRANULAR BACKFILL

CuM

1,089

1,199

1,295

1,151

1,247

1,151

1,086

646

115

34

02GRADE SUBGRADE WITH GEOTEXTILE

CuM

120

380

6,727

3,430

35

02KP1 King Post Driving

Nos

36

02LOCA EXCAVATE TO LOCATE

LM

37

02PS P-Sum (Marine Transportation for Excavated Materials) Revised

CuM

466,566

498,743

498,743

450,478

498,743

482,655

498,743

38

02RMBARR REMOVAL OF BARRIERS, SIGNS, DISPLAYS etc

DHS

41,287

136,907

105,001

96,869

43,951

148,908

86,335

39

02RMPEDUP REMOVAL OF PEDESTRIAN UNDERPASS

DHS

40

02ST1 Strut Install

Unit

41

02ST2 Strut Removal

Unit

42

02STONE STONE RIPRAP AT OUTFALL STRUCTURE

CuM

43

02TD1 Traffic Decking Installation

Unit

44

02TD2 Traffic Decking Removal

Unit

45

02UTILMARK UTILTY MARKERS

Nos

46

03RBASE AGGREGATE BASE COURSE

SqM

47

03SAND SAND ASPHALT

SqM

48

04ABASE ASPHALT BASE COURSE

CuM

49

04ADJUST ADJUSTMENT OF MANHOLES, INLETS, SERVICES

Nos

10

230

535

873

873

514

294

843

309,360

318,290

233

879

371

28,646

7,990,944

226

113

294,667

34,000

3,400,000

7,250

87

2,810

460,501

1,381,499

1,890

1,750

1,890

1,400

21,000

11,500

10,947

3,267

11,370

3,131

40,000

68

588

968

2,182

482,655

498,743

498,743

498,743

257,416

6,113,625

659,258

220,010

592,344

653

482,655

541,570

1,353,924

22

10

22

57

710

25

25

33

513

667

5,113

4,767

13,513

7,720

6,663

70

66

587

468

947

887

490

19

15

14

10

14,406

225

200

2,307

42

500

41,263

6,079

55,648

15,867

92,000

767

366

582

5,230

75

A5. Quantity Loading of BOQ by month


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

Resource ID

Unit of
Measure

2008
May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

50

04MILL MILLING EXISTING ASPHALT

CuM

188

101

841

736

51

04REGUL ASPHALT REGULATORY COURSE

CuM

188

22

329

1,041

52

04REIN REINSTATEMENT OF ASPHALT, KERBSTONE, TILES

DHS

94,152

97,918

86,620

101,684

53

04WEAR1 ASPHALT WEARING COURSE

CuM

62

124

520

54

04WEAR2 ASPHALT WEARING COURSE (ON TUNNEL)

CuM

55

05BC Barrier & Curb

56

05BS Base Slab

CuM

57

05CB C/Wall (Cap Beam)

CuM

58

05CL C/Wall (Column)

CuM

59

05PS P-Sum (Partition Wall)

CuM

60

05RS Roof Slab

CuM

61

05UR1 U/Room (Base)

CuM

71,556

90,386

LM

62

05UR2 U/Room (Inner)

CuM

63

05UR3 U/Room (Outer)

CuM

64

05UR4 U/Room (Roof)

CuM

65

05WA1 1ST Wall

CuM

66

05WA2 2ND Wall

CuM

67

05WP1 W/Proofing (Incl. Lean)

SqM

68

05WP2 W/Proofing (Wall)

SqM

69

06OUTFALL CONSTRUCTION OF OUTFALL STRUCTURE

DHS

70

06PAVCATCH PAVEMENT SUBBASE DRAINAGE - CATCH BASINS

Nos

71

06PAVPIPE PAVEMENT SUBBASE DRAINAGE - PIPELAYING

LM

72

06PERFPL PERFORATED PIPE LAYING

73

06PRECAST PRECAST SLAB FOR SIDE WALK DRAINAGE

DHS

74

06PUMP CONSTRUCTION OF PUMP STATION

DHS

75

06SLOTT SLOTTED TRENCH DRAIN FOR STORM WATER

LM

76

06STBKFILL STORM WATER LINE - BACKFILLING

LM

77

06STCONN STORM WATER - CONNECTION TO EXISTING LINE

Nos

3,436

4,903

21,852

84

168

931

2,190

79,407

1,796,588

4,079,566

3,771,853

880

14,790

1,006

1,334

45,151

39,325

21,546

3,430

125

388

221

214

378

436

642

810

529

737

408

811

246

635

490

559

1,324

1,434

1,193

1,156

1,172

96

131

435

450

435

450

450

406

145

366

1,190

1,664

2,559

3,814

3,730

4,025

Sep

Oct

Nov

Period Total

434

1,199

142

230

65

101,684

97,918

94,152

101,684

90,386

7,532

1,129,824

1,452

570

691

244

156

157

3,980

1,015

4,241

4,119

975

10,675

3,130

926

127

3,580

1,340

47,141

Aug
92

2,624

197

40,772

Jul
170

145

34,686

4,036

3,650

3,650

18,300

330,000

11

4,900

9,200

2,900

3,623

4,398

974

661

213

633

599

734

1,238

314

1,002

769

87

56

426

319

168

204

406

336

638

168

377

494

103

34

280

409

196

188

389

378

636

179

356

502

151

28

338

248

284

383

518

476

338

265

656

1,971

661

28,000

7,392

1,434

4,249

5,192

3,482

3,686

8,367

8,189

10,479

10,280

7,696

7,398

618

147

166

334

478

405

582

848

953

1,030

912

1,101

798

16,017

8,464

9,694

20,828

24,931

33,199

24,751

15,130

9,126

1,065

213

275

6,346

6,881

5,263

10,364

12,959

10,347

3,696

3,696

183

3,718

72,000

245

8,000

180,000

11,826

15,585

14,884

13,662

5,330

115,000

2,183,697

11,911,110

1,291,124

1,350,541

1,289,518

1,465,361

2,245,047

1,121,719

160,590

309

580

479

544

470

512

523

698

104

503

337

370

3,055

3,678

3,644

3,437

4,214

4,527

1,992

510

550

14

38

250

860

40

420

640

574

176

2,980

572

506

374

2,200

7,624

17,536

20,585

45,745

9,635,301

56

LM

413

103

69

176

49

108

100

108

28

400

65

5,024

30

78

06STDIPIPE DI DRAIN PIPE LAYING

06STEXC STORM WATER LINE - EXCAVATION

80

06STINGRT BASE SLAB DRAINAGE - INLET GRATES

301

81

06STLTCONN STORM WATER LATERALS - CONNECTION TO EXISTING LINES

Nos

82

06STLTEXC STORM WATER LATERALS - EXCAVATION

CuM

930

83

06STLTINLET STORM WATER LATERALS - CONSTRUCTION OF INLETS/CATCH BAS

Nos

10

84

06STLTPIPE STORM WATER LATERALS - PIPELAYING

LM

85

06STMHCN STORM WATER - MANHOLE CONSTRUCTION

Nos

86

06STNDDR STORM WATER - NDRC DRIVING

LM

243

87

06STPIPE STORM WATER LINE - PIPELAYING

LM

12

88

06STREMO STORM WATER - REMOVE EXISTING LINES

LM

89

06STTEST STORM WATER LINE - TESTING

LM

90

07AWTDUCT WATER DUCT

LM

91

07AWTPROT PROTECTION OF WATER LINE

92

07AWTSLEEVE GRP SLEEVE FOR WATER LINE

93

07BASBUILT WATER LINE - AS BUILT DOCUMENTATION

DHS

94

07BDAYWORKS WATER LINE - DAYWORKS

DHS

95

07BWTBFILL WATERLINE - BACKFILL / REINSTATEMENT

LM

96

07BWTBOX WATER LINE - TWIN BOX CULVERT

LM

97

07BWTCP WATER LINE - CORROSION PROTECTION

LM

98

07BWTCSPL WATER LINE - CS PIPELINE ACROSS TUNNEL

LM

LM

482

315

513

506

481

184

4,095

1,150

540

250

500

196

284

34,000

70

75

192

236

15

14

49

100

1,140

1,740

4,918

503

4,247

4,190

2,299

931

20,998

11

23

46

18

39

74

26

11

258

110

336

764

204

853

1,334

512

213

4,486

26

160

13

30

79

3,427

Jun

1,376

180

19,825

198

2,596

94,152

17,398

LM

CuM

146

30,537

20

711,400

May

11

17

17

14

15

12

169

183

80

70

97

37

22

688

788

528

553

531

620

553

772

393

91

239

246

871

795

664

617

508

761

560

194

606

124

901

116

129

49

36

15

50

5,925

10

186

90

31

13

50

15

20

20

171

165

101

66

200

158

900

23

23

129

230

95

236

190

122

1,100

124

256

152

86

91

98

850

SqM

76

23

29

LM

44

5,925

2,874

10,958

21,915

21,915

20,229

21,915

18,544

21,072

20,229

21,915

21,915

21,915

21,915

8,429

215

344

307

484

603

501

499

422

477

436

569

532

705

773

507

2,258

10,265

252,868

559

43

206

369

5,133

506

52

81

23

90

84

51

21

24

21

4,264

90

134

153

5,304

165

29

329

A5. Quantity Loading of BOQ by month


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

Resource ID

Unit of
Measure

99

07BWTDUCT WATER DUCT CROSSING TUNNEL

LM

100

07BWTEXC WATER LINE - TRENCH EXCAVATION

LM

101

07BWTHOUSE WATERLINE - HOUSE CONNECTION

LM

102

07BWTLOCA WATER LINE - EXCAVATE TO LOCATE

CuM

103

07BWTNDRC WATER LINE - NDRC DRIVING

LM

104

07BWTPL WATER LINE - PIPELAYING

LM

105

07BWTPROT WATER LINE - PROTECTION SLAB

LM

106

07BWTREMO WATER LINE - REMOVAL OF EXISTING WATER LINES

107

07BWTSHUT WATER LINE - SHUTDOWN & CONNECTION TO EXISTING LINE

108

07BWTUTIL WATERLINE THROUGH UTILITY BRIDGES

LM

109

07BWTVAC WATER LINE - CHAMBER

Nos

110

08BF Box Beam Fabrication

Nos

111

08BI Box Beam Installation

Nos

112

08GF I-Girder Fabrication

LM

113

08GI I-Girder Installation

LM

114

09GUIDSIGN GUIDE SIGN PANELS

Nos

115

09RDMARK ROAD MARKING

116

2008
May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec
9

434

464

437

499

486

500

488

466

384

Jan
45

Feb
78

Mar
112

Apr
402

16

416

416

384

91

Jun
5

188

203

429

470

438

575

530

761

719

504

440

360

409

393

426

426

426

426

409

245

LM

39

552

452

281

630

416

72

41

Nos

20

21

23

12

10

40

68

78

16

950

195

23

750

93

4,975

4,910

21

22

23

20

23

13

33

34

34

36

36

37

200

6,200

6,000

6,200

1,567

1,482

4,327

692

365

3,540

28

22

23

63

217

33

42

66

6,200

5,600

6,200

2,400

5,058

4,519

4,046

5,384

6,975

LM

200

640

1,840

09RDSTUD ROAD STUDS

Nos

150

450

117

09SIGN TRAFFIC SIGNS

SqM

26

118

10LAB1 S/Laboratory Set-Up

L/S

119

10LAB2 S/Laboratory Maintenance

1 L/S

120

10LAB3 S/Laboratory Removal

1 L/S

121

11BP Bored Pile

Nos

122

11PH P/Head Treatment

Nos

123

11PLT Pile Load Test

Nos

124

15AIRDUCT IRRIGATION DUCT

LM

125

15AIRPROT PROTECTION OF IRRIGATION LINE

LM

126

15AIRSLEEVE GRP SLEEVE FOR IRRIGATION LINE

LM

127

15BCONTROL IRRIGATION - INSTRUMENT CONTROL PANEL

DHS

128

15BINSTRCABL IRRIGATION - INSTRUMENTATION SIGNAL/POWER CABLE

DHS

129

15BIRBFILL IRRIGATION LINE BACKFILLING

LM

130

15BIRCONN CONNECTION TO EXISTING IRRIGATION LINE

Nos

131

15BIRREIN IRRIGATION LINE - REINSTATEMENT OF PAVEMENT

LM

110

153

114

72

167

135

165

132

15BIRREM REMOVAL OF EXISTING IRRIGATION LINE

LM

1,250

2,140

4,150

1,260

1,500

2,920

60

133

15BIRRPL IRRIGATION LINE - EXCAVATION & PIPELAYING

LM

475

359

483

473

502

501

496

509

440

509

403

80

130

80

134

15BIRVAC IRRIGATION VALVE CHAMBER

Nos

135

15BMARKER IRRIGATION LINE - MARKER PLATES

Nos

20

24

22

136

15BPROVIS IRRIGATION LINE - PROVISIONAL ITEM

DHS

137

16AEL1 Civil Works for Electrical Service

4 Sections

138

16AEL2 Survey and Installation of Anchoring, Supporting for Tunnel

4 Sections

139

16AEL3 Installation of Cable Tray and Conduit for Tunnel

140

16AEL4 Installation of Control and Power Cables for Tunnel

141

16AEL5 Installation of Street Lighting

142

16AEL6 Installation of Tunnel Elec Fixture

143

16BAD1 33KV / 11KV / LV : Deep Direction Drilling for HDD

L/S

144

16BAD2 33KV XLPE Cable Relocation

Nos

145

16BAD3 11KV XLPE Cable Relocation

Nos

146

16BAD4 LV XLPE Cable Relocation

Nos

147

16CTR1 132 KV XLPE Cable : Deep Direction Drilling for HDD

L/S

23

21

260

217

39,000

3,942

1,700

2,400

3,200

2,000

5,300

12,900

6,840

640

35,960

1,330

1,650

2,240

1,400

3,620

8,496

5,214

450

25,000

42

75

50

32

91

190

74

10

605

39,000

161

20

173

195

188

203

203

205

203

127

57

31

27

86

163

145

117

243

244

140

151

102

54

1,745

30

15

517

371

274

458

450

576

376

274

15

884

37

451

200

181

297

88

155

616

293

208

591

225

2,175

15

44

148

310

121

302

240

155

1,400

64

26

140

65

310

115

100

80

900

164,880

178,619

158,010

185,489

686,998

35,622

178,108

185,232

163,859

149,610

712,430

315

5,146

128

36

29

1,550

13,280

23

60

5,664

47

90

150,688

230,464

203,872

239,328

62,048

886,400

12

11

10

Nos

Section

Nos

Nos

1,745

273

165

Period Total

321

34

Nov

40

31

Oct

1,600

426

393

Sep

176

86

426

Aug

4,264

147

Jul
208

93

143

208

May

45

73

26

10

A5. Quantity Loading of BOQ by month


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

Resource ID

Unit of
Measure

2008
May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan
0

Feb
0

Mar
0

Apr
0

May
0

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Period Total

148

16CTR2 132 KV XLPE Cable : Excavation & Protection for Exist. 132 KV

L/S

149

16CTR3 132 KV XLPE Cable Relocation

Nos

150

17TCS1 Civil Works for TCS

151

17TCS2 TCS program

1 L/S

152

17TCS3 Installation of TCS Cable

1 L/S

153

17TCS4 Installation of TCS equipment in the Structures

Nos

154

17TCS5 Installation of Tunnel VMS, CCTV, LSCS

1 L/S

155

18DAY Daily Works

1 L/S

156

19ATEDUCT TELEPHONE DUCT

157

19ATEPROT PROTECTION OF TELEPHONE LINE

CuM

158

19ATEPULL TELEPHONE PULL BOXES

Nos

159

19ATESLEEVE PVC SLEEVE FOR TELEPHONE LINE

LM

160

19BTELADJ TELEPHONE LINE - ADJUST MANHOLE COVER & FRAME

Nos

161

19BTELBILL2 BILL No.2 - STORES CIVIL ACCESSORIES

DHS

58,978

70,773

76,671

64,875

73,722

70,773

76,671

76,671

20,642

589,775

162

19BTELBILL4-1 BILL No. 4 - STORES CABLE - CABLE F.O.

LM

11,203

24,443

26,480

22,406

25,461

24,443

26,480

26,480

16,295

203,689

163

19BTELBILL4-2 BILL No. 4 - STORES CABLE - CABLE F.O.

164

19BTELCONC TELEPHONE LINE RELOCATION - CONCRETE WORK

CuM

37

112

121

102

116

112

121

121

88

165

19BTELDUT1 TELEPHONE DUCT - EXCAVATION & LAYING

LM

237

270

292

232

301

270

258

166

19BTELDUT2 TELEPHONE DUCT THROUGH UTILITY CROSSING

167

19BTELEXC TELEPHONE LINE RELOCATION - EXCAVATION

CuM

272

326

354

299

340

326

354

354

95

2,720

168

19BTELFILL TELEPHONE LINE RELOCATION - FILLING

CuM

272

326

354

299

340

326

354

354

95

2,720

169

19BTELSLEW TELEPHONE LINE - SLEW/LOWER EXISTING DUCT

LM

144

247

268

227

258

247

268

268

134

2,060

170

19BTHDUCT THRUST BORING - TELEPHONE DUCT LAYING

LM

75

142

12

171

19BTHRUST TELEPHONE LINE - THRUST BORING

LM

38

108

84

172

19BTLCABLE TELEPHONE LINE CABLELAYING

LM

2,920

13,240

17,160

11,680

9,764

11,316

13,600

173

19BTLDTBK TELEPHONE DUCT - BACKFILLING

LM

203

270

291

236

298

271

292

174

19BTLMH TELEPHONE MANHOLE - CONSTRUCTION

Nos

175

19BTLREIN TELEPHONE LINE - REINSTATEMENT WORKS

SqM

1,350

100

550

700

300

1,250

176

19BTLTEST TELEPHONE LINE -TESTING & COMMISSIONING

DHS

21,015

77,055

28,020

42,031

177

20ASWDUCT SEWER DUCT

178

L/S

LM

15

15

38

LM

2,292

15

8,514

22

395

497

1,556

405

1,130

1,025

1,992

7,000

45

147

326

125

312

251

161

1,450

10

764

6,000

286

114

1,200

200

1,422

1,578

436

7,860

8,187

8,514

7,532

8,842

8,187

37

5,567

65,496

930

1,860

LM

22

227

133

251

150

783

229

229

3,880

8,550

3,643

4,980

8,147

6,000

114,880

1,860

33

850

5,100

31,523

52,538

84,060

117,334

15,761

14

39

82

36

54

77

26

350

20

16

16

105

139

65

161

129

83

750

467

2,333

150

200

43

234

274

234

249

166

34

233

274

235

254

183

51

10

77,056

546,392

LM

20ASWPROT PROTECTION OF SEWER LINE

SqM

16

179

20BSHTPILE SHEET PILE LEFT IN PLACE

SqM

180

20BSWABAN ABANDONING EXISTING SEWER LINE

LM

181

20BSWEXC SEWER LINE - EXCAVATION

LM

181

264

211

223

231

256

252

252

251

182

20BSWFILL SEWER LINE BACKFILLING

LM

141

264

216

221

228

254

253

251

251

183

20BSWFUTCONN SEWER FUTURE CONNECTIONS AT MANHOLES

Nos

184

20BSWMHCN SEWER MANHOLE CONSTRUCTION

Nos

57

185

20BSWMHEX SEWER MANHOLE EXCAVATION

Nos

48

186

20BSWMHFL SEWER MANHOLE BACKFILLING

Nos

187

20BSWNDRC NDRC FOR SEWER PIPES

LM

188

20BSWPIPE SEWER PIPELAYING

LM

189

20BSWPUMP OVERPUMPING SEWAGE

Nos

190

20BSWREIN REINSTATEMENT OF SEWER LINE

LM

191

20BSWTEST SEWER LINE TESTING

LM

192

21PUBTELE PUBLIC TELEPHONE BOOTH FOUNDATION

Nos

193

21REBUS REMOVE EXISTING BUS SHELTER

Nos

194

24ME1 Survey and Installation of Anchoring, Supporting

Section

195

24ME10 Installation of Fire Fighting Pump and Misting Pump

196

24ME11 Installation of Lift at Stru. No. 20

97

185

10

30

10

94

55

56

100

90

127

39

65

50

267

282

295

222

293

408

253

340

293

138

285

2,800

215

890

3,310

3,310

15

57

706

313

290

233

251

235

43

4,016

55

96

69

56

87

50

67

71

94

55

72

61

50

27

341

129

223

506

260

354

308

296

296

260

276

246

98

910

4,016

11

14

Section

L/S

A5. Quantity Loading of BOQ by month


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

Resource ID

Unit of
Measure

197

24ME12 Installation of Utility Building Piping

Nos

198

24ME13 Installation of Misc. Mech. Fixture

Nos

199

24ME14 Plumbing & Sanitary Installation (Architectural Works)

Nos

200

24ME15 Individual Fan, Pump, Lighting, FAS, Control Testing

L/S

201

24ME16 Individual Zone Testing & Commissioning

Nos

2008
May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar
1

Apr

May

Jun

Jul

Aug

Sep

14

11

Oct

Nov

Period Total

16

22

40

202

24ME2 Installation of Main Misting and Fire Landing Valve Pipe

Section

203

24ME3 Installation of Steel Frame for Duct and Smoke Dampers

Section

204

24ME4 Installation of Tunnel Fire Rated Duct

Section

205

24ME5 Duct Pressure Testing

Section

206

24ME6 Installation of Mech. Fixture

Section

207

24ME7 Installation Tunnel Ventilation Fan and Control Panels

Nos

15

208

24ME8 Installation Tunnel Dampers and Sound Attenuator

Nos

15

209

24ME9 Installation of Drainage Pumps and Piping

210

25FP F/Protection & Finishes

SqM

1,866

3,484

373

3,808

12,028

20,121

17,088

14,581

12,650

211

25LF Landscape & Furnitures

Unit

11

17

25

21

18

12

212

26MIL Military Communication System

L/S

213

27SCA1 SCADA program

L/S

214

27SCA2 Installation of SCADA Cable

L/S

215

27SCA3 Installation of SCADA equipment in the Structures

216

30QUAN QUANTITY

217

30REV REVENUE

Section

DHS

18,191

67,479

43,685

86,000

117

5,490

Nos

Variables

33,058

255

245

1,036

1,136

1,152

1,400

1,079

1,574

1,207

1,260

952

31

251

521

1,482

735

1,199

3,336

1,164

737

611,977

1,136,528

961,678

1,092,815

1,049,103

1,136,528

1,136,528

1,136,528

1,136,528

1,092,815

1,180,241

1,049,103

1,136,528

1,049,103

1,092,815

1,136,528

1,005,390

1,180,241

1,092,815

1,180,241

1,136,528

1,092,815

1,180,241

22

188,655

1,049,103

174,850

26,227,569

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 6
Monthly Quantity Distribution
for Key Activities

SAMSUNG-SAIF BIN DARWISH JV

-6-

A6. Monthly Quantity Distribution for Key Activities


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Activity ID

Diaphragm Wall

Excavation - 1st layer ( GL ~ 3.0m )

Unit of
Measure
LM

CuM

Budgeted
Quantity
7,250

460,500

2008
May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Sep

Oct

Nov

Dec

Jan

57

882

766

835

798

867

864

871

512

322

223

161

92

57

939

1,705

2,540

3,338

4,205

5,069

5,940

6,452

6,774

6,997

7,158

7,250

6,098

6,652

14,412

10,833

38,143

58,079

79,213

50,616

46,625

39,475

48,344

36,757

6,098

6,098

12,750

27,162

37,995

76,138

134,217

213,430

264,046

310,671

350,146

398,490

435,247

4,435

13,304

7,602

50,224

29,597

33,892

73,309

127,997

159,271

148,871

249,243

234,308

89,702

Bored Pile

Nos

1,745

Water Proofing

SqM

295,000

8,000

Aug

CuM

2010
Jul

2,810

Retaining Wall (2nd)

Jun

Nos

72,000

May

Earth Anchor Driving

CuM

Apr

Retaining Wall (1st)

Mar

1,381,500

330,000

Feb

CuM

CuM

Jan

Excavation - 2nd layer ( 3.0m ~ FL )

Base Slab

Dec

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

19,890

5,363

455,137

460,500
95,338

61,088

3,319

4,435

17,739

25,341

75,565

105,162

139,054

212,363

340,360

499,631

648,502

897,745

1,132,053

1,221,755

1,317,093

1,378,181

1,381,500

30

44

10

180

112

72

172

359

314

208

307

447

172

296

87

30

74

84

264

376

448

620

979

1,293

1,501

1,808

2,255

2,427

2,723

2,810

161

173

195

188

203

203

205

203

127

57

30

161

334

529

717

920

1,123

1,328

1,531

1,658

1,715

1,745

2,053

137

880

9,346

5,563

7,571

16,772

21,429

34,258

37,427

34,221

23,430

25,764

23,652

18,469

15,376

8,086

4,809

5,401

356

2,053

2,190

3,070

12,416

17,979

17,979

25,550

42,322

63,751

98,009

135,436

169,657

193,087

218,851

242,503

260,972

276,348

284,434

289,243

294,644

295,000

3,204

696

743

7,243

7,243

7,434

12,149

18,914

37,820

43,537

51,519

46,879

29,112

32,170

24,512

6,825

3,204

3,900

4,643

11,886

19,129

26,563

38,712

57,626

95,446

138,983

190,502

237,381

266,493

298,663

323,175

330,000

60

955

131

549

2,006

1,719

1,719

2,801

5,749

7,801

9,731

10,708

9,157

7,644

5,572

4,509

1,189

60

1,015

1,146

1,695

3,701

5,420

7,139

9,940

15,689

23,490

33,221

43,929

53,086

60,730

66,302

70,811

72,000

19

170

88

147

189

189

319

616

720

927

1,089

1,215

936

709

507

135

25

19

189

189

277

424

613

802

1,121

1,737

2,457

3,384

4,473

5,688

6,624

7,333

7,840

7,975

8,000

454

1,926

1,719

2,452

4,552

4,950

4,278

4,059

2,094

1,179

337

CuM

28,000

454

2,380

4,099

6,551

11,103

16,053

20,331

24,390

26,484

27,663

28,000

Precast Girder Installation

LM

39,000

2,184

2,213

2,838

2,968

8,284

5,916

6,446

4,204

3,296

651

2,184

4,397

7,235

10,203

18,487

24,403

30,849

35,053

38,349

39,000

Precast Box Beam Installation

Nos

217

36

36

37

72

36

36

72

109

109

109

181

217

Concrete Barrier & Curb

LM

18,300

197

1,340

1,428

2,688

3,517

2,905

3,417

1,948

383

462

15

197

1,537

2,965

5,653

9,170

12,075

15,492

17,440

17,823

18,285

18,300

Roof Slab

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 7
Monthly Budgeted Cost
by BOQ

SAMSUNG-SAIF BIN DARWISH JV

-7-

A7. Monthly Budgeted Cost by BOQ


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
2008

Budgeted
No

2009

2010

Activity ID
Total Cost

01

General

98,631,515

02

Earthworks

03

Subbase & Base Courses

04

Asphalt Works

05

Concrete Works

865,274,761

06

Storm Water Drainage System

134,347,811

May
243

Jun

Jul

Aug

Sep

5,935,465

12,415,498

20,138,327

26,547,841

24,251,001

778,538

116,233

137,367

219,841

335,578

46,211,202

571,791,156

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

545,754

481,965

405,477

443,123

618,113

467,258

435,985

419,983

342,958

305,721

330,665

305,721

318,371

330,665

292,716

342,958

318,015

342,958

330,309

318,371

342,958

467,234

57,324

43,205,775

44,262,709

42,437,353

52,684,093

51,774,167

65,962,358

59,732,992

46,028,386

38,651,402

26,050,187

22,588,684

13,391,555

6,973,997

3,075,367

2,394,192

1,936,004

1,132,359

1,822,305

543,698

8,223

55,508

49,341

10,280

21,969

28,564

218,959

204,142

578,681

716,106

285,336

261,469

1,489,140

424,601

4,228,967

24,053,347

07A

Water Works

07B

Water Line Relocation Works

90,943,965

08

Prestressed Concrete Works

144,891,895

09

Traffic Markings & Signs

4,368,736

10

Site Laboratory

7,025,204

11

Concrete Pile Foundations

7,121,731

11,241,317

15,833,157

12,255,407

11,077,835

47,817

25,458

15B

Irrigation Relocation Works

16A

Lighting & Electrical Distribution Works

16B

TRANSCO Services, 132KV Electrical Works

88,606,025

16C

ADDC Services, LV, 11KV & 33KV Electrical Works

61,453,155

17

Traffic Control System

64,169,176

18

Daily Works

1,171,068

19A

Telephone Works

3,359,413

19B

Telephone Line Relocation Works

20A

Sewerage Works

20B

Sewerage Line Relocation Works

165,466

297,371

274,496

552,745

6,793,062

6,074,747

25

Architectural & Hard Landscaping Works

176,788,742

26

Military Communication Works

27

SCADA System

31,774,132

ITEMS NOT INCLUDED IN THE PROGRAMME

26,227,569

Aug

71,556

94,881

435,245

292,260

1,410,093

2,083,310

1,262,258

3,106,117

2,195,868

2,424,176

4,866,952

4,693,158

1,851,239

252,971

54,076,709

38,371,712

46,778,207

68,170,617

90,282,065

102,934,997

104,979,885

101,738,719

69,587,702

48,744,550

27,679,914

28,230,221

16,502,088

8,202,706

9,889,729

7,627,988

6,092,450

6,936,011

3,630,218

1,254,061

373,987

2,780,532

1,404,640

1,348,533

2,645,443

3,696,631

7,731,095

1,528,065

5,939,955

8,684,544

3,666,754

1,587,728

222,302

70,678

1,006,302

1,499,580

876,002

626,476

1,011,653

870,410

8,942,080

10,811,071

7,838,062

8,984,284

7,214,980

16,668

7,530,222

5,839,117

Sep

2,031,474

684,330

134,496

1,566,321

1,394,121

1,287,258

3,694,960

3,552,633

2,434,853

2,396,722

1,494,996

17,668,059

21,287,069

22,342,711

22,022,686

19,198,966

21,827,528

13,985,546

3,990,763

1,073,571

82,926

47,557

192,632

306,409

20,766

266,323

281,391

311,540

301,490

419,974

713,327

1,401,018

822,585

95,219

311,540

301,490

311,540

243,615

18,893

2,364

2,043,934

311,540

311,540

281,391

311,540

301,490

311,540

301,490

311,540

311,540

301,490

311,540

301,490

311,540

311,540

1,271,157

3,177,893

317,789

3,376,102

3,626,769

4,093,778

3,939,829

4,284,682

4,308,035

4,340,004

4,288,658

2,730,413

1,262,785

690,833

85,831

47,491

31,968

17,097

14,705

14,705

184,470

282,035

819,565

1,675,824

1,506,456

1,010,847

1,649,912

802,506

916,229

1,369,376

197,848

74,984

733,234

594,315

525,740

937,478

475,882

18,038

201,111

784,889

1,271,487

4,990,959

7,664,554

8,443,490

21,743,376

17,428,753

23,638,738

31,668,393

13,930,627

8,463,230

7,290,870

4,245,871

6,620,904

6,010,563

12,637,718

9,141,247

5,646,710

203,701

1,925,502

1,672,829

2,135,471

1,244,387

1,233,199

1,404,951

1,527,256

1,319,383

767,441

337,546

1,265,799

1,077,015

2,257

301,490

37,524

Oct

399,020

240,934

4,907,612

8,230,338

7,826,864

8,507,232

8,465,039

4,762,582

283,008

1,253,321

1,132,032

1,253,321

1,212,891

1,355,803

8,946,814

6,725,147

6,771,237

7,292,193

9,361,301

4,799,114

2,143,974

958,669

890,070

1,157,606

1,071,858

1,157,606

1,597,782

872,635

663,694

553,079

368,450

581,764

601,156

581,764

601,156

601,156

542,979

601,156

581,764

601,156

581,764

601,156

601,156

593,334

616,988

5,683,099

7,386,797

5,201,160

1,077,274

1,229,892

1,135,783

1,233,668

1,153,598

3,008,789

11,126,299

14,811,892

2,464,026

44,874

43,426

44,874

43,426

44,874

44,874

40,531

44,874

43,426

44,874

43,426

44,874

44,874

43,426

44,874

43,426

44,874

44,874

40,531

44,874

43,426

44,874

43,426

44,874

44,874

43,426

13,205

13,205

87,230

96,556

474,503

446,666

506,544

763,591

431,407

493,054

156,136

162,642

177,889

1,062,561

623,511

807,059

1,008,285

651,388

21,352

47,302

196,374

324,954

147,023

288,112

304,515

143,833

4,909,005

2,527,871

3,366,460

1,151,247

30,134

146,385

9,475

974,764

111,284,270

224,155,288

Jul

38,527,691

3,342,433

3,099,180

2,464,932

2,414,119

2,367,719

2,966,880

1,804,717

1,351,536

7,112,367

8,763,019

8,023,953

8,572,357

8,851,998

12,001,438

6,391,981

33,452

657,877

1,555,027

Mechanical Works

Jun

39,166

25,039,498

24

May

26,972

149,363,300

Street Furniture

Apr

43,082

19,478,355

21

Mar

13,125,529

7,998,549

26,056

Feb

4,507,794

13,219

41,891,114

Irrigation Works

8,991

Jan

729,445

6,213,290

15A

4,495

Dec

8,737,565

51,204

27,840

21,625

8,053,297

6,449,065

169,148

32,097

5,530,424

4,702,333

4,788,354

185,994

43,112

7,912,320

38,981

61,549

221,545

791,232

759,583

822,881

822,881

822,881

822,881

664,635

664,635

664,635

822,881

31,650

416,752

77,054

747,280

3,862,238

44,645,314

56,257,787

53,447,286

41,197,032

17,409,242

3,005,780

2,204,172

919,293

3,628,827

5,669,277

2,796,451

10,056,325

25,055,358

40,320,913

34,098,956

29,312,378

24,120,217

1,730,040

63,601

61,549

63,601

63,601

57,446

63,601

61,549

63,601

61,549

63,601

63,601

61,549

590,351

2,454,886

3,855,056

4,212,126

2,968,055

4,709,586

4,494,458

2,973,386

2,266,654

1,115,123

703,660

581,412

611,977

1,136,528

961,678

1,092,815

1,049,103

1,136,528

1,136,528

1,136,528

1,136,528

1,092,815

1,180,241

1,049,103

1,136,528

1,049,103

1,092,815

1,136,528

1,005,390

1,180,241

1,092,815

1,180,241

1,136,528

1,092,815

1,180,241

1,049,103

174,849

MONTHLY COST SUBTOTAL

2,994,183,642

243

5,935,465

12,631,062

22,207,704

40,416,882

48,978,770

83,930,001

85,983,495

91,501,858

90,497,946

109,301,401

105,983,573

145,239,269

150,316,984

113,715,512

109,735,547

121,443,652

158,561,436

166,888,152

176,199,639

172,325,880

138,884,611

163,083,820

150,324,789

163,060,697

150,262,438

85,906,809

64,899,228

57,392,429

8,574,350

CUMMULATIVE COST TOTAL

2,994,183,642

243

5,935,708

18,566,770

40,774,474

81,191,356

130,170,126

214,100,127

300,083,622

391,585,480

482,083,426

591,384,827

697,368,400

842,607,669

992,924,653

1,106,640,165

1,216,375,712

1,337,819,364

1,496,380,800

1,663,268,952

1,839,468,591

2,011,794,471

2,150,679,082

2,313,762,902

2,464,087,691

2,627,148,388

2,777,410,826

2,863,317,635

2,928,216,863

2,985,609,292

2,994,183,642

MONTHLY PROGRESS

0.00%

0.20%

0.42%

0.74%

1.35%

1.64%

2.80%

2.87%

3.06%

3.02%

3.65%

3.54%

4.85%

5.02%

3.80%

3.67%

4.06%

5.30%

5.57%

5.89%

5.76%

4.64%

5.45%

5.02%

5.45%

5.02%

2.87%

2.17%

1.92%

0.29%

CUMMULATIVE PROGRESS

0.00%

0.20%

0.62%

1.36%

2.71%

4.35%

7.15%

10.02%

13.08%

16.10%

19.75%

23.29%

28.14%

33.16%

36.96%

40.63%

44.68%

49.98%

55.55%

61.44%

67.19%

71.83%

77.28%

82.30%

87.74%

92.76%

95.63%

97.80%

99.72%

100.00%

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 8
Monthly Cost Distribution
Base on Resources

SAMSUNG-SAIF BIN DARWISH JV

-8-

A8. Monthly Cost Distribution based on Resources


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
2008
Bill No. Resource ID
01DTBARR SAFETY BARRIER
01DTBARR1 TEMPORARY CONCRETE BARRIER
01DTBARR2 TEMPORARY CONCRETE BARRIER WITH SCREEN
01DTCONE TRAFFIC CONES, BARRICADES
01DTCRASH CRASH CUSHION
01DTDELIN DELINEATOR SYSTEM
01DTFENCE TEMPORARY FENCING
01DTMAINT TRAFFIC DETOUR MAINTENANCE
01DTMARK TEMPORARY ROAD MARKING
01DTPAVE TEMPORARY DETOUR PAVEMENT
01DTPED1 TEMPORARY PEDESTRIAN BRIDGE
01DTPED2 TEMPORARY PEDESTRIAN BRIDGE OVER DETOUR
1
01DTSCFEN TEMPORARY SIGHT SCREEN FENCING
01DTSCR TEMPORARY SCREEN
01DTSG TEMPORARY TRAFFIC SIGNAL CONTROLLER
01DTSIGN TEMPORARY CONSTRUCTION SIGNS
01DTSL1 TEMPORARY STREETLIGHTING
01DTSL2 RELOCATE EXISTING STREETLIGHT
01DTTREE REMOVE/REPLANT TREE
01GEBILL1 BILL No. 1 - ITEMS NOT INCLUDED
01GEOFFSITE1 ESTABLISH SITE OFFICE / CAMP FACILITIES
01GEOFFSITE2 MAINTAIN SITE OFFICE / VEHICLES
01GEOFFSITE3 REMOVAL SITE OFFICE / CAMP FACILITIES
Sub-Total
02BILL2 BILL No. 2 - ITEMS NOT INCLUDED
02BORE BOREHOLE
02CUT3 STRUCTURAL EXCAVATION
02DISPOS1 DISPOSAL OF SURPLUS SOIL BY ROAD
02DW D/Wall
02EA Earth Anchor
02EX1 1ST Excavation
02EX2 2ND Excavation
02FILL2 PERVIOUS BACKFILL
02FILL3 GRANULAR BACKFILL
02GRADE SUBGRADE WITH GEOTEXTILE
2
02KP1 King Post Driving
02LOCA EXCAVATE TO LOCATE
02PS P-Sum (Marine Transportation for Excavated Materials) Revised
02RMBARR REMOVAL OF BARRIERS, SIGNS, DISPLAYS etc
02RMPEDUP REMOVAL OF PEDESTRIAN UNDERPASS
02ST1 Strut Install
02ST2 Strut Removal
02STONE STONE RIPRAP AT OUTFALL STRUCTURE
02TD1 Traffic Decking Installation
02TD2 Traffic Decking Removal
02UTILMARK UTILTY MARKERS
Sub-Total
03RBASE AGGREGATE BASE COURSE
3
03SAND SAND ASPHALT
Sub-Total
04ABASE ASPHALT BASE COURSE
04ADJUST ADJUSTMENT OF MANHOLES, INLETS, SERVICES
04MILL MILLING EXISTING ASPHALT
04REGUL ASPHALT REGULATORY COURSE
4
04REIN REINSTATEMENT OF ASPHALT, KERBSTONE, TILES
04WEAR1 ASPHALT WEARING COURSE
04WEAR2 ASPHALT WEARING COURSE (ON TUNNEL)
Sub-Total
05BC Barrier & Curb
05BS Base Slab
05CB C/Wall (Cap Beam)
05CL C/Wall (Column)
05PS P-Sum (Partition Wall)
05RS Roof Slab
05UR1 U/Room (Base)
5
05UR2 U/Room (Inner)
05UR3 U/Room (Outer)
05UR4 U/Room (Roof)
05WA1 1ST Wall
05WA2 2ND Wall
05WP1 W/Proofing (Incl. Lean)
05WP2 W/Proofing (Wall)
Sub-Total
06OUTFALL CONSTRUCTION OF OUTFALL STRUCTURE
06PAVCATCH PAVEMENT SUBBASE DRAINAGE - CATCH BASINS
06PAVPIPE PAVEMENT SUBBASE DRAINAGE - PIPELAYING
06PERFPL PERFORATED PIPE LAYING
06PRECAST PRECAST SLAB FOR SIDE WALK DRAINAGE
06PUMP CONSTRUCTION OF PUMP STATION
06SLOTT SLOTTED TRENCH DRAIN FOR STORM WATER
06STBKFILL STORM WATER LINE - BACKFILLING
06STCONN STORM WATER - CONNECTION TO EXISTING LINE
06STDIPIPE DI DRAIN PIPE LAYING
06STEXC STORM WATER LINE - EXCAVATION
6
06STINGRT BASE SLAB DRAINAGE - INLET GRATES
06STLTCONN STORM WATER LATERALS - CONNECTION TO EXISTING LINES
06STLTEXC STORM WATER LATERALS - EXCAVATION
06STLTINLET STORM WATER LATERALS - CONSTRUCTION OF INLETS/CATCH BASINS
06STLTPIPE STORM WATER LATERALS - PIPELAYING
06STMHCN STORM WATER - MANHOLE CONSTRUCTION
06STNDDR STORM WATER - NDRC DRIVING
06STPIPE STORM WATER LINE - PIPELAYING
06STREMO STORM WATER - REMOVE EXISTING LINES
06STTEST STORM WATER LINE - TESTING
Sub-Total
07AWTDUCT WATER DUCT
07AWTPROT PROTECTION OF WATER LINE
7A
07AWTSLEEVE GRP SLEEVE FOR WATER LINE
Sub-Total
07BASBUILT WATER LINE - AS BUILT DOCUMENTATION
07BDAYWORKS WATER LINE - DAYWORKS
07BWTBFILL WATERLINE - BACKFILL / REINSTATEMENT
07BWTBOX WATER LINE - TWIN BOX CULVERT
07BWTCP WATER LINE - CORROSION PROTECTION
07BWTCSPL WATER LINE - CS PIPELINE ACROSS TUNNEL
07BWTDUCT WATER DUCT CROSSING TUNNEL
07BWTEXC WATER LINE - TRENCH EXCAVATION
07BWTHOUSE WATERLINE - HOUSE CONNECTION
7B
07BWTLOCA WATER LINE - EXCAVATE TO LOCATE
07BWTNDRC WATER LINE - NDRC DRIVING
07BWTPL WATER LINE - PIPELAYING
07BWTPROT WATER LINE - PROTECTION SLAB
07BWTREMO WATER LINE - REMOVAL OF EXISTING WATER LINES
07BWTSHUT WATER LINE - SHUTDOWN & CONNECTION TO EXISTING LINE
07BWTUTIL WATERLINE THROUGH UTILITY BRIDGES
07BWTVAC WATER LINE - CHAMBER
Sub-Total
08BF Box Beam Fabrication
08BI Box Beam Installation
8
08GF I-Girder Fabrication
08GI I-Girder Installation
Sub-Total
09GUIDSIGN GUIDE SIGN PANELS
09RDMARK ROAD MARKING
9
09RDSTUD ROAD STUDS
09SIGN TRAFFIC SIGNS
Sub-Total
10LAB1 S/Laboratory Set-Up
10LAB2 S/Laboratory Maintenance
10
10LAB3 S/Laboratory Removal
Sub-Total
11BP Bored Pile
11PH P/Head Treatment
11
11PLT Pile Load Test
Sub-Total
15AIRDUCT IRRIGATION DUCT
15AIRPROT PROTECTION OF IRRIGATION LINE
15AIRSLEEVE GRP SLEEVE FOR IRRIGATION LINE

May

Jun

Jul

2,215,971

Aug

4,415,636

4,015
995,270
1,081,201

1,310,445

3,161,186
595,092

26,690
8,098,242
97,547
5,550,167

447,983
282,847
1,499,113
14,781
41,879
3,162

2009
Sep
1,374,847
610,408
7,736,196
256,758
351,532
152,003
100,858

Oct
3,780,828

44,681
7,166,526
105,676
3,531,924
1,417,444
865,984
1,139,442
305,736
872,872
192,154

46,886
6,723,756
97,547
1,946,162
2,227,412
1,360,832
1,100,475
310,641

3,162

2,919

4,165,644
403,476
966,712
418,009
242,058

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

161,372
10,316

11,027

11,027

9,960

11,027

10,671

11,027

10,671

11,027

105,676

89,418

101,612

97,547

105,676

105,676

105,676

105,676

101,612

178,374
3,162

172,170
2,676

58,941
3,041

2,919

3,619
3,162

178,965
3,162

28,363
2,554

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

11,027

10,671

11,027

10,671

11,027

11,027

9,960

11,027

10,671

11,027

10,671

11,027

11,027

10,671

7,826

162,592

243

167,206
3,162
3,549,126

411,346
3,162
4,194,421

319,638

319,638

295,050

319,638

270,463

307,344

295,050

319,638

319,638

319,638

319,638

307,344

331,932

295,050

319,638

295,050

307,344

319,638

282,756

331,932

307,344

331,932

319,638

307,344

331,932

243

5,935,465

12,415,496

20,138,327

26,547,841

24,250,999

778,538

545,754

481,965

405,476

443,122

618,112

467,258

435,985
1,061

419,983
26,524

342,959
28,646

305,721
25,463

330,665
27,585

305,721
25,463

318,371
26,524

330,665
27,585

292,716
24,402

342,959
28,646

318,015
26,524

342,959
28,646

330,309
21,219

318,371

342,959

196,700
259,862
467,233

49,498
57,324

116,233

137,367

137,367

147,933
24,036
1,723,211
33,857,749
1,912,161
3,752,636
5,760,030

74,941
1,723,211
34,118,739
3,447,425
4,165,163
5,974,327

59,352

96,838

96,838

149,015
1,789,488
9,291,501
2,282,029
1,522,661
7,547,307
352,387
143,607

101,788
1,590,656
6,314,303
2,392,483
554,002
7,736,922
313,233
127,651
9,436

37,699
1,723,211
3,532,207
1,372,150
470,186
9,668,860
339,335
138,288

198,832

25,508

75,947
1,656,933
12,626,066
3,520,888
2,270,294
8,137,412
326,284
132,969

830,434
41,487
7,164,832
313,233
127,651
10,020

55,362

1,063

54,835
1,723,211
22,995,531
4,362,429
4,181,855
6,624,924
13,051
120,751
42,921

1,723,211

32,425,297
726,035
988,046
442,528

62,512
1,723,211
33,823,306
2,887,278
2,406,044
5,472,983

100,303
1,656,933

29,472,168
300,726
304,266

55,726
1,060,437
31,142,589
2,674,974
2,320,519
821,837

69,481
1,590,656

34,434,491

3,415,426
326,284
120,493
31,732

163,887
339,335
71,635
561,731

300,181
12,754
286,419

3,861,237

3,989,945

3,989,945

3,861,237

3,989,945

2,059,326

592,344
1,556,732

541,570
89,516

234,978

234,978

187,983

751,931

8,223
8,223
98,795
162,674
261,469
613,790

55,508
55,508

49,341
49,341

10,279
10,279

1,489,140
1,489,140
292,891

424,601
424,601
465,744

2,195,868
8,064,037

22,374
123,249
94,152
598,517
972,094
2,424,176
6,253,856

199,629
101,684
211,343
4,061,405
4,866,952
1,851,239

56,417
90,386
135,410
3,945,201
4,693,158
252,971

7,532
135,698
933,785
1,077,015

1,948,850

1,851,239

252,971

82,475

187,645

6,982,742
215,384
3,732,529
41,287

5,380,302

1,608,645

3,989,945
136,907

3,989,945
105,001

3,603,821
96,869
604,230

804,769

3,621,462

354,688
3,621,462

30,842

3,989,945
43,951
2,215,511

3,861,237
148,908

3,989,945
86,335

234,978

3,064,119

4,048,498

220,010
3,784,508
156,652

402,385

9,221,316

11,702,687

9,103,953

9,405,742

2,414,308

67,137

352,387

326,284

352,387

261,027

914,137

272,845

949,468

261,451

1,199,702

923,994

1,005,962

819,672

640,835

506,707

491,803

116,233

137,367

219,842

335,578

46,211,202

43,205,776

44,262,710

42,437,352

52,684,093

51,774,169

65,962,359

59,732,991

46,028,385

38,651,404

26,050,189

22,588,684

13,391,555

6,973,997
21,969

3,075,367
28,564

2,394,191
218,959

1,936,005
204,142

1,132,360
578,681

4,495

8,991

21,969
56,017
22,477
45,722
163,175
94,152
53,702

28,564
52,816
94,403
24,563
19,095
97,918
3,465

218,959
469,746
256,236
204,531
285,556
86,620
107,404

204,142
374,516
74,174
178,995
903,538
101,684
450,403

578,681
757,835
202,292
35,588

1,822,304
330,601
385,505
716,106
710,087
186,558
334,562
376,691
101,684
1,257,664
138,871
3,106,117
7,152,709

26,972

4,495

71,556

4,495

8,991

26,972

71,556

94,881

4,214,659

6,014,783

26,805,865

37,459,928
168,761
2,310,755

21,342,720
522,574
701,244

24,319,181
298,084
1,810,121
175,970

2,631,792
151,252

1,784,779
1,149,518
90,751

574,759
862,139
756,262

2,664,601
273,245
5,335,099
425,318
38,527,690

7,898,540
309,424
2,819,189
85,064
54,076,709

9,651,706
621,653
3,228,982
109,674
38,371,713

1,709,152
453,757
1,104,143
76,035
6,471,440
888,531
6,937,305
2,534,488
46,778,207

42,549,533
288,758
1,397,855
586,567
1,079,636
1,618,401
552,071
529,383
912,424
6,850,792
753,354
8,303,979
2,747,863
68,170,616

50,015,954
509,990
1,593,833
606,119
3,508,816
1,981,407
1,096,580
506,696
669,111
15,552,414
1,081,124
11,058,056
2,101,965
90,282,065

57,828,397
587,741
3,772,748
586,567
4,909,490
3,342,678
907,514
1,051,204
767,957
15,221,546
1,576,249
8,244,037
4,138,867
102,934,995

240,518

453,757

1,730,783

79,407

1,796,588

4,079,566

3,771,853

2,183,697

90,386

729,445

293,134

4,926,206

729,445

4,507,793

13,125,529

435,245
393,929
55,387,195
865,657
4,088,450
606,119
7,547,616
847,014
1,724,278
1,020,954
1,034,081
19,478,217
1,771,795
5,039,374
5,175,206
104,979,885

4,270
30,625
711,400

1,291,124

926,093

1,350,541

1,222,284

1,289,518

1,465,361

2,245,047

1,121,719

160,590

65,450

253,618

130,900

171,806

1,089,702

1,311,935

1,299,931

1,225,873

139,081
111,372
1,503,270

188,168
537,098
1,614,918

360,024
710,435

32,725
395,278
181,919

1,768,769
2,068,015
2,202,099

1,747,586
1,809,513
2,306,125

1,493,392
2,507,468
2,212,991

1,567,532
956,457
2,584,601

1,302,746
568,704
2,306,687

921,455

264,786

4,358,628
2,868,884

1,154,466
4,740,637
3,285,663

1,376,886

6,281,595
49,330

3,218,940

1,638,304

379,353

7,121,732

11,241,317

15,833,157

12,255,406

11,077,835

9,889,729

7,627,988

6,092,450

6,936,010

3,630,218

1,254,061

321,030

52,957

373,987

13,219
-

514,396
410,210
69,291
65,450
331,735
106,327
666,994
127,097

336,521
192,620

338,926

484,762

536,573

2,780,532

1,404,640

13,219

16,668

21,915

21,915

20,229

21,915

18,544
179,859

21,072
287,495

20,229
256,861

21,915
405,130

21,915
504,763

21,915
419,070

21,915
417,370

8,429
352,816

467,633

35,972

562,294

726,868

664,391

867,060

811,147

1,074,849

1,178,091

772,752

771,228

79,239

179,582

191,789

180,617

206,271

200,924

206,757

201,800

192,731

158,801

1,410,093
2,009,896
26,431,098
712,907
3,296,344
547,463
11,001,860
2,078,208
1,017,929
484,008
1,284,997
14,304,805
1,695,522

2,083,310
2,666,254
4,207,983
994,306
3,340,528
195,522
11,872,550
235,954
1,335,559
960,453
912,424
13,751,926
2,046,899

550,663
272,943

14,606

10,687,950

12,973,572

5,815,086

406,869
1,771,624

494,230

4,722,664
69,587,701

6,224,192
48,744,550

5,944,058
27,679,914

5,456,176
28,230,220

2,128,735
16,502,088

8,202,706

34,025
53,380
88,472
7,624

144,605
183,627
78,264
17,536

5,316
8,541
57,847
20,585

60,607
89,678

85,062
136,653

57,787
122,542

16,643
37,598

85,944

165,750

153,472

165,750

42,972

179,541
194,934
850,417
26,479

147,262
1,514,803
418,221
3,555,911

458,149
1,494,590
783,279
5,561,062

212,712
820,062
275,742
2,134,936

196,349
332,091
117,669
887,380

8,684,545
590,586
109,204
311,863
1,011,653

3,666,753
464,302
70,121
335,985
870,408
2,874

1,587,730

5,133

2,258

254,194
204,267

150,074

62,531

208,436

1,348,532
57,459
13,219
151,624
222,302

2,645,443
57,459
13,219

3,696,631
504,854
74,144
427,304
1,006,302

7,731,094
485,209
132,195
882,176
1,499,580

1,528,065
297,608
54,602
523,792
876,002

5,939,954
194,477
135,643
296,356
626,476

390,745

345,659

405,774

345,659
204,193
1,047,930
711,879
38,482
80,303

172,330
15,029
137,145
534,550
353,322
6,621

73,719

68,048

31,189
297,905

2,789,471
2,543,946
170,700

1,299,948
2,784,109
193,978

2,209,911
2,594,351
186,219
34,475
551,939

2,534,898
3,409,718
201,737
484,626
827,908

1,299,948
3,142,870
201,737

47,817

165,466

297,371

274,496

552,746

348,667
6,793,063

569,489
6,074,748

2,243,088
8,942,081

1,851,807
10,811,070

1,102,819
7,838,062

1,322,350
8,984,284

929,778
7,214,980

1,115,733
7,530,222

2,611,811
116,387
553,532
517,443
61,171
581,111
5,839,117

69,832

25,458

43,082

201,737

39,166

186,219

9,791
231,142

25,458

43,082

39,166

240,933

1,271,157
1,271,157

3,177,893
3,177,893

317,789
317,789

201,737

551,939

4,512,687
201,737
397,011
827,908

4,264,289
201,737

2,991,327
193,978
246,639
1,655,817

67,761

322,847
611,379

880,427

3,156,346

94,879
365,391
1,138,374
63,831
348,667
2,031,474

505,206
989,790
1,494,996

63,241
551,939
69,150
684,330
1,070,655
15,661,398
936,006
17,668,059

63,831

454,664

18,655

61,030
73,719

278,304
1,355,222
714,732
1,148,860
1,483,308

196,571
101,304
629,836
474,511
1,754,270
487,334
3,183,506
185,350

70,678

285,336
391,855
130,366
41,344
1,040,674
97,918
493,711

292,260
2,678,148
48,240,304
1,092,563
3,400,034
606,119
11,249,645
2,707,418
453,757
1,716,715
1,399,051
19,108,546
1,914,696
3,039,593
4,132,129
101,738,718

513,862
69,914
510,798
16,362
620,665
242,781
1,402,077
74,140

70,664

36,859

172,391
1,262,258
5,243,874

540,570
178,352
199,877
32,725
406,643
116,960
458,558
476,614

35,670

16,668

10,958

548,048
89,176
186,552

85,070

94,152

543,697
285,336

233,146
184,182
41,875

1,633,134

86,727

83,515

9,636

35,954
1,103,878
71,810
609,521
2,434,854
178,443
1,322,900

608,048

320,420

551,485

69,150

61,171

71,810

134,495
2,676,637
721,582
15,156,192
2,732,658
21,287,069

66,491
185,956
1,566,323
2,765,859
721,582
15,661,398
3,193,872
22,342,711

66,491
506,212
3,552,634
2,676,637
841,846
6,062,477
4,404,586
13,985,546

1,394,121
2,765,859
741,626
15,661,398
2,853,803
22,022,686

1,287,257
2,498,195

3,694,960
2,765,859

14,145,779
2,554,992
19,198,966

15,661,398
3,400,271
21,827,528

2,489,420
3,990,763

10,767
13,716
23,074
47,557

30,956
40,538
121,137
192,631

40,378
50,292
215,739
306,409

69,150

63,831

2,396,721

399,020

2,258

1,073,570
1,073,570
251,359
33,648
42,672
92,295
419,974

251,359
89,167
110,338
262,464
713,328

377,038
217,030
258,949
548,001
1,401,018

335,145
115,076
158,931
213,432
822,584

41,893
10,767
13,716
28,842
95,218

3,365
4,572
74,990
82,927

20,766
20,766

53,837
68,275
144,211
266,323

301,490

311,540

311,540

281,391

311,540

301,490

311,540

301,490

311,540

311,540

301,490

311,540

301,490

311,540

311,540

281,391

311,540

301,490

311,540

301,490

311,540

301,490
3,376,102

311,540
3,626,769

311,540
4,093,778

281,391
3,931,337
8,492

311,540
4,257,529
27,153

301,490
4,256,874
51,161

311,540
4,294,282
45,722

301,490
4,251,998
36,660

311,540
2,654,078
76,335

311,540
1,185,932
76,852

301,490
646,770
44,063

311,540

301,490

311,540

311,540

281,391

311,540

301,490

311,540

301,490

311,540

241,258
2,357
243,615

18,893
18,893

2,367
2,367

85,831

47,491

31,968

17,096

3,376,102

3,626,769

4,093,778

3,939,829

4,284,682

4,308,035

4,340,004

4,288,658

2,730,413

1,262,784

690,833

85,831

47,491

1,189,448
314,725
171,651

565,101
122,712
818,643

400,883
306,274
303,690

1,142,437
243,396
264,078

434,049
157,194
211,263

14,705

17,096
300,099
149,756
369,710

14,705

31,968
170,013
44,116
67,906

37,524

14,705
169,765

Period Total
5,155,675
10,403,200
12,496,932
660,234
1,318,244
570,013
504,288
256,110
122,272
22,983,795
1,219,341
12,109,454
3,644,856
2,226,816
2,687,900
899,224
3,682,431
369,527
1,240,864
36,490
7,743,547
7,990,944
309,360
98,631,517
318,289
538,900
806,283
19,883,200
284,033,946
26,764,373
22,977,158
68,931,274
3,915,408
1,275,396
3,340,160
13,971,689
485,504
48,909,000
659,258
1,353,924
15,508,576
1,723,175
385,530
50,298,084
5,588,676
123,352
571,791,155
1,767,047
2,461,920
4,228,967
4,185,297
1,011,458
887,680
3,168,025
1,129,824
3,447,317
10,223,746
24,053,347
36,566,914
404,817,600
6,606,611
26,225,373
3,910,447
82,595,072
19,965,319
9,982,659
9,982,659
10,036,667
133,834,176
14,870,464
59,954,400
45,926,400
865,274,761
11,911,110
404,044
636,290
340,278
45,745
9,635,301
613,888
981,747
4,374,770
12,127,936
1,615,009
1,603,520
7,490,070
2,743,248
18,700,842
13,133,377
23,291,016
24,699,619
134,347,810
2,651,954
632,236
2,929,100
6,213,290
10,265
252,868
3,567,058
1,502,866
8,082,405
2,089,508
7,459,028
1,764,375
321,210
283,533
10,432,079
29,501,471
2,327,733
3,109,338
7,727,144
797,888
11,715,197
90,943,966
17,398,143
4,349,536
98,515,248
24,628,968
144,891,895
1,256,794
604,991
762,000
1,744,951
4,368,736
117,497
6,884,091
23,616
7,025,204
36,575,451
548,823
4,766,839
41,891,113
4,202,030
1,419,813
2,376,706

A8. Monthly Cost Distribution based on Resources


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
2008
Bill No. Resource ID
15BCONTROL IRRIGATION - INSTRUMENT CONTROL PANEL
15BINSTRCABL IRRIGATION - INSTRUMENTATION SIGNAL/POWER CABLE
15BIRBFILL IRRIGATION LINE BACKFILLING
15BIRCONN CONNECTION TO EXISTING IRRIGATION LINE
15
15BIRREIN IRRIGATION LINE - REINSTATEMENT OF PAVEMENT
15BIRREM REMOVAL OF EXISTING IRRIGATION LINE
15BIRRPL IRRIGATION LINE - EXCAVATION & PIPELAYING
15BIRVAC IRRIGATION VALVE CHAMBER
15BMARKER IRRIGATION LINE - MARKER PLATES
15BPROVIS IRRIGATION LINE - PROVISIONAL ITEM
Sub-Total
16AEL1 Civil Works for Electrical Service
16AEL2 Survey and Installation of Anchoring, Supporting for Tunnel
16AEL3 Installation of Cable Tray and Conduit for Tunnel
16A 16AEL4 Installation of Control and Power Cables for Tunnel
16AEL5 Installation of Street Lighting
16AEL6 Installation of Tunnel Elec Fixture
Sub-Total
16BAD1 33KV / 11KV / LV : Deep Direction Drilling for HDD
16BAD2 33KV XLPE Cable Relocation
16B 16BAD3 11KV XLPE Cable Relocation
16BAD4 LV XLPE Cable Relocation
Sub-Total
16CTR1 132 KV XLPE Cable : Deep Direction Drilling for HDD
16CTR2 132 KV XLPE Cable : Excavation & Protection for Exist. 132 KV
16C
16CTR3 132 KV XLPE Cable Relocation
Sub-Total
17TCS1 Civil Works for TCS
17TCS2 TCS program
17TCS3 Installation of TCS Cable
17
17TCS4 Installation of TCS equipment in the Structures
17TCS5 Installation of Tunnel VMS, CCTV, LSCS
Sub-Total
18DAY Daily Works
18
Sub-Total
19ATEDUCT TELEPHONE DUCT
19ATEPROT PROTECTION OF TELEPHONE LINE
19A 19ATEPULL TELEPHONE PULL BOXES
19ATESLEEVE PVC SLEEVE FOR TELEPHONE LINE
Sub-Total
19BTELADJ TELEPHONE LINE - ADJUST MANHOLE COVER & FRAME
19BTELBILL2 BILL No.2 - STORES CIVIL ACCESSORIES
19BTELBILL4-1 BILL No. 4 - STORES CABLE - CABLE F.O.
19BTELBILL4-2 BILL No. 4 - STORES CABLE - CABLE F.O.
19BTELCONC TELEPHONE LINE RELOCATION - CONCRETE WORK
19BTELDUT1 TELEPHONE DUCT - EXCAVATION & LAYING
19BTELDUT2 TELEPHONE DUCT THROUGH UTILITY CROSSING
19BTELEXC TELEPHONE LINE RELOCATION - EXCAVATION
19BTELFILL TELEPHONE LINE RELOCATION - FILLING
19B
19BTELSLEW TELEPHONE LINE - SLEW/LOWER EXISTING DUCT
19BTHDUCT THRUST BORING - TELEPHONE DUCT LAYING
19BTHRUST TELEPHONE LINE - THRUST BORING
19BTLCABLE TELEPHONE LINE CABLELAYING
19BTLDTBK TELEPHONE DUCT - BACKFILLING
19BTLMH TELEPHONE MANHOLE - CONSTRUCTION
19BTLREIN TELEPHONE LINE - REINSTATEMENT WORKS
19BTLTEST TELEPHONE LINE -TESTING & COMMISSIONING
Sub-Total
20ASWDUCT SEWER DUCT
20A 20ASWPROT PROTECTION OF SEWER LINE
Sub-Total
20BSHTPILE SHEET PILE LEFT IN PLACE
20BSWABAN ABANDONING EXISTING SEWER LINE
20BSWEXC SEWER LINE - EXCAVATION
20BSWFILL SEWER LINE BACKFILLING
20BSWFUTCONN SEWER FUTURE CONNECTIONS AT MANHOLES
20BSWMHCN SEWER MANHOLE CONSTRUCTION
20BSWMHEX SEWER MANHOLE EXCAVATION
20B
20BSWMHFL SEWER MANHOLE BACKFILLING
20BSWNDRC NDRC FOR SEWER PIPES
20BSWPIPE SEWER PIPELAYING
20BSWPUMP OVERPUMPING SEWAGE
20BSWREIN REINSTATEMENT OF SEWER LINE
20BSWTEST SEWER LINE TESTING
Sub-Total
21PUBTELE PUBLIC TELEPHONE BOOTH FOUNDATION
21
21REBUS REMOVE EXISTING BUS SHELTER
Sub-Total
24ME1 Survey and Installation of Anchoring, Supporting
24ME10 Installation of Fire Fighting Pump and Misting Pump
24ME11 Installation of Lift at Stru. No. 20
24ME12 Installation of Utility Building Piping
24ME13 Installation of Misc. Mech. Fixture
24ME14 Plumbing & Sanitary Installation (Architectural Works)
24ME15 Individual Fan, Pump, Lighting, FAS, Control Testing
24ME16 Individual Zone Testing & Commissioning
24
24ME2 Installation of Main Misting and Fire Landing Valve Pipe
24ME3 Installation of Steel Frame for Duct and Smoke Dampers
24ME4 Installation of Tunnel Fire Rated Duct
24ME5 Duct Pressure Testing
24ME6 Installation of Mech. Fixture
24ME7 Installation Tunnel Ventilation Fan and Control Panels
24ME8 Installation Tunnel Dampers and Sound Attenuator
24ME9 Installation of Drainage Pumps and Piping
Sub-Total
25FP F/Protection & Finishes
25
25LF Landscape & Furnitures
Sub-Total
26MIL Military Communication System
26
Sub-Total
27SCA1 SCADA program
27SCA2 Installation of SCADA Cable
27
27SCA3 Installation of SCADA equipment in the Structures
Sub-Total
30QUAN QUANTITY
30REV REVENUE
Grand Total

May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov
35,622

203,701

26,056
26,056

203,701

79,105
143,128
211,230
585,795
906,244

1,925,502

65,347
199,106
361,626
442,587
604,163

1,672,829

283,008

48,151
147,414
701,284
596,700
641,923

2,135,472

1,253,321

13,757
93,514
212,920
584,355
339,842

1,244,388

1,132,032

37,833
216,900
619,745
358,722

1,233,200

1,253,321

17,197
175,338
253,476
619,098
339,842

1,404,951

1,212,891

13,757
214,302
493,433
611,839
207,681

1,527,255

337,546

1,265,799

283,008
1,307,992
3,599,620

1,253,321
1,307,992
6,922,346

1,132,032
1,181,413
6,645,452

1,253,321
1,307,992
7,199,240

1,212,891
1,265,799
7,199,240

1,010,740
158,931
70,907
115,225
1,355,803
886,068
3,876,514

10,139
628,011
264,321

930,933

55,029
234,433

27,515
385,094

13,757

543,019
509,762
27,132

628,034
245,441
33,298

1,384,080

1,319,382

27,515

13,757

60,188

8,598

13,757

98,764
113,281

160,492
188,801

98,764
254,881

9,440

74,073
113,281

203,872
2,201,565
1,738,186

239,328
2,443,933
4,679,734

62,048
1,486,728
5,014,000

1,667,949
5,415,119

1,003,617
4,813,440

2,974,973

133,707

2,634,357
2,410,250

3,761,322
3,678,803

3,725,097
2,417,712
182,727
6,089,217
17,428,753

3,317,011
3,671,341
2,165,314
9,069,952
23,638,737

2,363,743
1,779,705
3,677,380
19,034,125
31,668,393

1,108,682
749,939
3,348,472
5,748,561
13,930,627

677,679

195,171

1,589,724
6,062,119
8,463,229

7,095,699
7,290,870

165,783

38,129

497,524
226,561
29,599

32,065

1,233

804,965

197,848

259,454
200,560

150,688
1,015,271
1,370,493

230,464
1,413,880
1,738,187

650,572
134,317

309,796
761,132

2,053,431
1,567,036

2,948,999
2,977,368

1,660,695
8,443,488

784,889

1,271,488

4,990,960

7,664,554

4,132,195
1,818,777
2,995,841
8,946,813

3,337,542
967,887
2,419,718
6,725,147

3,337,542
1,013,977
2,419,718
6,771,237

3,337,542
1,290,516
2,664,134
7,292,192

4,132,195
1,597,782
3,631,324
9,361,301

1,447,123
3,351,991
4,799,114

1,305,979
837,995
2,143,974

958,669

890,070

1,157,606

1,071,858

1,157,606

1,597,782

872,635

663,694

553,078

958,669

890,070

1,157,606

1,071,858

1,157,606

1,597,782

872,635

663,694

553,078

12,637,718
12,637,718
1,014,745

9,141,247
9,141,247
1,055,334

5,646,709
5,646,709
933,565

1,095,924

1,014,744

1,095,924

1,055,334

486,908

6,269,505
102,547

4,011,435
134,391

143,709

133,968

121,038

137,744

98,264

5,201,160
44,874
44,874
34,365
129,232

1,077,274
40,531
40,531
107,686
287,163

1,229,892
44,874
44,874
28,023
110,041

1,233,668
44,874
44,874
70,949
220,962
26,439
113,057
431,407
6,372

1,153,598
43,426
43,426
137,804
141,733
15,668
197,849
493,054

57,850
2,464,031
3,008,789
44,874
44,874

38,161
11,088,139
11,126,300
44,874
44,874

27,707
14,784,185
14,811,892
43,426
43,426

2,464,031
2,464,031
13
13

98,561

7,826,865

8,507,232

8,465,039

4,762,582

4,245,871
4,245,871

6,620,904
6,620,904

542,979

601,156

581,764

601,156

581,764

601,156

601,156

581,764

601,156

11,570

15,833

6,010,563
6,010,563
771,374
96,891
4,765,869
48,966

593,334
43,426
43,426

616,989
44,874
44,874

5,683,100
43,426
43,426

33,452

13,205

7,386,797
44,874
44,874
27,331
39,615

33,452
10,620

18,407

74,025
87,230
16,991

29,610
96,556
17,699

310,906
474,503
18,407

51,818
446,667
16,283

368,481
506,545
19,115

1,135,782
43,426
43,426
78,187
274,662
1,958
408,783
763,590
17,699

40,584

150,740

139,145

144,943

150,740

133,347

156,538

144,943

8,741

91,494

53,539

101,041

719,773

306,710

419,236

685,819

505,104

70,140

35,070

40,080

100,200

70,140

31,523
1,062,560
176,603
148,351
324,954

52,538
623,510
77,850
69,174
147,024

84,060
807,059
116,774
171,337
288,111

117,334
1,008,286
167,232
137,283
304,515

15,761
651,388
55,504
88,329
143,833

77,056
77,056

30,134

9,475
9,475

368,450
44,874
44,874

581,764
43,426
43,426

601,156
44,874
44,874

581,764
43,426
43,426

601,156
44,874
44,874

601,156
44,874
44,874

542,979
40,531
40,531

601,156
44,874
44,874

581,764
43,426
43,426

601,156
44,874
44,874

58,978
345,945

70,773
754,790

76,671
817,689

64,875
691,891

73,722
786,240

70,773
754,790

76,671
817,689

76,671
817,689

20,642
503,193

41,216
95,405

123,647
108,823

133,951
117,699

113,343
93,507

128,799
121,168

123,647
108,488

133,951
103,657

133,951

97,888

39,930
4,489
22,193

47,916
5,387
38,045

51,908
5,836
41,215

43,923
4,938
34,875

49,912
5,611
39,630

47,916
5,387
38,045

51,908
5,836
41,215

51,908
5,836
41,215

13,975
1,571
20,608

85,721
245,817

245,735
1,114,596

192,016
1,444,597

983,269

821,973

952,626

1,144,902

326,634

35,070

275,549
557,172

130,260
226,996
77,055
2,464,932

70,140
288,904
28,020
2,414,119

100,200
123,816
42,031
2,367,719

75,150
515,900
2,966,879

1,804,716

581,764
43,426
43,426

601,156
44,874
44,874

13,205

13,205

13,205

13,205

1,351,536

1,351,536

4,227,651
2,884,716

7,112,367

2,833,944
120,200
18,104
2,443,776
3,053,361
293,635

8,763,020

657,877

10,812
17,027
27,839

21,625
21,625

51,204
10,812
21,284
32,096

68,368

91,157

169,147

156,136
4,325
17,027
21,352

162,642
30,275
17,027
47,302
325,939

19,599

177,888
85,058
111,316
196,374
1,629,693
84,320

1,818,970
96,160
78,699

912,336
88,147
106,156

1,588,985
104,173
52,725

1,438,830
104,173
90,544

1,134,718
40,067
93,319

248,263
342,126
24,040
28,967

3,135,962
957,504
261,952

2,522,171
191,501
151,620

2,715,584
239,376
199,847

2,543,549
909,629
168,125

461,061
957,504
139,972

1,436,256
74,942

1,053,255

155,436

3,382,732
875,432
197,071

12,001,438

6,391,980

8,737,565

8,053,298

6,449,064

5,530,425

4,702,332

4,788,354

4,909,006

2,527,872

3,366,459

1,151,249

1,613,694
56,093
77,071
5,683,610
4,415,534

8,023,953

8,572,356

8,851,999

124,131

17,117

204,187

38,981

61,549

63,601

61,549

5,935,465

12,631,060

38,981

22,207,704

221,545
221,545
63,601

791,232
791,232
63,601

759,583
759,583
57,446

822,881
822,881
63,601

60,383

97,994

1,944,416
136,227
106,742
2,237,642
3,169,562
273,573
185,136

1,054,888
112,187
39,274
4,027,755
3,171,595
255,335
190,965

1,140,420
120,200
50,135
2,908,934
3,677,476
656,574
139,615

992,165
24,040
93,264
4,475,283
2,400,864
319,168
267,572

1,037,782
56,093
84,362
1,745,360
2,734,471
492,431
241,481

1,647,907
72,120
189,271
2,493,953
3,187,728
280,868
152,106

601,156
44,874
44,874

350,812

44,211

243

2,043,933
2,043,933

601,156

9,623,517
21,743,376

8,230,338

Oct

601,156

Sep

4,907,612

Aug

581,764

Jul

1,265,799

3,342,433

Jun

337,546

974,764

May

601,156

Apr

Mar
185,489
149,610

581,764

Feb
158,010
163,859

Jan
178,619
185,232

368,450

155,310
41,272
21,015
3,099,179

Dec
164,880
178,108

822,881
822,881
61,549

822,881
822,881
63,601

822,881
822,881
61,549

664,635
664,635
63,601

664,635
664,635
63,601

664,635
664,635
61,549

822,881
822,881
63,601

57,446

63,601

61,549

63,601

61,549

63,601

63,601

61,549

526,751
590,352

40,416,884

611,977
48,978,767

1,136,528
83,930,002

961,678
85,983,496

1,092,815
91,501,860

1,049,103
90,497,948

1,136,528
109,301,398

1,136,528
105,983,572

1,136,528
145,239,267

1,136,528
150,316,981

1,092,815
113,715,510

1,180,241
109,735,549

1,049,103
121,443,650

1,136,528
158,561,437

1,049,103
166,888,151

82,462

33,634

5,935
133,715

952,722

919,293

1,168,988

1,355,523
645,710
815,162
53,447,286
18,434,526
6,620,832
25,055,358

1,190,884
493,163
43,475
41,197,030
30,838,651
9,482,261
40,320,912

1,306,515
204,883
213,147

2,239,741

2,231,766
1,154,546
739,080
56,257,786
5,835,579
4,220,746
10,056,325

17,409,241
26,190,207
7,908,750
34,098,957

3,005,779
22,348,285
6,964,094
29,312,379

2,204,172
19,388,698
4,731,519
24,120,217

1,730,039
1,730,039
-

747,280
2,859,921
768,906
3,628,827

63,601

43,312
589,011

1,794,559
1,244,402
858,638
44,645,313
572,116
2,224,336
2,796,452

416,753

63,601

1,642,987
35,583
136,125
3,310,243

9,206,572
536,595
22,176,191

43,113

61,549

30,134

3,417,417
62,271
436,218
3,628,309

19,000,789
987,822
23,029,122

685,994
511,971
152,164
3,862,238
5,339,746
329,531
5,669,277

63,601

2,825,941
120,094
386,718
4,246,771

24,485,562
914,650
21,323,261

475,622
271,658

61,549

1,577,269
111,198
875,530
2,844,924

16,650,184
682,939
15,253,788

265,251
151,502

6,309,076
115,646
887,905
848,176

1,175,307
48,781
1,083,834

27,440
15,673

31,649
31,649
10,251
1,460,705
983,930
2,454,886

99,012
47,373
146,385

121,954
10,437,804

919,293

1,921,980
1,933,076
3,855,056

1,230,067
2,982,059
4,212,126

2,968,055
2,968,055

4,709,586
4,709,586

4,494,458
4,494,458

2,973,386
2,973,386

2,266,654
2,266,654

1,115,123
1,115,123

703,660
703,660

581,414
581,414

1,092,815
176,199,647

1,136,528
172,325,876

1,005,390
138,884,606

1,180,241
163,083,822

1,092,815
150,324,785

1,180,241
163,060,697

1,136,528
150,262,429

1,092,815
85,906,814

1,180,241
64,899,230

1,049,103
57,392,428

174,850
8,574,362

Period Total
686,998
712,430
495,264
2,013,140
2,244,108
6,992,503
5,324,186
123,327
886,400
27,476,905
28,078,399
23,745,862
20,147,603
10,963,617
66,427,819
149,363,300
6,145,314
18,435,947
18,435,947
18,435,947
61,453,155
8,860,603
35,442,410
44,303,012
88,606,025
8,523,852
8,726,383
15,046,809
1,071,747
30,800,385
64,169,176
1,171,068
1,171,068
484,344
1,276,476
44,065
1,554,528
3,359,413
141,595
589,775
6,289,916
1,159,541
1,030,395
748,747
315,198
399,296
44,891
317,042
523,472
9,671,058
1,157,307
2,104,872
546,392
25,039,497
756,871
798,156
1,555,027
1,955,632
405,648
372,394
19,501,181
1,153,920
1,125,750
31,595,499
43,456,365
9,192,041
2,525,840
111,284,270
129,146
56,848
185,994
15,772,691
444,793
2,969,995
15,549,897
39,569
2,005,731
70,518,414
3,292,742
93,304,000
4,715,244
8,231,923
4,701,770
2,608,519
224,155,288
131,807,728
44,981,014
176,788,742
7,912,320
7,912,320
923,228
4,612,752
26,238,152
31,774,132
26,227,569
2,994,183,642

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 9
All Resources Histograms

SAMSUNG-SAIF BIN DARWISH JV

-9-

A9. All Resourses Histograms (Direct Labour)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

( Unit : Number)

2008

Resource ID

May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Period Total

Nov

1BOFICE3 DRAUGHTSMAN

1FAOPER OPERATOR

15

33

40

48

76

112

127

137

134

157

162

180

185

164

165

151

206

211

215

214

199

185

193

189

117

85

41

28

17

3,789

1FHDD H D DRIVER

11

27

40

39

52

57

71

77

75

79

89

88

80

70

69

60

63

54

58

57

58

41

37

49

26

29

22

16

10

1,502

1HFORE2 FOREMAN

13

16

21

29

50

54

55

59

65

65

73

76

72

68

74

107

120

137

145

141

162

160

152

111

60

32

22

2,148

1HFORE3 CHARGEHAND

12

13

10

162

1JMASON MASON

13

22

21

24

28

42

44

46

45

44

32

31

33

28

18

23

25

19

21

20

22

12

25

29

20

21

13

734

1KCARP CARPENTER

13

23

21

28

35

60

65

62

65

77

64

88

107

93

92

135

252

325

433

435

390

422

359

294

186

81

42

18

4,276

1LLABOUR LABOUR ( Common Labour )

95

178

188

228

261

369

392

414

421

445

444

470

450

431

427

453

595

575

553

553

569

502

538

539

382

296

174

121

56

11,118

1VWELD Welder

17

16

15

13

14

14

16

18

13

154

10

1VMECH Mechanic

20

34

57

133

208

223

168

62

37

42

1,000

11

1UHELP2 Helper

22

28

48

86

114

230

290

320

291

152

96

77

1,830

12

1VYDRILL Drill Operator

44

13

1MELEC ELECTRICIAN

10

19

22

32

59

63

105

94

115

141

103

68

45

979

14

1NGCHECK GRADE CHECKER

10

125

15

1NLCHECK LOAD CHECKER

127

16

1OFITER1 PIPE FITTER

13

21

22

25

24

26

23

26

20

20

16

15

12

11

15

11

17

10

17

24

14

11

413

17

1OFITER2 PLUMBER

29

18

1PSTEEL STEEL FIXER

22

33

34

37

18

31

32

30

34

61

49

106

133

120

144

226

441

561

715

685

682

617

497

351

199

76

34

10

5,981

19

1QLAMIN LAMINATOR

23

20

1QPAINT PAINTER

10

11

11

14

12

130

21

1RRAKE RAKEMAN

32

22

1RSCREW SCREWMAN

32

23

1RSPRAY SPRAYMAN

17

Sub-total

178

348

401

473

554

800

869

908

920

1,014

986

1,124

1,145

1,052

1,044

1,181

1,780

1,962

2,278

2,324

2,332

2,440

2,438

2,310

1,672

993

581

405

135

cumulation

178

526

926

1,399

1,954

2,754

3,623

4,531

5,450

6,465

7,451

8,575

9,720

10,772

11,816

12,997

14,777

16,739

19,017

21,341

23,673

26,113

28,551

30,860

32,532

33,525

34,107

34,512

34,647

Cumulative
Number

Number
3,000

40,000
Unit : Number

Monthly
35,000
2,500
30,000

Cumulative
2,000

25,000

1,500

20,000

15,000
1,000
10,000
500
5,000

0
May

Jun

Jul

Aug

Sep
2008

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul
2009

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun
2010

Jul

Aug

Sep

Oct

Nov

Time
Period

A.9 All Resouces Histograms (Indirect Labour)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
Total
MMth

Max No.

( Unit : Number)

2008

2009

2010

2011

No

Resource ID

Project Leader

33

Deputy Project Leader

33

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Technical Head

30

Design Manager

30

Design Engineer

78

Cad Operator

150

Planning Manager

33

Planning Engineer

78

External Engineer

61

10

Qty. Surveyor

94

11

Scheduler

52

12

Cost Manager

30

13

Cost Engineer

150

14

Construction Head

26

15

Construction Manager

148

16

Construction Engineer

17
18

Dec

Jan

Feb

707

27

13

13

13

13

24

25

25

25

25

25

25

25

27

27

27

27

27

27

27

27

27

27

27

27

18

18

18

18

15

15

10

10

10

Utility Manager

24

Utility Engineer

204

19

M & E Manager

30

20

Mechanical Engineer

84

21

Eletrical Engineer

115

22

Survey Manager

28

23

Surveyor

221

24

Contract Manager

33

25

Contract Engineer

30

26

SHE Manager

30

27

SHE Supervisor

169

28

QA Manager

28

29

Laboratory Engineer

78

30

QA/QC Engineer

49

31

Commercial Manager

30

32

Administration Manager

30

33

Accounting

89

34

Cashier

106

35

Procurement

140

36

Administration

25

37

Human Resource

60

38

PRO

Sub-total

32

3,368

127

cumulation

49

63

71

75

99

111

112

113

116

117

117

120

122

123

123

123

123

123

127

126

126

125

125

125

115

104

103

102

86

82

42

42

38

49

112

183

258

357

468

580

693

809

926

1,043

1,163

1,285

1,408

1,531

1,654

1,777

1,900

2,027

2,153

2,279

2,404

2,529

2,654

2,769

2,873

2,976

3,078

3,164

3,246

3,288

3,330

3,368

Cumulative
Number

Number
140

4,000

127

Unit : Number
Monthly

3,500

120

3,000

100

2,500
Cumulative

80
2,000
60
1,500
40

1,000

20

500
0

0
May

Jun

Jul

Aug

Sep
2008

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul
2009

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul
2010

Aug

Sep

Oct

Nov

Dec

Jan
2011

Time
Period

A9. All Resourses Histograms (Equipment)


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel
No

( Unit : Number)

2008

Resource ID

May

Jun

Jul

Aug

2009
Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Period Total

Nov

2BDOZER DOZER

11

12

14

12

14

11

2CGRADER GRADER

119
66

2DSHOVEL WHEEL LOADER

12

10

14

19

22

18

19

22

21

17

16

15

10

10

10

11

17

19

17

21

24

17

17

11

427

2EEXCA EXCAVATOR

10

10

13

14

16

16

18

18

17

17

17

15

10

254

2FJCB1 J C B

12

13

136

2GROLER1 STEEL ROLLER (SINGLE DRUM)

65

2GROLER2 STEEL ROLLER (DOUBLE DRUM)

32

2HPTR1 P T R (EARTHWORKS)

15

2HPTR2 P T R (ASPHALT)

12

10

80

10

2ICRANE1 CRANE ( Mobile Crane )

10

11

15

15

13

14

15

14

15

21

20

20

19

19

17

15

20

22

23

23

17

15

11

419

11

2ICRANE2 CRANE ( Crawler Crane )

10

12

17

22

22

20

23

19

13

240

12

2IFORK Fork Lift

12

17

22

24

21

26

23

20

14

209

13

2JDUMP Dump Truck

11

16

20

25

32

41

37

42

42

45

31

15

11

388

14

2ZDRILL Drilling Machine

44

15

2BPILE Boring Rig (Pile Driver)

79

16

2DWALL D/Wall Machin (Trench Cutter)

57

17

2SPLANT Slurry Plant (D/Wall)

57

18

2YWELD Welding Machine

80

19

2CARGO Cargo Truck

12

17

23

25

23

28

27

24

19

10

234

20

2FAB Fabrication Team (Precast)

21

2SLIFT Scissor Lift

12

14

13

79

22

2YJETT Jet Grouting Pump

44

23

2CARRIER Straddle Carrier

21

24

2JTANK1 WATER TANKER

14

22

31

33

31

32

30

29

28

23

20

17

18

14

13

10

12

10

14

453

25

2JTANK2 SPRAY TANKER

17

26

2JTRAIL1 TRAILER

18

18

19

18

19

17

19

18

19

19

18

15

261

27

2JTRAIL2 FLAT BED TRAILER

11

12

109

28

2JTRAIL3 LOW BED TRAILER

10

11

14

13

11

12

12

12

176

29

2JTRUCK SITE DUTY TRUCK

18

16

22

19

22

24

27

27

25

27

26

25

28

23

24

21

18

20

15

13

13

14

501

30

2MHIAB HIAB

71

31

2N27TON 7 TON PICKUP

50

32

2N33TON 3 TON PICKUP

10

10

10

175

33

2N4LDV L D VEHICLE

12

12

11

11

10

221

34

2PBOBCAT BOBCAT

108

35

2SPAVER1 ASPHALT PAVER

19

36

2TCUT ASPHALT CUTTER

21

37

2TMILL MILLING MACHINE

10

38

2UCOMP AIR COMPRESSOR

73

39

2VGENE* GENERATOR

96

40

2VGENE1 GENERATOR 300~700 KVA

20

41

2VGENE2 GENERATOR <300 KVA

42

2YDEWAT* DEWATERING PUMP

10

16

16

18

18

19

18

22

17

14

12

12

231

33

87

122

119

138

186

216

232

233

252

269

286

288

267

261

246

268

248

252

247

240

227

226

244

176

148

118

87

52

33

120

242

361

499

685

902

1,133

1,366

1,618

1,887

2,173

2,461

2,728

2,989

3,235

3,502

3,751

4,003

4,251

4,490

4,717

4,943

5,187

5,363

5,511

5,629

5,717

5,769

Sub-total
cumulation

Cumulative
Number
7,000

Number
350

Unit : Number

Monthly

Cumulative

300

6,000

250

5,000

200

4,000

150

3,000

100

2,000

50

1,000

May

Jun

Jul

Aug

Sep
2008

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul
2009

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun
2010

Jul

Aug

Sep

Oct

Nov

Time
Period

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 10
Cash Flow

SAMSUNG-SAIF BIN DARWISH JV

- 10 -

A10. CASH FLOW


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

Description

2008

(1,000 AED)

Progress (%)

Interim Payment

3,105,000

May

Jun

Jul

Aug

2009

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2010

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Sum

2011

Jul

Aug

Sep

Oct

Monthly

0.20%

0.42%

0.74%

1.35%

1.64%

2.80%

2.87%

3.06%

3.02%

3.65%

3.54%

4.85%

5.02%

3.80%

3.67%

4.06%

5.30%

5.57%

5.89%

5.76%

4.64%

5.45%

5.02%

5.45%

5.02%

2.87%

2.17%

1.92%

0.29%

Cummulative

0.20%

0.62%

1.36%

2.71%

4.35%

7.15%

10.02%

13.08%

16.10%

19.75%

23.29%

28.14%

33.16%

36.96%

40.63%

44.68%

49.98%

55.55%

61.44%

67.19%

71.83%

77.28%

82.30%

87.74%

92.76%

95.63%

97.80%

99.72%

100.00%

Nov

100%

Dec

100%

Monthly

5,935

12,631

22,208

40,417

48,979

83,930

85,983

91,502

90,498

109,301

105,984

145,239

150,317

113,716

109,736

121,444

158,561

166,888

176,200

172,326

138,885

163,084

150,325

163,061

150,262

85,907

64,899

57,392

119,391

Cummulative

5,936

18,567

40,774

81,191

130,170

214,100

300,084

391,585

482,083

591,385

697,368

842,608

992,925

1,106,640

1,216,376

1,337,819

1,496,381

1,663,269

1,839,469

2,011,794

2,150,679

2,313,763

2,464,088

2,627,148

2,777,411

2,863,318

2,928,217

2,985,609

3,105,000

3,105,000

3,105,000

155,250

77,625

77,625

Monthly

40,774

40,417

48,979

83,930

85,983

91,502

90,498

109,301

105,984

145,239

150,317

113,716

109,736

121,444

158,561

166,888

176,200

172,326

138,885

163,084

150,325

163,061

150,262

85,907

64,899

57,392

119,391

Cummulative

40,774

81,191

130,170

214,100

300,084

391,585

482,083

591,385

697,368

842,608

992,925

1,106,640

1,216,376

1,337,819

1,496,381

1,663,269

1,839,469

2,011,794

2,150,679

2,313,763

2,464,088

2,627,148

2,777,411

2,863,318

2,928,217

2,985,609

3,105,000

Jan

100%

Feb

100%

Mar

100%

Apr

100%

May

100%

Jun

100%

Jul

100%

Aug

Sep

Oct

100.0%

100.0%

100.0%

Nov

Dec

100%

100%

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

Interim Payment Installaments

1) Advance Payment (10%)

310,500

2) Release of Interim Payment

3,105,000

3) Release of Retention

4) A/Payment Refundment

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

3,105,000

155,250

25.00%

-310,500

5) Retention (5%)

3,105,000

5%

-155,250

6) Actual Interim Payment

3,105,000

3,105,000

3,105,000

3,105,000

155,250

155,250

-310,500

Monthly

-22,875

-22,624

-27,325

-26,496

-36,310

-37,579

-28,429

-27,434

-30,361

-39,640

-41,722

30,295

Cummulative

-22,875

-45,499

-72,824

-99,320

-135,630

-173,209

-201,638

-229,072

-259,433

-299,073

-340,795

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

Monthly

-2,039

-2,021

-2,449

-4,197

-4,299

-4,575

-4,525

-5,465

-5,299

-7,262

-7,516

-5,686

-5,487

-6,072

-7,928

-8,344

-8,810

-8,616

-6,944

-8,154

-7,516

-8,153

-7,513

-4,295

-3,245

-2,870

-5,970

Cummulative

-2,039

-4,060

-6,509

-10,706

-15,005

-19,580

-24,105

-29,570

-34,869

-42,131

-49,647

-55,333

-60,820

-66,892

-74,820

-83,164

-91,974

-100,590

-107,534

-115,688

-123,204

-131,357

-138,870

-143,165

-146,410

-149,280

-155,250

38,735

38,396

46,530

79,733

81,684

64,052

63,349

76,511

74,189

101,667

105,222

79,601

76,815

85,011

110,993

116,822

197,685

163,710

131,941

154,930

142,809

154,908

142,749

81,612

61,654

54,522

113,421

349,235

387,631

434,161

513,894

595,579

659,630

722,979

799,491

873,679

975,347

1,080,569

1,160,169

1,236,984

1,321,994

1,432,988

1,549,810

1,747,495

1,911,204

2,043,145

2,198,075

2,340,884

2,495,791

2,638,541

2,720,153

2,781,807

2,836,329

2,949,750

Monthly

155,250

77,625

77,625

Cummulative

155,250

232,875

310,500

310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-310,500

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

-155,250

3,105,000

155,250

2,949,750

2,949,750

2,949,750

2,949,750

2,949,750

2,949,750

2,949,750

2,949,750

2,949,750

3,105,000

3,105,000

3,105,000

080828_CASHFLOW, 2008-08-28

UPGRADING AL SALAM STREET AND


ABU DHABI CITY RING ROAD CONTRACT NO.1
(AL SALAM STREET TUNNEL)

BASELINE SUBMISSION REV.0

Appendix 11
Activity Movement Chart

SAMSUNG-SAIF BIN DARWISH JV

- 11 -

A11. ACTIVITY MOVEMENT CHART


Upgrading Al Salam Street & Abu Dhabi City Ring Road - Contract No.1 Al Salam Street Tunnel

STRUCTURE NO.1

STRUCTURE NO.2

STRUCTURE NO.3

Section No.1
Number of Units

117

Total Length (SB)

3,373

Section No.2

No of Units (SB) = 34

Units

No of Units (SB) = 21

AP

DR-1

DR-2

TN-1

DR-3

TN-1

DR-3

10.00

75.95

145.95

35.16

132.25

51.34

456.17

TN-2
49.32

37.59

Section No.4

No of Units (SB) = 25

TN-3

40.90

STRUCTURE NO.4

Section No.3

224.16

90.01

Section No.2

No of Units (SB) = 28

TN-4

TN-5

150.00

1591.05

No of Units (SB) = 9

10.00 23.38 23.38 29.19 29.19 29.19 29.19 29.23 29.15 35.16 26.45 26.45 27.45 25.45 26.45 25.67 25.67 28.51 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.50 28.68 24.66 24.66 20.45 20.45 20.26 17.33 24.99 25.51 28.95 28.94 28.94 28.94 28.94 28.94 30.51 29.50 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.09 29.91 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.08 29.92 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 31.05

DR-5

TN-6

9.94

21.40

162.23

89.86

9.94

21.40 26.68 26.85 26.85 26.85 26.84 28.15 29.88 30.69 29.29

Unit 9

Unit 8

Unit 7

Unit 6

Unit 5

Unit 4

Unit 3

Unit 2

Unit 1

AP

Unit 62

Unit 61

Unit 60

Unit 59

Unit 58

Unit 57

Unit 56

Unit 55

Unit 54

Unit 53

Unit 52

Unit 51

Unit 50

Unit 49

Unit 48

1+289.804

1+260.510

1+229.822

1+199.945

1+171.792

1+144.954

1+118.104

1+091.254

1+064.404

1+037.719

1+016.320

11+525.000

11+515.057

11+484.010

11+454.010

11+424.009

11+394.010

11+364.010

11+334.010

11+304.009

11+274.009

11+244.009

11+214.009

11+184.010

11+154.010

11+124.010

11+094.010

11+064.010

11+034.009

11+004.009

10+974.010

10+944.010

10+914.010

10+884.010

10+854.009

10+824.009

10+794.010

10+764.010

10+734.009

IP-56
(STA.1+050.000)

IP-36
(STA. 11+058.529)

IP- 36A
UB3H

V14(S14)

UB21

UB22

UB23

IP- 56

UB2H

IP- 36

2010

AP

PB08
UB20

UB1H
V13(S13)

Unit 47

Unit 46

Unit 45

Unit 44

Unit 43

Unit 42

Unit 41

Unit 40

Unit 39

Unit 38

Unit 37

10+704.009
IP-36A
(STA. 10+700.000)

UB19

IP- 11A

IP- 11
U12(S11)

Unit 36

10+674.009

10+644.009

10+614.009

10+584.009

10+554.009

UB18

Unit 35

Unit 34

Unit 33

Unit 32

Unit 31

10+524.009

IP-11A
(STA. 10+400.000)

UB17

V11(S8)

Unit 30

10+494.010

10+464.010

10+434.009

10+404.090

10+374.010

10+344.009

10+314.009

10+284.009

10+254.009

PB07

UB16

Unit 29

Unit 28

Unit 27

Unit 26

Unit 25

Unit 24

Unit 23

Unit 22

Unit 21

10+224.009

IP-11
(STA. 10+000.000)

V10(S7)

Unit 20

10+194.009

10+164.009

10+134.009

10+104.009

10+074.101

10+044.009

9+984.010

10+014.009

9+954.009

PB06
UB13 UB14 UB15

Unit 19

Unit 18

Unit 17

Unit 16

Unit 15

Unit 14

Unit 13

Unit 12

Unit 11

9+924.009

9+894.010

9+864.010

9+834.010

9+804.011

9+774.011

U22(S25)

Unit 10

Unit 9

Unit 8

Unit 7

Unit 6

Unit 5

Unit 4

Unit 3

UB10 UB11 UB12

IP- 9

U21(S23)

9+744.011

PB05

UB08 UB09

IP- 12

U20(S22)

IP-9
(STA. 9+704.935)

PB04
UB07

UB06

9+714.510

9+684.002

9+655.067

9+626.125

9+597.183

9+568.240

9+539.298

9+510.344

9+484.833

9+459.844
IP-12
(STA. 9+450.000)

UB04 UB05

Unit 2

Unit 1

Unit 14

Unit 13

Unit 12

Unit 11

Unit 10

Unit 9

Unit 8

Unit 7

9+442.513

9+422.251

9+401.802

9+381.354

9+356.695

9+332.038

9+303.363

9+274.863

9+246.364

9+217.865

9+189.366

9+160.867

9+132.368

9+103.869

9+075.370

9+046.871

9+018.372

UB02 UB03

Unit 6

Unit 5

Unit 4

Unit 3

Unit 2

Unit 1

Unit 32

Unit 31

Unit 30

Unit 29

Unit 28

Unit 27

Unit 26

Unit 25

Unit 24

Unit 23

8+989.873

27

Unit 22

8+961.374

28

Unit 21

8+932.876

29

Unit 20

Unit 19

30

Unit 18

10

PB03

PB02
UB01

IP- 41

31

8+904.376

11

IP-41
(STA. 8+850.737)

No

8+875.870

11

PB01

8+850.198

No

IP- 41A

No
No

Unit 17

8+824.527

8+798.076

8+772.625

8+745.176

IP-41A
(STA. 8+675.061)

8
23

Unit 16

Unit 15

Unit 14

Unit 13

Unit 12

Unit 11
8+718.724

8+692.273

8+657.117

8+627.972

8+598.739

8+569.550

8+540.361

8+511.172

8+481.983

8+458.604

SB

Unit 10

Unit 9

Unit 8

Unit 7

Unit 6

Unit 5

Unit 4

Unit 3

8+435.226

Cross
Horizontal

U15(S16)

V16(S18)

ES5(S27)

11/Jul/10

15/Jul/10

15/Jun/10
6

26

07/Jun/10
03/May/10

25

31/May/10

20/May/10

03/May/10

24/Apr/10
12/Apr/10

24

15/Apr/10

15/Apr/10

06/Apr/10
3

03/Apr/10

13/Mar/10

08/Apr/10

23

06/Mar/10
2

22

21

12

20

11

19

09/Mar/10

18/Mar/10
03/Mar/10
14/Dec/09

31/Dec/09

16/Mar/10

02/Feb/10

04/Feb/10
27/Jan/10

29/Dec/09

03/Jan/10
16/Nov/09

29/Nov/09

01/Dec/09

31/Oct/09

01/Nov/09

17/Oct/09
02/Nov/09
10

12/Nov/09

18

04/Oct/09

15/Sep/09
9

17

14/Oct/09

16/Sep/09

03/Oct/09
06/Sep/09
20/Aug/09

20/Aug/09

16

23/Aug/09
15

14

2009

23/Jun/09

15/Jul/09

08/Jul/09

20/Jul/09

13/Aug/09
10/Jun/09

17/May/09
07/Jun/09

13

12

11

10

12

11

10

06/Jun/09

28/Jun/09
21/Jun/09

07/May/09

05/May/09
15/Apr/09

25/May/09

07/Apr/09

14/Mar/09
30/Mar/09

09/Mar/09

01/Mar/09

23/Mar/09
04/Fec/09
11/Jan/09

24/Jan/09

16/Dec/08

02/Nov/08

01/Nov/08
01/Nov/08

01/Nov/08

2008

Utility / Vent. Room

Unit 2

8+425.226

Pedestrian Bridge
Utility Bridge

Unit 1

AP

* This scheme can


be changeable

Intersection Point
(Traffic + Working Deck)

DR-4

Remarks)
A. Work Sequence & Direction of this chart may be different from detailed BASELINE Programme.
B. The main purpose of movement chart help us getting schedule information regarding major works roughly.
C. All Scheduled Date Data came from submitted BASELINE.

Legends
D/Wall

1ST EXC

2ND EXC

Base

1ST Wall

2ND Wall

Roof