Sie sind auf Seite 1von 47

project check lists buildings

use in conjunction with the

2010
standard specification for small building works

INTRODUCTION
It is difficult during a visit to a construction site to memorise all of the details that need to be checked and while the obvious ones stand out, many other items that should be checked are forgotten. Superintendents may get distracted or over extended due to time constraints and overlook items that may have more serious consequences later in the project. These Check Lists provide a guide to the inspections that are required on site for a particular project. They are a prcis of the full clauses in the project specification and can be referred back to the specification if the full text of the particular item is required. The check Lists will remind you of virtually every potential problem in materials, workmanship and coordination between trades. The Check Lists include a list of the Hold Points, Witness Points and Tests that are required to be signed off by the Superintendent on projects that include the Project Control section. The rest of the checks are simply dot points to jog the memory of the Superintendent. Project specific checks may be added to the Check Lists for individual projects and the experience of Superintendents can be shared by the addition of particular checks on items or operations that are generally of concern on site. In this case less experienced Superintendents can use these Check Lists to provide them with the back up of more experienced officers. Provide one copy of the Check Lists book to the Superintendent and one copy to the Contractor for the particular project. HOW TO USE THESE CHECK LISTS Take photocopies of the relevant Check List sections before going on site and study these. This book of Check Lists is spiral bound to allow pages to be photocopied easily. Mark any items in the Check List that are of particular concern. At the project site, check off the work against the Check Lists and make notes of any action required in the space provided. When the work is completed and the final check has been made sign off and date in the box provided. There is also space to provide comments. Keep a record of all of the completed Check Lists for future reference if required. These could prove to be valuable if disputes arise on the project. There is no better way to document actual site conditions or details than by photographs, so dont forget to take a digital camera on site and take images to go with particular items in the Check lists. FURTHER DEVELOPMENT If you have any suggestions to improve on these Check Lists or the system in general please contact the Manager Documentation Services, 1st Floor Highway House, 14 Palmerston Circuit, Palmerston. Tel; (08)894 65021 or email at lawrence.foscaro@nt.gov.au

DEPARTMENT OF CONSTRUCTION & INFRASTRUCTURE CONSTRUCTION DIVISION

CONTENTS

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21.

GENERAL REQUIREMENTS SITE PREPARATION CONCRETE CONSTRUCTION TIMBER AND STEEL CONSTRUCTION BLOCK CONSTRUCTION INSULATION AND SARKING ROOFING DOORS AND WINDOWS CLADDING AND LINING SUSPENDED CEILINGS PLASTERING JOINERY AND FIXTURES TILING PAINTING FLOOR COVERINGS PLUMBING AND DRAINAGE ELECTRICAL INSTALLATIONS MECHANICAL INSTALLATIONS FENCES PAVING LANDSCAPE

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

GENERAL REQUIREMENTS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST GENERAL REQUIREMENTS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS [Specification Checks] TIMBER GENERALLY _ Allowances made for unseasoned timber _ Durability class meets minimum requirements TESTS _ COMPLETION _ _ _ _ _ _ NATA registered authority

Warranties provided in the name of the principal Instruction manuals provided Termite barrier certification provided Surveyors certificate provided when specified Services layout plan submitted Authorities approvals provided when specified [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

<< DPI CONSTRUCTION CHECK LIST AUG 2005>>

GENERAL REQUIREMENTS [Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<>DPI CONSTRUCTION CHECK LIST AUG 2005>>

SITE PREPARATION DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST SITE PREPARATION


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item If bad ground is encountered Adjoining structures before commencement of demolition Hazardous conditions or material is found HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Proof of required density has been recieved COMPLIANCE CHECKS [Specification Checks] DEMOLITION _ _ _ _ _ TREES _ _ Trees to be retained are clearly marked Protection is provided retained trees Demolished materials are removed from site Dust protection provided as specified Temporary supports provided Weather protection provided where specified Security provided where specified Checked Initial and date

ENVIROMENTAL PROTECTION _ Erosion control measures provided _ Dewatering is as specified SITE CLEARING _ Stumps grubbed out as specified _ Topsoil stockpiled and protected from contamination _ Surface graded to drain water away from buildings without ponding SURFACE PREPARATION _ Fill types are as specified

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

SITE PREPARATION

_ _ _ SANDLAYER _ PILING _ _

Placing is as specified Moisture content correct Required density achieved

Installed as specified

Bored piers installed as specified Screw in foundations are to required standards

SERVICE TRENCHES _ Trench widths correct _ Correct backfill method used _ Backfill compacted to required density [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

CONCRETE CONSTRUCTION DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - CONCRETE CONSTRUCTION


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Termite barrier and film underlay installed Completed formwork, and re-inforcement, cores and embedments fixed in place Commencement of concrete placing Before core filling masonary HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Hot weather mixing, prior approval required. Cores and imbedded items fixed to prevent movement during placing TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item TESTS Compressive strength COMPLIANCE CHECKS [Specification Checks] Checked Initial and date Checked Initial and date Checked Initial and date

GROUND SLAB VAPOUR BARRIER _ Vapour barrier installed to specified standards _ Joints lapped and sealed as specified REINFORCEMENT _ Dowels in one piece with ends cut square and free of burrs _ Exposed end primed as specified EMBEDDED ITEMS _ Correct positioning of embedded items as specified _ Correct Corrosion protected fixings used as specified CONCRETE _ _ _ _

Correct concrete grade used as specified Grout is as specified Concrete placing is as specified Concrete protected from premature drying

<<CD CONSTRUCTION CHECK LIST AUG 2005>>

CONCRETE CONSTRUCTION FORMWORK _ _ JOINTS _ Construction, slip and movement joints installed as specified

Surface finish class is to required standard All formwork removed after curing

FINISH TO UNFORMED SURFACES _ Correct screeding method used _ Specified finish correct including levels and falls MISCELLANEOUS ITEMS _ Clothes hoist footing is as specified _ Splash pads installed correctly and as specified _ Mowing strips installed as specified _ Gas cylinder pad installed as specified

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

TIMBER AND STEEL CONSTRUCTION DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - TIMBER AND STEEL CONSTRUCTION


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages;] Spec.Ref. Item Commencement of shop fabrication Surface preparation prior to painting Steelwork and column bases erected on site Steel framing erected onsite prior to lining and or cladding HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Shop drawings submitted with all specified information Do not attach cleats without prior approval. All temporary cleats to be removed on completion and make good any damaged surface Do not hand flame cut or otherwise enlarge any bolt holes without approval Checked Initial and date Checked Initial and date

TESTS Spec.Ref.

Item

Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Materials and components comply with specification requirements CONSTRUCTION _ Foundation bolts provided as specified _ Welds clean and primed _ Protective coating provided LIGHT STEEL FRAMING _ Fabrication is as specified _ Temporary earthing provided _ Steel battens fixed as specified TIMBER FRAMING _ Timber identified as specified _ Timber grades are as specified

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

TIMBER AND STEEL CONSTRUCTION Fasteners _ Correct type _ Galvanized as specified Adhesives are as specified Structural plywood is specified type and grade Structural sheet flooring _ Level _ Junctions have a smooth and level finish Timber decking _ Securely nailed to bearers _ Joints are flush and over floor joists Fibre cement flooring _ Type and thickness is as specified _ Ends joined correctly _ Expansion joints installed as specified Wall frames sizes and grades are as specified Damp proof course installed TIMBER ROOF TRUSSES _ Trusses marked as specified _ Certification provided _ Support trusses installed _ Ties and wind bracing provided MISCELLANEOUS Roof battens _ _

Correct type Fixed as specified

Ceiling battens _ Correct type _ Fixed as specified

[Supervisor Specific Checks Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

TIMBER AND STEEL CONSTRUCTION

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST - AUG 2005>>

BLOCK CONSTRUCTION DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - BLOCK CONSTRUCTION


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Materials and components comply with specification requirements _ Steel components _ Masonry units _ Flashing and damp proof courses _ Mortar materials CONSTRUCTION _ Joints installed where specified _ Perpends vertically aligned _ Unpainted facework clean as specified DAMP PROOF COURSES _ Installed where specified CONTROL OF MOVEMENT _ Blockwork control joints installed as specified _ Flexible ties and anchors provided _ Joint materials are as specified _ Bed joint reinforcement installed

<<DPI CONSTRUCTION CHECK LIST - AUG 2005>>

BLOCK CONSTRUCTION

STEEL LINTELS _ Correct material _ Installed as specified REINFORCED MASONRY _ Cleaning holes provided _ Bond beam installed as specified _ Starter bars secure _ Lintel blocks installed as specified _ Core filling grout is as specified Core holes _ Bond beams _ Lintels [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

INSULATION AND SARKING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - INSULATION AND SARKING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Sarking, vapour barrier and insulation inspection required before it is concealed or covered up. Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS MATERIALS _ _

[Specification Checks]

Compliance with standards as specified Support wires secure as specified

BULK INSULATION _ Check insulation installed tight and supported WALL SARKING _ Sarking installed to form weather proof seal ROOF SARKING _ Sarking covers whole of roof _ Sarking lapped at 150mm. Min. [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

INSULATION AND SARKING [Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

ROOFING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST ROOFING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspect substructure before roof sheeting is secured Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIAL AND COMPONENTS _ Materials moisture free and undamaged _ Ensure approved metal fixings are to be used only _ Roof screw type, including cyclone washers corrosion resistant ROOF STRUCTURE _ Alignment correct METAL FASCIA AND BARGE _ Fixing clips in place and fixed correctly METAL ROOFING _ Visible accessories have same finish as roof sheets _ Valleys turned up at ridge _ Pans turned down into gutters _ Eaves and ridge fillers fitted ROOF PLUMBING _ Flashings and cappings, correct material and fixings _ Gutters, size, fixings and overflows correct _ Downpipes, size and fixings correct _ Swarf and debris removed from roof

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

ROOFING [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]t

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

DOORS AND WINDOWS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - DOORS AND WINDOWS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Submit plans for window installation HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Comply with specification requirements _ Flashings _ Metal finishes _ Glass _ Doorsets _ Windows CONSTRUCTION _ Flashing and weatherings in place to avoid water penetration _ All doorsets and windows installed plumb, level, straight and true _ Doorsets and windows adequately fixed or anchored to building structure STEEL DOOR FRAMES _ Correct frames and necessary accessories used _ All welds ground smooth and welded joints galvanised prior to priming _ Ensure all frames are in masonry, and packed behind fixing points TIMBER DOORS _ Ensure correct door type is used ( NT designated or other) _ All areas subject to paint removal, primed prior to hanging DOOR FURNITURE _ Door stops installed _ Door seals secured to external doors and adjusted correctly _ Correct hinges to suit door as specified

<<DPI CONSTRUCTION CHECK LIST - AUG 2005>>

DOORS AND WINDOWS SLIDING INTERNAL DOORS _ All accessories including wheel carriages are appropriate to the size and mass of door SECURITY SCREEN DOORS _ Infill mesh secured to extruded aluminium frames _ Hinges and pneumatic closer functioning correctly ROLLER SHUTTERS _ Manual operation fixings and operation handle functioning _ Motorised operation Operating switch secure and functioning LOCKSETS _ _ _

Mounting height correct Ensure all passage, privacy and key-lockable sets are functioning correctly 2 keys provided for each lockset

CONSTRUCTION _ All fixings not visible on exposed side Aluminium screen mesh tightly strung and fasten with plastic continuous spline material

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

CLADDING AND LINING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - CLADDING AND LINING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Approval of the ceiling set out prior commencing installation Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS MATERIALS AND COMPONENTS _ Flashing material as specified _ Sarking material as specified _ All materials free from corrosion CLADDING _

[Specification Checks]

Materials used are specified

PLASTERBOARD _ Installation as specified _ Flush jointing materials correct _ Control joints in position _ Framed construction _ Masonry construction FIBRE CEMENT SHEETING _ Correct screws used _ Control Joints flushed and finished _ V joints flushed and finished TONGUE AND GROOVE LINING _ All boards fixed with a continuous grain pattern _ Visible nail heads treated as specified PLASTIC LAMINATE

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

CLADDING AND LINING _ Joins sealed

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

SUSPENDED CEILINGS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - SUSPENDED CEILINGS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspect suspension system prior to installation of panels or lining. Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Approval of the ceiling set out prior commencing installation Suspension member co-incide with grid lines Opposite margins equal Technical data provided on loadings Approved specialist fixers carrying out installation TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ All materials are as specified _ Materials comply with Australian Standards _ Check fastener type CONSTRUCTION _ Support members galvanised and adjustable _ Check for looseness or rattling of components _ Bracing fitted to prevent lateral movement _ Fasteners not visible _ Bulkheads comply with strength requirements CEILING PANELS _ Tiles painted before installation _ Panel lock clips fitted if required _ Tiles seated evenly within grid _ No visible damage to tile, edges etc.

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

SUSPENDED CEILINGS FLUSH CEILING _ Flush jointing materials finish _ Control joints in position TRIM _ _ _ Check all accessories and trims are provided Openings provided for light fittings, services, etc. Access panels provided and correctly finished

FINAL CHECK _ Ceiling complete No visible defects

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Check - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PLASTERING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST PLASTERING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Lime putty mixes mixed minimum 16 hours before use _ Gauged mixes as specified SUBSTRATE _ _ _ _ _ PLASTERING _ _ _ _ _

Defects in substrate repaired Substrate requires second coat Loose material and dust removed from substrate Embedded items sheathed Metal laths fixed as specified

Number of coats and thickness is as specified Curing even and within required timeframe V joints installed as specified Movement joints installed as specified Correct finish as specified or as shown on drawings

[Supervisor Specific Checks] Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PLASTERING [Project Specific Checks] Project specific checks can be listed here or inserted into the location in the previous checklist

[Project Officer to insert any special checks required for this project]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

JOINERY AND FIXTURES DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - JOINERY AND FIXTURES


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ All materials are as specified _ Moisture content checked _ Timber finished to required dimensions CONSTRUCTION _ Components manufactured square and installed plumb _ Fasteners and adhesives used correctly _ No visible fixings except where specified CUPBOARD AND DRAWER UNITS _ Plinth material and installation as specified _ Carcasses, drawer fronts, shelves and doors material and installation as specified _ Door hinges as specified _ Self closing action and hold open function operating as specified _ Drawer units operating smooth and true. BENCHTOPS _ Materials are as specified CEILING ACCESS _ Access panel provided as specified FIRE FIGHTING _ Extinguishers and location signs in position as per Australian Standards _ Fire blanket and location signs in position as per Australian Standards

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

JOINERY AND FIXTURES DISPLAY BOARDS _ Specified display board supplied _ White board screw fixed to wall as specified _ Pin boards screw fixed to wall as specified CLOTHES HOISTS _ Specified clothes hoist supplied _ Clothes hoist installed in required position GRAB RAILS _

Grab rail installed as specified

LETTER BOXES _ Letter box complies with current standard _ Lock supplied and operating. (if required) [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

TILING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CONSTRUCTION CHECK LIST TILING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Completion of water proof membrane Initial or trial setout HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS MATERIALS AND COMPONENTS _ All materials are as specified SAMPLES _

[Specification Checks]

Sample tiles and accessories provided as requested

WATERPROOFING _ Materials as specified _ Membrane turned down into floor wastes and puddle flanges _ Hobs; Membrane extended as specified _ Membrane fully cured before tile installation _ All floors and wall to floor junctions sealed TILING _ _ _ _ Tiles cut neatly to fit around fixtures Traffic kept off of floors until bedding attains a workable strength Tiles set out to give uniform widths as specified Falls and levels correct

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

TILING _ _ _ Preparation of tiles as specified Floor finish dividers in place as specified All sealed joints finished flush with tile surface as specified Movement joints installed as specified

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]t

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PAINTING DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST PAINTING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspect substrate prior to commencement of first coat Inspect prior to final coat application Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item List of paint trade names and manufacturer supplied Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Paint material is of premium quality and from an approved manufacturer _ Paint is new, manufacturer labelled and unopened _ All paint containers are APAS approved (Australian Paint Approvals Scheme) PAINTING _ _ _ -

Substrate clean and sound Free of mould growth Damaged surfaces patched and primed Ensure clear timber finishes are complete before commencing opaque finishes in the same area All door furniture, switch plates, light fittings and other fixtures removed prior to painting, and refixed on completion of painting _ Filler used matches the substrate for transparent finishes _ First coat applied immediately before substrate contamination can occur Ensure each coat of paint or clear finish is; _ Uniform in colour, thickness and texture _ Free from runs, sags, blisters or other discontinuities _ Exposed roof trim, timber doors including tops and bottoms primed with approved sealer before fixing _ Galvanised or Zinc surfaces that have been cut or welded primed with approved sealer _ Any damaged surfaces restored to original condition _ Any visible defects

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PAINTING ONSITE CHECKLIST _ Refer to attached onsite checklist [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PAINTING

PAINTING CHECKLIST
External walls Scrapeback required Substrate accepted Preparation approved Rub down External trims External fixtures Internal walls (wet areas) Internal walls (generally ) Internal ceilings (wet areas) Internal ceilings (generally) Internal trims Internal fixtures and joinery

Other Priming and patching Undercoat 1st coat finished Finishing coat Extra coat Required Any imperfections Site clean

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

FLOOR COVERINGS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - FLOOR COVERINGS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspect prepared underlay or substrate HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS GENERAL _

[Specification Checks]

Installation carried out by experienced fixers

MATERIALS AND COMPONENTS _ Hardboard underlay is as specified _ Carpet underlay is as specified SUBSTRATE _ _ _ _ _ _

All loose and deleterious materials removed High spots and projections removed from substrate Any depressions filled with approved filler Fixtures and fittings removed and refixed in position on completion Timber has an evenly planed sanded finish, prior to installation Concrete substrate tested for dryness

LAYING CARPET _ Carpet layed in continuous lengths _ Underlay joins do not coincide with carpet joins _ Correct seaming method used as specified _ Gripper strips are placed at 150mm maximum centres _ Correct adhesive used and rolled immediately after installation _ Edge strips fixed correctly as specified _ All doors trimmed and resealed if required to clear carpet by 3mm RESILIENT FINISHES _ Sheet joints kept to a minimum

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

FLOOR COVERINGS _ _ JOINTS _ _ _ Welding joints fixed as specified Junctions finish flush with adjoining surfaces Finished surface level, free of air bubbles, humps and depressions [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.] Sheets run parallel with long sides of floor Correct adhesive used for specified applications

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PLUMBING AND DRAINAGE DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - PLUMBING AND DRAINAGE


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINT Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspection of work ready for testing HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item commence work notice lodged and approved Drawings received and approved TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Sanitary pipes Waterpipes COMPLIANCE CHECKS [Specification Checks] Checked Initial and date Checked Initial and date Checked Initial and date

CONTRACTOR SUBMISSIONS _ "As installed" drawings submitted MATERIALS AND COMPONENTS _ Water supply pipes materials as specified _ Exposed piping, fittings and supports finished as specified _ Sanitary fixtures and tapware installed as specified CONSTRUCTION _ Piping installed in straight lines and to uniform grades _ Piping support installed to prevent water hammer and vibration _ Piping concealed where practicable STORMWATER _ Temporary covers on openings _ Completed work flushed with water and clean _ spigot ends same direction as water flow _ Subsoil drains materials as specified _ Trenches back filled _ Pit covers installed as specified WASTEWATER _ Temporary cover on openings

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PLUMBING AND DRAINAGE _ _ _ Completed work flushed with water and clean Septic tank materials and standards are as specified Vent pipe correctly installed

FRESHWATER _ Tap locations correct as specified _ All accessories and fittings correctly placed as specified _ Water heater type confirmed and installed as specified _ Isolation valve to water heater correctly installed _ All pipelines flushed and left clean FIRE HOSE REELS _ Fire hose reel type and locations as specified GAS _ _ _ _ _ _ Piping installed in straight lines and uniform grades Warning tape on all buried pipework as specified Manufacturers certificate with AGA/ALPGA approval for appliance and gas type Appliance installed as specified Compliance plate installed Certificate of approval received prior to practical completion

[Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

ELECTRICAL INSTALLATIONS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - ELECTRICAL INSTALLATIONS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspection of trench excavations and underground or concealed conduits before covering Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS GENERAL _ _ _

[Specification Checks]

All installations meet specified standards All work complies with specified regulations All materials and components meet specified requirements

INSTALLATION _ Concealed cables, conduits including underground cables installed as specified, and checked prior to concealment _ Accessories installed as specified CONSUMER MAINS AND METERING _ Consumers mains installed and connected to main service complying with regulatory standards _ Kwh meter installed by specified supply authority _ Meter box installed to regulatory standards DISTRIBUTION BOARD _ Distribution board installed correctly as specified ACCESSORIES _ GPO'S and light switches materials and installation as specified _ Mounting heights correct as specified _ Ceiling fans installed as specified _ Smoke alarms installed correctly and as specified

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

ELECTRICAL INSTALLATIONS TELECOMMUNICATIONS CABLING _ Pre wiring complete prior to installation of linings, paving and or landscaping _ Telephone wiring complete as specified TELEVISION _ _

Antennae conforms to specified standards Antennae correctly positioned

COMMISSIONING _ Any visual defects noticed _ Complete installation handed over in working order [Supervisor Specific Checks - Write any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks] Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

MECHANICAL INSTALLATIONS DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST - MECHANICAL INSTALLATIONS


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

AIR CONDITIONERS _ Split systems installed and tested as specified _ Room air conditioners installed as specified INSTALLATION _ Anti vibration mounts correctly installed _ Wiring installed as specified _ Any exposed wiring covered as specified _ Exposed pipework covered as specified _ Unit has recommended clearance requirements for airflow and maintenance _ External plant fitted as specified _ Connection of RAC is correct and as specified CONDENSATE DRAINS _ Drains installed to required standards and codes _ Drain size and type installed as specified FRESH AIR _ DUCTWORK _ _ FANS _ Fan has quiet operation and free from vibration

Air supply through unit to air-conditioned spaces meets specified standards

Ductwork materials installed as specified Fixed without sagging or restriction to airflow

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

MECHANICAL INSTALLATIONS _ Fan installation and positioning is as specified

COMMISIONING _ Any visual defects noticed [Supervisor Specific Checks - Write any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

FENCES DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST FENCES


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Materials and components comply with specification requirements CONSTRUCTION _ Vegetation cleared from fence alignment _ Fence lines, gate posts and bracing panels marked out clear and correct _ Footings have a firm base and vertical sides _ Vertical posts follow natural contours of ground _ Concrete footings finished with a weathered top and falls from post to ground level _ Drain holes provided where specified _ Mowing strip installed as specified GATES _ _ Gates correctly installed as specified Hand access holes provided for external access

FENCE TYPES _ Correct type _ Installation is as specified

[Supervisor Specific Checks - Write any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

FENCES [Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PAVING DEPARTMENT OF PLANNIONG AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST PAVING


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Checked Initial and date

HOLD POINTS Obtain the superintendents approval for the following stages; Spec.Ref. Item Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

MATERIALS AND COMPONENTS _ Mortar materials and mix proportions correct as specified CONSTRUCTION _ Paving evenly graded _ Falls are even and to drainage outlets _ No visual ponding BASE COURSE _ Material type, particle size and clay content correct as specified _ Base compacted to a firm and even surface _ Any soft areas visible _ Moisture content adjusted as required to facilitate compaction _ Base course minimum thickness is as specified ASPHALT PAVING _ Hot mix materials and thickness is as specified _ Finished surface levels and falls correct UNIT PAVING _ _ _ _ _ _

Paving units are of specified material Cut pavers maintain sharp edges and accurate joints and margins Concrete edge restraint provided as specified Concrete to required grade and standard Minimum thickness as specified Control joints correctly placed as specified

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

PAVING _ Expansion joints installed correctly as specified _ Correct finishing method used as specified

GRAVEL DRIVEWAY _ Approved materials used _ Minimum thickness and falls are correct [Supervisor Specific Checks - Write in any specific checks here, or insert them in the appropriate section under the previous headings and or checkpoints.]

[Project Specific Checks - Project specific checks can be listed here or inserted into the location in the previous checklist.]t

[Project Officer to insert any special checks required for this project.]

Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

LANDSCAPE DEPARTMENT OF PLANNING AND INFRASTRUCTURE CONSTRUCTION DIVISION

CHECK LIST LANDSCAPE


PROJECT Checked by Work lot SPEC.NO. Title Date

WITNESS POINTS Give sufficient notice so that inspection may be made at the following stages; Spec.Ref. Item Inspection of planting and garden edge set outs Inspection of irrigation system for testing Checked Initial and date

HOLD POINTS Obtain the Superintendents approval for the following stages; Spec.Ref. Item Drawings submitted for approval Checked Initial and date

TESTS Give sufficient notice so that the Superintendent may witness testing; Spec.Ref. Item Topsoil tested and documentation received Mulch tested and documentation received Fill irrigation pipe work and test at the required pressure Checked Initial and date

COMPLIANCE CHECKS

[Specification Checks]

List of compliance checks to be finalized.

<<DPI CONSTRUCTION CHECK LIST AUG 2005>>

LANDSCAPE

[Supervisor Specific Checks Write in any specific checks here, or insert them in the appropriate section under the previous headings or checkpoints.]

[Project Specific Checks Project specific checks can be listed here or inserted into the location in the previous check list.]

[Project Officer to insert any special checks required for this project.] Action Required - ITC issued on items that do not comply

Reported to: Final Check Made by: Comments

Date:

Date:

Das könnte Ihnen auch gefallen