21 February 2013 Mitsubishi Research Institute, Inc., Kyudenko Corporation, BIRUMEN KAGOSHIMA CO., LTD, Mitsubishi UFJ Morgan Stanley Securities Co., Ltd.
1-1 Overview of Feasibility Study Project for the JCM: Counterpart / Project Site
Counterpart: Indonesia BPPT (Assessment and Application of
Technology Badan Pengkajian Dan Penerapan Teknologi)
INDNESIA
Yogyakarta
BPPT Technopark
1-2 Overview of Feasibility Study Project for the JCM: Methodology for GHG Emissions Reduction
For reducing GHG emissions, the system as the alternative to diesel electric generation, in which highperformance small-sized wind-power generator (5kW) that BIRUMEN KAGOSHIMA CO., LTD. possesses is hybridized with solar power generation and Energy Management SystemEMS that Kyudenko Corporation possesses is incorporated, is introduced.
EMS Outline
Introduction of demand and supply control system which utilizes EMS and remote monitoring which utilizes network
RE y = EGPJ , y EFminigrid,y
REy: Reference emission (tCO2/yera) EGPJ,y: Net electricity supplied to mini-grid by the project activity (MWh/year) EFgrid,y: CO2 emission factor of mini-grid (tCO2/MWh)
EGPJ,y is monitored directly. EFminigrid,yis determined per calculation method. No project emission or leakage is considered.
5
Method 2
41,684,316 166,792,596 -
Simple OM Emission Factors Calculation of West Nusa Tenggara Grid for Year 2010
Fuel Unit Total EF (tC/TJ) 21.1 20.2 20.2 25.8 15.3 Oxidation (%) 1 1 1 1 1 NCV CO2 Emission (tCO2e ) 6,640,063 613,344,549 619,984,612
2,105,294 226,617,373 -
Simple OM Emission Factors Calculation of West Nusa Tenggara Grid for Year 2011
Fuel Unit Total EF (tC/TJ) MFO IDO HSD Coal Natural Gas Total kiloliter kiloliter kiloliter ton MMBTU 469,000 255,427,000 0 0 21.1 20.2 20.2 25.8 15.3 Oxidation (%) 1 1 1 1 1 40,767 37,219 36,542 27,444 MJ/kl MJ/kl MJ/kl MJ/ton NCV CO2 Emission (tCO2e ) 1,479,218 691,318,394 0 0 692,797,612
2010
619,984,612 849,204,681 0.730
2011
692,797,612 956,070,000 0.725
Directly monitor the net electricity supplied to grid by the Project Remote data collection Avoid complexity of monitoring under Programme CDM Simplify verification